Guidance DDR PetroGas Rig

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 11

Guidance for DDR Petrogas Rig

Font : Arial
Font Size : 12
Font Colour : Black
Thousand format : xx,xxxx (coma)
Decimal format : xx.xx (dot)
Length : ft
Size Inch :(“)
Name of Well : - 1 Word (Walio-01)
- 2 Word (Kasim Barat-1)
- 3 Word (SWO-1 (South West Oscar-1)

Type of Well Work and Colour in the Well Schedule :

GUIDANCE FOR HEADER REPORT AND ACTUAL WELL SCHEDULE (FOR COLOUR)
Drilling – Development Wellservices – Add Perforation

Drilling – Exploration Wellservices – Re-Perforation

Workover – Add Perf New Layer Wellservices – Drill Out EZBP

Workover – Hydraulic Fracturing Wellservices – Set EZBP

Wellservices – ODH ESP Wellservices – Re-Activation

Wellservices – ODH SRP Wellservices – Fishing Job

Wellservices – Pump Recovery Wellservices – Well Optimization Acid.

Wellservices – Pump Installation Wellservices – Well Optimization Surf.

Wellservices – Pump Change ESP to SRP Rig Maintenance

Wellservices – Pump Change SRP to ESP Rig Preparation / Rig Move

Wellservices – Pump Optimization

Wellservices – Well Integrity


Prepared by: Reviewed by: Approved by:

Yudha Yusriansyah M. Suheri Kurniawan Chandra M. Wirjowerdojo


Workover Engineer Sr. Supv Drilling Well Drilling and Well
Intervention Intervention Superintendent

Acknowledge by:

R. Tata Mardiyanta
Sr. Manager Operations
and Project
Example actual activity on 12 November 2020 and report on 13 November 2020

Subject Email
[Name of Rig- Type of Job]- Morning Report No. [xx] [Name of Well/Name of Location]
[Type of Job] on [Date Actual Activity]
Body of Email
[Name of Rig - Type of Job]- Morning Report No. [xx] [Name of Well/Name of
Location] [Type of Job] on [Date Actual Activity]

Last 24 Hrs Summary Operation :


- [Mention Rig Activity]
- [Mention Rig Activity]
- Rig Down [Name of Well/Name of Location] (Percentage xx%)
 Xxx,xxx,xxx
 Xxxx
 Xxxxx
- Rig Move [Name of Well/Name of Location] (Percentage xx%)
 Xxx,xxx,xxx
 Xxxx
 Xxxxx

- Rig Up [Name of Well/Name of Location] (Percentage xx%)


 Xxx,xxx,xxx
 Xxxx
 Xxxxx
- [Mention Rig Activity]
- [Mention Rig Activity]
- [Mention Rig Activity]

Present Operation:
- [Mention Rig Activity at 24.00]

00:00 – 06:00 Operation Update November 13, 2020


- [Mention Rig Activity at 00.00/ 06.00 (morning report)]
Operation Forecast:
- [Mention Plan activity from 06.00 to 24.00 (morning report), plan activity from 16.00 to 24.00
Afternoon report)]

BOP Status :
Last function & pressure test BOP's : [dd-mm-yyyy]

Weather : [Sunny/Rain]
Location : [Muddy/xxx/xxx]
Remarks : [Slow Move/Block Local People/Slow Operation/etc]
Heavy Equipment Used Load Total Load Hrs Remarks

Thanks & Regards,


[Name]
[Tittle]
PBL Rig #2 / PBL Rig #3 / PBL Rig #4
Petrogas (Basin) Ltd.
Telp : xxxxx
Email : xxxxx

Field Units

MEASURMENT UNITS ROUNDING and ANSWER


FORMAT
Depth feet X
Pressure psi X
Pressure Gradient psi/foot X.XXXX
Mud Weight ppg X.X
Volume bbls X.X
Capacity and bbls/foot X.XXXX
Displacement
Pump Speed in stroke per SPM X
minute
Strokes Stk or stks X
Speed in feet per hour Feet/hour X
Area Feet/hour X.XXXX
Force lbs X
Wait and Weight Pressure Psi/100 stks or psi/10 X
Reduction Schedule steps
BOP pressure rating inch(“) – psi (K psi) 13-5/8” – 3K
Wellhead pressure rating inch(“) – psi (M psi) 7-1/16” – 2M

