Professional Documents
Culture Documents
2022-02-11 Hangar 14 Investment Study - FINAL (Lo Res)
2022-02-11 Hangar 14 Investment Study - FINAL (Lo Res)
2022-02-11 Hangar 14 Investment Study - FINAL (Lo Res)
City of Edmonton
Hangar 14
Investment Study
Table of Contents
1.0 Introduction.................................................................................. 01 3.0 Findings Analysis, and Conclusions............................................ 11 3.4 Option 2a: 40 Year Rehabilitation..............................................................27
1.1 Terms of Reference.........................................................................................01 3.1 Examination & Validation of 2017 Reports..............................................11 Opportunities & Constraints: Synthesis......................................................27
Project Scope...................................................................................................02 Methodology and Approach.......................................................................11 Heritage: Goals and Impacts......................................................................27
Heritage Statement of Significance...........................................................03 Heritage: Conserve and Sustain.................................................................11 Building systems: Envelope & Interiors......................................................27
Current Heritage Recognition and Terms of Reference.......................04 Conservation Objectives...............................................................................11 Building systems: Structural..........................................................................28
Heritage Standards & Guideline................................................................04 Objectives of Conservation Include...........................................................12 Building systems: Mechanical......................................................................29
Character Defining Elements.......................................................................05 Windows and Wall/Roof Assemblies........................................................12 Building systems: Electrical...........................................................................29
Energy and Emissions: Analysis..................................................................05 Hangar Roof Assemblies..............................................................................12 Energy & Emissions.........................................................................................30
Hangar Doors..................................................................................................12
2.0 Executive Summary...................................................................... 07 Mechanical Systems.......................................................................................12 3.5 Option 2b: 40 Year Rehabilitation with 50% GHG Reductions...........31
1.1 Synopsis and Outcomes................................................................................07 Energy and Emissions: Base Case.............................................................12 Opportunities & Constraints: Synthesis......................................................31
Option Outcomes............................................................................................07 Heritage: Conserve and Sustain.................................................................31
3.2 Option 1a: 20 Year Rehabilitation..............................................................13 Building systems: Envelope & Interiors......................................................32
Opportunities & Constraints.........................................................................13 Building systems: Structural..........................................................................32
Heritage: Conserve and Sustain.................................................................13 Building systems: Mechanical......................................................................33
Building systems: Envelope & Interiors......................................................14 Building systems: Electrical...........................................................................33
Building systems: Structural..........................................................................14 Energy & Emissions: Path to Net Zero.......................................................34
Building systems: Mechanical......................................................................15
Building systems: Electrical...........................................................................17 3.6 Option 3: New Zero Emissions Warehouse.............................................35
Energy & Emissions: Baseline Energy Performance..............................18 Opportunities & Constraints.........................................................................33
Building systems: Outline Specification.....................................................38
3.3 Option 1b: 20 Year Rehabilitation with 50% GHG Reductions...........19 Building systems: Structural..........................................................................39
Opportunities & Constraints.........................................................................19 Building systems: Mechanical......................................................................40
Heritage: Conserve and Sustain.................................................................19 Building systems: Electrical...........................................................................40
Building systems: Envelope & Interiors......................................................23 Energy & Emissions: Net-Zero Ready.........................................................40
Building systems: Structural..........................................................................23
Building systems: Mechanical......................................................................24
Building systems: Electrical...........................................................................25
Energy and Emissions: 50% GHG Reduction...........................................26
Table of Contents
Hangar 14
1.0 Introduction
Project Scope
The consultant team has been tasked with combining in-person, visual
condition assessments of the main structural, mechanical, electrical,
interior finish and envelope systems with a comprehensive desktop
review and validation of the 2017 facility condition assessments and
engineering studies. Having performed these opening tasks, the
team’s attentions are to be concentrated on the further analysis of the
four rehabilitation scenarios and one facility replacement scenario to
develop and test rehabilitation strategies and replacement building
system configurations. Each of these explorations, energy model inputs
and outputs, recommended actions and predicted outcomes, are to
be guided by a shared and integrated alignment around key heritage
conservation and sustainable buildings and climate resiliency policies
and procedures. Lastly and perhaps most importantly, the team is to
“run the numbers” on each option to create a robust, Class 4 set of
estimates related to capital, maintenance, and operations costs over 20
and 40-year lifecycle phases. These are to be based on a consistent
data set of building system descriptions, service environments, regulatory
requirements, predicted service life estimates, maintenance and
operations inputs and outcomes. In addition to cost estimates, the team
is to perform valuations and appraisals of the existing facility and of the
impacts of each rehabilitation option and the replacement scenario. The
theoretical replacement building is to be based on buildings systems
calibrated to provide a useful comparative analog of the existing building
as well as to achieve a 20 percent improvement over the NECB 2017
and a TEDI measuring less than 50 kWhrs/sqm.
Heritage Statement of Significance These trusses are built of Douglas Fir, as are the rigidly braced wood
columns on which they rest. Hangar #14 also used a Canadian
The following Statement of Significance for the property is taken from the patented system of connection with steel bolted joints and split-ring
Register of Municipal Historic Resources, City of Edmonton Planning and connectors, making the joints stronger than in traditional Warren
Development, and is included here for reference: truss systems. The roof and superstructure were constructed of heavy
Description of Historic Place timbers, specified because of the shortage of steel during wartime.
Integral to the wide-span design is the operation of the steel section
Hangar #14 is a tall, one-storey rectangular plan structure, with doors on the end wall, which are top-hung and slide horizontally.
lean-to additions on the east and west sides. The interior consists of Furthermore, Hangar #14 symbolizes Canada’s wartime aviation
an exposed heavy timber truss system stayed with tension cables, experiences and Edmonton’s important role in the BCATP during
allowing for a clear span width of 34 metres. It is located on the World War Two..
southwest side of Edmonton’s Municipal Airport on one large lot,
located north of Kingsway Avenue. It backs onto the airport on its Hangar #14 was one of a number of facilities built across the
north and east, and faces a parking lot to the south. country to house the BCATP, an agreement between Canada, Great
Britain, Australia and New Zealand to train aircrews for duty during
Heritage Value the war. This training took place in Canada due to ideal conditions
Hangar #14 has heritage value as a rare surviving Canadian on the prairies and a low population density. Hangar #14 served
example of hangar design from the World War Two period and several different training schools, but was utilized primarily by the
as a symbol of Canada’s wartime experience. It has additional Air Observers School. Hangar #14 is additionally valued for its
significance for its association with Wilfred R. May, one of Edmonton’s associations with Wilfred R. May (1896-1952), one of the most famous
most significant aviation figures and the 418 City of Edmonton figures in Edmonton aviation, who was best known for escaping the
Squadron. Built in 1942, Hangar #14 is significant as the only ‘Red Baron’ during World War One. In 1919, May and his brother
remaining ‘double wide, double long’ hangar in Canada. The hangar started May Airplanes Limited and built their first hangar in 1920.
is a good example of standard British Commonwealth Air Training As a result of his contributions to Canadian aviation, May was
Plan (BCATP) design, which could be doubled in width or depth appointed as an Officer of the British Empire in 1935. During World
depending on the size of the school or facility required. Its most War Two, Hangar #14 and other structures were built adjacent to
notable architectural feature is the roof structure that spans a width these original hangars, and May was instrumental in running the Air
of 34 metres without intermediate supports, employing a modified Observers School from these hangars. May’s involvement with the
Warren truss system. First developed in 1848, a Warren truss consists growth of this airfield entrenched the development of Edmonton’s
of parallel upper and lower chords with diagonal connecting first municipal airport in this location. There is also historical value
members forming a series of equilateral triangles. associated with the use of Hangar #14 by the 418 City of Edmonton
Squadron between 1946 and 1957. The Squadron is remembered for
its triumphant performance in the battles at Dieppe and Normandy
during World War Two. (Source: City of Edmonton Planning and
Development (Bylaw: 12868)) Aerial view of Blatchford Field, Edmonton.
Source: CSCE Archives
Current Heritage Recognition and Terms of Reference compatible contemporary use of an historic place, or an individual
N
component, while protecting its heritage value” (pg. 17).
The Hangar 14 building (Aviation Museum) is designated as a Provincial
Historic Resource under the Alberta Historical Resources Act (Historic The Standards and Guidelines elaborate further:
Resources Management Branch, File: Des. 1827), and is municipally Rehabilitation involves the sensitive adaptation of an historic place or
designated under City of Edmonton By-Law 12868. As such, the property individual component for a continuing or compatible contemporary use,
is legally protected from demolition or inappropriate alteration and while protecting its heritage value.
required to be maintained in a fair condition under the Alberta Historical
Resources Act, and under Policy C-450B of the Register of Municipal Consider Rehabilitation as the primary treatment when:
Historic Resources. a Repair or replacement of deteriorated features is necessary;
The Standards and Guidelines for the Conservation of Historic Places in b Alterations or additions to the historic place are planning for a
Canada (“the Standards and Guidelines”) is produced by Parks Canada new or continued use; and,
and serves as the Canadian government’s guiding document on the c Depiction during a particular period in its history is not appropriate
treatment of historic places across the country. It was adopted by the (pg. 16).
Province of Alberta as a guiding heritage document in 2003, and the
All nine of the General Standards apply to Rehabilitation projects, as do
City of Edmonton’s Historic Resource Management Plan’s Heritage Policy
Standards 10, 11 and 12, which are specific to Rehabilitation projects.
#6 directs that the City’s “Historic Resource Management Program will
The Standards that are most relevant to this study center around three
be aligned with the Standards and Guidelines for the Conservation of
concepts:
Historic Places in Canada.”
• The conservation of character-defining elements, even throughout N
a conversion to a new use. Character-defining elements are to be
Heritage Standards & Guidelines
maintained wherever possible, repaired where necessary, and
The Standards and Guidelines prescribes a three-step conservation replaced in kind (where evidence permits) only where they are so
decision-making process: lost or deteriorated that there is no ability to repair;
1 Determine the primary treatment; • An aim toward minimal intervention, i.e., only the intervention that
is necessary to accommodate contemporary safety, accessibility,
2 Review the Standards; and,
programmatic and other requirements; and,
3 Follow the Guidelines.
• Contemporary interventions must be compatible with,
Hangar 14 will no longer be used as an airplane hangar building, as the distinguishable from and subordinate to the original resource, and
Edmonton City Centre Airport has been closed. Under the Standards and they must be as reversible as possible. Aerial SLIM and Land Use Maps of Hangar 14 Site
Guidelines, Rehabilitation is considered the most appropriate intervention Source: City of Edmonton
The relevant Guideline sections should be consulted with respect to the
in instances involving a change to a new use. Rehabilitation is defined
specific elements of the proposed work.
as follows: “the action or process of making possible a continuing or
Character Defining Elements: In addition, the Municipal designation includes: Energy model analysis was based on review of the 2017 condition
assessment, 2017 conservation plan draft, 2019 structural evaluation,
Elements that convey the heritage character of Hangar 14 as a 1940s • Exposed framing including Douglas fir vertical wood posts
existing drawings, and photos of the Hangar 14 facility, as well a 2020
hangar building include its: supporting long Warren trusses, reinforced with bays of double
technical study of emissions neutral buildings conducted by Integral
diagonal frames; truss system of connection with steel bolts and
• Landmark location adjacent to the runway of the City Group for the City of Edmonton. The model was calibrated using
split ring connector;
Municipal Airport; recent utility billing data and site visit observations to reflect the actual
• Exposed surface-rim conduit, wires and brackets; performance of the existing facility. The modelling methodology followed
• Form, scale and massing expressing its functional industrial design;
• Open interior layout with spaces for administration, storage, ASHRAE Standard 211 Standard for Commercial Building Energy Audits
• Rectangular plan with lean-to additions to the east and west; workshop and mechanical equipment; and referenced the 2017 National Energy Code of Canada for Buildings
• One-storey height with an internal clear span width of 34 metres; (NECB 2017) where applicable for the proposed investment alternatives.
• Remnants or artifacts from BCATP period.
• Four quadrant subdivided roof that slopes from the centre to the • Source: Alberta Culture and Community Spirit, Historic Resources Management It is helpful to compare the overall energy use intensity of the proposed
Branch (File: Des. 1827)(https://hermis.alberta.ca/ARHP/Details
outer walls; aspx?DeptID=1&ObjectID=4665-0774) options against the existing building operations, to provide context for
• Exterior elements such as its: the relative improvement in energy performance and carbon emissions.
Energy use intensity from sampled building types in NRCan’s National
• Cedar shingle siding; Energy and Emissions: Analysis
Energy Use Database suggest that the existing building’s overall energy
• Top-hung, sliding steel section doors with glazing; consumption is relatively low. This may reflect the current occupancy
An energy model was built using RETScreen Expert whole-building energy
• Off-centre two-storey vehicle entrance with rolling door; and simulation software developed by Natural Resource Canada, which is and space use rather than an evaluation of the base building energy
• Central timber column with shingle siding on the end elevations; available in both free and paid-subscription versions. The software performance, and opportunities for substantial improvement are evident
calculates energy use on a daily basis for both the existing building and in particular for space heating as shown in the detailed analysis.
• Lean-to additions on the east and west elevations, consisting of
the proposed lifecycle alternatives to allow comparison of the relative
wood frame construction with cedar shingle siding; four doors
impact of design elements on the overall building performance, including
on the east facade and five doors on the west facade; off-centre
interactive effects.
two-storey entrance with rolling door on the east facade; central
one and one-half storey addition with smaller garage doors on the
Energy Use Intensity, Thermal Energy
west facade; GHG Emissions
EUI Demand Intensity, TEDI
• Regular fenestration with large, industrial rectangular 36-pane Reduction
(kWh/m2) (kWh/m2)
wooden windows on the east and west elevations; 6-over-6 double-
hung wooden windows and 12-pane wooden storm windows on Existing 184 165
the lean-to addition, interior elements such as its exposed interior Option 1A/2A 147 135 20%
framing and truss structure, with Douglas Fir vertical wood Option 1B/2B 79 67 57%
posts supporting long Warren trusses; and reinforced concrete Option 3 43 31 76%
slab floors. Typical AB Transportation and Warehousing Building* 486
• Source: City of Edmonton Planning and Development (Bylaw: 12868) Typical AB Office Building* 467
• (https://hermis.alberta.ca/ARHP/Detailsaspx?DeptID=1&ObjectID=4664-0131) Typical AB Information and Cultural Industries Building* 656
* Natural Resources Canada National Energy Use Database (NEUD) 2018 values
Project Team 2.1 Synopsis and Outcomes Energy model analysis was conducted to compare energy and GHG
performance of three design options, over two rehabilitation lifespans,
CITY OF EDMONTON against the existing building. Option 1a/2a results in the first round of
There are two different but interrelated frameworks for analyzing and
lifecycle measures showed in a 20% reduction in GHG emissions. Option
comparing the various building options covered by this study. The first
1b/2b included all of the measures from Option 1a/2a plus additional
CITY OF EDMONTON PROJECT MANAGER framework encompasses a set of stepwise improvements to the existing
building envelope improvements, resulting in a 57% reduction in GHG
building; the second, its complete replacement. The former is guided by an
PRIME CO N S U LTA NT emissions relative to the existing building (marginally exceeding the 50%
overarching heritage conservation strategy and an aligned set of policies
reduction target). Option 3 included new construction measures for an
GEC ARCHITECTURE and procedures. This framework applies urgent stabilizing and rehabilitative
Jason Pare Bob Stirling
equivalent building developed based on approximately 20% better than
measures to the building superstructure as well as character-respecting
Partner-in-Charge Project Architect NECB 2017 prescriptive requirements as per the City’s administrative
performance upgrades to other building systems. The second framework
procedure for climate resilient design, which demonstrated a 76%
SU B- CO N S U LTANT S provides a new building and therefore a new performance reference model
reduction in GHG emissions relative to the existing building.
for energy, emissions and materials use.
STRUCTURAL, ELECTRICAL, MECHANICAL
Williams Engineering Each framework—rehabilitation and replacement—represents an investment of Options Outcomes
Nathaniel Curtis Ben Rajewski Victor Lam energy, materials and other resources to achieve more sustainable outcomes
Structural Lead Mechanical Lead Electrical Lead Based on the outcomes of and comparisons between the cost estimates
for each of the different building scenarios, each operating for the next 20
and energy models created for the above options and the existing
HERITAGE CONSULTANT and 40 years. For each of the rehabilitation options, these added inputs
building, we offer the following general observations and conclusions:
ERA Architects conform and adapt to a set of existing opportunities and constraints. These
Scott Weir Ryan Love are, in turn, dictated as much by the building’s unique, historical, character- 1 With respect to the scope of immediate repairs, modest upgrades
Heritage Lead Heritage Architect
defining elements as by its basic form and function. The replacement option, and 20 and 40-year life-cycle maintenance and repairs associated
COST CONSULTANT by contrast, starts from zero in terms of material and energy investments, with Options 1a and 2a, it can be seen that that these will:
Atlus Group and from there is constrained only by the limits of size, form and program of • Result in modest gains in operational efficiency, compared to the
David Crane Curtis Cameron the original building and the current sustainable building goals, policies, and
Cost Lead Cost Consultant existing building, through lowered energy consumption along with
administrative procedures of the City of Edmonton. the associated utility costs and emissions.
SUSTAINABILITY/GHG TRACKING The rehabilitation framework begins with a new, performance baseline
Williams Engineering • Have only modest impacts on maintenance costs over the study
Lindsay Austrom
(Options 1a and 2a) for the existing building based on a limited but strategic life-cycle periods.
Sustainability Lead scope of structure stabilization, building envelope repairs and mechanical • Be significantly less-expensive, from a first cost standpoint,
system upgrades. From here, more ambitious benchmarks in energy compared to Options 1b, 2b and 3.
consumption and GHG emissions are pursued through further building
envelope and HVAC systems improvements. The replacement framework • Will not significantly enhance the value of the building relative to
goes immediately to a new, higher-performing but otherwise standard the current valuation.
replacement (Option 3). The energy consumption of the existing building • Cannot be deferred for more than 5 years when it is expected
performance upgrades and new building have also been modeled and the the rehabilitation scope will become critical for major envelope
associated maintenance and operations outcomes estimated through 20 and assemblies (e.g., roof, glazing assemblies and walls), building
40-year life-cycles (Options 1b and 2b, respectively). mechanical and electrical systems.
7
2.0 Executive Summary
4 Some important things to note about the differences and similarities Comparative Capital Outlay Summary
between the various options related to initial capital costs, on-going
maintenance and operations costs, and life-cycle renewals costs: Investment Options
• All of the major building renewals occur in the first 20 years of GFA: 8593 m2
either Rehab scenario (1a/2a). Years 21-40 essentially allow for
Ref Description OPTION 1A/2A $/m2 OPTION 1B/2B $/m2 OPTION 3 $/m2
major life cycle renewals on renovations that already occurred in
Required Capital $16,070,380.23 $1,870.17 $22,158,244.00 $2,578.64 $31,534,825.00 $3,669.83
year 1-20. Years 21-40 do not introduce new scope to the project
- Assumes construction in year one
options, therefore they do not act as standalone options.
for each option
• The costing mirrors the scope renewal document, so some scope - Excludes renewals within the first
was repaired initially, while other items were deferred for a 20 years
few years before renovations occurred. To simplify and to align - Project capital project
better with likely project funding mechanisms and processes, an construction dollars
additional summary (see adjacent “Comparative Capital Outlay
Summary”) is provided here that shows the initial capital required
for all three options, assuming completion in year 1. It varies
slightly from the current 1-20 year summaries for each option
shown in Part 4 of the Study as completing everything in Year 1
eliminates some escalation dollars.
• For maintenance costs, the discounting shown in Part 4 of the
Study is summarized in Year 1 for both the 20yr and 40yr version of
each option.
Note that for Existing Building Rehab scenarios and New (Option 3)
scenario, General Facility Repair and Maintenance costs are very similar
owing to the similarity in size and basic function of each option. Major
renovations occurring in Option 1 and 2, or with the new build of Option
3, have similar starting points with similar assumptions about base
building systems and program areas. This translates into small variability
when it comes to maintenance costs. The energy consumption and
emissions data, on the other hand, paints a very different picture and
does vary significantly between options (See table below and in Part 3,
“Energy and Emissions: Path to Net Zero”.
Objectives of conservation include: Hangar Roof Assembly Energy and Emissions: Base Case
• The extensive rehabilitation of the building envelope, with local Due to existing loading constraints on the main hangar roof, and
repairs to the existing sheathing, to restore weather tightness; the Character Defining nature of the exposed roof structure, no new Miscellaneous
insulation above or below the hangar roof is contemplated. An Lights
• Building envelope repairs and upgrades that are physically
and visually compatible with the building’s original fabric and additional layer of insulation will be provided on the flat roofs of the
lean-to additions, to improve energy efficiency. Existing roof lines will
Character Defining Elements; 7.1%
be maintained such that no visual impacts to exterior elevations are
• The full replacement of exterior windows through sensitive design
introduced.
and upgrading;
• The conservation of the property’s heritage value and Character
Defining Elements; Hangar Doors
• Minimal intervention solutions to preserve Character Defining Given the significant amount of air leakage and heat loss arising from
Elements to the greatest extent possible. the existing hangar doors, it is recommended that a secondary glazing
system be installed on the interior side of the doors to meet building
envelope performance targets while restoring and maintaining the
Windows and Wall/Roof Assemblies hangar doors in their original location. A minimum scope of repairs is
The scope of work is intended to restore and conserve the building’s proposed to conserve the hangar doors in their present shell condition, 89.8%
exterior envelope, including its Character Defining Elements, while as non-functioning heritage artifacts. Above the hangar doors, new
improving overall energy efficiency and meeting performance targets for insulation will be fitted into the existing wall space from the interior
Space
each rehabilitation option. Insulation will be fitted from the interior side side, such that existing exterior proportions and cladding finishes are
heating
of walls, such that the existing exterior proportions of walls and windows, maintained.
including window setback dimensions from the outer wall face, will be
maintained. While this strategy will entail a 4” reduction in floor space
Mechanical Systems
at the outer walls due to the added insulation, visual impacts to exterior
Character Defining Elements are minimized. The scope of work includes the salvaging of two gas furnaces from Fuel consumption - base case
BCATP era, to be removed from their current location and reinstated as Section kWh %
non-functioning heritage artifacts elsewhere in the building. A new high
Space heating 1,421,332 89.8%
efficiency gas furnace will be installed in the existing mechanical room.
For options 1b and 2b, a second high efficiency gas furnace is proposed Lights 112,749 7.1%
in the central mezzanine area, with above-ground ducting to meet Miscellaneous 48,208 3%
energy performance targets. Air intake and exhaust penetrations will be Mechanical equipment 47,908 3%
strategically located on roofs and minimized on walls, to minimize visual Hot water 300 0.02%
impacts on exterior Character Defining Elements.
3.2 Option 1a: 20 Year Rehabilitation Heritage: Conserve and Sustain • 100% replacement of vinyl-clad operable sash and fixed factory
windows with new aluminium clad operable sash windows to
The following heritage-related items have been identified as requiring match original design;
Opportunities and Constraints immediate remedial work in order to maintain the existing Character
• Salvage 2 original exterior doors, 1 original double door at west
Defining Elements and supporting structure for another 20 years, in order
The main opportunity for improvement for this option are based on a elevation, to be later reinstated as potential non-functioning
of priority:
host of immediate steps to: heritage artifacts; pack, record and store in dry, secure location;
• 100% replacement of joint sealants at exterior windows, doors, • Perform localized wood soffit and shingle siding repairs, where
• Stabilize the roof structure (trusses) walls and related flashings (assume once every 6 to 10 years); damaged or missing (assume 5% repairs over 2 to 3-year, 6 to 10-
• Improve the overall aesthetics and appearance of the building • 100% replacement of weatherstripping at exterior doors, including year and 11 to 20-year timeframes);
interior and exterior through targeted, strategic improvements hangar doors (assume once every 6 to 10 years);
to the building envelope (window replacements, sealant • Strip paint from hangar doors to bare steel, remove minor surface
• 100% replacement of glazing putty and replacement of cracked corrosion and pitting, prime with rust-inhibiting primer and repaint
replacement) and interior finishes (painting)
Georgian wired glass lites above hangar doors; w/ 2 coats metal alkyd enamel paint to match original colour;
• Improve the overall energy performance (consumption) of the replace deformed or severely corroded steel sections with new
• 100% replacement of east canopy cement board soffit with new
building mechanical system (furnace), electrical system (power galvanized steel to match, using original fastener methods;
wood deck soffit
supply, controls, lighting) and building envelope (sealants, window
replacements) and therefore the thermal comfort of occupants, • Perform repairs to roof structure as needed; salvage original • Salvage and retain 2 decommissioned gas furnaces from BCATP
protection of contents, lowering of operational costs related to timber truss members where replacement is required (assume era, as non-functioning heritage artifacts;
energy utilities. 14 top chords, 5 bottom chords, 18 verticals, 295 diagonals, 38 • Salvage 19 decommissioned electrical panels/switch boxes from
struts, 121 strut wedges, 2 columns, 2 truss turning points (per 2019 BCATP era, to be later reinstated as potential non-functioning
Apart from the potentially significant impacts on the operations of the
Structural Evaluation Report) heritage artifacts; pack, record and store in dry, secure location;
facility related to the roof truss stabilization efforts, most of the above
measures are focused on exterior elements or more readily accessed • Salvage 1 original wood sash window on west elevation; pack, • Salvage 1 entrance canopy from Blatchford era at south elevation,
interior elements that require less in the way of partial demolition or record and store in dry, secure location; to be later reinstated as potential non-functioning heritage artifact;
deconstruction to carry out. The majority are technically straightforward • Replace (67) existing non-original PVC operable windows with pack, record and store in dry, secure location;
and pose only minor technical or other conservation challenges in that new metal-clad double hung wood windows to match original • Strip, prime and repaint interior wood roof structure and timber
they involve like-with-like replacement of mostly non-original elements. three-over-three sash configuration, using salvaged original wood wall framed elements (assume once every 11 to 20 years);
window as a template for replication; • Repaint exterior wood siding and soffits (assume once every 6-10
Option 1a also provides an opportunity to create (and model) a new
performance baseline for the building. The model will measure impacts • Replace (35) existing non-original PVC fixed windows with new years)
on energy use and emissions, and will assist with determining and metal-clad fixed wood windows to match original six-over-six
comparing the immediate performance gains and of the 1a and 1b configuration, using salvaged original wood window from the
rehabilitation, relative to the up-front capital costs, as well as the 20- and second-floor interior office as a template for replication;
40-year operation and maintenance costs.
The modifications to existing structural systems for the Hangar 14 to the foundations.
Investment Study include the reinforcement of the roof trusses, further Column Foundations
analysis of roof trusses to determine maximum potential capacity with
The column foundations could not be visually assessed but do not show
reinforcements, and further investigation of the building foundations to
any immediate signs of failure. The original drawings for the column
determine condition and capacity for future upgrades.
foundations are not available and cannot be assessed for their current
The following recommended modifications to the existing structural capacity.
systems of Hangar 14 consider the various Building Condition
Option 1a Recommendation: investigate the existing column foundations
Assessments and engineering studies undertaken in the past four years
and analyze their capacity to withstand future load increases.
as well as recent and proposed (elsewhere in this study) mechanical and
architectural changes to the existing building. Slabs On Grade
The structural design will conform to the local City of Edmonton standards The existing interior slab on grade appears to be in fair condition with
and will be based on the latest editions of the Alberta Building Code, some cracking that appears to be typical with an old slab. The current
CSA A23.3 – Design of Concrete Structures, CSA S16 – Design of Steel state appears to satisfy the current requirements for occupancy.
