Sub-Head of Work: Building Extension of Existing Laboratory
Sub-Head of Work: Building Extension of Existing Laboratory
Schedule - A
SCHEDULE OF QUANTITIES
Name of Work : Provision for additional work/ testing machine for construction materials
Sub-Head of Work: Building Extension of Existing Laboratory
Rate in
Sl No. Item of Work Qty Unit figure (in Rate in words Amount in Rs. Amount in words Remarks
Rs.)
SH: I : SITE DEVELOPMENT
1.1 Demolishing RCC work
including stacking of steel bars
and disposal of un-serviceable
materials within 50 metres lead.
1.12 Cum 1334.28 1494.00
1.2 Demolishing brick work in
cement mortar including
stacking of serviceable material
and disposal of unserviceable
material within 50 metres lead.
3.48 Cum 772.83 2689.00
SH: II : EARTHWORK
2.1 Earth work in excavation in
foundation and trenches etc. in
all kinds of soil (excluding soil
containing 50% or more of
shingle or small size boulders
upto 30 cm size, saturated soil
and rock), lift upto 1.50 m and
stacking the excavated soil not
more than 3 m clear from the
edge of the excavation and
returning the stacked soil in 15
cm layers, when required, into
plinth sides of foundation etc
consolidating each deposited
layer by ramming and watering
and then disposing of all surplus
soil as directed within a lead of
50m.
a) 1 : 2 : 4 (1 cement : 2 coarse
sand : 4 stone aggregate 20
mm nominal size).
1.480 Cum 10842.45 16047.00
4.6 Centring and shuttering
including strutting, propping etc
and removal of form work for :
b) Ornamental grill.
48.440 Kg 198.46 9613.00
6.5 Providing and fixing MS tower
bolts (barrel type) with
necessary screws etc complete.
b) 100 mm
16.000 Each 82.56 1321.00
6.7 Providing and fixing iron press
butt hinges bright finished with
necessary screws etc
complete.
(b) 75 x 47 x 1.70 mm
32.000 Each 40.00 1280.00
6.8 Providing and fixing MS Hooks
and Eyes.
b) 150 mm
24.000 Each 39.43 946.00
SH: VII : STEEL WORK
7.1 Welding by Electric plant
300.000 Cm 9.50 2850.00
7.2 Steel work in built up tubular
trusses including cutting,
hoisting, fixing in position and
applying a priming coat of
approved steel primer welded
and bolted including special
shaped washers etc complete
(welding to be paid separately).
a) 40 mm thick
103.330 Sqm 509.01 52596.00
SH: IX :: ROOFING
Page 7
Rate in
Sl No. Item of Work Qty Unit figure (in Rate in words Amount in Rs. Amount in words Remarks
Rs.)
9.1 Providing corrugated G.I.sheet
roofing fixed with galvanised
iron J or L hooks, bolts & nuts 8
mm dia with bitumen and G.I.
limpet washers or with G.I.
limpet washers filled with white
lead complete, excluding the
cost of purlins, rafters and
trusses.
Total 2123244.00
Executive Engineer,
PHE&WS, Division,