1. ESP ODH Procedure

24 Hrs Summary Operation : (Operation from 00.00- 24.00)

- Continued Rigged down at X Location (previous location) and MIRU to X Location (new
location).
- R/D Activity (Percentage: XXX%):
Lowered down upper and lower mast …
- R/M Activity (Percentage: XXX%):
Pulled Rig carrier from X Location (previous location) to X (new location) and arrived on
location
at XX.X hrs.
Trip #1: XXX
Trip #2: XXX
Trip #3: XXX
R/U Activity (Percentage: XXX %):
Set up jack and beam matting to centre well and leveling….
- Completed MIRU to X (New Location), filled up the well with water XX bbls. Observed the well
static.
- N/D ESP X- mastree, N/U 11” 2K BOP’s function test and pressure tested.
Annular 250 psi – low, 1000 psi – high, Rams 250 psi – low, 1500 psi – high, made safety
inspection.
- POH with (ESP Unit Type) ESP unit on total XX jts XX EUE tubing production string to surface.
- Disassembled and checked with ESP unit found : motor, protector damaged - pump and flat
cable still good (Based on ESP Unit condition). L/D whole ESP unit and boxed same.
- Pick up, assembled and serviced with … (ESP unit Type).
- RIH with ... (ESP unit type) on XXX (amount of tubing) jts XX (size of tubing) EUE tubing to ±
XXXX ft (Installed 2 ea cable band it each joint and cable protector every 3 jts tubing, total: XX
ea cable protector).
  Megger Test depth          Phase to Phase                              Phase to ground
     500 ft                            1.4 Ohm (Balance)                          Infinite
Continued Megger Test every +/- 500 ft.
- Installed tubing hanger and landed pump intake at XXXX ft, bottom of motor at XXXX ft. (WOS
XX klbs).
- N/D 11” 2K BOP’s, N/U ESP X- mastree, final megger test: XXXX depth, phase to phase: XX,
phase to ground: XX.
- Put the well back online, WHP: XXX psi, rate: XXX BFPD.
- Rig down rig equipment and MIRU to the next location.

2. SRP ODH Procedure

24 Hrs Summary Operation: (Operation from 00.00- 24.00)


- Continued rigged down at X (previous location) and MIRU to X Location (new location)
- R/D Activity (Percentage: XXX %):
Lowered down upper and lower mast …
- R/M Activity (Percentage:XXX%):
Pulled Rig carrier from X to X and arrived on location at XX.X hrs.
Trip #1: XXX
Trip #2: XXX
Trip #3: XXX
R/U Activity (Percentage: XXX %):
Set up jack and beam matting to centre well and leveling….
- Completed MIRU to X (New Location), filled up the well with water XX bbls. Observed the well
static.
- Pressure tested 2-7/8” EUE tubing production string, pressure drop 0 psi (if indication tubing
leak).
- N/D sucker rod X- mastree, N/U sucker rod pulling equipment.
- POH with 1½” x 12’ x 2’ HF pump (based on type) on total XX jts 3/4” (based on size) sucker
rods to surface.
- Checked HF pump on surface, ok.
- RIH with 2-3/8” (based on type) seating nipple on total XX jts XX” EUE tubing + X jts 3½” EUE
tubing strainer, landed bottom of seating nipple XXXX ft, bottom of tubing run at XXXX ft.
- RIH with with 1½” x 12’ x 2’ (based on HF pump type) HF pump on total XX jts XX” (based on
size) sucker rods. Installed XX" polish rod, inserted HF pump to seating nipple at XXXX ft KB.

- Filled up tubing string with water and pressure tested mechanical HF pump to 500 psi holding
10 minutes, Good.
- N/D sucker rod running equipment.
- Rigged down at X (Previous location) move to X (Next Location).