Structures, CSA S304 – Design of Masonry Structures, and CSA O86 – Option 1a Recommendation: seal cracks in the concrete as necessary
Design of Wood Structures. and continue to monitor for excessive movement in the future. Typical existing arrangement of roof truss, column, and
lateral bracing elements in main hangar spaces
Canopies The following is a description of the mechanical systems recommended Recommendations: The recommendation for Option 1a is to
The existing canopy structure could not be visually assessed due to the for the Hangar 14 Investment Study. The study was requested by replace both furnaces with similar performing units. This will allow
presence of wood soffit, but there were areas of water staining in the the City of Edmonton to provide them with options for the building for higher efficient gas burners and parts will be available for
soffit that could indicate damage to the roof joists. rehabilitation and/or the possible replacement of the building. The future repairs. It is also recommended to provide 7,500 CFM of
recommendations look at 20- and 40-years rehabilitations, with or outdoor air, which assumes a building occupancy of 500 people
Option 1a Recommendation: when replacing damaged wood soffit, without 50% greenhouse gas reductions. at 15 CFM/person.
arrange for a structural engineer to review the condition and capacity
The mechanical design will be based on the latest editions of the Offices Ventilation
of the roof joists.
Canadian Building Code - Alberta Edition, the Canadian Plumbing Offices along the east side and in the centre core of the building
Option 1a Recommendation: when replacing damaged wood soffit, Code, the National Energy Code of Canada for Buildings, ASHRAE do not have a ventilation system.
arrange for a structural engineer to review the condition and capacity standards and the City of Edmonton standards.
of the roof joists. Recommendation: It is recommended that transfer fan be provide
The recommendations are based on a site review of the facility, the to the offices to provide transfer air to the spaces. Transfer air will
Building Systems: Mechanical Heating and review of the 2017 building assessment and the criteria outlined in the be brought in from the hangar air space.
City of Edmonton’s RFP.
Ventilation Domestic Hot Water Heaters
Option 1a Design Criteria: Mechanical Heating And
Mechanical systems recommendations for the Hangar 14 Investment Four existing domestic hot water heaters provide hot water for the
Ventilation System
Study to provide the City of Edmonton options for the building sinks and lavatories in the facility
The option 1a design criteria consist of a building rehabilitation to
rehabilitation and/or the possible replacement of the building. Based Recommendation: It is recommended to replace the four hot
extend the life of the building by 20 years without any specified GHG
on a site review, review of the 2017 building assessment and the water heaters with heat pump style to help improve the efficiency
reductions. Two existing 55,000 CFM, gas-fired furnaces provide
current building codes and the City of Edmonton requirements, it is our of the heaters.
heating and ventilation air to the entire facility, through below slab
opinion that mechanical rehab Option 1b (same as 2b) is the most
air distribution ductwork. One furnace is no longer operational and
viable option for the building. This option provides for new gas-fired
is currently being used as spare parts for the remaining operational
furnaces, heat pump type hot water heaters, and supplemental fresh air
unit, as spare parts are not available. This has resulted in uneven
supply via a dedicated intake and exhaust equipment and openings in
air distribution throughout the facility, creating zones of in which
the building envelope, to be determined through further analysis and
areas are heated and ventilated and zones that are unheated and
design (e.g. HRV’s). Furnaces (gas-fired) can be replaced as part of
unventilated. Outdoor air appears to through infiltration through the
normal life-cycle renewals over the 40-year (Option 2) period to all-
building envelope. Outdoor air appears to be supplied mainly through
electric units as carbon pricing and utilities-based or on-site renewable
infiltration and exchange through the building envelope.
energy integration dictate.
individual spaces within the facility. In the open museum, gathering, and Recommendation: It is recommended that new data cabling be run as Energy and Emissions: New Baseline
workshop areas this would include either upgrading and customizing necessary with conduit and dedicated LAN rooms/closets be provided
the existing original high-bay luminaires or replacing them with new for head end equipment. Miscellaneous
LED fixtures that closely match the character, scale, and materials of the
Fire Alarm System
original. Within the office area this would be new 1’x4’ LED troffers and
pot lights, and for specialty museum lighting this would be LED track The existing fire alarm system is a single stage conventional system with 8.1%
heads. minimal signalling throughout the facility and limited detection.
The exterior lighting can remain as is. A new low voltage lighting control Recommendation: It is recommended that the fire alarm system be
system is recommended to be added in concert with the LED lighting replaced with a new addressable system. As this is a public facility it is
upgrade. This would provide timeclock, and occupancy control to many recommended that the fire alarm system be upgraded for all options as
of the spaces as well as adding dimmability for many of the museum it is currently not code compliant.
exhibit lighting. The system will have the following features:
Emergency Lighting
• Automatic alarm initiating devices (smoke detectors, heat detectors).
A small scattering of battery packs currently exists within the facility to
• Manual alarm initiating devices (pull stations) throughout the facility.
act as emergency lighting. A few red EXIT type exit signs are located at
some egress paths. • Signalling devices (horn/strobes) throughout the facility. 91.9%
• Connections to mechanical systems for an emergency shut-down.
Recommendation: Emergency lighting is required to be added to
Space
illuminate the egress paths throughout the facility as per the Alberta heating
Building Code. As this is a life safety item all options should incorporate
this. Energy and Emissions: Baseline Energy Performance
Illuminated LED-type running man exit signs should be provided The Option 1a lifecycle investment scenario was limited by overall
constraints of the Heritage conservation objectives. The proposed
throughout the facility to conform to the requirements of the Alberta Fuel consumption - proposed case
Building Code. measures included minimal changes to the existing building systems
to avoid impact to Heritage elements for both the interior and exterior, Section kWh %
Telephone/Data Cabling System And Building Service using replacement technologies and equipment to improve performance Space heating 1,162,382 91.9%
The existing data and telephone system appears to have been modified (energy, GHG and operating cost) without introducing additional modern Miscellaneous 102,644 8.1%
many times over the years and is run free air and exposed throughout interventions to the facility.
Lights 61,936 4.9%
the facility.
Mechanical equipment 40,621 3.2%
Hot water 87 0.007%
3.3 Option 1b: 20 Year Rehabilitation infiltration/exfiltration at the existing hangar door openings as well as • Provide an additional 3” rigid insulation on flat roofs of lean-to
conductive losses through the smaller roof assemblies and east and west additions;
with 50% GHG Reductions walls of the single-storey lean-to elements. The upper exterior walls of • Remove interior drywall finish and batt insulation from north and
the main hangar were also targeted. south elevations above hangar doors; provide new Rockwool batt
Opportunities and Constraints To tackle these losses in a manner that maintained the character-defining insulation and drywall finishes;
The main opportunities for improvement with this option are the same as integrity of the existing hangar doors, it was decided to deploy full-height • Install new frameless curtain wall glazing system on interior side of
those outlined in Option 1a above plus those aimed at: curtainwall assemblies, set inboard of the historic hangar doors, and north hangar doors, to be restored in-situ;
comprising high-performance glazing and frame components. The other • Replace existing non-original metal storefront on south elevation
• Improving the overall energy performance as well as the thermal remedies involved adding insulation and improved air and moisture w/ new high performance glazed storefront system.
comfort of occupants, protection of contents, lowering of operational barrier elements to the above-mentioned roof and wall assemblies. It is
costs related to energy utilities. anticipated that these measures, from a cost-benefit standpoint, will have
• Lowering energy consumption and the associated GHG emissions to more durable impacts on lifecycle operations and maintenance costs,
a level 50% below that of the existing building which include emissions, and will also achieve better outcomes from a
heritage conservation standpoint when compared to the less compatible
Option 1b applies a menu of strategic envelope upgrades, in addition to
roof truss remediation avenues.
those set out in Option 1a, that deliberately avoid increasing the thermal
performance of the existing roof. This is being done to avoid increases in
Heritage: Conserve and Sustain
roofing assembly weights as well as predicted increases in snow loads
from a reduced rate of snow melt (due to reduced heat loss through the Further to the work described in Option 1a above, the following heritage-
roof). As mentioned below and as pointed out in previous engineering related items have been identified as part of the overall building strategy
analyses, the current roof structure capacity is likely inadequate to to reduce GHG by 50%:
provide the needed margins of safety to support these added loads, at
least not without significant modifications (e.g., applied reinforcements) • 100% replacement of existing wood shingle siding and soffits,
or even replacement. Alterations to or removal and replacement of the including related flashings, with new painted wood to match;
trusses were reviewed and discussed extensively by the team’s heritage reinstall as new rainscreen assembly c/w new air barrier
architects and structural engineer. Ultimately, none were viewed as membrane, battens and counter-battens; provide local repairs to
completely acceptable from the viewpoint of heritage conservation, existing underlying sheathing as needed;
especially on what is likely the most significant character-defining • Remove interior drywall finish and batt insulation from walls and
Existing south hangar doors.
element of the hangar interior. With feedback from an initial energy ceilings of lean-to additions and replace with new Rockwool batt
model prepared by the team’s sustainability specialist, it was decided to insulation; build out walls studs in staggered arrangement, to
pursue other emissions-reducing strategies. The modeled energy use and accommodate an additional 4” batt insulation; install new drywall
emissions outcomes, described below, pointed to the need to reduce finishes throughout;
energy consumption caused by excessive heat losses through other wall
and roof assemblies. This included convective losses via, especially,
2-Ply SBS Single-storey (Lean-to) Roofs (also applies to “bump-out” element roofs)
1/4” (6.4 mm) GWB
6 mil Poly VB
1/4” (6.4 mm) GWB
2x8 (38x184 mm) wood studs
R-28 (7.25” thk.) mineral fibre insulation (e.g. Rockwool “Comfortbatt”)
3/4” (19mm) plywood sheathing
2-ply 15# organic felt vapour retarder
2” Type 1 EPS insulation (e.g. Plastifab “Plastispan”)
1/2” coverboard (e.g. IKO “Protectshield”)
Base Sheet (e.g. IKO Torchflex - 180)
Cap Sheet (e.g. IKO Torchflex - 180 Cap)
stairs
UP 2-Ply SBS Main Hangar Roof Assembly-
38mm wood deck (existing)
2 x13mm fibre board
Vapour retarder (bitumen)
66mm polyiso insulation
13mm fibre board
SBS Base Sheet
SBS Cap Sheet
NOTE: Existing Hangar roof is as described above. For the purposes of determining the existing
building’s thermal performance, roof and wall assemblies throughout the east and west lean-to
elements (and newer south east corner) were assumed to be as follows:
Roof:
• SBS membrane, fiber board and insulation layers similar to hangar
• 19 mm (3/4”) ply decking
• 38 x 184 (2” x 8”) joists,
• glass fiber batt insulation
• 6 mil AVB
• 13mm (1/2”) GWB
Walls:
• Wood shingles (prefinished metal cladding at opaque wall assemblies surrounding
aluminum storefront glazing assemblies at south elevation)
• 19 x 140 mm (1” x 6”) diagonal wall sheathing (19 mm plywood at south elevation walls)
• 38 x 89 mm (2” x 4”) studs
• Glass fiber insulation
• 13mm (1/2”) GWB
$ % & ' ( ) * + -
- + * ) ( ' & % $
- + * ) ( ' & % $
- + * ) ( ' & % $
WEST ELEVATION City of Edmonton | Hangar 14 Investment Study | February 11, 2022 22
Not to Scale
3.0 Findings Analysis, and Conclusions
Daylight harvesting in existing hangar museum exhibit space (L) Existing fluorescent troffer ceiling fixtures in wood
working shop (R)
Energy and Emissions: > 50% Improved over Base Energy and Emissions: Improved Baseline
84.8%
Space
heating
Existing wood truss roof structure above hangar museum exhibit space.
Existing cast-in furnace supply duct outlet (L) and existing building water services entry point (R).
Typical ceiling/roof assembly of wood joists, insulation, vapour barrier and gypsum panel ceiling at existing east and
west lean-to elements
Wall Foundations
Option 2b Recommendation: Same recommendations as option 1a.
Column Foundations
Option 2b Recommendation: Same recommendations as option 1a.
Slabs On Grade
Option 2b Recommendation: Same recommendations as option 1a.
Mezzanine
Option 2b Recommendation: Same recommendations as option 1a.
Roof
Option 2b Recommendation: Same recommendations as option 1b.
Canopies
Option 2b Recommendation: Same recommendations as option 1a.
Existing office space at east side of Hangar (top) and ad Existing roof truss, side wall, and underside of roof
hoc insulation installation at hangar doors (bottom) deck elements.
Existing woodworking shop interior with overhead door from hangar interior.
Cost
GHG($) Existing Option
Option1a/2a
1a/2a Option
Option2a/2b Option 33
GHG Tonnes Existing Option
Space
Tonnes Existing 2a/2b Option Cost
GHG ($) 1a/2a
Tonnes
Option 2a/2b Option 3
GHG Tonnes
SpaceHeating
Heating $ 30,527
266 $ 24,965
218 $ 12,350
108 $ 5,661
Space Heating
49 266 218 108 49
Lights
Lights $ 20,971
27 $ 11,520
15 $ 11,520
15 $EXISTING
10,703
Lights 14 $70,000
350 27 15 15 14 OPTION
350
OPTION 1A/2A 1B/2B OPTION 3
Mechanical Equipment
Mechanical Equipment $ 8,911
11 $ 7,556
10 $ 7,599
10 $ 8,955
Mechanical
12 Equipment
$60,000 11 10 10 12
Energy End Uses: Energy (kWh) Energy (%) 300(tonnes)
Cost ($) GHG Energy (kWh) Energy (%) Cost ($) GHG (tonnes) Energy (kWh) 300 Cost ($) GHG (tonnes)
Energy (%) Energy (kWh) Energy (%) Cost ($) GHG (tonnes)
Hot
HotWater
Water $ 560 $ 16 0 $ 16 0 $ 160
Hot Water 0 0 0 0
Space heating 1,421,332 90% $30,527 $50,000
250 266 1,162,382 92% $24,965 218 575,045 250
85% $12,350 108 263,593 71% $5,661 49
Lights 112,749 7% $20,971 $40,000
200 27 61,936 5% $11,520 15 61,936 9%
200 $11,520 15 57,541 16% $10,703 14
Mechanical equipment 47,908 3% $8,911 $30,000
150 11 40,621 3% $7,556 10 40,856 6%
150 $7,599 10 48,143 13% $8,955 12
Hot water 300 0% $56 $20,000 0 87 0% $16 0 87 0% $16 0 87 0% $16 0
100 100
TOTAL 1,582,289 100% $60,465 305 1,265,026 100% $44,057 242 677,924 100% $31,486 132 369,364 100% $25,335 75
$10,000
50 50
Energy Use Intensity, EUI (kWh/m2) 184 147 79 43
Thermal Energy Demand Intensity, TEDI (kWh/m2) 165 - $- 135 67 -
31
Existing
Existing Option1a/2a
Option 1a/2a Option 1b/2b
Option 1b/2b Option
Option33 Existing Option 1a/2a Option 1b/2b Option 3
GHG Reduction 20% 57% 76%
Space
SpaceHeating
Heating Lights
Lights Mechanical
MechanicalEquipment
Equipment Hot
HotWater
Water Space Heating Lights Mechanical Equipment Hot Water
GHG Tonnes Existing Option 1a/2a Option 2a/2b Option 3 City of Edmonton | Hangar 14 Investment Study | February 11, 2022 34
GHG Tonnes
Space Heating 266 218 108 49
Lights 27 15 15 14 350
3.0 Findings Analysis, and Conclusions
The new facility also differs from the original with respect to the types,
locations, and extents of the mechanical, electrical, and building Example of light steel frame building office interior (Pure Technologies, GEC Architecture)
envelope systems. However, its primary structural system mimics the
original with respect to the relative extents and arrangement of long-
span, column-free spaces of the warehouse (main hangar) volume and
the shorter spans of the office (served) and other contiguous (services
and support) spaces.
The same approach is assumed for the provision of light throughout the
facility wherein abundant daylight and electric lighting are provided
and controlled, variously, through passive and active means using high-
performance glazing, occupancy and light-level sensors and automated
controls. Allowances have also been made in the replacement building
for accommodating the task or hazard-specific requirements of the
woodworking and spray-painting spaces of the original. It is assumed
that the mature technologies of these “state-of-the-shelf” mechanical,
electrical, and envelope systems will be optimized to achieve
performance levels that would be considered closer to “state-of-the art”
by contemporary standards for this building type. The intent is, through
greater levels of optimization, for any premium paid, up front in either or
both soft and capital costs, to be recouped or offset by lower operations
and maintenance costs over the 40-year lifecycle period set for the study.
Other than the obvious differences noted above, the most meaningful
changes from old to new have mainly to do with materials. The wood- Example of mass timber building office interior (GEC office; West Block, GEC Architecture)
based superstructure, secondary structural and non-structural wall and
partition framing, structural roof decking, and exterior cladding of the
original are here replaced by a typical, all-steel, office-warehouse
Building Systems: Outline Specification • Total depth of office bar is 16.5 m (to keep it simple, imagine a
1.5m-wide corridor bisecting/serving two equal 7.5 m deep floor
1 Structural systems for the office-warehouse replacement facility plates).
are based on standard, stick-built or post-and-beam steel systems
• Interior Finish to basic but durable standard with minimal interior
adopting a similar or even identical structural grid or comparable
applied finishes (e.g. polished concrete and carpet tile floors,
analog with respect to the long-span and short-span primary
fixed and moveable interior partitions, exposed ceilings with
elements.
visible soffits plus targeted areas of suspended gypsum and LAT
2 Building envelope for office and warehouse to be based on off-site, ceilings for acoustic privacy, FRR continuity, etc.
modular fabrication (see ‘MOD Panel’ and ‘GlasCurtain’ custom
4 Mechanical systems to be tailored/optimized for each space/zone:
wall panel and fiberglass curtain wall systems, respectively, from
local manufacturers), Passive House-level effective R-values and air- • Office and warehouse to incorporate de-coupled heat/cool and
tightness ventilation approach with heat recovery (desiccant wheel or
similar). Consider using heat pumps powered by BIPV or off-site
• Assume effective R-value of office exterior walls to be min. 22.
renewables as a further energy and emissions reduction strategy.
• Assume effective R-value of warehouse north opaque walls
• Warehouse to incorporate ceiling fans, air curtains, and
(without high-bay doors) to be min. 38.
mechanical rooftop mechanical AHU “doghouse” elements along
• Assume effective R-value of warehouse east and west walls (with center column line as needed to maintain (pick set-point for
high-bay doors) to be min. 28. building type per latest ASHRAE reference standard).
• Assume effective R-values of warehouse roof (with roof monitor 5 Lighting to be based on high degree of daylight harvesting in both
glazed openings equal to approx. 35% of roof area) to be R25 components:
overall and roof of office (with multiple roof monitors down central
• Floor plate depth in office block is optimal for south half to be
corridor) to be min. R25 overall.
side-lighted and rear half to be top-lighted (Assume WWR of .35
• Exterior wall cladding, warehouse: Standard prefinished metal; and glazing thermal performance optimized for min. 68% VLT).
office: FRC (e.g. Hardi-Panel, fibre-C or Swiss Pearl.
• Warehouse to utilize roof monitors or saw-tooth elements that have
• Roofing systems to be 2-ply SBS with high-emissivity (cool roof, the vertical glazing facing north and the sloped roofs facing south
Energy Star rated) finish for office and warehouse. ready for PV mounting.
3 Interiors: Office block is configured as a 16.5 m deep bar down the • On-site renewables: BIPV (roof and façade-mounted) to be
longest side of the warehouse, with a 2-hr FRR separation between considered for application on saw-tooth roof monitors of
the two elements warehouse and as sloped window shading elements on south
• Arranged on two floors, with a double-loaded corridor; add/allow office façade.
for fire compartments and vertical circ. (incl. elevator), etc. as Pure Technologies, GEC Architecture
needed to meet code.
Option 3 Design Criteria: Option 3 Recommendation: The new roof structure will be a metal deck
diaphragm supporting all anticipated design loads (snow, storm water,
The option 3 design criteria consists of a full building replacement with
roofing assemblies, light monitors, and photovoltaic systems). The existing
a zero-emissions warehouse facility utilizing standard steel framing,
structural wood decking of the original could be analyzed for potential
concrete foundations, and slab-on-grade construction in a typical office-
reuse in an all-wood version of the new building. Likewise, the existing
warehouse format.
roof trusses could be analyzed by a qualified professional to determine
Wall Foundations the most environmentally sustainable material selection for use in an all-
Option 3 Recommendation: Walls will be supported on either or both wood (mass-timber or stick-built hybrid) structure.
cast-in-place, grade beam-on-pile and strip footing foundations. As an
added option, within a broader sustainability strategy of re-using or
repurposing some or all the existing wall foundations in the new facility,
a further assessment could be performed to determine their suitability
and capacity more accurately.
Column Foundations
Option 3 Recommendation: Columns will be supported on cast-in
place concrete piles or piers. As above, the existing building’s column
foundations could be assessed to determine their suitability to be re-used
as part of the new building structure.
Slabs On Grade
Option 3 Recommendation: concrete slabs on grade will be used for the
main floor of the office block and warehouse. These will be designed
to accommodate in-slab hydronic heating lines where required in both
office and warehouse components. As above, options for re-use or re-
purposing (as opposed to re-cycling) of all or parts of the existing slab-
on-grade structure could be further assessed.
Second-Floor Composite Floor Slabs
Option 3 Recommendation: These slabs will be composite one-way
slabs utilizing metal deck and reinforced concrete. There may be limited Airdrie Transit Operations Centre: Steel frame Office- Mass timber office interior; West Block, GEC Architecture
scope for repurposing structural steel from the mezzanine structure of the Warehouse format (GEC Architecture)
existing building.
Building Systems: Mechanical The lighting will be comprised of all new LED fixtures, controlled with a Energy and Emissions: ENBR and Beyond
new relay-based lighting control system. The fixtures and controls will
Option 3 Design Criteria: Mechanical Heating And Ventilation Miscellaneous
be designed to meet or exceed the controls requirements set out by the
System Mechanical
NECB 2017. This will ensure that the facility is highly efficient in terms of
The option 3 design consists of a full building replacement with a new equipment
energy used by lighting.
zero emissions warehouse facility of similar size and design. Heating
would be through in-slab hydronic system provide heat to the office and The life safety systems will be designed to meet modern code 13%
warehouse spaces from a central boiler. In-slab heating will provide heat requirements and will include a new addressable fire alarm safety,
where the people are at low level, instead of heat accumulating at high emergency lighting installed throughout the space, and new LED running
level. Initially the boiler would be a gas-fired unit that may be replaced man type exit signs. Lights
in the future by a new gas-fired or electrically heated boiler. 15.6%
The communications systems will be designed to suit a modern facility
Ventilation of the office and warehouse space would be by multiple heat with CAT6 cable run throughout and data racks located as necessary.
recovery ventilators (HRV). The quantity of HRVs depend on the layout of Wireless access points will be installed throughout the facility as well.
the spaces to better serve the occupants. A new facility will also allow an integrated design of a photovoltaic
Air movement would be provided by ceiling fans in the office space system on the roof or the site further reducing emissions and providing 71.4%
and giant fans in the warehouse. Fans would help move warm air a source of renewable energy to the facility. Infrastructure would also be Space
accumulating near the ceiling down during the winter and help circulate considered for future electric vehicle charging stations heating
air in the summer. Energy and Emissions: 50% GHG Reductions
Analysis
The option 2a or 2b rehabilitation will allow replacement or upgrades
Energy and Emissions: Net-Zero Ready
to the mechanical systems over a longer time frame that will allow The Option 3 lifecycle investment scenario modelled a replacement
for new technologies to be incorporated as they become available or building using similar geometry and occupancy inputs but with design
economical, while using the existing building. measures based on approximately 20% more stringent than NECB
Fuel consumption - proposed case
2017 prescriptive requirements, LEED Silver energy requirements, and
a Thermal Energy Demand Intensity (TEDI) value less than 80 kWh/m2 Section kWh %
Building Systems: Electrical
as per the City’s climate resilient design requirements. The resulting Space heating 263,593 71.4%
Option 3 Design Criteria design scope provides a highly efficient, solar-ready building. Using Lights 57,541 15.6%
A completely new facility will allow the electrical service to be sized to the emissions neutral pathway described in the 2020 Integral report,
Mechanical equipment 48,143 13%
suit the needs of the space and will allow for a single new electrical this would place Option 3 somewhere in the range of an “Efficient +
Electrified Building” (ENBR) and a net-zero-emissions-ready building. Miscellaneous 87 0.02%
service to be brought into the facility. Power distribution will be designed
to suit the needs of the spaces including museum and workshop power Hot water 87 0.02%
This would result in a building with the capacity to achieve zero emissions
requirements.
with the addition of on-site renewable energy (such as rooftop solar
photovoltaic panels) and off-site renewables for remaining offsets.
Based on the identified above options, the following capital cost • Option 2a (21-40 years) - $10,888,169.32 3 The scope of immediate replacement of the existing building with a
estimates, operation and maintenance costs, and appraised values can • These costs are based on the architectural, structural, heritage, new zero-emissions warehouse of similar size and design in Option 3
be derived. In addition, a net present value has been calculated for mechanical, electrical recommendation from the consultant team has an estimated capital cost of:
each of the options to provide a neutral comparison of the capital costs over the next 21-40 year life span of the building • Option 3 (1-20 years) - $33,197,408.11
and operation and maintenance costs for all options.
• All the pricing assumptions for 1a apply to 2a except the time • This is predominately the initial capital outlay for the new build
1 The scope of immediate repairs and modest upgrades and 20 and sensitive escalation numbers with minor life cycle upgrade assumptions.
