Guidance DDR PetroGas Rig
Guidance DDR PetroGas Rig
Guidance DDR PetroGas Rig
Font : Arial
Font Size : 12
Font Colour : Black
Thousand format : xx,xxxx (coma)
Decimal format : xx.xx (dot)
Length : ft
Size Inch :(“)
Name of Well : - 1 Word (Walio-01)
- 2 Word (Kasim Barat-1)
- 3 Word (SWO-1 (South West Oscar-1)
GUIDANCE FOR HEADER REPORT AND ACTUAL WELL SCHEDULE (FOR COLOUR)
Drilling – Development Wellservices – Add Perforation
Acknowledge by:
R. Tata Mardiyanta
Sr. Manager Operations
and Project
Example actual activity on 12 November 2020 and report on 13 November 2020
Subject Email
[Name of Rig- Type of Job]- Morning Report No. [xx] [Name of Well/Name of Location]
[Type of Job] on [Date Actual Activity]
Body of Email
[Name of Rig - Type of Job]- Morning Report No. [xx] [Name of Well/Name of
Location] [Type of Job] on [Date Actual Activity]
Present Operation:
- [Mention Rig Activity at 24.00]
BOP Status :
Last function & pressure test BOP's : [dd-mm-yyyy]
Weather : [Sunny/Rain]
Location : [Muddy/xxx/xxx]
Remarks : [Slow Move/Block Local People/Slow Operation/etc]
Heavy Equipment Used Load Total Load Hrs Remarks
Field Units
- Continued Rigged down at X Location (previous location) and MIRU to X Location (new
location).
- R/D Activity (Percentage: XXX%):
Lowered down upper and lower mast …
- R/M Activity (Percentage: XXX%):
Pulled Rig carrier from X Location (previous location) to X (new location) and arrived on
location
at XX.X hrs.
Trip #1: XXX
Trip #2: XXX
Trip #3: XXX
R/U Activity (Percentage: XXX %):
Set up jack and beam matting to centre well and leveling….
- Completed MIRU to X (New Location), filled up the well with water XX bbls. Observed the well
static.
- N/D ESP X- mastree, N/U 11” 2K BOP’s function test and pressure tested.
Annular 250 psi – low, 1000 psi – high, Rams 250 psi – low, 1500 psi – high, made safety
inspection.
- POH with (ESP Unit Type) ESP unit on total XX jts XX EUE tubing production string to surface.
- Disassembled and checked with ESP unit found : motor, protector damaged - pump and flat
cable still good (Based on ESP Unit condition). L/D whole ESP unit and boxed same.
- Pick up, assembled and serviced with … (ESP unit Type).
- RIH with ... (ESP unit type) on XXX (amount of tubing) jts XX (size of tubing) EUE tubing to ±
XXXX ft (Installed 2 ea cable band it each joint and cable protector every 3 jts tubing, total: XX
ea cable protector).
Megger Test depth Phase to Phase Phase to ground
500 ft 1.4 Ohm (Balance) Infinite
Continued Megger Test every +/- 500 ft.
- Installed tubing hanger and landed pump intake at XXXX ft, bottom of motor at XXXX ft. (WOS
XX klbs).
- N/D 11” 2K BOP’s, N/U ESP X- mastree, final megger test: XXXX depth, phase to phase: XX,
phase to ground: XX.
- Put the well back online, WHP: XXX psi, rate: XXX BFPD.
- Rig down rig equipment and MIRU to the next location.
- Filled up tubing string with water and pressure tested mechanical HF pump to 500 psi holding
10 minutes, Good.
- N/D sucker rod running equipment.
- Rigged down at X (Previous location) move to X (Next Location).
3. Acidizing Job
24 Hrs Summary Operation: (Operation from 00.00- 24.00)
- Continued Rigged down at X Location and MIRU to X Location (New location).
- R/D Activity (Percentage: XXX %):
Lowered down upper and lower mast …
- R/M Activity (Percentage: XXX %):
Pulled Rig carrier from X to X and arrived on location at XX.X hrs.
Trip #1: XXX
Trip #2: XXX
Trip #3: XXX
R/U Activity (Percentage: XXX %):
Set up jack and beam matting to centre well and leveling….
- Completed MIRU to X (New Location), filled up the well with water XX bbls. Observed the well
static.
- P/T cementing line XXX psi hold 5 minutes.
- N/D ESP X- mastree, N/U 11” 3K BOP’s (based on BOP specification) function test and
pressure tested.
Annular 250 psi – low, 1500 psi – high, Rams 250 psi – low, 1500 psi – high, kill line and
HCR valve low 250 psi - high 2000, made safety inspection.
- POH ESP Unit / kill string on XX” EUE tubing to surface.
- M/U 7'' Casing scraper BHA: 6-1/8" rock bit + 7" casing scraper (BHA Length = XX.X ft). RIH
same on XX jts XX'' EUE tubing to XXXX ft.
- Rig up the 2" line to tubing and annulus.
- Mix acid for tubing pickle XX bbls + add, pump KCL X bbls rate: X.X bpm at XXX Psi, continue
10 bbls acid pickle rate: 1.5 bpm at 50 Psi, displaced XX bbls water rate: X.X bpm at XXX psi.
Switch line to annulus reversed out XX bbls rate: 2 bpm at XXX psi.
- POOH 7'' Casing scraper BHA: 6-1/8" rock bit + 7" casing scraper (BHA Length = XX.X ft) on
XX” EUE tubing to surface.