3. Acidizing Job
24 Hrs Summary Operation: (Operation from 00.00- 24.00)
- Continued Rigged down at X Location and MIRU to X Location (New location).
- R/D Activity (Percentage: XXX %):
Lowered down upper and lower mast …
- R/M Activity (Percentage: XXX %):
Pulled Rig carrier from X to X and arrived on location at XX.X hrs.
Trip #1: XXX
Trip #2: XXX
Trip #3: XXX
R/U Activity (Percentage: XXX %):
Set up jack and beam matting to centre well and leveling….
- Completed MIRU to X (New Location), filled up the well with water XX bbls. Observed the well
static.
- P/T cementing line XXX psi hold 5 minutes.  
- N/D ESP X- mastree, N/U 11” 3K BOP’s (based on BOP specification) function test and
pressure tested.
Annular 250 psi – low, 1500 psi – high, Rams 250 psi – low, 1500 psi – high, kill line and
HCR valve low 250 psi - high 2000, made safety inspection.
- POH ESP Unit / kill string on XX” EUE tubing to surface.
- M/U 7'' Casing scraper BHA: 6-1/8" rock bit + 7" casing scraper (BHA Length = XX.X ft). RIH
same on XX jts XX'' EUE tubing to XXXX ft.
- Rig up the 2" line to tubing and annulus.
- Mix acid for tubing pickle XX bbls + add, pump KCL X bbls rate: X.X bpm at XXX Psi, continue
10 bbls acid pickle rate: 1.5 bpm at 50 Psi, displaced XX bbls water rate: X.X bpm at XXX psi.
Switch line to annulus reversed out XX bbls rate: 2 bpm at XXX psi.

- POOH 7'' Casing scraper BHA: 6-1/8" rock bit + 7" casing scraper (BHA Length = XX.X ft) on
XX” EUE tubing to surface.
- M/U stimulation BHA: 7” Mechanical RBP + its retrieving tool, tail pipe and pup joint + 7" RTTS
Packer + X" tail pipe (BHA length= XX.X ft) RIH same on XX jts 3½" EUE tubing to test set
packer at XXXX' KB with 10 Klbs
- R/U the 2" line P/T string side X XPSI, leak and back side to 500 PSI for 5 minutes, OK.
Released pressure.
- Perform injectivity rate interval X, XXXX ft – XXXX ft (XX ft); XXXX ft - XXXX ft (XX ft);
respectively. Test rate result (based on result):

Rate Volume Pressure


0.5 – 1.0 bpm 6 bbls 400 psi
1.0 – 2.0 bpm 8 bbls 700 psi (stop pumping press hold 220 psi)
1.0 bpm 10 bbls 550 psi
- Pre Acid swab test all interval (XXXX ft – XXXX ft)
Made: XX runs, FL: XXXX ft, Swab from: XXXX ft, Fluid Rec. today: XXX bbls, total rec: XXX
bbls, Rate. XX BFPH.

Run: XX, W/C: XX%, CHL:  XXXX PPM, NO3: XXX PPM, PH: X.X

Run: XX, W/C: XX%, CHL:  XXXX PPM, NO3: XXX.X PPM, PH: X.X

- PJSM acid job, mixing, iron reducing, KCL HCL, acid XX bbls (XX% - gal/ft). Open bypass
port, spot acid XX bpm, close bypass port, squeeze XX bbls acid for perforation interval 3,4 &
5 (XXXX ft – XXXX ft), over displace with XX bbls KCL water (XX time Vol string) as follow:
Initial injection Rate: X.X bpm @YYY psi, final injection rate: X.X bpm @ XXX psi. Initial
shutdown pressure XXX psi. Press after 5 min XX psi, press after 10 min XX psi, press after
15 min XX psi, press after 20 min xx psi. After 30 min bleed off return to tank XX bbls.
- R/U swab equipment and accessories.
- Post Acid swab test all interval (XXXX ft – XXXX ft)
Made: 32 runs, FL: XXXX ft, Swab from: XXXX ft, Fluid Rec. today: XXX bbls, total rec: 220
bbls, Rate. XXX BFPH.

Run: XX, W/C: XX%, CHL:  XXXX ppm, NO3: XXX ppm, PH: X.X

Run: XX, W/C: XX%, CHL:  XXXX ppm, NO3: XXX ppm, PH: X.X
- R/D swab equipment and accessories.
- Unset 7" RTTS packer and POH 7" RTTS packer on 3-1/2" EUE tubing to surface and laid
down same.