40-year lifecycle maintenance and repairs associated with Options • Compounded escalation for the 21-40 year period is 67% • The new warehouse is a theorical model that is built immediate
1a and 2a have an estimated capital cost of: for comparison purposes and does not incur a delay for design or
2 The scope of immediate and ongoing building envelope and
• Option 1a (1-20 years) - $23,483,942.26 mechanical system upgrades and 20 and 40-year lifecycle construction
• These costs are based on the architectural, structural, heritage, maintenance and repairs associated with Options 1b and 2b have • Estimate for the theoretically new construction excludes demolition
mechanical, electrical recommendations from the consultant team an estimated capital cost of: of the existing
over the next 20-year life of the building • Option 1b (1-20 years) - $31,576,802.67 • Estimate is inclusive of general requirements, contractor fees,
• Estimates include the demolition and renovation costs • These costs are based on the architectural, structural, heritage, design and pricing contingency (10%), as well as construction
• Estimates are inclusive of general requirements, contractor fees, mechanical, electrical recommendations from the consultant team contingency for change order (5%)
design and pricing contingency (15%), as well as construction to improve greenhouse gas emissions (GHG) over the next 20-year • Future estimates for cyclical renewals have also been adjusted
contingency for change order (10%) life of the building for escalation, the first renewals occur in the 4-5 year period
• Estimates have also been adjusted for escalation, renovations • All the pricing assumptions for 1a to 1b having 15% compounded escalation, 6-10 year renewals have
considered immediate have 0% escalation, 2-3 year renovations 24% compounded escalation and 11-20 year renewals have 42%
• Option 2b (21-40 years) - $10,795,259.50
have 9% compounded escalation, 4-5 year renovations have compounded escalation
• These costs are based on the architectural, structural, heritage,
15% compounded escalation, 6-10 year renovations have 24% • Similarly, to Option 1 and 2 the escalations are calculated to the
mechanical, electrical recommendations from the consultant team
compounded escalation and 11-20 year renovations have 42% mid-point of each of the time periods, as the renovation could
to improve greenhouse gas emissions (GHG) over the next 21-40
compounded escalation occur any time within the defined range
year life span of the building
• The escalations are calculated to the mid-point of each of the time • Option 3 (21-40 years) - $3,630,855.89
• All the pricing assumptions for 2a to 2b
periods, as the renovation could occur any time within the defined • These costs are based off the cyclical renewals for the theoretical
range new build over the 21-40 year time period
• All the pricing assumptions for Option 3 (1-20 year) apply to year
21-40 except the time sensitive escalation numbers
• Compounded escalation for the 21-40 year period is 67%
4.0 Recommendations & Cost Estimates
4 Demolition and salvage of select existing historical components were 5 Operation and Maintenance costs were also considered for each 7 Separate to the estimate values noted above, the Altus Research,
not specifically costed in the previous options, however below some of the options, these are the costs related to keeping the facility Valuation & Advisory (RVA) team also prepared appraised value for
breakout pricing: operational outside of the major life cycle component replacement each of the options:
• Complete Demolition of Existing - $773,370 which were includes are part of the renovation: • As-Is Market Value - $2,900,000
• These costs assume demolition, remove of debris from site • Option 1a (1-20 years) - $7,094,051 or $825 per m2 • Option 1a - $5,300,000
• Select Removal of Wood Trusses - $250,000 to $500,000 • Option 2a (21-40 years) - $17,221,472 or $2,004 per m2 • Option 2a - $6,400,000
• There is nearly 3400 meters of wood trusses, so certainly the • Option 1b (1-20 years) - $6,000,613 or $698 per m2 • Option 1b - $7,100,000
number of historical trusses desired to be salvaged and the • Option 2b (21-40 years) - $14,106,512 or $1.641 per m2 • Option 2b - $8,200,000
required salvage location drive the potential cost of this item • Option 3 (1-20 years) - $5,553,678 or $646 per m2 • Option 3 (1-20 year) - $16,400,000
• These costs are in addition to the complete demolition cost • Option 3 (21-40 years) - $12,833,292 or $1,493 per m2 • Option 3 (21-40 year) - $17,900,000
• Select Removal of Electrical Distribution - $5,000 to $10,000 6 A discounted cashflow was requested which combines the capital This only meant to be a brief summary of the findings, specific
• The historical electrical components are not operational, this costing and the operation maintenance costing to provide a current assumptions and calculations for the costing and appraised values can
cost is for the proper tagging, storage and transportation of the dollar comparison of the options: be found within the appendices.
equipment for potential reuse for display purposes • Option 1a (1-20 years) - $22,833,740
• These costs are in addition to the complete demolition cost • Option 2a (21-40 years) - $9,656,724
• Option 1b (1-20 years) - $30,742,103
• Option 2b (21-40 years) - $8,580,751
• Option 3 (1-20 years) - $36,468,512
• Option 3 (21-40 years) - $5,617,433
• Discount rate of 3.53% was provided by City of Edmonton for use in
these calculations
4.1 Comparative
COMPARATIVE Executive
EXECUTIVE Summary
SUMMARY
Investment Options
GFA: 8593 m2
Ref Description OPTION 1A/2A $/m2 OPTION 1B/2B $/m2 OPTION 3 $/m2
C New facility zero-emission warehouse $31,534,825.00 $0.00 $4,516.28 $711,909.30 $1,077,982.53 $33,329,233.11
21-40 Years
Year 22 Year 23 Year 24 Year 25 Year 26 Year 27 Year 28 Year 29 Year 30 Year 31 Year 32 Year 33 Year 34 Year 35 Year 36 Year 37 Year 38 Year 39 Year 40 Year 41 40-YEAR TOTAL
2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 2058 2059 2060 2061
Rehabilitation Capital Costs (1A / 2A)
Rehabilitation capital costs $10,888,169.32
Architectural $8,354,524.43 $8,354,524.43
Structural $0.00 $0.00
Heritage $2,532,875.18 $2,532,875.18
Mechanical $769.71 $769.71
Electrical $0.00 $0.00
Hanger 14 - New Warehouse Facility - 2 storey Office 3,234 m² 34,810 sf 316 /sf $11,008,043
Hanger 14 - New Warehouse Facility - Warehouse (Open Space 5,359 m² 57,684 sf 277 /sf $15,957,437
only)
GST EXCLUDED
100463 - Hanger 14 - Option 3, Class D Estimate, R0 December 13, 2021 100463 - Hanger 14 - Option 3, Class D Estimate, R0 December 13, 2021
Unpublished Work Copyright © 2021 | Altus Group | altusgroup.com Unpublished Work Copyright © 2021 | Altus Group | altusgroup.com
ELEMENTAL SUMMARY
HANGER 14 - NEW WAREHOUSE FACILITY -
WAREHOUSE (OPEN SPACE ONLY)
4.5 Option 3: Warehouse $18,351,000 $3,424/m² 5,359 m²
TOTAL /m²
HANGER 14 - NEW WAREHOUSE FACILITY -
WAREHOUSE (OPEN SPACE ONLY) TOTAL
$318/sf 57,684 sf
COMP. GCA
TOTAL /sf
GCA Element Element $ Total /m2
Element Ratio Quantity Unit Rate
Cost Total GCA
%
A SUBSTRUCTURE 1,224,008 228 /m2 6.7%
A10 Foundations 1,224,008 228 /m2 6.7%
A1010 Standard Foundations 1.00 5,359 m2 66.07 /m2 354,109 66 /m2 1.9%
A1020 Special Foundations 1.00 5,359 m2 64.45 /m2 345,400 64 /m2 1.9%
A1030 Slab on Grade 1.00 5,359 m2 97.87 /m2 524,499 98 /m2 2.9%
B SHELL 7,922,733 1,478 /m2 43.2%
B10 Superstructure 3,087,181 576 /m2 16.8%
B1020 Roof Construction 1.00 5,359 m2 576 /m2 3,087,181 576 /m2 16.8%
B20 Exterior Enclosure 3,599,933 672 /m2 19.6%
B2010 Exterior Walls 0.24 1,261 m2 786 /m2 991,762 185 /m2 5.4%
B2020 Exterior Windows 0.21 1,134 m2 2,152 /m2 2,439,187 455 /m2 13.3%
B2030 Exterior Doors 0.01 28 no. 6,035 /no. 168,984 32 /m2 0.9%
B30 Roofing 1,235,618 231 /m2 6.7%
B3010 Roof Covering 1.00 5,359 m2 230 /m2 1,232,618 230 /m2 6.7%
B3020 Roof Openings 0.00 2 ea 1,500 /ea 3,000 1 /m2 0.0%
C INTERIORS 318,337 59 /m2 1.7%
C30 Interior Finishes 318,337 59 /m2 1.7%
C3020 Floor Finishes 1.00 5,359 m2 48.00 /m2 257,242 48 /m2 1.4%
C3030 Ceiling Finishes 1.00 5,359 m2 11.40 /m2 61,095 11 /m2 0.3%
D SERVICES 4,483,730 837 /m2 24.4%
D20 Plumbing 396,360 74 /m2 2.2%
D2010 Plumbing Fixtures and Equipment 1.00 5,359 m2 19.14 /m2 102,600 19 /m2 0.6%
D2020 Warehouse Plumbing Piping 1.00 5,359 m2 51.56 /m2 276,310 52 /m2 1.5%
D2090 Other Plumbing Systems 1.00 5,359 m2 3.26 /m2 17,450 3 /m2 0.1%
D30 HVAC 2,216,441 414 /m2 12.1%
D3040 Distribution Systems 1.00 5,359 m2 230 /m2 1,231,751 230 /m2 6.7%
D3050 Terminal and Package Units 1.00 5,359 m2 95.28 /m2 510,605 95 /m2 2.8%
D3060 Controls and Instrumentation 1.00 5,359 m2 64.58 /m2 346,084 65 /m2 1.9%
D3090 Other HVAC Systems & Equipment 1.00 5,359 m2 23.88 /m2 128,000 24 /m2 0.7%
D40 Fire Protection 350,085 65 /m2 1.9%
D4010 Sprinklers 1.00 5,359 m2 65.32 /m2 350,085 65 /m2 1.9%
D50 Electrical 1,520,845 284 /m2 8.3%
D5010 Electrical Service and Distribution 1.00 5,359 m2 80.71 /m2 432,523 81 /m2 2.4%
D5020 Lighting and Branch Wiring 1.00 5,359 m2 102 /m2 546,618 102 /m2 3.0%
D5030 Communications and Security 1.00 5,359 m2 72.56 /m2 388,878 73 /m2 2.1%
D5090 Other Electrical Services 1.00 5,359 m2 28.52 /m2 152,826 29 /m2 0.8%
Net Construction Estimate $13,948,808 2,603 /m2 76.0%
Z GENERAL REQUIREMENTS & ALLOWANCES 4,402,245 821 /m2 24.0%
Z1 General Requirements & Fee 2,008,629 375 /m2 10.9%
Z11 General Requirements 10.0 % 1,394,881 260 m2 7.6%
Z12 Fee (Head office overheads, and profit) 4.0 % 613,748 115 m2 3.3%
Total Construction Estimate (Excluding Contingencies) $15,957,437 2,978 /m2 87.0%
Z2 Contingencies 2,393,616 447 /m2 13.0%
Z21 Design and Pricing Contingency 10.0 % 1,595,744 298 m2 8.7%
Z22 Escalation Contingency EXCLUDED
Z23 Construction Contingency 5.0 % 797,872 149 m2 4.3%
TOTAL CONSTRUCTION COST $18,351,053 3,424 /m2 100%
$525,000 $524,523/m²1 m²
TOTAL /m²
SITE DEVELOPMENT TOTAL
$48,730/sf 11 sf
COMP. SCA
TOTAL /sf
SCA Element Element $ Total /ls
Element Ratio Quantity Unit Rate
Cost Total SCA
%
G BUILDING SITEWORK 456,107 456,107 87.0%
G BUILDING SITEWORK 456,107 456,107 /ls
/ls 87.0%
G30 Site Civil/Mechanical Utilities 130,500 130,500 /ls 24.9%
G3010 Water Supply 1.00 1 ls 30,750 /ls 30,750 30,750 /ls 5.9%
G3020 Sanitary Sewer 1.00 1 ls 33,200 /ls 33,200 33,200 /ls 6.3%
G3030 Storm sewer 1.00 1 ls 66,550 /ls 66,550 66,550 /ls 12.7%
G40 Site Electrical Utilities 325,607 325,607 /ls 62.1%
G4010 Electrical Distribution 1.00 1 ls 325,607 /ls 325,607 325,607 /ls 62.1%
Net Construction Estimate $456,107 456,107 /ls 87.0%
Z11 General Requirements EXCLUDED
Z12 Fee (Head office overheads, and profit) EXCLUDED
Total Construction Estimate (Excluding Contingencies) $456,107 456,107 /ls 87.0%
Z2 Contingencies 68,416 68,416 /ls 13.0%
Z21 Design and Pricing Contingency 10.0 % 45,611 45,611 ls 8.7%
Z22 Escalation Contingency EXCLUDED
Z23 Construction Contingency 5.0 % 22,805 22,805 ls 4.3%
TOTAL CONSTRUCTION COST $524,523 524,523 /ls 100%
B
Total each year $ 6,270,265.14 $ 6,281,810.14 $ 4,048,202.95 $ 4,063,792.70 $ 1,224,913.96 $ 1,240,551.85 $ 440,180.81 $ 456,133.54 $ 472,252.07 $ 488,542.26 $ 503,321.79 $ 1,143,967.22 $ 1,156,753.30 $ 1,170,096.55 $ 1,184,021.95 $ 1,198,555.60 $ 1,213,724.80 $ 1,229,558.11 $ 1,246,085.41 $ 1,263,337.94 $ 1,281,348.41
Discount Rate 3.53%
Year 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Present Value $ 6,270,265.14 $ 6,067,623.05 $ 3,776,850.98 $ 3,662,122.80 $ 1,066,205.04 $ 1,042,998.90 $ 357,465.25 $ 357,790.26 $ 357,803.15 $ 357,524.83 $ 355,781.69 $ 781,061.49 $ 762,862.34 $ 745,351.14 $ 728,505.37 $ 712,303.33 $ 696,724.05 $ 681,747.29 $ 667,353.52 $ 653,523.90 $ 640,240.22
NPV - Option 1B/2B $ 39,322,855.49
NPV - Option 1B/2B 20 Years $ 30,742,103.73
NPV - Option 1B/2B 40 Years $ 8,580,751.76
C
Total each year $ 31,666,794.00 $ 142,487.40 $ 156,340.39 $ 170,082.26 $ 185,980.99 $ 199,771.00 $ 353,839.42 $ 367,944.26 $ 382,214.91 $ 396,657.22 $ 409,866.06 $ 386,409.55 $ 398,013.67 $ 410,115.89 $ 422,738.19 $ 435,903.58 $ 449,636.11 $ 463,960.92 $ 478,904.29 $ 494,493.70 $ 510,757.89
Discount Rate 3.53%
Year 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Present Value $ 31,666,794.00 $ 137,629.09 $ 145,860.86 $ 153,271.13 $ 161,883.91 $ 167,958.26 $ 287,348.49 $ 288,614.76 $ 289,586.24 $ 290,281.55 $ 289,720.89 $ 263,827.15 $ 262,484.36 $ 261,243.69 $ 260,102.47 $ 259,058.13 $ 258,108.17 $ 257,250.22 $ 256,481.99 $ 255,801.27 $ 255,205.96
NPV - Option 3 $ 42,085,946.40
NPV - Option 3 20 Years $ 36,468,512.60
NPV - Option 3 40 Years $ 5,617,433.80
February 5, 2022
21-40 Years
Year 22 Year 23 Year 24 Year 25 Year 26 Year 27 Year 28 Year 29 Year 30 Year 31 Year 32 Year 33 Year 34 Year 35 Year 36 Year 37 Year 38 Year 39 Year 40 Year 41
2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 2058 2059 2060 2061
$ 1,097,047.00 $ 1,121,387.74 $ 1,146,829.33 $ 1,173,422.72 $ 1,201,221.25 $ 1,230,280.79 $ 1,260,659.84 $ 1,292,419.65 $ 1,325,624.39 $ 1,360,341.25 $ 1,396,640.62 $ 1,434,596.20 $ 1,474,285.20 $ 1,515,788.49 $ 1,559,190.78 $ 1,604,580.80 $ 1,652,051.50 $ 1,701,700.24 $ 1,753,629.04 $ 1,807,944.73
22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41
$ 529,461.93 $ 522,756.08 $ 516,387.68 $ 510,346.75 $ 504,623.72 $ 499,209.31 $ 494,094.64 $ 489,271.09 $ 484,730.42 $ 480,464.66 $ 476,466.13 $ 472,727.46 $ 469,241.53 $ 466,001.51 $ 463,000.83 $ 460,233.14 $ 457,692.36 $ 455,372.63 $ 453,268.34 $ 451,374.05
$ 998,197.07 $ 1,017,827.58 $ 1,038,323.44 $ 1,059,723.81 $ 1,082,069.67 $ 1,105,403.91 $ 1,129,771.38 $ 1,155,219.04 $ 1,181,796.02 $ 1,209,553.74 $ 1,238,546.01 $ 1,268,829.13 $ 1,300,462.06 $ 1,333,506.47 $ 1,368,026.93 $ 1,404,091.03 $ 1,441,769.52 $ 1,481,136.44 $ 1,522,269.32 $ 1,565,249.30
22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41
$ 481,754.52 $ 474,479.56 $ 467,530.27 $ 460,896.65 $ 454,569.06 $ 448,538.19 $ 442,795.08 $ 437,331.08 $ 432,137.86 $ 427,207.38 $ 422,531.91 $ 418,103.97 $ 413,916.39 $ 409,962.23 $ 406,234.83 $ 402,727.76 $ 399,434.82 $ 396,350.07 $ 393,467.75 $ 390,782.37
$ 601,471.44 $ 619,176.68 $ 637,651.00 $ 656,928.76 $ 677,045.88 $ 698,039.93 $ 719,950.21 $ 742,817.83 $ 766,685.76 $ 791,598.98 $ 817,604.51 $ 844,751.57 $ 873,091.62 $ 902,678.52 $ 933,568.60 $ 965,820.79 $ 999,496.77 $ 1,034,661.07 $ 1,071,381.18 $ 1,109,727.77
22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41
$ 290,284.95 $ 288,640.91 $ 287,117.80 $ 285,712.43 $ 284,421.71 $ 283,242.69 $ 282,172.50 $ 281,208.42 $ 280,347.82 $ 279,588.18 $ 278,927.06 $ 278,362.14 $ 277,891.18 $ 277,512.04 $ 277,222.67 $ 277,021.10 $ 276,905.43 $ 276,873.87 $ 276,924.68 $ 277,056.21
21-40 Years
Year 22 Year 23 Year 24 Year 25 Year 26 Year 27 Year 28 Year 29 Year 30 Year 31 Year 32 Year 33 Year 34 Year 35 Year 36 Year 37 Year 38 Year 39 Year 40 Year 41 40-YEAR TOTAL
2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 2058 2059 2060 2061
$17,221,472.22
$328,747.86 $345,185.25 $362,444.51 $380,566.74 $399,595.08 $419,574.83 $440,553.57 $462,581.25 $485,710.31 $509,995.83 $535,495.62 $562,270.40 $590,383.92 $619,903.12 $650,898.27 $683,443.19 $717,615.35 $753,496.11 $791,170.92 $830,729.46 $10,870,361.59
$223,890.68 $231,794.02 $239,976.35 $248,447.51 $257,217.71 $266,297.50 $275,697.80 $285,429.93 $295,505.61 $305,936.95 $316,736.53 $327,917.33 $339,492.81 $351,476.91 $363,884.04 $376,729.15 $390,027.69 $403,795.66 $418,049.65 $432,806.80 $6,351,110.63
$14,106,512.36
$234,543.41 $246,270.58 $258,584.11 $271,513.32 $285,088.98 $299,343.43 $314,310.61 $330,026.14 $346,527.44 $363,853.81 $382,046.51 $401,148.83 $421,206.27 $442,266.59 $464,379.91 $487,598.91 $511,978.86 $537,577.80 $564,456.69 $592,679.52 $7,755,401.73
$223,890.68 $231,794.02 $239,976.35 $248,447.51 $257,217.71 $266,297.50 $275,697.80 $285,429.93 $295,505.61 $305,936.95 $316,736.53 $327,917.33 $339,492.81 $351,476.91 $363,884.04 $376,729.15 $390,027.69 $403,795.66 $418,049.65 $432,806.80 $6,351,110.63
$12,833,292.99
$196,037.96 $205,839.86 $216,131.86 $226,938.45 $238,285.37 $250,199.64 $262,709.62 $275,845.10 $289,637.36 $304,119.23 $319,325.19 $335,291.45 $352,056.02 $369,658.82 $388,141.76 $407,548.85 $427,926.29 $449,322.61 $471,788.74 $495,378.17 $6,482,182.35
$223,890.68 $231,794.02 $239,976.35 $248,447.51 $257,217.71 $266,297.50 $275,697.80 $285,429.93 $295,505.61 $305,936.95 $316,736.53 $327,917.33 $339,492.81 $351,476.91 $363,884.04 $376,729.15 $390,027.69 $403,795.66 $418,049.65 $432,806.80 $6,351,110.63
T
11410 Kingsway NW, Edmonton, AB
In accordance with your request by way of a contract dated June 14, 2021 and as per the terms of
reference (TOR) provided herein, I have provided an opinion of the current market value on an all-cash
basis of the fee simple interest in the subject property as at the effective date of November 18, 2021. The
AF
intended user of this report is The City of Edmonton. The intended use is to provide information for
planning purposes and no other use. No additional intended users are identified or intended by the
author.
This Appraisal Report and Appendices must be read as a whole as sections taken alone may be
misleading and lead the reader to an incorrect conclusion. Information provided by the client and
collected through market research and analyses are stored in the working file. This assignment has been
completed in accordance with the Scope of Work as outlined in Section 1.2.
As per the Terms of Reference for this assignment, we have been asked to value the subject property
R
under several different scenarios, the first being the As Is market value. The other scenarios involve
redevelopment scenarios based on information as provided by the client.
Subject to the Ordinary Assumptions and Limiting Conditions in Appendix A, it is my opinion that the
current market value of the fee simple interest in the subject property, effective November 18, 2021, is:
D
As Is Market Value Estimate: $2,900,000
Redevelopment Scenario 1A: $5,300,000
Redevelopment Scenario 1B: $7,100,000
Redevelopment Scenario 2A: $6,400,000
Redevelopment Scenario 2B: $8,200,000
Redevelopment Scenario 3A: $16,400,000
DRAFT v.1 - December 13, 2021
Redevelopment Scenario 3B: $17,900,000
I estimate that an exposure time of 9 to 12 months would have been required prior to the effective date to
sell the subject property at its current market value. Should you have any questions, please contact
Angela Barron, AIC Candidate Member or Mike deJong, AACI at your convenience.
DRAFT
Altus Group Limited
5.0 Value (Appraisal) Additions
Address 11410 Kingsway NW Site Area 4.88 ac Effective Date November 18, 2021
T
upon a total of 128 surface
Property Class Hangar / Warehouse parking stalls
Redevelopment Scenario 1B Market Value Estimate: $7,100,000
T
Net Leasable Area 81,913 sf (7,610 m²), as per Zoning DC1
information provided by the Redevelopment Scenario 2 Valuation Reconciliation
AF client
Municipal Historic Resource
AF
Year Built 1941 Condition Dated and in poor physical
condition Income Approach Capitalization Rate
R
Effective Date November 18, 2021
D
Direct Comparison $2,900,000 Unit Value $35.00 per sf
Approach Income Approach Capitalization Rate
As Is Market Value Estimate: $2,900,000 Redevelopment Scenario 3A Market Value Estimate: $16,400,000
Redevelopment Scenario 3B Market Value Estimate: $17,900,000
CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB i City of Edmonton | Hangar 14 Investment Study | February 11, 2022 58
CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB
5.0 Value (Appraisal) Additions
DRAFT v.1 - December 13, 2021
Economic Summary
5.3 Economic Summary
T
AF
R
D
Source: Altus Group Economic Consulting
► Future residential community of Blatchford abutting the subject parcel ► Overall, the subject involves a former airport hangar, with a total
along the subject’s north and east boundaries.
T
rentable area of 81,913 sf. Currently, the subject is owner-user
occupied and operates as an Airport Museum.
► Ceiling height of 29 ft and clear height of 19 ft
► The subject is in poor to fair physical condition and is nearing the end
T
► Physically, the subject is in fair to poor condition. The subject was built of its useful life. It requires major renovations and repair; however, this
in 1941 and is nearing the end of its useful life. is complicated by its designation as a Historical Resource, which may
AF ► Multiple components of deferred maintenance exist, including the
heating system which has sub-par functionality. A significant amount of
be regarded as a deterrent to potential investors, as renovations
and/or demolition is restricted by this designation.
AF
capital investment is required to bring the subject up to an average ► The subject improvements no longer support the highest and best use
state of condition and repair. of the site; whereby the highest and best use as vacant land would be
► The subject involves a former airport hangar and currently functions as for the development of a commercial project.
a large open warehouse facility. However, it is lacking typical industrial
user requirements such as overhead doors and dock loading doors.
R
Historical Resource, one of the site-specific bylaws, bylaw 19628,
imposes limitations on loading and storage areas.
D
D
► As vacant land, the subject presents an opportunity for general
business or industrial business use.
1
Appendix
61 City of Edmonton | Hangar 14 Investment Study | February 11, 2022
Energy Model
Miscellaneous Miscellaneous
Lights
7.1% 8.1%
89.8% 91.9%
Space Space
heating heating
Miscellaneous
Mechanical Miscellaneous
equipment Mechanical
equipment
Lights
6%
13%
9.1%
Lights
15.6%
71.4%
84.8% Space
heating
Space
heating
$10,000
Space Heating Lights Mechanical Equipment Hot Water
65 City of Edmonton | Hangar 14 Investment Study | December 13 2021 $-
Existing Option 1a/2a Option 2a/2b Option 3
16%
Lights 100% $ 20,971 $ 11,520 $ 11,520 $ 10,703 $70,000
13%
Mechanical 90%
Equipment $ 8,911 $ 7,556 $ 7,599 $ 8,955 $60,000
Hot Water 80%
0% $ 56 $ 16 $ 16 $ 16
70% $50,000
60%
$40,000
50%
40% $30,000
30% $20,000
20%
10% $10,000
0% $-
Existing Option 1a/2a Option 2a/2b Option 3 Existing Option 1a/2a Option 2a/2b Option 3
Space Heating Lights Mechanical Equipment Hot Water Space Heating Lights Mechanical Equipment Hot Water
ionGHG
3 Tonnes Existing Option 1a/2a Option 2a/2b Option 3
5,661
Space Heating
Cost
266
($) 218 108 49
GHG Tonnes
10,703
Lights $70,000 27 15 15 14 350
8,955
Mechanical$60,000
Equipment 11 10 10 12 300
16Water
Hot 0 0 0 0
$50,000 250
$40,000 200
$30,000 150
$20,000 100
$10,000 50
$- -
Existing Option 1a/2a Option 2a/2b Option 3 Existing Option 1a/2a Option 2a/2b Option 3
Space Heating Lights Mechanical Equipment Hot Water Space Heating Lights Mechanical Equipment Hot Water
ion 3
49
GHG Tonnes
14 350
12 300
0
250
200
150
100
50
GEC Architecture
14055 West Block Dr NW, Unit 310
Aviation Museum Investment Study Edmonton AB T5N 1L8
Edmonton, Alberta
Attention: Mr. Bob Stirling
Dear Bob,
We submit for your review the Cost Estimate for the Aviation Museum Investment Study, in accordance
with the terms of our engagement.
Please note that this estimate in general includes all direct and indirect construction costs, general
Prepared for:
conditions, as well as contractor’s overheads and profit. The estimate also addresses the following
GEC Architecture contingencies and allowance values, detailed within the body of this report.
14055 West Block Dr. NW, Unit310
Edmonton AB T5N 1L8 - Project contingency has been included.
- Escalation of construction costs has been included
- Phasing contingency has been excluded
Please note that this report is not intended for general circulation, publication or reproduction for any
other person or purpose without prior express written permission to each specific instance. Furthermore,
Prepared by:
this report was written for the exclusive use of GEC Architecture and the City of Edmonton and is not to
ALTUS GROUP LIMITED
be relied upon by any other party. Altus Group Limited does not hold any reporting responsibility to any
Suite 780, 10180-101st Street NW other party.
Edmonton, Alberta T5J 3S4
Phone: 780.424.4244 Should you have any questions related to this report please do not hesitate to contact Curtis Cameron at
Fax: 780.424.9423 the address listed below.
Yours truly,
Research, Valuation & Advisory │ Cost Consulting │ Realty Tax Consulting │ Geomatics │ ARGUS Software
10180 - 101 Street NW, Suite 780, Edmonton, AB T5J 3S4 Canada T 780.424.4244 F 780.424.9423
www.altusgroup.com
Aviation Museum Investment Study Aviation Museum Investment Study Report Date: February 5, 2022
Edmonton, Alberta Report Date: February 5, 2022 Edmonton, Alberta
2 Project Details.......................................................................................................................... 1 The scope of work for this Investment Study was the estimate for the following Options.
6 General Statement of Liability……………………………………………………….……. 6 Within the executive summary appendix, there are two summaries; 1) Summarizing the options noted
above and 2) Summarizing each of the options as an initial capital project.