- M/U stimulation BHA: 7” Mechanical RBP + its retrieving tool, tail pipe and pup joint + 7" RTTS
Packer + X" tail pipe (BHA length= XX.X ft) RIH same on XX jts 3½" EUE tubing to test set
packer at XXXX' KB with 10 Klbs
- R/U the 2" line P/T string side X XPSI, leak and back side to 500 PSI for 5 minutes, OK.
Released pressure.
- Perform injectivity rate interval X, XXXX ft – XXXX ft (XX ft); XXXX ft - XXXX ft (XX ft);
respectively. Test rate result (based on result):
Run: XX, W/C: XX%, CHL: XXXX PPM, NO3: XXX PPM, PH: X.X
Run: XX, W/C: XX%, CHL: XXXX PPM, NO3: XXX.X PPM, PH: X.X
- PJSM acid job, mixing, iron reducing, KCL HCL, acid XX bbls (XX% - gal/ft). Open bypass
port, spot acid XX bpm, close bypass port, squeeze XX bbls acid for perforation interval 3,4 &
5 (XXXX ft – XXXX ft), over displace with XX bbls KCL water (XX time Vol string) as follow:
Initial injection Rate: X.X bpm @YYY psi, final injection rate: X.X bpm @ XXX psi. Initial
shutdown pressure XXX psi. Press after 5 min XX psi, press after 10 min XX psi, press after
15 min XX psi, press after 20 min xx psi. After 30 min bleed off return to tank XX bbls.
- R/U swab equipment and accessories.
- Post Acid swab test all interval (XXXX ft – XXXX ft)
Made: 32 runs, FL: XXXX ft, Swab from: XXXX ft, Fluid Rec. today: XXX bbls, total rec: 220
bbls, Rate. XXX BFPH.
Run: XX, W/C: XX%, CHL: XXXX ppm, NO3: XXX ppm, PH: X.X
Run: XX, W/C: XX%, CHL: XXXX ppm, NO3: XXX ppm, PH: X.X
- R/D swab equipment and accessories.
- Unset 7" RTTS packer and POH 7" RTTS packer on 3-1/2" EUE tubing to surface and laid
down same.
4. Scabliner Instalation
- PJSM, M/U with 7" scabliner, installed 6 pins upper w/36 Klbs, 7 pins lower w/ 42 Klbs (1 ea 6
Klbs). RIH same on 3-1/2" EUE tubing to XXXX ft (XX jts, scabliner length: XX.X ft).
- RIH same with 7" scabliner on 3-1/2" EUE tubing and rabbit every stand to setting depth as
per program (WOS XX Klbs).
- R/U the 2" line, P/T to 4000 psi.
- Drop ball 2.25 inch, fill up string, pressure up on tubing 500 psi, 1500 psi, 2500 psi, 3500 hold
every 5 minutes, bleed off pressure. Pump to the tubing to 3500 psi to set Packer. Pump out
plug shear at XXXX psi (XX pins) and YYY psi (YY pins). Lower packer at XXXX ft, upper
packer at XXXX ft, and top scabliner depth at XXXX ft.
- R/D the 2" line, Pick up string to XX Klbs, slack off to XX Klbs, turn left and released running
tool [brand/ type of scabliner], ok.
- POOH w/ running tool [brand/type of scabliner] on 3-1/2" EUE tubing to surface. Laydown
running tool [brand/ type of scabliner].
6. Perforation Job
- Trip in with GR/JB (CCL if required) and POOH to surface.
- PJSM. Loaded explosives 1st Gun. 7 ft x 4.5" Casing gun 5 SPF 35 ea (HMX Charge).
- Radio Silent: M/U 7’ x 4.5” 5 SPF casing gun & RIH to depth, Correlate gun depth
- Perforate Interval #X XXXX ft – XXXX ft (7 ft, Re- perforation) – got indication gun
fired
- POOH with casing gun to surface (1 ea miss fired – 99% fired).
- R/D Wireline unit.
- Loaded explosives 1st Gun. 4 ft x 4.5" Casing gun 5 SPF 20 ea (HMX Charge).
- Trip in with casing gun to perforate Interval XXXX ft – XXXX ft (4 ft) --> Remedial
Cement Job.
- POOH with casing gun to surface (1 ea miss fired – 99% fired).
- M/U and RIH Cement retainer on wireline to XXXX ft. Fired detonator to set CR at
XXXX ft. POOH CR setting tool.
- R/D Wireline unit.
- M/U mule shoe BHA: 3-1/2” mule shoe on 3-1/2” EUE tubing. RIH same and sting
into cement retainer.
- R/U cementing unit, P/T line 3000 psi. Perform injection rate: 0.5 bpm, 1000 psi, 1
bpm 1600 psi (total inject 10 bbls).
- PJSM, pump 5 bbls water ahead, mix & pump 4 BBLS cement slurry 15.8 ppg +
additives. Displaced XX bbls water.
- Squeezed XX bbls cement by hesitated: IIP 500 psi/ 0.7 bpm, FIP 1000 psi/ 0.3
bpm, stop pump at 1000 psi hold during 10 minutes. Bleed off pressure, had 2 bbls
fluid return to displacement tank, CIP at 05:00 hrs.
- POOH with M/U mule shoe BHA: 3-1/2” mule shoe on 3-1/2” EUE tubing and L/D
same.