4. Scabliner Instalation
- PJSM, M/U with 7" scabliner, installed 6 pins upper w/36 Klbs, 7 pins lower w/ 42 Klbs (1 ea 6
Klbs). RIH same on 3-1/2" EUE tubing to XXXX ft (XX jts, scabliner length: XX.X ft).
- RIH same with 7" scabliner on 3-1/2" EUE tubing and rabbit every stand to setting depth as
per program (WOS XX Klbs).
- R/U the 2" line, P/T to 4000 psi.
- Drop ball 2.25 inch, fill up string, pressure up on tubing 500 psi, 1500 psi, 2500 psi, 3500 hold
every 5 minutes, bleed off pressure. Pump to the tubing to 3500 psi to set Packer. Pump out
plug shear at XXXX psi (XX pins) and YYY psi (YY pins). Lower packer at XXXX ft, upper
packer at XXXX ft, and top scabliner depth at XXXX ft.
- R/D the 2" line, Pick up string to XX Klbs, slack off to XX Klbs, turn left and released running
tool [brand/ type of scabliner], ok.
- POOH w/ running tool [brand/type of scabliner] on 3-1/2" EUE tubing to surface. Laydown
running tool [brand/ type of scabliner].

5. C/O Log Job


- Continued Rigged down at X Location and MIRU to X Location (New location).
- R/D Activity (Percentage: XXX%):
Lowered down upper and lower mast …
- R/M Activity (Percentage: XXX%):
Pulled Rig carrier from X to X and arrived on location at XX.X hrs.
Trip #1: XXX
Trip #2: XXX
Trip #3: XXX
R/U Activity (Percentage: XXX %):
Set up jack and beam matting to centre well and leveling….
- Completed MIRU to X (New Location), filled up the well with water XX bbls. Observed the well
Static.
- P/T cementing line XXX psi hold 5 minutes.  
- N/D ESP X- mastree, N/U 11” 3K BOP’s (based on BOP specification) function test and
pressure tested.
Annular XXX psi – low, XXXX psi – high, Rams XX psi – low, XXXX psi – high, kill line and
- POH ESP Unit / kill string on XX” EUE tubing to surface.
- M/U 7'' Casing scraper BHA: 6-1/8" rock bit + 7" casing scraper (BHA Length = XX.X ft). RIH
same on XX jts XX'' EUE tubing to XXXX ft KB.
- POOH 7'' Casing scraper BHA: 6-1/8" rock bit + 7" casing scraper (BHA Length = XX.X ft) on
XX” EUE tubing to surface.
- R/U wireline unit, M/U & Rig Up C/O Log tools equipment, P/T shooting nipple for XXX
Psi hold 5 mins, OK.
- Trip in with GR/JB (CCL if required) and POOH to surface.
- Set up C/O Log Mode and perform C/O Log Pass #1 (XXXX ft – XXXX ft), running
speed at XX ft/min.
- Record C/O Log Pass #X (XXXX ft – XXXX ft), running speed at XX ft/min.
- Record C/O Log Pass #X (XXXX ft – XXXX ft), running speed at XX ft/min.
- Shut off C/O log mode and cooling down C/O Log equipment for 1 hrs at 300 ft.
- POH C/O log equipment to surface and lay down C/O Log tools.
- Processing C/O Log Result while C/O process.

6. Perforation Job
- Trip in with GR/JB (CCL if required) and POOH to surface.
- PJSM. Loaded explosives 1st Gun. 7 ft x 4.5" Casing gun 5 SPF 35 ea (HMX Charge).
- Radio Silent: M/U 7’ x 4.5” 5 SPF casing gun & RIH to depth, Correlate gun depth
- Perforate Interval #X XXXX ft – XXXX ft (7 ft, Re- perforation) – got indication gun
fired
- POOH with casing gun to surface (1 ea miss fired – 99% fired).
- R/D Wireline unit.

7. Drill Out EZBP


- M/U BHA: 6" Tricone Bit + 6 jts 4-3/4" DC (BHA length= xx ft). RIH same on XX jts 3½" DP
to XXXX ft.
- Drill out EZBP, and push down to XXXX ft.
- Drilling Parameter (based on result)
WOB : 1-5 klbs, RPM : 50-70, GPM : 180-300, SPM : 65-70, Pump press. : 250 psi
- POOH BHA: 6" Mill Bit + 6 jts 4-3/4" DC (BHA length= xx ft) on XX jts 3½" DP to surface.
Note: bit grading: B…, G…., and T….