Appendices
Appendix A – Executive Summary The Cost Estimate is intended to provide a realistic budget for the provided scope. The estimate reflects
Appendix B – Capital Cost Summary our opinion as to the fair market value for the construction of this proposed project and is not intended to
Appendix C – Operation and Maintenance Summary predict the lowest bid. Of note the City of Edmonton provided the discount rate utilized in this report,
Appendix D – Discounted Cashflow Summary 3.53%.
Appendix E – Option 1A and 2A
Appendix F – Option 1B and 2B The estimate includes all direct construction costs, which excludes soft costs and FF&E, consistent with
Appendix G – Option 3 our understanding of the requirements. Certain inclusions, exclusions and qualifications may apply;
Appendix H – Maintenance Model please refer to Section 4.1 & 4.2 and the details contained within the Appendices.
Appendix I – Documentation
2 Project Details
2.1 General Information
From the information provided, we have assumed quantities from information provided and applied unit
rates for the specific item of work based on historical and current cost data for this type of project. As
design information was limited, we made design assumptions based upon our experience on projects of a
similar type, size, and standard of quality.
We confirm that for the development of this report, we reviewed the documents provided by the owner
and inquired if necessary.
2.2 Location
Aviation Museum Investment Study Report Date: February 5, 2022 Aviation Museum Investment Study Report Date: February 5, 2022
Edmonton, Alberta Edmonton, Alberta
The rates used and developed for this estimate where applicable include labour and material, equipment, The effective use of contingencies in construction cost planning requires a clear understanding of
and subcontractor’s overheads and profit. Pricing developed for this project is based upon our firms and estimating risks in both a project specific and general construction market sense. The appropriate level of
indeed teams experience with similar projects, and/or quotes provided by subcontractors as noted within contingency is dependent on the amount of information available, knowledge of the design teams’
the estimate. methods and philosophy, the timing of the estimate preparation relative to the project design and
construction schedule, and the anticipated complexity of the construction work. For this project,
2.4 Environmental Sustainability contingencies for the present and future have both been included.
The sites will be remediated after demolition and all demolished materials will be disposed of in an 3.2 Project Contingency
environmental responsible manner. Each option carries a very detailed set of assumptions that can be
found within the prime consultant reporting. Project contingency has been included in this estimate for design and pricing changes prior any tender at
15% for options 1 and 2; and 10% for option 3.
2.5 Taxes
3.3 Escalation Allowance
The estimate excludes the Goods and Services Tax (GST).
Construction escalation to the anticipated tender date has been included from this report. This allowance
2.6 Fees and General Requirements addresses the anticipated changes in construction costs due to labour, equipment and material increases
between the date of this estimate and the anticipated tender date for the project. For immediate work we
The fee and general requirements included are included as a percentage of the hard construction cost. have include 0%; 2-3 years 9%; 4-5 years 15%; 6-10 years 24%; 11-20 years 42% and 21-40 years 67%.
The general requirements include the cost associated with bonding, insurance, and permit fees. These amounts are considered compounded values.
We have assumed that the project would be completed with a standard City of Edmonton form of Construction contingency has been included within this report. The renovation options carry 10%, while
contract or similar. We have assumed a minimum of five bids for all sub-trade categories to establish the new build option is 5%. This allowance typically is retained outside of the hard construction cost for
competitive bidding and tender results. The estimate is a determination of fair market pricing and not a change orders that may occur during the construction phase of the project.
prediction of lowest bid in any trade category.
3.5 Phasing Allowance
2.8 Schedule / Phasing
No specific phasing allowance was contemplated for this estimate; however, the varied scope delivery
All the options take place over a 40-year time period. Options 1 and 2 are heavily phased, Option 3 was considered when compiling the estimate for each of the options.
assumed the initial new build is completed in a single phase, future renovations are phased as required. It
is understood that the works cannot be combined as varying scopes are being completed throughout the
40-year study period.
The unit rates in our estimate are based on construction activities occurring during normal working hours
and proceeding within a non-accelerated schedule. The estimate does not include for decanting of any
personnel or equipment before or after construction.
Aviation Museum Investment Study Report Date: February 5, 2022 Aviation Museum Investment Study Report Date: February 5, 2022
Edmonton, Alberta Edmonton, Alberta
5 Project Statistics
4 Project Description and Scope Assumptions
Gross Floor Area / Project Statistics
Inclusions, Allowances and Assumptions
Hanger 14 GFA – 8,593m2 for all 3 options
4.1 Exclusions
Option 1 and 2 – 5,866 m2 Warehouse and 2,727 m2 Office; Total GFA 8,593 m2
The following are excluded from the estimate:
Goods and Services Tax (GST) Interest/finance charges Option 3 – 5,329 m2 Warehouse and 3,234 m2 Office; Total GFA 8,593 m2
Acceleration Premium Extensive winter construction
Legal fees Market (non-competitive) allowance
Realty taxes and levies, if applicable Marketing/promotion
Hazardous Materials
6 General Statement of Liability
Probable Costs and Ongoing Cost Control
The estimate is based on a building Gross Floor Area supplied and verified with the prime consultant. Altus Group Limited does not guarantee that tenders or actual construction costs will not vary from this
estimate. Acute market conditions, proprietary and/or sole source specifications, or reduced competition
4.2 Scope Review among contractors will cause tenders to vary from reasonable estimates based on normal and abnormal
competitive conditions. In particular the COVID-19 pandemic has the potential to materially impact the
Altus Group Limited recommends the owner and/or design team review the cost estimate report project construction budget beyond the estimate provided herein and outside of “standard“ project
including allowances, assumptions, exclusions, and contingencies to ensure the appropriate design intent contingencies. This estimate does not include any potential COVID-19 related impact costs. We
has been accurately captured within the report. recommend that the client assess each project individually and apply an appropriate contingency if
deemed necessary.
Assumptions included in the maintenance and operations model:
Assumed assets and general allowances included in each of the line items
Assumption that the identified assets in the capital plan have undergone
refurbishment/replacement works
Reactive maintenance generally assumed at 30% of planned activity; there would be a premium
that would need to add related to reactive maintenance for assets that have a delayed
refurbishment schedule
Materials allowance included at 10% of subcontract cost
Overall contingency included at 10% and for the new construction Option 3, the assumptions
would still be relevant but could actually increase however we have maintained the same
assumptions throughout the options
Operational activity has been excluded as they are heavily influenced by operational need and
strategy (for the likes of cleaning, snow removal, pest control, landscaping contractor etc.) and
the other operations and maintenance assume to be unchanged across options.
Utility data was provided by the consultant team separately
Utility escalation (short term) was provided by the consultant team, long term uses 5% per
annum
Operations and Maintenance uses 5%, 4% and 3.75% and returns to an inflationary average of
3.53% for the remaining years
Appendix A
Executive Summary
Investment Options
GFA: 8593 m2
Ref Description OPTION 1A/2A $/m2 OPTION 1B/2B $/m2 OPTION 3 $/m2
Investment Options
GFA: 8593 m2
Description OPTION 1A/2A $/m2 OPTION 1B/2B $/m2 OPTION 3 $/m2
Appendix B
Capital Cost Summary
C New facility zero-emission warehouse $31,534,825.00 $0.00 $4,516.28 $711,909.30 $1,077,982.53 $33,329,233.11
February 5, 2022
21-40 Years
Year 22 Year 23 Year 24 Year 25 Year 26 Year 27 Year 28 Year 29 Year 30 Year 31 Year 32 Year 33 Year 34 Year 35 Year 36 Year 37 Year 38 Year 39 Year 40 Year 41 40-YEAR TOTAL
2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 2058 2059 2060 2061
Rehabilitation Capital Costs (1A / 2A)
Rehabilitation capital costs $10,888,169.32
Architectural $8,354,524.43 $8,354,524.43
Structural $0.00 $0.00
Heritage $2,532,875.18 $2,532,875.18
Mechanical $769.71 $769.71
Electrical $0.00 $0.00
Appendix C
Maintenance and Operations Cost Summary
February 5, 2022
21-40 Years
Year 22 Year 23 Year 24 Year 25 Year 26 Year 27 Year 28 Year 29 Year 30 Year 31 Year 32 Year 33 Year 34 Year 35 Year 36 Year 37 Year 38 Year 39 Year 40 Year 41 40-YEAR TOTAL
2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 2058 2059 2060 2061
$17,221,472.22
$328,747.86 $345,185.25 $362,444.51 $380,566.74 $399,595.08 $419,574.83 $440,553.57 $462,581.25 $485,710.31 $509,995.83 $535,495.62 $562,270.40 $590,383.92 $619,903.12 $650,898.27 $683,443.19 $717,615.35 $753,496.11 $791,170.92 $830,729.46 $10,870,361.59
$223,890.68 $231,794.02 $239,976.35 $248,447.51 $257,217.71 $266,297.50 $275,697.80 $285,429.93 $295,505.61 $305,936.95 $316,736.53 $327,917.33 $339,492.81 $351,476.91 $363,884.04 $376,729.15 $390,027.69 $403,795.66 $418,049.65 $432,806.80 $6,351,110.63
$14,106,512.36
$234,543.41 $246,270.58 $258,584.11 $271,513.32 $285,088.98 $299,343.43 $314,310.61 $330,026.14 $346,527.44 $363,853.81 $382,046.51 $401,148.83 $421,206.27 $442,266.59 $464,379.91 $487,598.91 $511,978.86 $537,577.80 $564,456.69 $592,679.52 $7,755,401.73
$223,890.68 $231,794.02 $239,976.35 $248,447.51 $257,217.71 $266,297.50 $275,697.80 $285,429.93 $295,505.61 $305,936.95 $316,736.53 $327,917.33 $339,492.81 $351,476.91 $363,884.04 $376,729.15 $390,027.69 $403,795.66 $418,049.65 $432,806.80 $6,351,110.63
$12,833,292.99
$196,037.96 $205,839.86 $216,131.86 $226,938.45 $238,285.37 $250,199.64 $262,709.62 $275,845.10 $289,637.36 $304,119.23 $319,325.19 $335,291.45 $352,056.02 $369,658.82 $388,141.76 $407,548.85 $427,926.29 $449,322.61 $471,788.74 $495,378.17 $6,482,182.35
$223,890.68 $231,794.02 $239,976.35 $248,447.51 $257,217.71 $266,297.50 $275,697.80 $285,429.93 $295,505.61 $305,936.95 $316,736.53 $327,917.33 $339,492.81 $351,476.91 $363,884.04 $376,729.15 $390,027.69 $403,795.66 $418,049.65 $432,806.80 $6,351,110.63
Appendix D
Discounted Cashflow Summary
B
Total each year $ 6,270,265.14 $ 6,281,810.14 $ 4,048,202.95 $ 4,063,792.70 $ 1,224,913.96 $ 1,240,551.85 $ 440,180.81 $ 456,133.54 $ 472,252.07 $ 488,542.26 $ 503,321.79 $ 1,143,967.22 $ 1,156,753.30 $ 1,170,096.55 $ 1,184,021.95 $ 1,198,555.60 $ 1,213,724.80 $ 1,229,558.11 $ 1,246,085.41 $ 1,263,337.94 $ 1,281,348.41
Discount Rate 3.53%
Year 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Present Value $ 6,270,265.14 $ 6,067,623.05 $ 3,776,850.98 $ 3,662,122.80 $ 1,066,205.04 $ 1,042,998.90 $ 357,465.25 $ 357,790.26 $ 357,803.15 $ 357,524.83 $ 355,781.69 $ 781,061.49 $ 762,862.34 $ 745,351.14 $ 728,505.37 $ 712,303.33 $ 696,724.05 $ 681,747.29 $ 667,353.52 $ 653,523.90 $ 640,240.22
NPV - Option 1B/2B $ 39,322,855.49
NPV - Option 1B/2B 20 Years $ 30,742,103.73
NPV - Option 1B/2B 40 Years $ 8,580,751.76
C
Total each year $ 31,666,794.00 $ 142,487.40 $ 156,340.39 $ 170,082.26 $ 185,980.99 $ 199,771.00 $ 353,839.42 $ 367,944.26 $ 382,214.91 $ 396,657.22 $ 409,866.06 $ 386,409.55 $ 398,013.67 $ 410,115.89 $ 422,738.19 $ 435,903.58 $ 449,636.11 $ 463,960.92 $ 478,904.29 $ 494,493.70 $ 510,757.89
Discount Rate 3.53%
Year 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Present Value $ 31,666,794.00 $ 137,629.09 $ 145,860.86 $ 153,271.13 $ 161,883.91 $ 167,958.26 $ 287,348.49 $ 288,614.76 $ 289,586.24 $ 290,281.55 $ 289,720.89 $ 263,827.15 $ 262,484.36 $ 261,243.69 $ 260,102.47 $ 259,058.13 $ 258,108.17 $ 257,250.22 $ 256,481.99 $ 255,801.27 $ 255,205.96
NPV - Option 3 $ 42,085,946.40
NPV - Option 3 20 Years $ 36,468,512.60
NPV - Option 3 40 Years $ 5,617,433.80
February 5, 2022
21-40 Years
Year 22 Year 23 Year 24 Year 25 Year 26 Year 27 Year 28 Year 29 Year 30 Year 31 Year 32 Year 33 Year 34 Year 35 Year 36 Year 37 Year 38 Year 39 Year 40 Year 41
2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 2058 2059 2060 2061
$ 1,097,047.00 $ 1,121,387.74 $ 1,146,829.33 $ 1,173,422.72 $ 1,201,221.25 $ 1,230,280.79 $ 1,260,659.84 $ 1,292,419.65 $ 1,325,624.39 $ 1,360,341.25 $ 1,396,640.62 $ 1,434,596.20 $ 1,474,285.20 $ 1,515,788.49 $ 1,559,190.78 $ 1,604,580.80 $ 1,652,051.50 $ 1,701,700.24 $ 1,753,629.04 $ 1,807,944.73
22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41
$ 529,461.93 $ 522,756.08 $ 516,387.68 $ 510,346.75 $ 504,623.72 $ 499,209.31 $ 494,094.64 $ 489,271.09 $ 484,730.42 $ 480,464.66 $ 476,466.13 $ 472,727.46 $ 469,241.53 $ 466,001.51 $ 463,000.83 $ 460,233.14 $ 457,692.36 $ 455,372.63 $ 453,268.34 $ 451,374.05
$ 998,197.07 $ 1,017,827.58 $ 1,038,323.44 $ 1,059,723.81 $ 1,082,069.67 $ 1,105,403.91 $ 1,129,771.38 $ 1,155,219.04 $ 1,181,796.02 $ 1,209,553.74 $ 1,238,546.01 $ 1,268,829.13 $ 1,300,462.06 $ 1,333,506.47 $ 1,368,026.93 $ 1,404,091.03 $ 1,441,769.52 $ 1,481,136.44 $ 1,522,269.32 $ 1,565,249.30
22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41
$ 481,754.52 $ 474,479.56 $ 467,530.27 $ 460,896.65 $ 454,569.06 $ 448,538.19 $ 442,795.08 $ 437,331.08 $ 432,137.86 $ 427,207.38 $ 422,531.91 $ 418,103.97 $ 413,916.39 $ 409,962.23 $ 406,234.83 $ 402,727.76 $ 399,434.82 $ 396,350.07 $ 393,467.75 $ 390,782.37
$ 601,471.44 $ 619,176.68 $ 637,651.00 $ 656,928.76 $ 677,045.88 $ 698,039.93 $ 719,950.21 $ 742,817.83 $ 766,685.76 $ 791,598.98 $ 817,604.51 $ 844,751.57 $ 873,091.62 $ 902,678.52 $ 933,568.60 $ 965,820.79 $ 999,496.77 $ 1,034,661.07 $ 1,071,381.18 $ 1,109,727.77
22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41
$ 290,284.95 $ 288,640.91 $ 287,117.80 $ 285,712.43 $ 284,421.71 $ 283,242.69 $ 282,172.50 $ 281,208.42 $ 280,347.82 $ 279,588.18 $ 278,927.06 $ 278,362.14 $ 277,891.18 $ 277,512.04 $ 277,222.67 $ 277,021.10 $ 276,905.43 $ 276,873.87 $ 276,924.68 $ 277,056.21
Appendix E
Option 1A and 2A
A10 Foundations
A1010.01 Wall Foundations
A1010.02 Column Foundations
A1030.02 Structural Slabs on Grade IR
A1030.04 Slab on Grade Trenches
A10 Foundations SUBTOTAL: $0 $0 $0 $0 $0 $0
B10 Superstructure
B1010.05 Mezzanine Construction
B1020.01 Roof Structural Frame PM
Main entrance front canopy is clad in prefinished metal (fascia and low parapet
cap flashing) with flat membrane roofing and prefinished metal interlocking
B1020.04 Canopies PM 10 Cost in heritage
soffit slats. Underside of canopy at joint with aluminum door frame shows signs
of water ingress (rust staining on metal angeltrim/closure)
Prefin. Standard Vert. Batten Metal cladding with green PVDF or similar coating
on framed and sheathed infill (with curtain wall/aluminum strip window) of
B2010.01.06.03 Metal Siding PM PM hangar doors between GL 2 & 3 on S. Elevation. Coating system is badly faded 10 Cost in heritage
from UV exposure but metal substrate shows no obvious signs of corrosion or
misalignment.
Shingle/shake siding mostly intact, aligned, and free of major defects other than
B2010.01.06.04 Wood Siding PM PM coatings failures. Old asbestos cement shakes applied to parachute tower 10 Cost in heritage
appear to be intact but should be investigated further.
B2010.01.11 Joint Sealers IR IR Deteriorated throughout in virtually all locations and applications 0
On wood siding (peeling and blistering observed) and several other substrates
B2010.01.13 Paints IR IR on building exterior (metal on hangar doors and other exterior doors, frames, 0-5 Cost in heritage
and windows)
B2010.02.05 Wood Framing No exterior wood framing was observed
Where observed, insulation was of poor to fair quality , discontinuous, and
showing signs of moisture damage and soiling via air and moisture
B2010.03.03.01 Batt Insulation IR IR 0-10 Cost in heritage
ingress/exfiltration through poor quality AVB. Further investigation
recommended.
Framed interior GWB walls: varied in quality, condition (surface and coating
B2010.04.02 Gypsum Board CB integrity), age and extents depending on location in building.
0-20 Cost in heritage
B2010.07.04 Awnings IR IR Frame may be salvageable but fabric covering is marginal 0-3 Cost in heritage
Refers to wood soffits and possibly wood door trim, frames, fascia and corner
battens. Where observed on each elevation appeared to be in mostly fair
B2010.09.01 Finish Carpentry PM condition but further investigation recommended where coatings failures have
0-10 $ 46,488.75 $ 46,488.75 $ 46,488.75 $ 46,488.75
occurred and bare wood is showing.
U/S of exterior canopy at SE corner of building: soffit is clad in sagging, stained,
B2010.09.05 Gypsum Board IR IR 0
moisture-affected interior-grade GWB
B20 Exterior Enclosures SUBTOTAL: $0 $46,489 $46,489 $46,489 $0 $46,489
B2020 Exterior Windows
S. Elevation: Unpainted HM door with painted steel frame set into hangar door
at Youth and Cultural Center entrance has inset georgian wire lite and thumb
latch lever and pull handle hardware. Function not observed. Sprinkler Rm.
door is painted HM in PSF set into original wood dooor frame. Coating is badly
B2030.02.01 Metal Doors and Frames IR IR marred and faded/chalked and steel door skin is damaged with a riveted patch. 0-5 $ 17,629.50 $ 17,629.50
Hardware is old round nob type with latch protector.
W. elevation: two HM doors with PSF's btw. GL's 7 & 9 are missing hardware
(auto closer, sweeps and seals/weather stripping. exit devices and outside
hardware are not to current standards
There are 2 steel egress doors and frames at the west elevation that appear to
be original. Condition of doos and frames vary somewhat but both require
B2030.02.01.01 Steel Doors and Frame IR CB significant work to upgrade to current exit function and energy performance 5 Cost in heritage
while retaining important heritage characteristics. Further investigation and
study required.
E. Elevation: 2 wood doors and frames with oudated hardware and failing
B2030.02.02.01 Wood Doors IR IR weatherstripping. Refer to ERA comments on other doors and locations. 0-5 Cost in heritage
Replace with HMD in PSF
B2030.03.05 Hangar Doors IR CB Refer to ERA comments 5
B2030 Exterior Doors SUBTOTAL: $5,000 $17,630 $6,219 $1,449 $17,630 $12,668
C10 Interior Construction
1. Painted, ribbed terracotta hollow units (structural clay block wall) observed at
N & S interior walls of Paint Storage Room (R9). Possibly original? Need to
confirm continuity and FRR of surrounding wall, floor, and ceiling joints and of
ceramic block material.
C1010.01.03 Unit Masonry Assemblies PM 2. Painted CMU partitions/demising walls observed at select portions of east
25 $ 40,753.13
wall of Paint Storage Rm. and Woodworking Shop (R4) along GL's 1 & 2
respectively. Complete extents TBC as some may be behind furring and GWB
assemblies. FRR and other code-related function TBC.
C2020.08 Stair Railings and Balustrades PM CB Per description in FCAR 2017. 5 $ 2,898.00
C20 Stairs SUBTOTAL: $0 $0 $8,694 $0 $0 $0
C30 Interior Finishes
C3010.02 Wall Paneling PM CB Per description in FCAR 2017. Further code review recommended. 5 $ 85,491.00 $ 85,491.00 $ 85,491.00
C3010.06 Tile Wall Finishes PM PM Per description in FCAR 2017. 10 Cost in heritage
C3010.11 Interior Wall Painting PM PM Per description in FCAR 2017. 10 Cost in heritage
Per description in FCAR 2017. Note deficiencies/damaged floor coatings in west
C3020.01 Concrete Floor Finishes IR IR 0 $ 172,672.50 $ 172,672.50 $ 172,672.50 $ 172,672.50
side of facility.
C3020.07 Resilient Flooring PM PM Per description in FCAR 2017 WRT locations and condition of VCT 0-5 $ 4,516.05
Per description in FCAR 2017 WRT locations and condition of carpet except at
C3020.08 Carpet Flooring PM R3 where immediate replacement is recommended
5 $ 56,511.00 $ 56,511.00 $ 56,511.00 $ 56,511.00
Not observed (except for drone aerial photos). Ponding observed at multiple
B3010.04.04 Modified Bituminous Membrane Roofing CB locations in photos but time to latest rain event is unknown as is avg. depth of $ 349,533.55 $ 349,533.55 $ 349,533.55 $ 349,533.55 $ 3,434,960.46 $ 3,434,960.46
ponds
B3010.08.01 Sheet Metal Flashing and Trim CB CB Per description in FCAR 2017. 7 $ 9,892.44 $ 9,892.44 $ 95,513.25
B3010.08.02 Metal Gutters and Downspouts PM PM Per description in FCAR 2017. Should consider alternates to discharge to grade. 5 $ 2,028.60 $ 2,028.60 $ 2,028.60 $ 2,028.60 $ 17,289.89
Included in Included in
B3010.08.03 Joint Sealers PM Not observed $ 15,929.94
B3010.04.04 above B3010.04.04 above
B30 Roofing SUBTOTAL: $ 361,454.59 $351,562 $361,455 $367,492 $3,547,764 $3,434,960
TOTAL CONSTRUCTION COST $ 684,127.09 $ 1,901,811.02 $ 837,300.15 $ 892,281.25 $ 4,060,628.70 $ 4,351,314.81
DESIGN AND PRICING CONTINGENCY $ 102,619.06 $ 285,271.65 $ 125,595.02 $ 133,842.19 $ 609,094.30 $ 652,697.22
CONSTRUCTION CONTINGENCY $ 68,412.71 $ 190,181.10 $ 83,730.02 $ 89,228.12 $ 406,062.87 $ 435,131.48
ESCALATION CONTINGENCY $ - $ 171,162.99 $ 125,595.02 $ 214,147.50 $ 1,705,464.05 $ 2,915,380.92
TOTAL COST $ 855,158.86 $ 2,548,426.77 $ 1,172,220.21 $ 1,329,499.06 $ 6,781,249.92 $ 8,354,524.43
A10 Foundations
Some cracking and exposure of corroded steel wire mesh was observed
at east end of north elevation; gravel fill has been added at the east end No change from 20 Expose deteriorated portions of wall to inspect
A1010.01 Wall Foundations TBD See heritage See heritage See heritage See heritage See heritage
of the south elevation as a temporary means of covering and concealing year scope condition of structural elements.
deteriorated wall plates/footing
Structural engineer
to advise The current trusses require extensive repair
and rehabilitation. The extent of which are
WEC: One of the carefully documented in the BPTEC report.
first steps could be to Not only will individual connections (546) and
Existing Douglas fir Warren trusses, steel bolt and split ring connectors, re-engage BPTEC members (332+) need to be replaced or
roof deck, built-up braced wood columns, are character defining elements and consult them reinforced, but all of the post-tensioned wires
and should be conserved as part of any future repair programme. There about additional will need replacement which will require all
Cost included in
are numerous occasions of severe splitting and cracking of truss dead loads and drift trusses to be shored. Rigid insulation on the
B3010.04.04 Modified
B1020.01 Roof Structural Frame members and diagonal wall bracing members. Numerous wood straps 0 associated with solar See heritage See heritage roof will likely increase the snow load on the
Bituminous Membrane
have been added to the underside of roof deck to cover gaps and cracks. panels. This will Roofing roof and could contribute to higher humidity in
Steel fasteners have generally corroded. There has been apparent determine the the building which would deteriorate the
movement at numerous splice connections, where horizontal bracing maximum limit the trusses. Additionally, future development of
members between trusses are sagging. trusses can take, the surrounding area could increase the snow
even with load on the roof. If solar panels are considered
reinforcing. This will to be added to the roof, this would also
give a clearer picture increase the snow load by adding area of snow
for costing moving drift.
forward.
East canopy cement board soffit has significant water damage, leading to
widespread staining and deformation of panels; south canopy is metal
siding and in fair condition; several wood soffit boards above the hangar Existing joists need to be exposed and
B1020.04 Canopies TBD See heritage See heritage See heritage See heritage
doors were noted to have loosened or formed small gaps and should be reviewed for water damage.
replaced. A non-original metal clad barrel vaulted canopy on the south
elevation was heavily corroded and in poor condition.
Some cracking and exposure of corroded steel wire mesh was observed
at east end of north elevation; gravel fill has been added at the east end of
A1010.01 Wall Foundations PM $ 929.78 $ 929.78 $ 929.78 $ 929.78 $ 93,484.65
the south elevation as a temporary means of covering and concealing
deteriorated wall plates/footing
No replacement or other
Existing concrete floor slabs are original and remain in good to fair upgrades
A1030.02 Structural Slabs on Grade IR PM ● condition overall. There is cracking in various locations throughout the $ 47,092.50 recommended due to
slab, but these are minor and do not suggest ongoing movement. impact to character
defining element
Integral cast-in-place concrete floor ducts formed part of the original heat
distribution system of the building. Furture interventions should consider
A1030.04 Slab on Grade Trenches CB ● Maintenance excluded Maintenance excluded
their preservation as salvaged artifacts for potential reuse in a heritage
interpretation strategy.