8. Drill Out Cement


- M/U BHA: 6" Tricone Bit + 6 jts 4-3/4" DC (BHA length= xx ft). RIH same on XX jts 3½" DP
to XXXX ft. (Break circulated every XXXX ft good returns).
- Drill out cement from XXXX ft to XXXX ft, reversed circulate hole clean every 30 ft progress.
- Drilling Parameter (based on result)
WOB: X-X klbs, RPM : XX-XX, GPM : XXX-XXX, SPM : XX-XX, Pump press : XXX psi
- POOH BHA: X" Bit + 6 jts 4-3/4" DC (BHA length= xx ft) on XX jts 3½" DP to surface.
9. Cement Squeeze Job
9a. Water Shut off (Chemical Water Shut off)
- R/U Wireline Unit.
- M/U new 7" RP-10 EZBP. RIH on Wireline and correlate depth with CCL Log. Fire
gun and EZBP set at XXXX ft. RIH to re-tagged, ok. POOH setting tool and R/D
wireline unit.
- Fill up hole, pressure test to 300 -500 psi, hold for 5 min ok.
- M/U 7'' Casing scraper BHA: 6-1/8" rock bit + 7" casing scraper (BHA Length =
XX.X ft). RIH same on XX jts XX'' EUE tubing to XXXX ft.
- Circulate hole clean. POOH 6-1/8" rock bit + 7" casing scraper (BHA Length =
XX.X ft) to surface. Reciprocate at intended packer setting depth. POOH to surface
and L/D same.
- M/U BHA: 7" RTTS Packer + X" tail pipe (BHA length= XX.X ft) RIH same on XX jts 3½"
EUE tubing to test set packer at XXXX' KB with 10 Klbs.
- Circulated with 2x70 spm, 302 gpm, pump press. XXX psi good returns.
- R/U cementing unit, P/T line 3000 psi. Perform injection rate: 0.5 BPM 1000 PSI, 1
bpm 1600 psi (total inject 10 bbls).
- PJSM, pump 5 bbls water ahead, mix & pump 4 BBLS cement slurry 15.8 ppg +
additives. Displaced XX bbls water.
- Squeezed 2.9 bbls cement by hesitated: IIP 500 psi/ 0.7 bpm, FIP 1000 psi/ 0.3
bpm, stop pump at 1000 psi hold during 10 minutes. Bleed off pressure, had 2 bbls
fluid return to displacement tank, CIP at 05:00 hrs, estimate TOC at XXXX ft.
- Unset 7” RTTS and POOH 5 stands tubing to XXXX ft. Reversed circulate to clear
pipe of cement.
- POOH 7” RTTS on XXX jts 3-1/2” EUE tubing to surface.

9b. Remedial Cement Job


- M/U 7'' Casing scraper BHA: 6-1/8" rock bit + 7" casing scraper (BHA Length =
XX.X ft). RIH same on XX jts XX'' EUE tubing to XXXX ft.
- Trip in with GR/JB (CCL if required) and POOH to surface.

- Loaded explosives 1st Gun. 4 ft x 4.5" Casing gun 5 SPF 20 ea (HMX Charge).
- Trip in with casing gun to perforate Interval XXXX ft – XXXX ft (4 ft) --> Remedial
Cement Job.
- POOH with casing gun to surface (1 ea miss fired – 99% fired).

- M/U and RIH Cement retainer on wireline to XXXX ft. Fired detonator to set CR at
XXXX ft. POOH CR setting tool.
- R/D Wireline unit.
- M/U mule shoe BHA: 3-1/2” mule shoe on 3-1/2” EUE tubing. RIH same and sting
into cement retainer.
- R/U cementing unit, P/T line 3000 psi. Perform injection rate: 0.5 bpm, 1000 psi, 1
bpm 1600 psi (total inject 10 bbls).
- PJSM, pump 5 bbls water ahead, mix & pump 4 BBLS cement slurry 15.8 ppg +
additives. Displaced XX bbls water.
- Squeezed XX bbls cement by hesitated: IIP 500 psi/ 0.7 bpm, FIP 1000 psi/ 0.3
bpm, stop pump at 1000 psi hold during 10 minutes. Bleed off pressure, had 2 bbls
fluid return to displacement tank, CIP at 05:00 hrs.
- POOH with M/U mule shoe BHA: 3-1/2” mule shoe on 3-1/2” EUE tubing and L/D
same.