A10 Foundations SUBTOTAL: $ 929.78 $ 929.78 $ 929.78 $ 929.78 $ 140,577.15 $ -
B10 Superstructure
Added as per email on
B1010.05 Mezzanine Construction $48,583.76 Nov 30, 2021
Existing Douglas fir Warren trusses, steel bolt and split ring connectors,
roof deck, built-up braced wood columns, are character defining elements
and should be conserved as part of any future repair programme. There For scope of work in
Cost included in
are numerous occasions of severe splitting and cracking of truss 2032-2041, assume
Structural engineer to B3010.04.04 Modified
B1020.01 Roof Structural Frame PM PM ● members and diagonal wall bracing members. Numerous wood straps $ 195,011.25 $ 195,011.25 repair work in favor of
advise Bituminous Membrane
have been added to the underside of roof deck to cover gaps and cracks. full replacment of roof
Roofing
Steel fasteners have generally corroded. There has been apparent trusses
movement at numerous splice connections, where horizontal bracing
members between trusses are sagging.
East canopy cement board soffit has significant water damage, leading to
widespread staining and deformation of panels; south canopy is metal
siding and in fair condition; several wood soffit boards above the hangar
B1020.04 Canopies PM IR ● $ 25,357.50 $ 2,535.75 $ 2,535.75 $ 6,592.95
doors were noted to have loosened or formed small gaps and should be
replaced. A non-original metal clad barrel vaulted canopy on the south
elevation was heavily corroded and in poor condition.
Not original. UV degradation of anodized coating observed on south Cost for access to
B2010.01.06.03 Metal Siding PM $ 3,169.69 $ 3,169.69 $ 3,169.69 $ 14,490.00
elevation metal siding is included
B2010.01.11 Joint Sealers IR IR General failure observed throughout building. $ 36,225.00 $ 36,225.00 $ 36,225.00
No double-glazing
Cost for non glazed
Hangar door steel windows show general air leakage, loss of putty upgrades
portion of hangar door
B2020.01.01 Windows - Aluminum IR ● around muntins and frames; corrosion and paint loss at muntins and $ 9,056.25 $ 9,056.25 $ 44,436.00 recommended due to
included in
frames and muntins. Several lites were observed to be cracked. impact to character
B2030.03.05
defining elements
Hangar door panels show some localized paint loss, general sheet/frame
deformation from impact near grade, corrosion at base/bottom rails,
hardware and fasteners. While the top-hung rolling doors appear to
Cost for glazed portion
remain operational, there is significant air leakage from lack/failure of
B2030.03.05 Hangar Doors IR IR ● $ 9,660.00 $ 9,660.00 $ 16,905.00 $ 9,660.00 of hangar door included
weatherstripping and air seals, putty, caulking, etc. Temporary plugs and in B2020.01.01
tape have been applied to seal gaps. Organic growth was generally
observed at the base from lack of positive drainage away from the
building.
C1010.04 Interior Balustrades and Screens, Interior Railings IR No impact to character defining elements
Paint finishes on the interior roof structure and timber wall framed
elements are in fair condition with many areas exhibiting water staining
and localized loss of paint. Water staining is particularly evident at the east
C3010.11 Interior Wall Painting CB ● $ 56,994.00 $ 56,994.00
and west walls, and is generally present on truss members. There is
general flaking and peeling of the paint coating on horizontal board
sheathing in restoration area
Roof not observed. Previous site photos from 2017 condition assessment Cost included in
B3010.04.04 Modified Bituminous Membrane Roofing CB CB
have been referenced for this study. architectural
Roof not observed. Previous site photos from 2017 condition assessment Cost included in
B3010.08.01 Sheet Metal Flashing and Trim CB PM
have been referenced for this study. architectural
Cost included in
B3010.08.02 Metal Gutters and Downspouts PM PM No impact to character defining elements
architectural
Roof not observed. Previous site photos from 2017 condition assessment Cost included in
B3010.08.03 Joint Sealers PM IR
have been referenced for this study. architectural
B30 Roofing SUBTOTAL: $ - $ - $ - $ - $ - $ -
D20 PLUMBING
Urinals No impact to character defining elements (See C1030.14 above) (See C1030.14 above)
Lavatories No impact to character defining elements (See C1030.14 above) (See C1030.14 above)
Sinks No impact to character defining elements (See C1030.14 above) (See C1030.14 above)
Mechanical engineer to
Pipes and Tubes: Domestic Water No impact to character defining elements
advise
Mechanical engineer to
Domestic Water Heaters No impact to character defining elements
advise
Mechanical engineer to
Waste and Vent Piping No impact to character defining elements
advise
SUBTOTAL: $0 $0 $0 $0 $0 $0
D30 Heating Ventilating and Air Conditioning (HVAC)
Gas Supply Systems
Integral cast-in-place concrete floor ducts formed part of the original heat
distribution system of the building. Future interventions should consider Mechanical engineer to Cost included in
Ducts: Air Distribution IR CB ●
their preservation as salvaged artifacts for potential reuse in a heritage advise mechanical
interpretation strategy.
Electric and Electronic Controls No impact to character defining elements
No visible signs of deterioration from excess relative humidity inside
Other Special HVAC Systems and Equipment CB CB No cost required
building.
SUBTOTAL: $0 $0 $0 $0 $0 $0
D40 Fire Protection
Wet-Pipe Fire Sprinkler Systems
Fire Extinguisher, Cabinets and Accessories
SUBTOTAL: $0 $0 $0 $0 $0 $0
D5010 Electrical Service and Distribution
D5010.01.01 Transformers IR No impact to character defining elements
D5010.03.07 Enclosed Switches and Circuit Breakers IR No impact to character defining elements
D5010.03.09 Enclosed Bus Assemblies IR No impact to character defining elements
Several decommissioned electrical panels appear to be original to the
BCATP period and of historic significance. Future electrical upgrades No cost required as per
D5010.05.01 Switchboards, Panelboards and Control Centers IR CB ●
should consider their preservation as salvaged artifacts for potential reuse electrical engineer
in a heritage interpretation strategy.
D5010.05.02 Enclosed Switches and Circuit Breakers IR No impact to character defining elements
D5010 Electrical Service and Distribution SUBTOTAL: $0 $0 $0 $0 $0 $0
D5020 Lighting and Branch Wiring
D5020.01 Electrical Branch Wiring IR No impact to character defining elements
D5020.01.02 Conductors and Cables No impact to character defining elements
D5020.01.03 Wiring Devices No impact to character defining elements
D5020.02.02 Interior Luminaries IR No impact to character defining elements
D5020.02.03 Emergency Lighting No impact to character defining elements
D5020.02.03 Exit Lighting IR No impact to character defining elements
D5020.02.05 Special Purpose Lighting No impact to character defining elements
D5020.03.01 Exterior Luminaries No impact to character defining elements
D5020 Lighting and Branch Wiring SUBTOTAL: $0 $0 $0 $0 $0 $0
D5030 Communications and Security
D5030.01.03 Smoke Alarm No impact to character defining elements
D5030.02 Security Access and Surveillance No impact to character defining elements
D5030.04 Voice and Data Systems IR No impact to character defining elements
D5030 Communications and Security SUBTOTAL: $0 $0 $0 $0 $0 $0
2-3 Years Immediate 2-3 Years 4-5 Years 6-10 Years 11-20 Years 21-40 Years
D20 PLUMBING
Water Closets (floor mount, tank type assumed) Appears in fair condition. 15 $ 17,551.01
Urinals Appears in fair condition. 15 $ 7,299.34
Lavatories Appears in fair condition. 15 $ 12,805.54
Rates are based on
a single per unit
Sinks Appears in fair condition. 15 $ 1,216.56
basis, as quantities
are unknown
Staff has advised that both furnaces appear to be original and parts for
repair are difficult to source. Also furnace F1 has failed and does not
contribute to the heating of the hangar. Areas are now unevenly
serviced, with areas cold and other areas overly warn. If some of the
areas that are cold should drop below the freezing temperature,
domestic water and fire water/sprinkler piping may be at risk of freezing. Cost of salvaging
This may lead to the pipes bursting and releasing water that may
Furnaces IR IR 0 $ 414,655.50 existing furnace
damage the airplanes in the facility.
Recommend: Repair or replace the non-operating furnace to ensure included
that the building has heat during the winter. Recommend replacing the
operating furnace as soon as possible.
(There is no information on the current furnaces. A guessimate on a
replacement from Engineered Air would be a Model DG650,
approximately +60,000 cfm)
Underslab ductwork
Staff has advised that there was water in the under slab ductwork that
provides air distribution to the building.
Option 1: If water in the distribution passages, recommend scoping the
Assume Option1:
underslab passages and access the condition.
Option 2: If water in the plenum directly under the furnances, this may Cost shown is for air
be from the exterior landscaping, which is not sloping away from the transfer fan.Assume
building. If that is the case, slope landscape away from building. 40 hours of video
Ducts: Air Distribution IR IR 0 $ 18,021.94
inspection for the
Airflow distribution to rooms underslab passage
Air distribution is currently no airflow to the upper floor and central main as the space scope
floor offices.
is unknown
Offices: Recommend a transfer air fan to circulate air to the offices or
provide HRV to provide airflow. (Transfer fans approximately in the 100
to 300 cfm range)
There are no transformers in the facility however, the site is fed from 3
separate services with 3 different utility transformers. We recommend
replacing these services with one new EPCOR utility service sized for the
D5010.01.01 Transformers IR IR entire facility and distribution transformers inside the facility as necessary
2 1,110,900.00
to service the existing systems. It would be recommended to bring in a
3phase 600V service and then transform down to 120/208V.
The panels as well as the breakers within them have reached the end of
D5010.03.07 Enclosed Switches and Circuit Breakers IR IR their service life and it is recommended that they be replaced.
2 318,313.91
The panels as well as the breakers within them have reached the end of
D5010.03.09 Enclosed Bus Assemblies IR IR their service life and it is recommended that they be replaced.
2 355,795.91
The panels as well as the breakers within them have reached the end of
D5010.05.01 Switchboards, Panelboards and Control Centers IR IR their service life and it is recommended that they be replaced.
2 409,261.60
The panels as well as the breakers within them have reached the end of
D5010.05.02 Enclosed Switches and Circuit Breakers IR IR their service life and it is recommended that they be replaced.
2 380,785.13
$0 $2,575,057 $0 $0 $0
The branch wiring has been modified and run with various different types
of cable and conduit throughout the space. Some of the installations do
D5020.01 Electrical Branch Wiring IR IR not appear up to code and are not to the COE standards. It is 2 230,401.87
recommended that conduit and cable be rerun when the new panel
installations are done.
The branch wiring has been modified and run with various different types
of cable and conduit throughout the space. Some of the installations do
D5020.01.02 Conductors and Cables IR not appear up to code and are not to the COE standards. It is 2 307,139.70
recommended that conduit and cable be rerun when the new panel
installations are done.
Many of the wiring devices have reached the end of their useable life and
D5020.01.03 Wiring Devices should be replaced. They are currently functional so this replacement is 5 25,357.50
not immediate.
The existing exit lighting in the facility is currently red EXIT type as well as
unlit signs. It does not adequately guide occupants along the egress path.
D5020.02.03 Exit Lighting IR IR
It is our recommendation that new green LED running man exit signs be
0 36,225.00
installed throughout the facility to illuminate the egress path per code.
It is recommended that the special purpose lighting be evaluated at the As per engineer,
D5020.02.05 Special Purpose Lighting same time as the full lighting replacement and coordinated with the new 10 existing to
lighting control system.
remian
The exterior lighting is a combination of building mounted wall packs As per engineer,
which have been upgraded to LED and pole lighting for the parking lot. It
D5020.03.01 Exterior Luminaries
was not observed on at the time of the review but is assumed that they are
10 existing to
adequate for the intended purpose. remian
$107,996 $537,542 $458,973 $0 $0
The security system appears to be a primarily CCTV system. The system As per engineer,
D5030.02 Security Access and Surveillance is not a City of Edmonton standard system but appears functioning for its 10 existing to
intended purpose.
remian
The telephone and CATV services are mounted to exposed backboards in
the facility. It is recommended that a LAN room be installed and new
D5030.04 Voice and Data Systems IR network cabling run throughout the facility. The systems have been 5 346,243.38
modified continuously throughout the years and are showing the wear
from use.
$397,956 $0 $346,243 $0 $0
Appendix F
Option 1B and 2B
A10 Foundations
A1010.01 Wall Foundations
A1010.02 Column Foundations
A1030.02 Structural Slabs on Grade IR
A1030.04 Slab on Grade Trenches
A10 Foundations SUBTOTAL: $0 $0 $0 $0 $0 $0
B10 Superstructure
B1010.05 Mezzanine Construction
B1020.01 Roof Structural Frame PM
Main entrance front canopy is clad in prefinished metal (fascia and low parapet
cap flashing) with flat membrane roofing and prefinished metal interlocking
B1020.04 Canopies PM 10 Cost in heritage
soffit slats. Underside of canopy at joint with aluminum door frame shows signs
of water ingress (rust staining on metal angeltrim/closure)
Prefin. Standard Vert. Batten Metal cladding with green PVDF or similar coating
on framed and sheathed infill (with curtain wall/aluminum strip window) of
B2010.01.06.03 Metal Siding PM PM hangar doors between GL 2 & 3 on S. Elevation. Coating system is badly faded 10 Cost in heritage
from UV exposure but metal substrate shows no obvious signs of corrosion or
misalignment.
Shingle/shake siding mostly intact, aligned, and free of major defects other than
B2010.01.06.04 Wood Siding PM PM coatings failures. Old asbestos cement shakes applied to parachute tower 10 Cost in heritage
appear to be intact but should be investigated further.
B2010.01.11 Joint Sealers IR IR Deteriorated throughout in virtually all locations and applications 0
On wood siding (peeling and blistering observed) and several other substrates
B2010.01.13 Paints IR IR on building exterior (metal on hangar doors and other exterior doors, frames, 0-5 Cost in heritage
and windows)
B2010.02.05 Wood Framing No exterior wood framing was observed
Where observed, insulation was of poor to fair quality , discontinuous, and
showing signs of moisture damage and soiling via air and moisture
B2010.03.03.01 Batt Insulation IR IR 0-10 Cost in heritage
ingress/exfiltration through poor quality AVB. Further investigation
recommended.
Framed interior GWB walls: varied in quality, condition (surface and coating
B2010.04.02 Gypsum Board CB integrity), age and extents depending on location in building.
0-20 Cost in heritage
B2010.07.04 Awnings IR IR Frame may be salvageable but fabric covering is marginal 0-3 Cost in heritage
Refers to wood soffits and possibly wood door trim, frames, fascia and corner
battens. Where observed on each elevation appeared to be in mostly fair
B2010.09.01 Finish Carpentry PM condition but further investigation recommended where coatings failures have
0-10 $ 46,488.75 $ 46,488.75 $ 46,488.75 $ 46,488.75
occurred and bare wood is showing.
U/S of exterior canopy at SE corner of building: soffit is clad in sagging, stained,
B2010.09.05 Gypsum Board IR IR 0
moisture-affected interior-grade GWB
B20 Exterior Enclosures SUBTOTAL: $0 $46,489 $46,489 $46,489 $0 $46,489
B2020 Exterior Windows
S. Elevation: Unpainted HM door with painted steel frame set into hangar door
at Youth and Cultural Center entrance has inset georgian wire lite and thumb
latch lever and pull handle hardware. Function not observed. Sprinkler Rm.
door is painted HM in PSF set into original wood dooor frame. Coating is badly
B2030.02.01 Metal Doors and Frames IR IR marred and faded/chalked and steel door skin is damaged with a riveted patch. 0-5 $ 17,629.50 $ 17,629.50
Hardware is old round nob type with latch protector.
W. elevation: two HM doors with PSF's btw. GL's 7 & 9 are missing hardware
(auto closer, sweeps and seals/weather stripping. exit devices and outside
hardware are not to current standards
There are 2 steel egress doors and frames at the west elevation that appear to
be original. Condition of doos and frames vary somewhat but both require
B2030.02.01.01 Steel Doors and Frame IR CB significant work to upgrade to current exit function and energy performance 5 Cost in heritage
while retaining important heritage characteristics. Further investigation and
study required.
E. Elevation: 2 wood doors and frames with oudated hardware and failing
B2030.02.02.01 Wood Doors IR IR weatherstripping. Refer to ERA comments on other doors and locations. 0-5 Cost in heritage
Replace with HMD in PSF
B2030.03.05 Hangar Doors IR CB Refer to ERA comments 5
B2030 Exterior Doors SUBTOTAL: $12,607 $17,630 $0 $1,449 $18,390 $7,210
C10 Interior Construction
1. Painted, ribbed terracotta hollow units (structural clay block wall) observed at
N & S interior walls of Paint Storage Room (R9). Possibly original? Need to
confirm continuity and FRR of surrounding wall, floor, and ceiling joints and of
ceramic block material.
C1010.01.03 Unit Masonry Assemblies PM 2. Painted CMU partitions/demising walls observed at select portions of east
25 $ 40,753.13
wall of Paint Storage Rm. and Woodworking Shop (R4) along GL's 1 & 2
respectively. Complete extents TBC as some may be behind furring and GWB
assemblies. FRR and other code-related function TBC.
C2020.08 Stair Railings and Balustrades PM CB Per description in FCAR 2017. 5 $ 2,898.00
C20 Stairs SUBTOTAL: $0 $0 $8,694 $0 $0 $0
C30 Interior Finishes
C3010.02 Wall Paneling PM CB Per description in FCAR 2017. Further code review recommended. 5 $ 85,491.00 $ 85,491.00 $ 85,491.00
C3010.06 Tile Wall Finishes PM PM Per description in FCAR 2017. 10 Cost in heritage
C3010.11 Interior Wall Painting PM PM Per description in FCAR 2017. 10 Cost in heritage
Per description in FCAR 2017. Note deficiencies/damaged floor coatings in west
C3020.01 Concrete Floor Finishes IR IR 0 $ 172,672.50 $ 172,672.50 $ 172,672.50 $ 172,672.50
side of facility.
C3020.07 Resilient Flooring PM PM Per description in FCAR 2017 WRT locations and condition of VCT 0-5 $ 4,516.05
Per description in FCAR 2017 WRT locations and condition of carpet except at
C3020.08 Carpet Flooring PM R3 where immediate replacement is recommended
5 $ 56,511.00 $ 56,511.00 $ 56,511.00 $ 56,511.00
Not observed (except for drone aerial photos). Ponding observed at multiple
B3010.04.04 Modified Bituminous Membrane Roofing CB locations in photos but time to latest rain event is unknown as is avg. depth of $ 3,147,359.35 $ 3,147,359.35 $ 3,147,359.35
ponds
B3010.08.01 Sheet Metal Flashing and Trim CB CB Per description in FCAR 2017. 7 $ 120,061.73 $ 120,061.73
B3010.08.02 Metal Gutters and Downspouts PM PM Per description in FCAR 2017. Should consider alternates to discharge to grade. 5 $ 2,028.60 $ 2,028.60 $ 2,028.60 $ 2,028.60 $ 17,289.89
Included in Included in
B3010.08.03 Joint Sealers PM Not observed $ 15,929.94
B3010.04.04 above B3010.04.04 above
B30 Roofing SUBTOTAL: $ 3,269,449.67 $2,029 $2,029 $17,959 $3,284,711 $3,147,359
TOTAL CONSTRUCTION COST $ 3,599,729.42 $ 1,552,277.48 $ 471,655.54 $ 542,747.70 $ 3,798,336.78 $ 4,058,255.79
DESIGN AND PRICING CONTINGENCY $ 539,959.41 $ 232,841.62 $ 70,748.33 $ 81,412.16 $ 569,750.52 $ 608,738.37
CONSTRUCTION CONTINGENCY $ 359,972.94 $ 155,227.75 $ 47,165.55 $ 54,274.77 $ 379,833.68 $ 405,825.58
ESCALATION CONTINGENCY $ - $ 139,704.97 $ 70,748.33 $ 130,259.45 $ 1,595,301.45 $ 2,719,031.38
TOTAL COST $ 4,499,661.78 $ 2,080,051.82 $ 660,317.75 $ 808,694.08 $ 6,343,222.43 $ 7,791,851.12
A10 Foundations
Some cracking and exposure of corroded steel wire mesh was observed
at east end of north elevation; gravel fill has been added at the east end No change from 20 Expose deteriorated portions of wall to inspect
A1010.01 Wall Foundations TBD See heritage See heritage See heritage See heritage See heritage
of the south elevation as a temporary means of covering and concealing year scope condition of structural elements.
deteriorated wall plates/footing
Structural engineer
to advise The current trusses require extensive repair
and rehabilitation. The extent of which are
WEC: One of the carefully documented in the BPTEC report.
first steps could be to Not only will individual connections (546) and
Existing Douglas fir Warren trusses, steel bolt and split ring connectors, re-engage BPTEC members (332+) need to be replaced or
roof deck, built-up braced wood columns, are character defining elements and consult them reinforced, but all of the post-tensioned wires
and should be conserved as part of any future repair programme. There about additional will need replacement which will require all
Cost included in
are numerous occasions of severe splitting and cracking of truss dead loads and drift trusses to be shored. Rigid insulation on the
B3010.04.04 Modified
B1020.01 Roof Structural Frame members and diagonal wall bracing members. Numerous wood straps 0 associated with solar See heritage See heritage roof will likely increase the snow load on the
Bituminous Membrane
have been added to the underside of roof deck to cover gaps and cracks. panels. This will Roofing roof and could contribute to higher humidity in
Steel fasteners have generally corroded. There has been apparent determine the the building which would deteriorate the
movement at numerous splice connections, where horizontal bracing maximum limit the trusses. Additionally, future development of
members between trusses are sagging. trusses can take, the surrounding area could increase the snow
even with load on the roof. If solar panels are considered
reinforcing. This will to be added to the roof, this would also
give a clearer picture increase the snow load by adding area of snow
for costing moving drift.
forward.
East canopy cement board soffit has significant water damage, leading to
widespread staining and deformation of panels; south canopy is metal
siding and in fair condition; several wood soffit boards above the hangar Existing joists need to be exposed and
B1020.04 Canopies TBD See heritage See heritage See heritage See heritage
doors were noted to have loosened or formed small gaps and should be reviewed for water damage.
replaced. A non-original metal clad barrel vaulted canopy on the south
elevation was heavily corroded and in poor condition.
Some cracking and exposure of corroded steel wire mesh was observed
at east end of north elevation; gravel fill has been added at the east end of
A1010.01 Wall Foundations PM $ 929.78 $ 929.78 $ 929.78 $ 929.78 $ 93,484.65
the south elevation as a temporary means of covering and concealing
deteriorated wall plates/footing
No replacement or other
Existing concrete floor slabs are original and remain in good to fair upgrades
A1030.02 Structural Slabs on Grade IR PM ● condition overall. There is cracking in various locations throughout the $ 47,092.50 recommended due to
slab, but these are minor and do not suggest ongoing movement. impact to character
defining element
Integral cast-in-place concrete floor ducts formed part of the original heat
distribution system of the building. Furture interventions should consider
A1030.04 Slab on Grade Trenches CB ● Maintenance excluded Maintenance excluded
their preservation as salvaged artifacts for potential reuse in a heritage
interpretation strategy.
A10 Foundations SUBTOTAL: $ 929.78 $ 929.78 $ 929.78 $ 929.78 $ 140,577.15 $ -
B10 Superstructure
Added as per email on
B1010.05 Mezzanine Construction Fire Rating $ 48,583.76
Nov 30, 2021
Existing Douglas fir Warren trusses, steel bolt and split ring connectors,
roof deck, built-up braced wood columns, are character defining elements
and should be conserved as part of any future repair programme. There For scope of work in
Cost included in
are numerous occasions of severe splitting and cracking of truss 2032-2041, assume
Structural engineer to B3010.04.04 Modified
B1020.01 Roof Structural Frame PM PM ● members and diagonal wall bracing members. Numerous wood straps $ 195,011.25 $ 195,011.25 repair work in favor of
advise Bituminous Membrane
have been added to the underside of roof deck to cover gaps and cracks. full replacment of roof
Roofing
Steel fasteners have generally corroded. There has been apparent trusses
movement at numerous splice connections, where horizontal bracing
members between trusses are sagging.
East canopy cement board soffit has significant water damage, leading to
widespread staining and deformation of panels; south canopy is metal
siding and in fair condition; several wood soffit boards above the hangar
B1020.04 Canopies PM IR ● $ 46,416.30 $ 2,320.82 $ 2,320.82
doors were noted to have loosened or formed small gaps and should be
replaced. A non-original metal clad barrel vaulted canopy on the south
elevation was heavily corroded and in poor condition.
Not original. Shingles are generally intact with minor splits and checks Include gypsum and
B2010.01.06.04 Wood Siding PM PM ● $ 939,461.57 $ 46,973.08 $ 46,973.08 $ 46,973.08 $ 939,461.57
throughout. insulation work
Hangar door panels show some localized paint loss, general sheet/frame
deformation from impact near grade, corrosion at base/bottom rails,
hardware and fasteners. While the top-hung rolling doors appear to Cost for glazed portion
of hangar door included
remain operational, there is significant air leakage from lack/failure of
B2030.03.05 Hangar Doors IR IR ● $ 744,184.67 in B2020.01.01.
weatherstripping and air seals, putty, caulking, etc. Temporary plugs and Includes gypsum and
tape have been applied to seal gaps. Organic growth was generally insulation work
observed at the base from lack of positive drainage away from the
building.
C1010.04 Interior Balustrades and Screens, Interior Railings IR No impact to character defining elements
Paint finishes on the interior roof structure and timber wall framed
elements are in fair condition with many areas exhibiting water staining
and localized loss of paint. Water staining is particularly evident at the east
C3010.11 Interior Wall Painting CB ● $ 56,994.00 $ 56,994.00
and west walls, and is generally present on truss members. There is
general flaking and peeling of the paint coating on horizontal board
sheathing in restoration area
Roof not observed. Previous site photos from 2017 condition assessment Cost included in
B3010.04.04 Modified Bituminous Membrane Roofing CB CB
have been referenced for this study. architectural
Roof not observed. Previous site photos from 2017 condition assessment Cost included in
B3010.08.01 Sheet Metal Flashing and Trim CB PM
have been referenced for this study. architectural
Cost included in
B3010.08.02 Metal Gutters and Downspouts PM PM No impact to character defining elements
architectural
Roof not observed. Previous site photos from 2017 condition assessment Cost included in
B3010.08.03 Joint Sealers PM IR
have been referenced for this study. architectural
Water Closets No impact to character defining elements (See C1030.14 above) (See C1030.14 above)
Urinals No impact to character defining elements (See C1030.14 above) (See C1030.14 above)
Lavatories No impact to character defining elements (See C1030.14 above) (See C1030.14 above)
Sinks No impact to character defining elements (See C1030.14 above) (See C1030.14 above)
Mechanical engineer to
Pipes and Tubes: Domestic Water No impact to character defining elements
advise
Mechanical engineer to
Domestic Water Heaters No impact to character defining elements
advise
Mechanical engineer to
Waste and Vent Piping No impact to character defining elements
advise
SUBTOTAL: $0 $0 $0 $0 $0 $0
D30 Heating Ventilating and Air Conditioning (HVAC)
Gas Supply Systems
Integral cast-in-place concrete floor ducts formed part of the original heat
distribution system of the building. Future interventions should consider Mechanical engineer to Cost included in
Ducts: Air Distribution IR CB ●
their preservation as salvaged artifacts for potential reuse in a heritage advise mechanical
interpretation strategy.
Electric and Electronic Controls No impact to character defining elements
No visible signs of deterioration from excess relative humidity inside
Other Special HVAC Systems and Equipment CB CB No cost required
building.
SUBTOTAL: $0 $0 $0 $0 $0 $0
D40 Fire Protection
Wet-Pipe Fire Sprinkler Systems
Fire Extinguisher, Cabinets and Accessories
SUBTOTAL: $0 $0 $0 $0 $0 $0
D5010 Electrical Service and Distribution
D5010.01.01 Transformers IR No impact to character defining elements
D5010.03.07 Enclosed Switches and Circuit Breakers IR No impact to character defining elements
D5010.03.09 Enclosed Bus Assemblies IR No impact to character defining elements
Several decommissioned electrical panels appear to be original to the
BCATP period and of historic significance. Future electrical upgrades No cost required as per
D5010.05.01 Switchboards, Panelboards and Control Centers IR CB ●
should consider their preservation as salvaged artifacts for potential reuse electrical engineer
in a heritage interpretation strategy.
D5010.05.02 Enclosed Switches and Circuit Breakers IR No impact to character defining elements
D5010 Electrical Service and Distribution SUBTOTAL: $0 $0 $0 $0 $0 $0
D5020 Lighting and Branch Wiring
D5020.01 Electrical Branch Wiring IR No impact to character defining elements
D5020.01.02 Conductors and Cables No impact to character defining elements
D5020.01.03 Wiring Devices No impact to character defining elements
D5020.02.02 Interior Luminaries IR No impact to character defining elements
D5020.02.03 Emergency Lighting No impact to character defining elements
D5020.02.03 Exit Lighting IR No impact to character defining elements
D5020.02.05 Special Purpose Lighting No impact to character defining elements
D5020.03.01 Exterior Luminaries No impact to character defining elements
D5020 Lighting and Branch Wiring SUBTOTAL: $0 $0 $0 $0 $0 $0
D5030 Communications and Security
D5030.01.03 Smoke Alarm No impact to character defining elements
D5030.02 Security Access and Surveillance No impact to character defining elements
D5030.04 Voice and Data Systems IR No impact to character defining elements
D5030 Communications and Security SUBTOTAL: $0 $0 $0 $0 $0 $0
Note: The total costs shown in this summary are only for
components where the scope of work could be
determined. There are some components where the scope
of work could not be determined (These are assigned as
TBD). Thus, the actual total cost is expected to be
considerably higher than stated total cost.
2-3 Years Immediate 2-3 Years 4-5 Years 6-10 Years 11-20 Years 21-40 Years
D20 PLUMBING
Water Closets (floor mount, tank type assumed) Appears in fair condition. 15 $ 17,551.01
Urinals Appears in fair condition. 15 $ 7,299.34
Lavatories Appears in fair condition. 15 $ 12,805.54
Rates are based on
a single per unit
Sinks Appears in fair condition. 15 $ 1,216.56
basis, as quantities
are unknown
Staff has advised that both furnaces appear to be original and parts for
repair are difficult to source. Also furnace F1 has failed and does not
contribute to the heating of the hangar. Areas are now unevenly
serviced, with areas cold and other areas overly warn. If some of the
areas that are cold should drop below the freezing temperature,
domestic water and fire water/sprinkler piping may be at risk of freezing. Cost of salvaging
This may lead to the pipes bursting and releasing water that may
Furnaces IR IR 0 $ 414,655.50 existing furnace
damage the airplanes in the facility.
Recommend: Repair or replace the non-operating furnace to ensure included
that the building has heat during the winter. Recommend replacing the
operating furnace as soon as possible.
(There is no information on the current furnaces. A guessimate on a
replacement from Engineered Air would be a Model DG650,
approximately +60,000 cfm)
Assume Option1:
Cost shown is for air
transfer fan.Assume
Heat recovery wheel to transfer building exhaust air (for 380 people
40 hours of video
Heat recovery IR IR maximum) to the incoming outdoor air and ductwork/insulation to serve 0 $ 1,304,100.00
new heat recovery units. inspection for the
underslab passage
as the space scope
is unknown
Assume Option1:
Cost shown is for air
transfer fan.Assume
Above ground ductwork around the perimeter of the building with duct
40 hours of video
Ducts: Air Distribution IR IR sock branch ducting would be used to avoid the reported water in the 0 $ 382,777.50
ductwork. inspection for the
underslab passage
as the space scope
is unknown
There are no transformers in the facility however, the site is fed from 3
separate services with 3 different utility transformers. We recommend
replacing these services with one new EPCOR utility service sized for the
D5010.01.01 Transformers IR IR entire facility and distribution transformers inside the facility as necessary
2 1,110,900.00
to service the existing systems. It would be recommended to bring in a
3phase 600V service and then transform down to 120/208V.
The panels as well as the breakers within them have reached the end of
D5010.03.07 Enclosed Switches and Circuit Breakers IR IR their service life and it is recommended that they be replaced.
2 318,313.91
The panels as well as the breakers within them have reached the end of
D5010.03.09 Enclosed Bus Assemblies IR IR their service life and it is recommended that they be replaced.
2 355,795.91
The panels as well as the breakers within them have reached the end of
D5010.05.01 Switchboards, Panelboards and Control Centers IR IR their service life and it is recommended that they be replaced.
2 409,261.60
The panels as well as the breakers within them have reached the end of
D5010.05.02 Enclosed Switches and Circuit Breakers IR IR their service life and it is recommended that they be replaced.
2 380,785.13
$0 $3,086,088 $0 $0 $0
The branch wiring has been modified and run with various different types
of cable and conduit throughout the space. Some of the installations do
D5020.01 Electrical Branch Wiring IR IR not appear up to code and are not to the COE standards. It is 2 230,401.87
recommended that conduit and cable be rerun when the new panel
installations are done.
The branch wiring has been modified and run with various different types
of cable and conduit throughout the space. Some of the installations do
D5020.01.02 Conductors and Cables IR not appear up to code and are not to the COE standards. It is 2 307,139.70
recommended that conduit and cable be rerun when the new panel
installations are done.
Many of the wiring devices have reached the end of their useable life and
D5020.01.03 Wiring Devices should be replaced. They are currently functional so this replacement is 5 25,357.50
not immediate.
The existing exit lighting in the facility is currently red EXIT type as well as
unlit signs. It does not adequately guide occupants along the egress path.
D5020.02.03 Exit Lighting IR IR
It is our recommendation that new green LED running man exit signs be
0 36,225.00
installed throughout the facility to illuminate the egress path per code.
The exterior lighting is a combination of building mounted wall packs As per engineer,
which have been upgraded to LED and pole lighting for the parking lot. It
D5020.03.01 Exterior Luminaries
was not observed on at the time of the review but is assumed that they are
10 existing to
adequate for the intended purpose. remian
$107,996 $537,542 $650,362 $0 $0
The existing fire alarm system is a conventional system. The fire alarm
system has limited signalling throughout the facility. As this is a public
occupied facility for both the museum and convention area it is concerning
that there is little to no visual and audible signalling. It is recommended
D5030.01.03 Smoke Alarm IR
that the fire alarm system be replaced with a new addressable system
0 397,955.78
that includes signalling and detection to current building codes. It is also
recommended that a remote annunciator be installed near the main
entance door for fire fighters to locate upon entry.
The security system appears to be a primarily CCTV system. The system As per engineer,
D5030.02 Security Access and Surveillance is not a City of Edmonton standard system but appears functioning for its 10 existing to
intended purpose.
remian
The telephone and CATV services are mounted to exposed backboards in
the facility. It is recommended that a LAN room be installed and new
D5030.04 Voice and Data Systems IR network cabling run throughout the facility. The systems have been 5 346,243.38
modified continuously throughout the years and are showing the wear
from use.
$397,956 $0 $346,243 $0 $0
Appendix G
Option 3
$31,535,000 $3,670/m²
TOTAL /m²
8,593 m²
Hanger 14 - New Warehouse Facility - 2 storey Office 3,234 m² 34,810 sf 316 /sf $11,008,043
Hanger 14 - New Warehouse Facility - Warehouse (Open Space 5,359 m² 57,684 sf 277 /sf $15,957,437
only)
GST EXCLUDED
100463 - Hanger 14 - Option 3, Class D Estimate, R0 December 13, 2021 100463 - Hanger 14 - Option 3, Class D Estimate, R0 December 13, 2021
Unpublished Work Copyright © 2021 | Altus Group | altusgroup.com Unpublished Work Copyright © 2021 | Altus Group | altusgroup.com
100463 - Hanger 14 - Option 3, Class D Estimate, R0 December 13, 2021 100463 - Hanger 14 - Option 3, Class D Estimate, R0 December 13, 2021
Unpublished Work Copyright © 2021 | Altus Group | altusgroup.com Unpublished Work Copyright © 2021 | Altus Group | altusgroup.com
100463 - Hanger 14 - Option 3, Class D Estimate, R0 December 13, 2021 100463 - Hanger 14 - Option 3, Class D Estimate, R0 December 13, 2021
Unpublished Work Copyright © 2021 | Altus Group | altusgroup.com Unpublished Work Copyright © 2021 | Altus Group | altusgroup.com
100463 - Hanger 14 - Option 3, Class D Estimate, R0 December 13, 2021 100463 - Hanger 14 - Option 3, Class D Estimate, R0 December 13, 2021
Unpublished Work Copyright © 2021 | Altus Group | altusgroup.com Unpublished Work Copyright © 2021 | Altus Group | altusgroup.com
100463 - Hanger 14 - Option 3, Class D Estimate, R0 December 13, 2021 100463 - Hanger 14 - Option 3, Class D Estimate, R0 December 13, 2021
Unpublished Work Copyright © 2021 | Altus Group | altusgroup.com Unpublished Work Copyright © 2021 | Altus Group | altusgroup.com
Windows
B.B2020 .1 TOTAL FOR B3010 ROOF COVERING 1,617 m2 230 /m2 $371,945
Aluminum windows, Triple-Pane (GlasCurtain) 410 m2 2,151.68 883,006
100463 - Hanger 14 - Option 3, Class D Estimate, R0 December 13, 2021 100463 - Hanger 14 - Option 3, Class D Estimate, R0 December 13, 2021
Unpublished Work Copyright © 2021 | Altus Group | altusgroup.com Unpublished Work Copyright © 2021 | Altus Group | altusgroup.com
Steel Stud and Drywall Partition Assemblies Washroom Accessories - Commercial Grade
B.C1010.1 Demising partition 2,150 m2 146.31 314,565 B.C1030.1 Washroom accessories to common area washrooms 4 sum 4,750.00 19,000
92mm (3-5/8'') s/studs 406mm (16'') o/c to walls 2,150 m2 44.40 95,466
89mm (3-1/2'') sound attenuation batt. 2,150 m2 10.50 22,576
15.9mm (5/8'') fire rated (type 'X') drywall to walls 4,300 m2 16.20 69,665 Other Millwork
Tape & finish (Level 4 finish) to walls 2,150 m2 13.30 28,597 B.C1030.2 Allowance for lobby millwork 1 sum 14,300.00 14,300
15.9mm (5/8'') fire rated (type 'X') drywall to walls 4,300 m2 16.20 69,665
Tape & finish (Level 4 finish) to walls 2,150 m2 13.30 28,597 B.C1030.3 Allowance for amenity millwork 1 sum 23,800.00 23,800
B.C1010.2 Corridor Partition 1,748 m2 135.07 236,098
B.C1030.4 Allowance for amenity kitchen millwork 1 sum 4,280.00 4,280
92mm (3-5/8'') s/studs 610mm o/c to walls 1,748 m2 32.80 57,321
89mm (3-1/2'') batt insulation 1,748 m2 27.10 47,359
15.9mm (5/8'') fire rated (type 'X') drywall to walls 3,495 m2 16.20 56,622
Tape & finish (Level 4 finish) to walls 1,748 m2 13.30 23,243 Other Interior Specialties
B.C1030.5 Steel ladder 2 no. 1,430.00 2,860
15.9mm (5/8'') fire rated (type 'X') drywall to walls 1,748 m2 16.20 28,311
Tape & finish (Level 4 finish) to walls 1,748 m2 13.30 23,243
B.C1030.6 Elevator pit ladder 1 no. 713.00 713
Misc. Metals, Rough Carpentry, Sealing etc.
B.C1010.3 B.C1030.7 Misc. metals - above grade 3,234 m2 7.20 23,287
Rough carpentry - above grade 3,234 m2 12.00 38,812
B.C1010.4 Allow for sealing and caulking 3,234 m2 2.50 8,086 TOTAL FOR C1030 FITTINGS 3,234 m2 27.28 /m2 $88,240
TOTAL FOR C1010 PARTITIONS 3,898 m2 153 /m2 $597,561 C20 Stairs
C2010 Stair Construction
C10 Interior Construction
C1020 Interior Doors Stair Construction - Metal
B.C2010.1 Concrete filled metal pan stairs 8 flt. 850.00 6,800
Wood Interior Doors
B.C1020.1 Hollow core interior wood door - Single 32 lvs 580.50 18,576 Handrails
Supply hollow core interior door 32 no. 105.00 3,360 B.C2010.2
Install hollow core interior door 32 no. 180.00 5,760
Steel wall rail 15 m 171.00 2,565
Wood door frame - single 32 no. 85.00 2,720
Hardware to wood interior door - suite 32 no. 85.50 2,736
TOTAL FOR C2010 STAIR CONSTRUCTION 8 flt. 1,171 /flt. $9,365
Interior paint to wood door and frame 32 no. 125.00 4,000
B.C1020.2 Hollow core interior wood door - Double 14 lvs 1,210.00 16,940
Supply hollow core interior door 14 no. 105.00 1,470
Install hollow core interior door 14 no. 180.00 2,520
Wood door frame - double 7 no. 100.00 700
Hardware to wood interior door - common 14 no. 750.00 10,500
Interior paint to wood door and frame 14 no. 125.00 1,750
100463 - Hanger 14 - Option 3, Class D Estimate, R0 December 13, 2021 100463 - Hanger 14 - Option 3, Class D Estimate, R0 December 13, 2021
Unpublished Work Copyright © 2021 | Altus Group | altusgroup.com Unpublished Work Copyright © 2021 | Altus Group | altusgroup.com
TOTAL FOR C3010 WALL FINISHES 7,795 m2 14.33 /m2 $111,690 Passenger Elevators
B.D1010.1 Traction elevator - #1 2 stop 23,900.00 47,800
C30 Interior Finishes
B.D1010.2 Allow for cab finishes 1 1 cab 30,000.00 30,000
C3020 Floor Finishes
D20 Plumbing
Carpeting D2010 Plumbing Office Allowance
B.C3020.2 Carpet flooring 293 m2 52.30 15,298
Plumbing allowance
B.D2010.1 3,234 m2 115.00 371,910
Wall Base Finishes
B.C3020.3 Resilient base 2,128 m 5.00 10,642
TOTAL FOR D2010 PLUMBING OFFICE ALLOWANCE 3,234 m2 115 /m2 $371,910
Hardeners and Sealers
B.C3020.4 Polished Concrete - SOG 2,817 m2 48.00 135,206 D30 HVAC
D3010 Energy Supply
B.C3020.5 No Finish (Shafts/Elevators, Etc.) m2 Area Only
Hot Water Supply System (From Central Plant)
B.D3010.1 1 sum 503,500.00 503,500
TOTAL FOR C3020 FLOOR FINISHES 3,184 m2 53.74 /m2 $171,121 B-Gas fired high efficiency building heating boilers,estimated at XXXX 2 no. 180,000.00 360,000
MBH each
boilers circulating pumps 2 no. 4,500.00 9,000
C3030 Ceiling Finishes
P-Building heating system pumps, VFD 2 no. 14,500.00 29,000
ET-Expansion tank-heating 1 no. 22,500.00 22,500
Gypsum Wallboard Ceiling Finishes ET-Expansion tank-glycol 1 no. 16,500.00 16,500
B.C3030.1 15.9mm (5/8'') suspended drywall ceiling system 3,088 m2 67.50 208,443 HX-Heat exchanger, glycol 1 no. 16,500.00 16,500
Allowance for glycol feed tank, chemical treatment, etc 1 no. 24,000.00 24,000
B.C3030.2 Interior paint drywall ceilings 3,088 m2 12.00 37,057 Allowance for air separators, gauges, valves, etc 1 sum 17,000.00 17,000
Allowance for boiler flue vent 1 sum 9,000.00 9,000
100463 - Hanger 14 - Option 3, Class D Estimate, R0 December 13, 2021 100463 - Hanger 14 - Option 3, Class D Estimate, R0 December 13, 2021
Unpublished Work Copyright © 2021 | Altus Group | altusgroup.com Unpublished Work Copyright © 2021 | Altus Group | altusgroup.com
TOTAL FOR D3050 TERMINAL AND PACKAGE UNITS 3,234 m2 97.77 /m2 $316,230
100463 - Hanger 14 - Option 3, Class D Estimate, R0 December 13, 2021 100463 - Hanger 14 - Option 3, Class D Estimate, R0 December 13, 2021
Unpublished Work Copyright © 2021 | Altus Group | altusgroup.com Unpublished Work Copyright © 2021 | Altus Group | altusgroup.com
B.D5010.2 Mechanical distribution and step down transformers 1 sum 16,935.88 16,936
TOTAL FOR D5020 LIGHTING AND BRANCH WIRING 3,234 m2 112 /m2 $362,208
100463 - Hanger 14 - Option 3, Class D Estimate, R0 December 13, 2021 100463 - Hanger 14 - Option 3, Class D Estimate, R0 December 13, 2021
Unpublished Work Copyright © 2021 | Altus Group | altusgroup.com Unpublished Work Copyright © 2021 | Altus Group | altusgroup.com
B.D5090.2 Testing & commissioning 1 sum 11,000.00 11,000 B.A1010.2 Rough grading - As per Geotech Report Need to remove 5,359 m2 18.00 96,466
600mm to 1700mm of non-Engineered fill.
B.D5090.3 Permits, inspection & job set-up 1 sum 26,300.00 26,300
Grade Beams
B.A1010.3
Emergency Lighting and Power Grade Beams - 250x900mm - 35 MPa 305 m 515.61 157,345
B.D5090.4 Trench excavation - earth (by machine) 481 m3 18.00 8,651
Battery Packs, remote heads and exit signs 3,234 m2 9.00 29,106
Cart material off site 481 m3 5.70 2,740
Granular backfill - supply & place (by machine) 409 m3 42.80 17,485
B.D5090.5 DC Branch wiring 3,234 m2 5.00 16,170 Formwork - grade beam 549 m2 114.00 62,619
Void form - 100mm 76 m2 42.80 3,265
35 MPa, C1 (5000Psi) - supply 72 m3 214.00 15,428
TOTAL FOR D5090 OTHER ELECTRICAL SERVICES 3,234 m2 26.61 /m2 $86,076 Air entrainment 72 m3 6.00 433
Concrete accessories 69 m3 4.30 295
Allow for admixtures (based on concrete volume) blend 22 m3 25.00 541
NET BUILDING COST (Excluding Site) 3,234 m2 2,975 /m2 $9,622,415
Winter heat 36 m3 21.00 757
Environmental 72 m3 7.00 505
General Requirements 10.00 % 962,242 Waste water handling fee ($2.50 /m3) 72 m3 2.50 180
Fuel & carbon levy surcharge 72 m3 3.93 283
Fee (Head office overheads, and profit) 4.00 % 423,386 Dampproofing to grade beams 275 m2 19.00 5,218
Protection board 275 m2 23.80 6,537
50mm (2") rigid insulation (R10) 275 m2 42.30 11,617
TOTAL CONSTRUCTION ESTIMATE (Excluding contingencies) 3,234 m2 3,404 /m2 $11,008,043 Place concrete 69 m3 42.80 2,939
Black reinforcing steel - labour, material, and accessories 6,866 kg 2.60 17,852
Design and Pricing Contingency 10.00 % 1,100,804
B.A1010.4 Grade Beams - 200x600mm - 35 MPa 293 m 315.42 92,260
Trench excavation - earth (by machine) 246 m3 18.00 4,423
Escalation Contingency EXCLUDED Cart material off site 246 m3 5.70 1,400
Granular backfill - supply & place (by machine) 209 m3 42.80 8,939
Construction Contingency 5.00 % 550,402 Formwork - grade beam 351 m2 114.00 40,014
Void form - 100mm 59 m2 42.80 2,504
35 MPa, C1 (5000Psi) - supply 37 m3 214.00 7,887
TOTAL CONSTRUCTION ESTIMATE (Including contingencies) 3,234 m2 3,914 /m2 $12,659,249 Air entrainment 37 m3 6.00 221
Concrete accessories 35 m3 4.30 151
Allow for admixtures (based on concrete volume) blend 11 m3 25.00 276
TOTAL CONSTRUCTION ESTIMATE (Excluding Taxes) 3,234 m2 3,914 /m2 $12,659,249 Winter heat 18 m3 21.00 387
Environmental 37 m3 7.00 258
Waste water handling fee ($2.50 /m3) 37 m3 2.50 92
Fuel & carbon levy surcharge 37 m3 3.93 145
Dampproofing to grade beams 176 m2 19.00 3,335
Protection board 176 m2 23.80 4,177
50mm (2") rigid insulation (R10) 176 m2 42.30 7,424
Place concrete 35 m3 42.80 1,502
Black reinforcing steel - labour, material, and accessories 3,510 kg 2.60 9,126
100463 - Hanger 14 - Option 3, Class D Estimate, R0 December 13, 2021 100463 - Hanger 14 - Option 3, Class D Estimate, R0 December 13, 2021
Unpublished Work Copyright © 2021 | Altus Group | altusgroup.com Unpublished Work Copyright © 2021 | Altus Group | altusgroup.com
Miscellaneous
TOTAL FOR A1020 SPECIAL FOUNDATIONS 5,359 m2 64.45 /m2 $345,400 B.B1020.3 Horizontal firestopping 556 m 15.00 8,340
A10 Foundations
A1030 Slab on Grade TOTAL FOR B1020 ROOF CONSTRUCTION 5,359 m2 576 /m2 $3,087,181
TOTAL FOR A1030 SLAB ON GRADE 5,359 m2 97.87 /m2 $524,499 Windows
B.B2020 .1 Aluminum windows, Triple-Pane (GlasCurtain) 834 m2 2,151.68 1,793,683
100463 - Hanger 14 - Option 3, Class D Estimate, R0 December 13, 2021 100463 - Hanger 14 - Option 3, Class D Estimate, R0 December 13, 2021
Unpublished Work Copyright © 2021 | Altus Group | altusgroup.com Unpublished Work Copyright © 2021 | Altus Group | altusgroup.com
B2030 Exterior Doors TOTAL FOR C3020 FLOOR FINISHES 5,359 m2 48.00 /m2 $257,242
100463 - Hanger 14 - Option 3, Class D Estimate, R0 December 13, 2021 100463 - Hanger 14 - Option 3, Class D Estimate, R0 December 13, 2021
Unpublished Work Copyright © 2021 | Altus Group | altusgroup.com Unpublished Work Copyright © 2021 | Altus Group | altusgroup.com
TOTAL FOR D3090 OTHER HVAC SYSTEMS & EQUIPMENT 5,359 m2 23.88 /m2 $128,000
100463 - Hanger 14 - Option 3, Class D Estimate, R0 December 13, 2021 100463 - Hanger 14 - Option 3, Class D Estimate, R0 December 13, 2021
Unpublished Work Copyright © 2021 | Altus Group | altusgroup.com Unpublished Work Copyright © 2021 | Altus Group | altusgroup.com
Main Transformers
B.D5010.1 New Main Electrical Service panel - feeds both area's 1 no. 40,370.00 40,370 Lighting Equipment - Lighting Control
B.D5020.7 Lighting control system - Addressable c/w daylight harvesting 5,359 m2 20.00 107,180
B.D5010.2 Meter cabinet c/w empty conduit 1 no. 1,370.00 1,370
TOTAL FOR D5020 LIGHTING AND BRANCH WIRING 5,359 m2 102 /m2 $546,618
B.D5010.3 New CDP's, step down transformers and feeders - 1 sum 114,963.43 114,963
Warehouse area
D50 Electrical
B.D5010.4 Mechanical distribution and step down transformers 1 sum 28,064.12 28,064 D5030 Communications and Security
100463 - Hanger 14 - Option 3, Class D Estimate, R0 December 13, 2021 100463 - Hanger 14 - Option 3, Class D Estimate, R0 December 13, 2021
Unpublished Work Copyright © 2021 | Altus Group | altusgroup.com Unpublished Work Copyright © 2021 | Altus Group | altusgroup.com
D50 Electrical TOTAL CONSTRUCTION ESTIMATE (Including contingencies) 5,359 m2 3,424 /m2 $18,351,053
D5030 Communications and Security
B.D5030.6 Plywood backboards 1 sum 6,055.00 6,055 TOTAL CONSTRUCTION ESTIMATE (Excluding Taxes) 5,359 m2 3,424 /m2 $18,351,053
B.D5030.7 Allowance for trunk conduit & cabling 1 sum 17,550.00 17,550
Security Systems
B.D5030.9 Allowance for security system including CCTV camera, 5,359 m2 25.00 133,975
access door devices, etc.
TOTAL FOR D5030 COMMUNICATIONS AND SECURITY 5,359 m2 72.56 /m2 $388,878
TOTAL FOR D5090 OTHER ELECTRICAL SERVICES 5,359 m2 28.52 /m2 $152,826
100463 - Hanger 14 - Option 3, Class D Estimate, R0 December 13, 2021 100463 - Hanger 14 - Option 3, Class D Estimate, R0 December 13, 2021
Unpublished Work Copyright © 2021 | Altus Group | altusgroup.com Unpublished Work Copyright © 2021 | Altus Group | altusgroup.com
Transformers
S.G4010.1 Allowance for utility provider to decommission existing 1 sum 222,577.50 222,578
services and provide anew single source service
RSL =
Aviation Museum Investment Study Report Date: February 5, 2022
Option 3 - Office
Facility
Remaining PERIOD
Edmonton, Alberta
Service Life
RSL 2021-2022 2023-2024 2025-2026 2027-2031 2032-2041 2042-2061
BUILDING SYSTEM Build 2021
Immediate 2-3 Years 4-5 Years 6-10 Years 11-20 Years 21-40 Years
A10 Foundations
A1010 Standard Foundation 75 yrs
A1020 Special Foundation 75 yrs
A1030 Slab on Grade 75 yrs
A10 Foundations SUBTOTAL: - - - - - -
B10 Superstructure
B1010 Floor Construction 75 yrs
B1020 Roof Construction 75 yrs
B10 Superstructure SUBTOTAL: - - - - - -
B20 Exterior Enclosures
Maintenance Model
Gypsum Board Partition 75 yrs
C1020 Interior Doors
Wooden Doors - Hollow Core 10-40yrs
Replace Hardware/Repaint 10yrs 38,862.18 43,556.94
Replace Wooden Door 40yrs 92,988.45
C1030 Fittings
Total Maintenance
Planned Maint. Reactive Maint. Total Total Maintenance Hours
CAT. LEVEL 1 INFORMATION LEVEL 2 INFORMATION and SUBTOTALS Hours
Hrs/Year Hrs/Year Maint.Hours (Subcontracted)
(Self Perform)
A SUBSTRUCTURE SUBTOTAL SUBSTRUCTURE - - - - -
D SERVICES
D1 Conveying System - - - - -
D2 Plumbing 39.0 11.7 50.7 15.6 35.1
D3 Heating, Ventilation And Air Conditioning 153.5 46.1 199.6 129.4 70.2
D4 Fire Protection 38.0 11.4 49.4 46.8 2.6
D5 Electrical 96.0 28.8 124.8 58.5 66.3
SUBTOTAL SERVICES 326.5 98.0 424.5 250.3 174.2
E EQUIPMENT & FURNISHINGS SUBTOTAL EQUIPMENT & FURNISHINGS 6.0 2.4 8.4 3.2 5.2
G BUILDING SITE WORK SUBTOTAL BUILDING SITE WORK 323.0 96.9 419.9 414.7 5.2
Note: - Costs excludes other services influenced by operational specifics and standards including cleaning, snow removal, pest control, landscaping
B2030.03.05 Hangar Doors 1 LS Inspection and adjustment, grease, track clean etc Annual 0.08 4 12 Subcontract Door Contractor 4 Low 0.3 1.2 5.2 5.2 $780.00 $78.00 $858.00
B30 - ROOFING B3010 - ROOF COVERING & OPENINGS General allowance for minor repairs, touch up etc As needed 0.08 8 12 Subcontract Roofing Contractor 8 Low 0.3 2.4 10.4 10.4 $1,040.00 $104.00 $1,144.00
B3010.04.04 Modified Bituminous Membrane Roofing 780 m2 Included in general allowance
B3010.08.01 Sheet Metal Flashing and Trim 565 lm Included in general allowance
B3010.08.02 Metal Gutters and Downspouts 336 lm Seasonal clean out gutters As needed 0.17 4 12 Self Perform Maintenance Assistant 8 Low 0.3 2.4 10.4 10.4
B3010.08.03 Joint Sealers 565 lm Included in general allowance
B3020 - ROOF OPENINGS n/a
B3030 - BALCONIES AND PROJECTIONS n/a
SUBTOTAL SHELL 82.50 24.75 107.25 91.65 15.60 1820.00 182.00 2002.00
C INTERIORS C10 - INTERIOR CONSTRUCTION C1010 - PARTITIONS n/a
C1010.01.03 Unit Masonry Assemblies 75 m2 n/a
C1010.01.07 Framed Partitions 230 m2 n/a
D2040 - RAIN WATER DRAINAGE General Allowance (spring/seasonal clean up) As needed 0.17 4 12 Self Perform Maintenance Assistant 8 Low 0.3 2.4 10.4 10.4
D2090 - SPECIAL PLUMBING SYSTEMS
Natural Gas (asset assumption) Inspection and check operational condition Annual 0.08 1 12 Subcontract Plumbing Contractor 1 Low 0.3 0.3 1.3 1.3 $104.00 $10.40 $114.40
Domestic Water Heaters (asset assumption) Annual Inspection and checks, clean out etc Annual 0.08 2 12 Subcontract Plumbing Contractor 2 Low 0.3 0.6 2.6 2.6 $208.00 $20.80 $228.80
Domestic Water Storage Tanks & Mixing Valves (asset
assumption) Annual Clean, Inspection and checks Annual 0.08 2 12 Subcontract Plumbing Contractor 2 Low 0.3 0.6 2.6 2.6 $208.00 $20.80 $228.80
Water Softener (asset assumption) Annual Inspection and checks Annual 0.08 1 12 Subcontract Plumbing Contractor 1 Low 0.3 0.3 1.3 1.3 $104.00 $10.40 $114.40
D30 - HVAC D3010 - ENERGY SUPPLY n/a
D3020 - HEAT GENERATING SYSTEMS Included in asset details
Operational / BAS condition checks (assume via
No
Furnace / Boilers 2 web/cloud) Weekly 1 1 12 Subcontract Controls Contractor 12 Low 0.3 3.6 15.6 15.6 $2,340.00 $234.00 $2,574.00
No
Furnace / Boilers 2 Inspection and operational checks and adjustments Quarterly 1.00 2 8 Subcontract Mechanical Contractor 16 Low 0.3 4.8 20.8 20.8 $1,976.00 $197.60 $2,173.60
Inspection and condition (insurance inspection) review,
No
Furnace / Boilers 2 operational checks and adjustments Annual 0.08 4 12 Subcontract Mechanical Contractor 4 Low 0.3 1.2 5.2 5.2 $494.00 $49.40 $543.40
Expansion/Fill Tanks (asset assumption) 2 No Inspection and Check Quarterly 0.25 0.5 12 Self Perform Maintenance Assistant 1.5 Low 0.3 0.5 2.0 2.0
Expansion/Fill Tanks (asset assumption) Inspection and Check Annual 0.08 1 12 Subcontract Mechanical Contractor 1 Low 0.3 0.3 1.3 1.3 $123.50 $12.35 $135.85
Pumps (asset assumption) Inspection and Check Monthly 1.00 0.5 12 Self Perform Maintenance Assistant 6 Low 0.3 1.8 7.8 7.8
1 of 4
Sensors (asset assumption) Inspection, check and tests Annual 0.08 2 12 Subcontract Mechanical Contractor 2 Low 0.3 0.6 2.6 2.6 $247.00 $24.70 $271.70
D3030 - REFRIGERATION n/a
D3040 - HVAC DISTRIBUTION SYSTEMS
Piping & Insulation Exercise main distribution and isolation valves Annual 0.08 1 12 Self Perform Maintenance Assistant 1 Low 0.3 0.3 1.3 1.3
Ductwork and Fire Dampers Inspection, clean and operational checks Annual 0.08 1 12 Subcontract Mechanical Contractor 1.0 Low 0.3 0.3 1.3 1.3 $123.50 $12.35 $135.85
Grilles & Diffusers Inspection and operational checks Annual 0.08 1 12 Self Perform Maintenance Assistant 1 Low 0.3 0.3 1.3 1.3
Fans Inspection and Checks Quarterly 0.25 1 12 Subcontract Mechanical Contractor 3 Low 0.3 0.9 3.9 3.9 $370.50 $37.05 $407.55
Fans Inspection and Checks on main system fans only Annual 0.08 1 12 Subcontract Mechanical Contractor 1 Low 0.3 0.3 1.3 1.3 $123.50 $12.35 $135.85
D3050 - TERMINAL & PACKAGE UNITS
Heat Exchangers n/a
Cooling - Split A/C n/a
Cooling - Water Chiller n/a
Cooling - Water Chiller n/a
Cooling - Water Chiller n/a
Roof Top & Make Up Air Units n/a
Unit Heaters, Fan & Heating Coils n/a
Radiant Panels n/a
D3060 - HVAC CONTROLS & INSTRUMENTATION BAS fault review, and operational checks Quarterly 0.25 1 12 Subcontract Controls Contractor 3.0 Low 0.3 0.9 3.9 3.9 $585.00 $58.50 $643.50
Inspect system status alarms Daily 30.00 0.25 12 Self Perform Building Operator 90 Low 0.3 27 117 117
BAS analysis, software update, and operational checks,
D3070 - TESTING, ADJUSTING & BALANCING adjustments Annual 0.08 1 12 Subcontract Controls Contractor 1.0 Low 0.3 0.3 1.3 1.3 $195.00 $19.50 $214.50
D3090 - OTHER SPECIAL HVAC SYS. & EQUIPT.
Periodic analysis and testing, filter checks and
Water Treatment (asset assumption) and quality replacement Quarterly 0.25 2 12 Subcontract Mechanical Contractor 6 Low 0.3 1.8 7.8 7.8 $741.00 $74.10 $815.10
Clean out lint from extract exhaust system (asset assumption) Inspection and operational condition checks Quarterly 0.25 1 12 Subcontract Mechanical Contractor 3.0 Low 0.3 0.9 3.9 3.9 $370.50 $37.05 $407.55
Glycol and Snow melt system n/a
Condensate Tank (asset assumption) Inspection, clean and operational checks Annual 0.08 1 12 Subcontract Mechanical Contractor 1 Low 0.3 0.3 1.3 1.3 $123.50 $12.35 $135.85
D40 - FIRE PROTECTION D4010 - FIRE PROTECTION SPRINKLER SYSTEM
Sprinklers and pumps (asset assumption) Visually inspect system Monthly 1.00 1 12 Self Perform Maintenance Assistant 12 Low 0.3 3.6 15.6 15.6
System test, check pumps, certified by licensed Fire and Security
Sprinklers System (asset assumption) contractor. Annual 0.08 2 12 Subcontract Contractor 2 Low 0.3 0.6 2.6 2.6 $260.00 $26.00 $286.00
D4020 - STAND-PIPE & HOSE SYSTEMS n/a
D4030 - FIRE PROTECTION SPECIALTIES n/a
Fire Extinguishers, Cabinets and Accessories Inspection and checks of emergency equipment Monthly 1.00 2 12 Self Perform Maintenance Assistant 24 Low 0.3 7.2 31.2 31.2
D4090 - OTHER FIRE PROTECTION SYSTEMS n/a
General allowance for reactive response to Electrical
D50 - ELECTRICAL D5010 - ELECTRICAL SERVICE & DISTRIBUTION issues As needed 0.25 4 12 Subcontract Electrical Contractor 12 Low 0.3 3.6 15.6 15.6 $1,560.00 $156.00 $1,716.00
D5010.01.01 Transformers Inspection, test, check oil levels, clean Annual 0.08 2 12 Subcontract Electrical Contractor 2 Low 0.3 0.6 2.6 2.6 $260.00 $26.00 $286.00
D5010.03.07 Enclosed Switches and Circuit Breakers Inspection and test dist. Boards & circuits, thermoscan Annual 0.08 2 12 Subcontract Electrical Contractor 2 Low 0.3 0.6 2.6 2.6 $260.00 $26.00 $286.00
D5010.03.09 Enclosed Bus Assemblies Inspection and check tightness, test Annual 0.08 1 12 Subcontract Electrical Contractor 1 Low 0.3 0.3 1.3 1.3 $130.00 $13.00 $143.00
D5010.05.01 Switchboards, Panelboards and Control Centers Inspection and test dist. Boards & circuits, thermoscan Annual 0.08 1 12 Subcontract Electrical Contractor 1 Low 0.3 0.3 1.3 1.3 $130.00 $13.00 $143.00
D5010.05.02 Enclosed Switches and Circuit Breakers Inspection and test dist. Boards & circuits, thermoscan Annual 0.08 1 12 Subcontract Electrical Contractor 1 Low 0.3 0.3 1.3 1.3 $130.00 $13.00 $143.00
Grounding System (asset assumption) Inspection and test grounding Annual 0.08 2 12 Subcontract Electrical Contractor 2 Low 0.3 0.6 2.6 2.6 $260.00 $26.00 $286.00
TVSS n/a
D5020 - LIGHTING & BRANCH WIRING General allowance and reactive bulb replacement As needed 0.25 1 12 Self Perform Maintenance Assistant 3 Low 0.3 0.9 3.9 3.9
D5020.01 Electrical Branch Wiring n/a
D5020.01.02 Conductors and Cables n/a
D5020.01.03 Wiring Devices Inspection and test GFI's and switches Annual 0.08 2 12 Subcontract Electrical Contractor 2.0 Low 0.3 0.6 2.6 2.6 $260.00 $26.00 $286.00
D5020.02.02 Interior Luminaries Included in general allowance
D5020.02.03 Emergency Lighting Test for proper operation Monthly 1.00 1 12 Self Perform Maintenance Assistant 12 Low 0.3 3.6 15.6 15.6
D5020.02.03 Exit Lighting Included in general allowance
D5020.02.05 Special Purpose Lighting Included in general allowance
D5020.03.01 Exterior Luminaries Included in general allowance
D5030 - COMMUNICATION & SECURITY SYSTEMS
Fire Alarm Test (addressable) Monthly 1.00 1 12 Self Perform Building Operator 12 Low 0.3 3.6 15.6 15.6
System/Smoke/Heat detector inspection and test to Fire and Security
D5030.01.03 Smoke Alarm cover full system annually Annual 0.08 4 12 Subcontract Contractor 4 Low 0.3 1.2 5.2 5.2 $520.00 $52.00 $572.00
System functional check to FA speakers (addressable) Monthly 1.00 0.5 12 Self Perform Building Operator 6 Low 0.3 1.8 7.8 7.8
D5030.02 Security Access and Surveillance
(assume no access control system) Surveillance system functional check Monthly 1.00 1 12 Self Perform Building Operator 12 Low 0.3 3.6 15.6 15.6
General allowance for reactive response to network and
D5030.04 Voice and Data Systems WIFI issues As needed 0.25 2 12 Subcontract Electrical Contractor 6 Low 0.3 1.8 7.8 7.8 $780.00 $78.00 $858.00
System inspection and functional check,
updates/upgrades Monthly 1.00 1.5 12 Subcontract Electrical Contractor 18 Low 0.3 5.4 23.4 23.4 $2,340.00 $234.00 $2,574.00
D5090 - OTHER ELECTRICAL SYSTEMS n/a
SUBTOTAL SERVICES 326.5 97.95 424.45 250.25 174.20 $17,862.00 $1,786.20 $19,648.20
EQUIPMENT &
E FURNISHINGS E10 - EQUIPMENT E1010 - COMMERCIAL EQUIPMENT n/a
E1020 - INSTITUTIONAL EQUIPMENT n/a
E1030 - VEHICULAR EQUIPMENT n/a
E1090 - OTHER EQUIPMENT
Shop equipment Inspect and check equipment operation Annual 0.08 2 12 Self Perform Maintenance Assistant 2 Medium 0.6 1.2 3.2 3.2 $0.00 $0.00 $0.00
E20 - FURNISHINGS E2010 - FIXED FURNISHINGS
General allowance for reactive damage repair and lock
Cabinetry / Millwork replacement etc As needed 0.17 2 12 Subcontract Carpenter Contractor 4 Low 0.3 1.2 5.2 5.2 $390.00 $39.00 $429.00
Window Treatments n/a
E2020 - MOVABLE FURNISHINGS n/a
SUBTOTAL EQUIPMENT & FURNISHINGS 6.00 2.40 8.40 3.20 5.20 $390.00 $39.00 $429.00
SPECIAL
F CONSTRUCTION F10 - SPECIAL CONSTRUCTION F1010 - SPECIAL STRUCTURES n/a
& DEMOLITION F1020 - INTEGRATED CONSTRUCTION n/a
F1030 - SPECIAL CONSTRUCTION SYSTEMS n/a
F1040 - SPECIAL FACILITIES n/a
F1050 - SPECIAL CONTROLS & INSTRUMENTATION n/a
F20 - SELECTIVE BUILDING F2010 - BUILDING ELEMENTS DEMOLITION n/a
DEMOLITION F2020 - HAZARDOUS COMPONENTS ABATEMENT n/a
SUBTOTAL SPECIAL CONST. & DEMO 0.00 0.00 0.00 0.00 0.00 $0.00 $0.00 $0.00
BUILDING SITE
G WORK G10 - SITE PREPARATION G1010 - SITE CLEARING n/a
G1020 - SITE DEMOLITION & RELOCATIONS n/a
G1030 - SITE EARTHWORK n/a
G1030.01.01 Rough Grading 730 m2 n/a
G1030.01.02 Finish Grading 730 m2 n/a
G1040 - HAZARDOUS WASTE REMEDIATION n/a
G2010 - ROADWAYS n/a
G2010 - ROADWAYS n/a
G2010.02.02 Flexible Pavement 250 m2 General Allowance for small repairs, potholes etc As needed 0.17 4 12 Self Perform Maintenance Assistant 8 Low 0.3 2.4 10.4 10.4
G2010.05 Roadway Curbs and Gutters 60 lm General Allowance (spring/seasonal clean up) As needed 0.17 1 12 Self Perform Maintenance Assistant 2 Low 0.3 0.6 2.6 2.6
G2020 - PARKING LOTS n/a
G2020.02.02 Flexible Pavement 4000 m2 General Allowance for small repairs, potholes etc As needed 0.17 4 12 Self Perform Maintenance Assistant 8 Low 0.3 2.4 10.4 10.4
G2020.02.04 Pavement Markings 133 stalls Line marking touch Up Annual 0.08 4 12 Self Perform Maintenance Assistant 4 Low 0.3 1.2 5.2 5.2
G2020.05 Parking Lot Curbs and Gutters 260 lm General Allowance (spring/seasonal clean up) As needed 0.17 1 12 Self Perform Maintenance Assistant 2 Low 0.3 0.6 2.6 2.6
G2030 - PEDESTRIAN PAVING n/a
G2030 - PEDESTRIAN PAVING n/a
G2030.02 Flexible Pedestrian Pavement 2415 m2 n/a
G2030.02.04 Pavement Markings n/a
G2030.03.02 Brick Pavers 240 m2 Pressure wash high traffic areas and main entrances annual 0.08 4 12 Self Perform Maintenance Assistant 4 Low 0.3 1.2 5.2 5.2
G2030.04.01 Rigid Pavement 2140 m2 n/a
G2030.04.02 Pavement Markings Line marking touch Up Annual 0.08 1 12 Self Perform Maintenance Assistant 1 Low 0.3 0.3 1.3 1.3
G2040 - SITE DEVELOPMENT
G2040.02.01 Chain Link Fences and Gates 400 lm Inspect and check operation, minor repair Annual 0.08 2 12 Self Perform Maintenance Assistant 2 Low 0.3 0.6 2.6 2.6
G2040.05.01 Seating n/a
G2040.08 Flagpoles n/a
2 of 4
3 of 4
Total Total
Expected Self Perform Total Total Sub Contract Sub Contract Sub Contract
LEVEL 1 2021 REFURB Quantity of Task Time per Months of PPM Reactive Reactive Maintenance Maintenance
DIV LEVEL 2 INFORMATION LEVEL 3 INFORMATION Unit Tasks Events or Personnel / Trade Reactive Maintenance Annual Labour Material Cost @ Total Annual
INFORMATION BUDGET Assets Frequency Event (hrs) Season Hrs/Yr Risk Level Risk Factor Hrs Hrs
Per Month Subcontract Hrs Hrs Cost 10% Cost
(Self Perform) (Contracted)
Appendix I - Documentation
HANGAR 14 Documents
1 Hangar 14_LCC 03_DRAFT_21-09-29_ALL_Disciplines_Combi (Excel files)
2 Hangar 14_LCC 03_DRAFT_21-10-06_ALL_Disciplines_Combi (Excel files)
3 Hangar 14 Structural Report (Word Documents)
4 Hangar 14 Structural Report (Word Documents)
5 Hangar 14 Mechanical Report Report (Word Documents)
6 Hangar 14 Electrical Report (Word Documents)
7 Option 3 proforma_Draft_21-11-24 (Word Documents)
8 P_CA_COM146_COM146_REC_STUDY_CA_DOC_2017_FINAL
9 Varoius emails/ phone calls from the architects/consultant.
T
11410 Kingsway NW, Edmonton, AB
In accordance with your request by way of a contract dated June 14, 2021 and as per the terms of
reference (TOR) provided herein, I have provided an opinion of the current market value on an all-cash
basis of the fee simple interest in the subject property as at the effective date of November 18, 2021. The
AF
AF
intended user of this report is The City of Edmonton. The intended use is to provide information for
planning purposes and no other use. No additional intended users are identified or intended by the
author.
This Appraisal Report and Appendices must be read as a whole as sections taken alone may be
misleading and lead the reader to an incorrect conclusion. Information provided by the client and
collected through market research and analyses are stored in the working file. This assignment has been
completed in accordance with the Scope of Work as outlined in Section 1.2.
As per the Terms of Reference for this assignment, we have been asked to value the subject property
R
R
under several different scenarios, the first being the As Is market value. The other scenarios involve
redevelopment scenarios based on information as provided by the client.
Subject to the Ordinary Assumptions and Limiting Conditions in Appendix A, it is my opinion that the
current market value of the fee simple interest in the subject property, effective November 18, 2021, is:
D
D
As Is Market Value Estimate: $2,900,000
I estimate that an exposure time of 9 to 12 months would have been required prior to the effective date to
sell the subject property at its current market value. Should you have any questions, please contact
Table of Contents
Angela Barron, AIC Candidate Member or Mike deJong, AACI at your convenience.
1 Introduction ........................................................................................................................................... 1
1.1 Terms of Reference .............................................................................................................................. 1
Respectfully submitted,
1.2 Scope of Work ...................................................................................................................................... 1
DRAFT 1.3 Extraordinary Limiting Conditions ......................................................................................................... 2
Altus Group Limited 1.4 Extraordinary Assumptions ................................................................................................................... 3
1.5 Hypothetical Conditions ........................................................................................................................ 3
1.6 Ownership and History ......................................................................................................................... 3
T
2.2 Site Description ..................................................................................................................................... 7
2.2.1 Site Survey / Plan .............................................................................................................................9
2.3 Land Use Controls .............................................................................................................................. 10
2.4 Building Description ............................................................................................................................ 11
2.5 Municipal Assessment and Taxes ...................................................................................................... 17
AF
AF
2.6 Property Commentary ......................................................................................................................... 17
5 Valuation .............................................................................................................................................. 21
5.1 Valuation Methodology Selected ........................................................................................................ 21
R
6.2 Estimate of Market Value (Direct Comparison Approach) .................................................................. 26
D
7.2 Other Revenue ................................................................................................................................... 29
7.3 Vacancy and Bad Debt Allowance ...................................................................................................... 29
7.4 Recovery Expense Revenue and Operating Expenses ...................................................................... 29
7.5 Income and Expense Pro Forma ........................................................................................................ 30
7.6 Yield Selection .................................................................................................................................... 31
7.6.1 Alternative Investment Yields ......................................................................................................... 31
7.6.2 Recent Investment Market Activity.................................................................................................. 32
7.6.3 Capitalization Rate Analysis ........................................................................................................... 34
7.6.4 Capitalization Rate Rationalization ................................................................................................. 34
7.6.5 Capitalization Rate Conclusion ....................................................................................................... 35
7.7 Direct Capitalization ............................................................................................................................ 36
7.7.1 Estimate of Market Value (Direct Capitalization)............................................................................. 36
CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB
ii
T
11.1.3 Income and Expense Pro Forma .................................................................................................. 57
11.1.4 Estimate of Market Value – Direct Capitalization .......................................................................... 57
11.2 Summary ........................................................................................................................................ 59
12 Certification ......................................................................................................................................... 60
AF
AF
Appendices
Appendix A Altus’ Terms of Reference
Appendix B Visual Identification
Appendix C Comparable Lease Data
R
R
Subject
D
D
Alberta Aviation Museum (Hangar 14)
11410 Kingsway NW, Edmonton, AB
Executive Summary
T
upon a total of 128 surface
Property Class Hangar / Warehouse parking stalls
Redevelopment Scenario 2 Valuation Reconciliation
Net Leasable Area 81,913 sf (7,610 m²), as per Zoning DC1
information provided by the Effective Date November 18, 2021
AF
AF
Municipal Historic Resource
client
Income Approach Capitalization Rate
Year Built 1941 Condition Dated and in poor physical Scenario 2A $6,400,000 Scenario 2A 7.00%
condition
Scenario 2B $8,200,000 Scenario 2B 6.50%
Number of Storeys Single Storey, with some minor Highest and Future General Business or
mezzanine office and storage Best Use Industrial Business Use Redevelopment Scenario 2A Market Value Estimate: $6,400,000
space
Redevelopment Scenario 2B Market Value Estimate: $8,200,000
R
R
As Is Valuation Reconciliation
D
Income Approach $2,900,000 Capitalization Rate 10.00%
Income Approach Capitalization Rate
Direct Comparison $2,900,000 Unit Value $35.00 per sf Scenario 3A $16,400,000 Scenario 3A 6.00%
Approach
Scenario 3B $17,900,000 Scenario 3B 5.50%
CONFIDENTIAL CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB i 11410 Kingsway NW, Edmonton, AB ii
T
► Ceiling height of 29 ft and clear height of 19 ft
► Physically, the subject is in fair to poor condition. The subject was built
in 1941 and is nearing the end of its useful life.
AF
AF
► Multiple components of deferred maintenance exist, including the
heating system which has sub-par functionality. A significant amount of
capital investment is required to bring the subject up to an average
state of condition and repair.
R
► Tight site coverage ratio as compared to a more typical industrial use.
D
► Limited interior office development. The subject essentially involves an
open warehouse space, with limited interior demising.
1
Strengths, Weaknesses, Opportunities, Threats
CONFIDENTIAL CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB iii 11410 Kingsway NW, Edmonton, AB iv
► The subject is in poor to fair physical condition and is nearing the end
T
of its useful life. It requires major renovations and repair; however, this
is complicated by its designation as a Historical Resource, which may
be regarded as a deterrent to potential investors, as renovations
and/or demolition is restricted by this designation.
AF
AF
► The subject improvements no longer support the highest and best use
of the site; whereby the highest and best use as vacant land would be
for the development of a commercial project.
R
R
D
D
Appraisal
CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB v
1 Introduction Review of publicly available physical, legal, social, political, economic and other factors that could
affect the value of the subject property
Collection of municipal information pertaining to the subject property such as zoning, assessment and
1.1 Terms of Reference taxes
Review of documentation relating to the subject property provided by the client or their agent,
The following table provides a summary of the terms of reference (TOR) guiding this appraisal
including but not limited to building condition reports. Documents provided by the client are not
assignment. The TOR were provided by Yogi Subramonian of The City of Edmonton. This report is
available for review without client approval.
subject to the TOR outlined below, as well as the Ordinary Assumptions and Limiting Conditions outlined
in Appendix A. Please also refer to Appendix A of this report for definitions of market value and Highest Research of transactional data on land and buildings comparable to the subject property. As well, a
and Best Use. market rental survey has been conducted to estimate rental rates for the subject property. Sources of
market evidence included real estate agents, vendors, purchasers active in the market etc.
Terms of Reference Estimation of the highest and best use “as if vacant” and the highest and best use of the land “as
improved”, as at the Effective Date.
Client The City of Edmonton
T
Valuation of the interest in the subject property utilizing the most appropriate appraisal methodology;
Intended User Same as client above. No other users are identified or intended by the
in this regard, the Income and Direct Comparison Approaches have been applied and later reconciled
author.
to a final estimate of value
Intended Use of Report To provide information for planning purposes and no other use Consideration of the possible effect on value of an assemblage, consideration of the possible effect
AF
AF
on value of anticipated public or private improvements and there is deemed to be none
Purpose To provide an opinion of the current market value on an all-cash
basis, of the fee simple interest in the property. As per the Terms of Completion of a narrative report outlining background, descriptions, analyses and value conclusion(s)
Reference for this assignment, we have been asked to value the
subject property under several redevelopment scenarios, in addition The analysis set out in this report relied on written and verbal information obtained from a variety of
to the current As Is market value. sources that are considered to be reliable. Unless otherwise stated herein, client-supplied information
was not verified and is believed to be correct. The mandate for the appraisal did not require a report
Ownership The City of Edmonton, as detailed in Section 1.6 prepared to the standard appropriate for court purposes or for arbitration; full documentation or
confirmation of all information by reference to primary sources was not completed.
Interest to be Valued 100% fee simple interest
The following was not included in the scope of work for this assignment:
R
R
Effective Date November 18, 2021
This valuation does not consider any personal property
Signing Date of the Report Draft
Findings that may be discovered through more rigorous due diligence mandate
Current Use of the Property Alberta Aviation Museum
A technical investigation such as the following was not completed:
Property Identification 11410 Kingsway NW, Edmonton, AB
D
D
► detailed inspections or engineering review of the structure, roof or mechanical systems
CONFIDENTIAL CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB 1 11410 Kingsway NW, Edmonton, AB 2
During the course of appraising the subject property, no Extraordinary Limiting Conditions were invoked.
2 Property Description
1.4 Extraordinary Assumptions
2.1 Location Overview
An Extraordinary Assumption, as defined in Section 3.23 of CUSPAP 2020, is an assumption, directly
related to a specific assignment that, if found to be false, could materially alter the opinions or The subject property is situated along Kingsway NW, an arterial road of central Edmonton, located within
conclusions. the Blatchford neighbourhood. The primary land use in this area is mixed use, with general business /
commercial use south of the subject, along Kingsway, and industrial business use west of the subject.
During the course of appraising the subject property, no Extraordinary Assumptions were invoked.
Land uses east and north of the subject involve lands preserved for the future Blatchford Community, a
residential community under development by the City of Edmonton, which will incorporate low to mid rise
1.5 Hypothetical Conditions residential housing and row housing.
A Hypothetical Condition, as defined in Section 3.31 of CUSPAP 2020, is that which is contrary to what A map indicating the exact location of the subject property is contained below. Additional photographs of
T
exists, but is supposed to exist for the purposes of reasonable analysis. the subject property and maps are located in the Appendices.
During the course of appraising the subject property, no Hypothetical Conditions were invoked.
Neighbourhood Map
AF
AF
1.6 Ownership and History
There has been no sales activity for this property within the past three years. Based on research
Subject
completed, it is understood that the subject property is not under an agreement of sale. The subject
property is not currently listed for sale nor has it been listed in the last 12 months on the open market.
R
R
D
D
Source: Edmonton SLIM Maps
CONFIDENTIAL CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB 3 11410 Kingsway NW, Edmonton, AB 4
2.1.1 Former City Centre Airport Due to its central city location, the airport had several curfew and noise abatement procedures. Strict
noise regulations were enforced, as well as height restrictions on all the downtown buildings due to safety
Prior to November 2013, the subject site was home to the Edmonton City Centre Airport (ECCA), also measure for approaching and departing aircraft. The buildings in downtown Edmonton could not be built
known as “Blatchford Field”, which was named after Edmonton’s Mayor at the time, Keith Alexander higher than 150 m above downtown, due to safety clearance for aircraft. The height restrictions of
Blatchford. 2 downtown buildings had impeded several urban projects from proceeding, projects that have been
deemed vital to urban densification and allowing more people to live centrally. Activities due to flight
In 1929, Blatchford Field was created, and it became Canada’s first licenced airfield. It quickly became a activity make developing compact urban neighbourhoods challenging. The tallest building is the Manulife
hub and allowed Edmonton to boom even during the great depression, and it was the busiest airfield in building, rising 150 m above runway threshold. 2
Canada.
In 2009, the city council decided to begin a phased closure of the airport. The airport had two runways; in
The airport was bordered by Yellowhead Trail to the north, Kingsway to the south, 121 Street to the west August 2010, one of the two runways was officially closed (runway 16/34). This closure was seen as a
and NAIT (Northern Alberta Institute of Technology) to the east. It encompassed approximately 144 ac of political phase out move, as the closure of a singular runway did not give the city any additional land to
land just north of the Edmonton’s city centre. 3 work with. By November 30, 2013, the Edmonton City Centre Airport officially closed. 2
T
Former Edmonton City Centre Airport Today, without the airport, the height restrictions have been lifted and the tallest building that can be built
is 312 m, over double the height of the tallest building.2 Following the closure of the airport, the Alberta
Aviation Museum Association approached the City of Edmonton and commenced a lease agreement to
occupy the former airport hangar. As such, the Alberta Aviation Museum and some non-aviation institutes
remained on site. Some lands were transferred to the NAIT and the rest of the land area was converted
AF
AF
by the city, for future residential development. As of 2018, 525 ac of the former Blatchford Field is
undergoing redevelopment into a medium- and high-density neighbourhood.3
Regional / Local Access Local access is afforded from Kingsway NW, an arterial roadway of
central Edmonton, running northwest to southeast.
R
R
Regional access is available from Yellowhead Trail (Highway 16), via
121 Street NW.
Public Transit Kingsway LRT Station is located 1km southeast from the subject.
Edmonton Transit services routes 691 and 903, both east bound and
D
D
west bound, with bus stops available in the immediate subject
vicinity.
Source: flytime.ca Amenities Numerous commercial amenities, such a grocery stores, fuel
stations, banks and general convenience are available along
The airport served as a military airbase during World War II and was a major stop-over on the Northwest Kingsway, directly across the street from the subject.
Stagging Route, which was a series of flight routes developed in 1942, and also hosted two British
Surrounding Land Use South and west from the subject is primarily commercial, including
Commonwealth Air Training Plan schools. 3
general business and industrial business use; future low to medium
density use (Blatchford) is situated east and north of the subject.
Prominent Tenants in the Real Canadian Superstore, Canadian Tire, Servus Credit Union,
2
https://www.flytime.ca/edmonton-city-centre-airport-closure-end-of-era Vicinity Starbucks and U-Haul.
3
https://en.wikipedia.org/wiki/Edmonton_City_Centre_Airport
CONFIDENTIAL CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB 5 11410 Kingsway NW, Edmonton, AB 6
Property Description – Adjacent Land Uses The parking lot is and site area along the east elevation of the building
are finished with asphalt paving. Rigid concrete pavement to the back
North Future Multi-Residential / Blatchford Low to Medium Rise Zone (north side) of the building.
South Commercial Use / Real Canadian Superstore Legal and Title Limitations A full search and interpretation of the title are beyond the scope of this
appraisal and the report is based on the assumption that there are no
East Future Multi-Residential / Blatchford Low to Medium Rise Zone
material encumbrances that would affect value unless otherwise
West Commercial and Industrial Business / ADTEL Inc., Pemco noted. However, as encumbrances can have a significant impact on
Construction, Canadian Tire and Edmonton Inn & Conference Centre the market value and / or marketability, legal advice should be
obtained if this assumption is required to be verified.
T
► 784OX: Utility Right of Way
Property Description - Site Description ► 972 242 986: Caveat Re: Lease
Site Area 4.88 ac ► 002 212 641: Order - Under the Historical Resources Act
AF
AF
Legal Description Lot 1, Block 15C, Plan 5328MC ► 042 452 811: By-law – Under the Historical Resources Act
Topography Generally level and at grade with surrounding parcels and road ► 042 452 812: Condition / Covenant Under the Historical
allowances. Resources Act
The encumbrances related to the Historical Resources Act are
Frontage ± 580 ft, more or less, along Kingsway assumed to have an impact on the marketability of the subject.
Depth ± 620 ft, more or less, from the centreline of the site Environmental Limitations I am not an expert in environmental matters and make no
representations regarding them. For the purpose of this report, it is
Configuration Irregular
assumed that there is no environmental contamination. In order to
verify this assumption, an environmental assessment would be
R
R
Services Standard municipal water and sewer services
required.
Site Coverage ±38.55%
As a result of this assumption, the impact on value of contamination, if
Site Density 2.6 - based upon a building area of 81,913 sf and site area of 212,470 any, has not been taken into account in this appraisal. If contamination
sf does exist, this could have a negative impact on value.
D
D
Ingress / Egress Multi-directional access is afforded from Kingsway NW. Additional
access is available from a service road, which runs parallel to
Kingsway NW.
Site Improvements Perimeter chain-link fencing and landscaping, with one (1) pylon sign
and four (4) exhibition/collection structures related to the aviation
museum.
CONFIDENTIAL CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB 7 11410 Kingsway NW, Edmonton, AB 8
Zoning / Land Use DC1 (Direct Development Control Provision) per Charter Bylaw 19628
General Purpose To preserve Hangar 14, housing the Alberta Aviation Museum, a
designated Municipal Historic Resource, as a museum and
community hub, including additional signage opportunities and
improvements to site accessibility.
T
conditions applied as a result of designation of a historical resource
under the Historical Resources Act, shall take precedence
AF
Maximum Height Maximum height of any structure shall not exceed 14 m (± 45 ft)
Site Specific By-Law 12868 By-law 12868 designates Hangar #14 (the subject) as a Municipal
– Municipal Historic Historic Resource.
Resource
The by-law stipulates that the Hangar #14 shall not be removed,
destroyed, disturbed, altered, rehabilitated or repaired or otherwise
R
R
Source: Alberta Land Titles Plan No. 5328MC permanently affected, other than in accordance with “Schedule B:
General Guidelines for Rehabilitation” so that the regulated historic
features of the building are not impacted.
Land Use Limitations For the purpose of this appraisal, it has been assumed the data
obtained from others is correct and, except to the extent noted, the
D
D
use of property either conforms to the applicable bylaws and
regulations or is a legal non-conforming use. In order to verify this
assumption legal and planning advice would be required.
CONFIDENTIAL CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB 9 11410 Kingsway NW, Edmonton, AB 10
Roof Type Low-slope roof system, finished with modified bitumen membrane
roofing, installed in 2001. The roof slopes above the annexes of the
east and west elevations of the building.
Floor Concrete slab on grade above metal decking and a crawl space
T
Windows & Doors All windows were reportedly installed in 1995.
The windows serving the staff area consist of insulated glazing units
with PVC frames; the windows servicing the museum, hall area and
AF
AF
restoration area consist of insulated glazing units within aluminum
frames.
Entrance doors serving the museum are single glazed with aluminum
frame; with doors serving remaining areas consisting of painted steel
doors.
Source: Edmonton SLIM Maps
Large, painted metal hangar doors are located along the north and
2.4 Building Description south elevations of the building.
Fire & Safety Wet-pipe sprinkler system is provided, as well as fire extinguisher
R
R
The following is based on an inspection completed on November 18, 2021 and data obtained from the cabinets, smoke alarms and accessories
Client:
Security Standard security access and surveillance system
Property Description – Building Description Mechanical Systems The subject is heated via a forced air heating system, with heat
provided by two (2) x Dravo gas-fired furnaces. The forced air passes
D
D
Type Single-Storey Hangar (Double Wide)
through a central conduit duct, located in a crawl space beneath the
Year Built 1941 floor slab.
Number of Storeys Single-Storey, with some minor mezzanine office and storage space The furnaces are original, dated 1941. At the date of inspection, it was
reported that one of the furnaces was no longer functioning, and that
Net Rentable Area 81,913 sf the heat source is inadequate to maintain an appropriate standard of
heating within the subject.
Number of Units Single rentable unit
Mezzanine Space Minor upper mezzanine areas are installed along the central wall of Hot water system is provided by a total of four (4) electric hot water
the building (north to south) as well as a mezzanine level along the tanks, with a main 175-litre hot water tank, as well as three (3) 67 litre
east elevation of the building. hot water tanks located in the washrooms and laundry station.
CONFIDENTIAL CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB 11 11410 Kingsway NW, Edmonton, AB 12
Electrical Total of six (6) electrical service stations, with amperage ranging from Main Floor Plan
100 AMPs to 400 AMPs. Electrical systems are assumed to be
adequate for building use.
Layout The subject involves a double wide hangar with annexes along the
east and west elevations of the building.
The layout of the subject involves a main floor entrance with visitor
reception and a gift shop to the east. The main floor of the building is
divided into three major spaces:
T
Cadet / Hall Area: located in the southwest quadrant of the
building
AF
workshops along east and west annexes, and within the central
demising wall of the hangar, as illustrated in the floor plans below.
R
R
D
D
CONFIDENTIAL CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB 13 11410 Kingsway NW, Edmonton, AB 14
2nd & 3rd Floor Plan Functional Utility The building has below average functional utility for industrial use.
(Mezzanine Levels)
Condition/Appeal The overall condition/appeal of the building is below average.
T
structural and mechanical systems original. The Marshall & Swift
Tables estimate a typical life of 45 to 50 years for a comparable
building of this class and construction. Ultimately, the subject building
is nearing or has passed the point of having any remaining economic
life and will require substantial reinvestment in order to remain viable.
AF
AF
Functional obsolescence pertains to a building’s inability to perform its
intended function efficiently. The design of the subject building was
originally for airport hangar accommodation. The building as it
currently exists exhibits substantial functional obsolescence for any
alternative commercial or industrial use.
R
Building Description A structural survey has not been undertaken, and for the purpose of
Finish Ceilings consist of exposed heavy timber and truss system with Limitation this report, it is assumed that the building is structurally sound. In order
tension cables, allowing for a clear span of 34 m (± 112 ft). to verify this assumption, a qualified engineer should be retained.
Interior walls finished with painted gypsum board and flooring consists Historical Designation The subject is encumbered by:
of exposed concrete slab flooring.
D
D
Bylaw 12868, a bylaw designation the subject (Hangar 14) as a
Clear Height 19 ft Municipal Historic Resource under the Historical Resource Act,
as well as;
Lighting Fluorescent shop light fixtures and fluorescent high bay lighting
Charter Bylaw 19628, a Direct Development control provision
Shipping The subject is not afforded any loading docks nor loading bays. aimed to preserve Hagar 14, which is designated as a Municipal
Historic Resource, housing the Alberta Aviation Museum, as a
Washrooms Three (3) sets of men’s and ladies’ washrooms are provided. museum and community hub.
CONFIDENTIAL CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB 15 11410 Kingsway NW, Edmonton, AB 16
Municipal assessment and taxes are not applicable, as the subject is owned by the City of Edmonton.
T
2.6 Property Commentary
AF
utilized as a large, warehouse facility, owner-occupied by the City of
Edmonton (Alberta Aviation Museum).
The subject improvements are nearing the end of its useful life,
wherein the underlying land value is greater than the value of the
improvements.
R
D
D
Source: Altus Group Economic Consulting
4
https://www.edmonton.ca/city_government/edmonton_archives/restoring-a-historical-resource
CONFIDENTIAL CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB 17 11410 Kingsway NW, Edmonton, AB 18
Given the location of the subject property, the size and configuration of the site, as well as the current
zoning, it is likely that its use would be consistent with similar properties in the immediate area if it were
vacant land. Based on the foregoing, it is concluded that the highest and best use of the subject property,
as vacant land, as at November 18, 2021, would be for the development of a commercial project,
involving general business use or industrial business use.
T
Based on a review of the existing by-laws, the subject property appears to conform to existing land use
controls. A formal legal review would be required for certainty.
AF
AF
The subject property is improved with an 81,193-sf warehouse facility, built in 1941. As described in this
report, the subject improvements are in fair to poor condition, and nearing the end of their useful life.
Further, the improvements have below average functionality for a standard industrial user.
It is also noted that the subject is impacted by a Historical Resource designation, which imposes
restrictions and limitations on potential renovations, repairs and/or demolition. Further, it is estimated that
the current underlying land value of the subject site is greater than the value of the improvements. As
such, the current use of the subject no long supports the highest and best use of the site.
Having regard for the location, the size and configuration of the site, as well as the current zoning, it is
R
R
likely that its use would be consistent with similar properties in the immediate area. Surrounding land
uses in the immediate subject vicinity mainly involve general business and industrial business use, with
future residential use to the north of the subject lands.
Based on the existing surrounding land uses and given the subject’s prominent location with frontage
along Kingsway NW, it is concluded that the current use of the subject property is an underutilization
D
D
Source: Altus Group Economic Consulting
based on the current Highest and Best use of the site.
CONFIDENTIAL CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB 19 11410 Kingsway NW, Edmonton, AB 20
The Income Approach recognizes the principle of anticipation, where the anticipation of future benefits The Direct Comparison Approach is considered useful not only in terms of estimated value, but also in
creates value. The Income Approach is usually used as the primary method of valuation when a property demonstrating that the final value estimate concluded in the appraisal falls within a reasonable range of
is expected to be acquired by an investor. The Income Approach is comprised of two primary methods: value evident in the marketplace.
Direct Capitalization: This procedure involves dividing the stabilized net annual operating
The typical procedure for undertaking the Direct Comparison Approach involves:
income (NOI) by a singular rate that takes into account the investment characteristics of the
subject property. researching the market for data from sales, contracts, offers and listings of competitive properties;
T
Discounted Cash Flow (DCF): This method calculates the present value of the future cash verifying that the data is accurate and representative of arm’s-length transactions;
flows over a specified time period, including the potential proceeds of a deemed disposition, to
determine market value. determining relevant units of comparison;
comparing the subject with the comparable property sales and adjusting the comparable property
AF
AF
Direct Comparison Approach sales for differences; and
The Direct Comparison Approach recognizes the principle of substitution, according to which a buyer will reconciling the multiple value indications into a single value or range of values for the subject
not pay more for one property than for another that is equally desirable. By this approach, an opinion of property.
value is developed by applying a comparative analysis of properties that are similar to the subject
property that have recently sold, are listed for sale or are under contract, by focusing on the similarities
and differences that affect value. 6.1 Comparable Property Sales Activity
The Direct Comparison Approach requires adjustments to be made to the comparable property sales to
Cost Approach
reflect differing characteristics. The ‘adjusted’ comparable property sale price reflects the price that would
The Cost Approach recognizes the principle of substitution, according to which a knowledgeable have been paid if the comparable property sale had all the same characteristics as the subject.
R
R
purchaser would not pay more for a property than it would cost to construct a property of similar design
and utility, assuming no unreasonable delays. The Cost Approach involves adding the market value of the The adjustment process can take the form of either ‘quantitative’ or ‘qualitative’ adjustments. The
land to the depreciated value of the building and site improvements. quantitative method applies specific plus and minus adjustments to each characteristic. The qualitative
method provides an opinion as to whether the comparable property sale has superior or inferior
characteristics to the subject but does not apply dollar or percentage quantum to each character
5.1 Valuation Methodology Selected difference. The qualitative method has been utilized for the Direct Comparison Analysis.
D
D
The subject property is an owner-user property, consequently, the Direct Comparison Approach has been The most important characteristics of each comparable property together with time and qualitative
used as the primary method of valuation. The market value is determined in using a range of market unit adjustments for differences to the subject are shown in tabular form on the next page.
prices demonstrated by the sales or listings of comparable properties.
A survey of market evidence for properties having similar characteristics to the subject property has been
The Income Approach has also been applied, primarily as a cross-check, supporting the value conclusion
conducted. The sales summarized mainly pertain to larger, older warehouse buildings which were
derived from the Direct Comparison Approach.
reported to be in below average to poor physical condition at the date of sale. A number of the sales
outlined were purchased with the intention renovate and/or demolish and redeveloped.
The Cost Approach has not been used, as it does not typically reflect the motives and actions of buyers
and sellers of this type of property.
From the research, the most appropriate in terms of comparable property sales evidence for the Direct
Comparison Approach is contained at and summarized below.
In addition, based on the physical condition and underutilization of the subject property, we have
completed a supplemental analysis determining the underlying land value of the subject property utilizing
the Direct Comparison Approach.
CONFIDENTIAL CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB 21 11410 Kingsway NW, Edmonton, AB 22
The building was vacant at the date of sale, has an area of 77,089 sf and sold in March 2021 for
2 Civic Address 5910 97 Street NW Sale Date Mar-21 $43.43 Slightly Superior
$3,800,000, reflecting a unit rate of $49.29 per sf. Sale details denote that the building was purchased
Municipality Edmonton, AB Adj Sale Price $1,150,000
Rentable Area 26,482 sf with the intention to demolish, as Potential Environmental Concerns (PECs) existed. As such, the sale
price equates to approximately $900,000 per ac based on the site area. The vendor had completed partial
remediation of the site prior to the sale, and also absorbed the cost to complete remediation prior to
3 Civic Address 16295 132 Ave Nw Sale Date Sep-20 $48.63 Slightly Superior
Municipality Edmonton, AB Adj Sale Price $1,950,000 closing of the sale. However, there remained contamination beneath the building foundation which cannot
Rentable Area 40,096 sf be remediated until the building is demolished.
T
4 Civic Address 12229 Fort Rd Nw
Municipality Edmonton, AB
Sale Date Sep-20
Adj Sale Price $1,150,000
$38.33 Similar
Index 2
Rentable Area 30,000 sf
Index 2 relates to a 26,482-sf warehouse facility located along 97 Street, in Coronet Industrial, of south
central Edmonton. The building was vacant at the date of sale and sold in March 2021 at a unit value of
5 Civic Address 15253 121A Ave Nw Sale Date Apr-20 $49.38 Slightly Superior
$43.43 per sf. The building is of concrete block construction, built in 1974, and was vacant at the date of
Municipality Edmonton, AB Adj Sale Price $3,250,000
sale. The building includes a machine shop and fabrication warehouse as well as office and mezzanine
AF
AF
Rentable Area 65,810 sf
space and a paint booth. The property is also equipped with craneways throughout, a clear height of 18.5
ft and a grade loading overhead door. Physically, the property was in below average condition; however,
6 Civic Address 15205 112 Ave Sale Date Feb-19 $69.66 Slightly Superior
Municipality Edmonton, AB Adj Sale Price $3,350,000 functional for a standard industrial user, and, smaller in magnitude than the subject. As such, a unit value
Rentable Area 48,093 sf slightly below this range is suggested for the subject.
R
Municipality Edmonton, AB Adj Sale Price $1,600,000
Rentable Area 32,144 sf of sale. It is of metal frame construction, demised into an office, showroom and 36,799 sf of warehouse
space. The building is also afforded 11 dock level loading doors and one grade level loading door with
clear heights ranging from 17.5 ft to 23 ft. The building was vacant at the date of sale; the purchaser
planned to renovate and occupy the space.
D
D
Index 4
Index 4 references the sale of a 30,000-sf warehouse facility which sold in September 2020 for
$1,150,000, or, $38.33 per sf. The facility is located along Fort Road, approximately 7 km northeast from
the subject, in the Yellowhead Corridor East neighbourhood. The building is of older vintage, constructed
in 1978. It is of concrete block construction, with 15,000 sf of main floor space demised into 6 warehouse
bays, and 15,000 sf of 2nd floor office space. At the sate of sale, the property was mostly vacant and in
poor physical condition; the property was marketed as a potential condo conversion project. This property
is similar to the subject in terms of physical condition and functionality; however, a unit rate slightly below
this range is suggested for the subject, given the variance in building size.
CONFIDENTIAL CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB 23 11410 Kingsway NW, Edmonton, AB 24
The subject lacks some standard industrial amenities such as overhead loading doors, dock loading
Index 6 doors and truck turning space.
Index 6 refers to a 48,093-sf warehouse facility located in High Park Industrial, approximately 5 km west The subject features limited office development, and a tight site coverage ratio resulting in limited
from the subject, which was reported to have physical deficiencies at the date of sale and purchased with onsite yard storage and truck access.
T
the intention of demolishing portions of the building for redevelopment. The property was vacant at the
date of sale, and sold in February 2019 for $3,350,000, equating a unit value of $69.66 per sf. The facility The subject is influenced by a heritage resource designation, which could be seen as a deterrent to
was built in 1966, is of concrete block construction, and is demised into two floors, including 35,293-sf of protentional investors / users, as it imposes restrictions on building renovations and/or demolition.
main floor shop/warehouse space with a 19.5-ft clear height and grade loading doors. As rate below this
range is recommended for the subject, being a larger facility with a heritage resource designation, and, in Giving consideration to the discussion, the final unit rate conclusion towards the lower end of the range is
AF
AF
inferior physical condition. estimated for the subject property, at $35.00 per sf.
Based on this unit value conclusion, it is my opinion that the value of the subject property through use of
Index 7 the Direct Comparison Approach is $2,900,000 as set out in the calculation below.
Index 7 involves the June 2018 sale of a single-tenant warehouse facility which occupies a prominent
location along 107 Avenue in the Queen Mary Park neighbourhood of north central Edmonton. The June Direct Comparison
2018 sale price of $4,800,000 reflects a unit rate of $73.08 per sf.
R
demolishing approximately half of the building, and renovating the remaining half of the property, forming Value Conclusion $2,866,955
a retail development known as Manchester Square, a 20-bay retail property with a total rentable area of Final Value $2,866,955
52,890 sf. Final Value (Rounded) $2,900,000
Index 8
D
D
Index 8 involves the sale of a 32,144-sf warehouse facility located along 93 Street in Strathcona Industrial
Park. The building transferred in December 2018 at a purchase price of $1,600,000, or, $49.78 per sf.
The property was reported to be vacant and in poor physical condition at the date of sale. The property is
of tilt-up construction, was built in 1980 and includes a 20-ft clear height, eight overhead loading doors,
10 interior jib cranes and 1 exterior crane. The purchaser, Redco Properties, planned to renovate and
lease the building. With this property being superior in terms of industrial user amenities, and, given that it
is of smaller magnitude and is not influenced by a heritage resource designation, a unit value below this
range is suggested for the subject.
CONFIDENTIAL CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB 25 11410 Kingsway NW, Edmonton, AB 26
7 Income Approach – As Is Value The estimate of the market rental rates varies throughout the subject property and is influenced by a
number of factors including the location, size, configuration and potential use. It is noted that the subject
was observed to be in a fair state of physical condition and repair, with multiple elements of deferred
The theory of the Income Approach is that the value of a property is the present worth of all the net maintenance. Consequently, the lease comparables selected mainly involve older facilities which were in
income that it will produce for each year of its remaining useful life. Net income serves as a measurement a similar state of condition and repair at the commencement of their respective lease terms. While some
that, in turn, is capitalized into a value estimate by the use of a capitalization rate taken from the of the lease comparables are older, they are reflective of a typical price per sf range that can be achieved
experience of similar properties that have already sold or from the state of the financial market at the time for older warehouse facilities. It is also noted that a prospective tenant for the subject would incur higher
of the appraisal. The rental income of a property will generally reflect all attributes and amenities inherent than average operating costs, due to the inferior function of the subject’s heating system. This would have
in that property. an additional impact on the market rent that the subject could likely obtain.
7.1 Income Forecasts The comparable rental rates vary between $2.50 per sf and $6.50 per sf, with an average of $4.48 per sf,
for single-tenant and two-tenant facilities, with net effective rents (NER) ranging from $2.59 per sf to
$5.43 per sf.
The following section outlines an analysis of the subject property leasing activity, current tenant profile,
market rent factors, and estimate of normalized vacancy and bad debt, operating expenses, and capital
T
Single tenant properties are known to engender a premium rental rate compared to multi-tenant
expenses.
properties. This is due to the motivation of the tenant to control their yard and storage area, along with the
benefits of associating their building with a brand or manufacturer name. Control of a yard can also
7.1.1 Tenant and Income Profile influence the rate, as site storage with either compacted gravel or paved with concrete or tarmac, will
raise the level of improvements (and cost) provided by the landlord.
The subject is currently occupied by the owner. For area that is occupied by an owner, a market rental
AF
AF
rate is assumed. The lease rate assumes the owner to lease the premises over a lease term typical in the The lower end of the range is set by Index 3, relating to a 25,000 sf warehouse facility located in the
market. Foothills Industrial area of Calgary. This new lease deal was at $2.50 per sf, for an 8-year term,
commencing in Q1 2020, for a bay within a multi-tenant facility that was reported to be in poor shape and
7.1.2 Market Rent Analysis nearly obsolete. A rate slightly above this range is recommended for the subject, given that it is a single-
tenant facility.
The term “market rent” is generally defined as being the most probable rent that a rental unit would
command if exposed to the open market for a reasonable period of time. The process of estimating the Index 1, towards the upper end of the range, at $5.00 per sf, involves an older, 55,000 sf warehouse
market rent presumes that the space in question is vacant and available for lease. Since no two rental facility which was built in 1967, located in Calgary’s Manchester Industrial area. The lease was a new
units are alike, the estimation of market rent must account for the specific characteristics of each lease deal, commencing in Q3 2018, for a 10-year term. A rate below this range is suggested for the
particular location, as well as the physical features and functional attributes of each space. In order to subject, given that it is in an inferior state of physical condition and repair.
R
R
estimate market rent for the subject property, recent leasing activity in the subject property and at
comparable premises have been reviewed. Details of the analysis are provided below. Special reference is made to Index 12, relating to an "as-is" lease agreement for an airport hangar located
on leased land at the Edmonton International Airport. The total rentable area of 70,000 sf includes the
Comparable Leasing hangar bay which has an area of 34,727 sf. The total rentable area also includes additional office,
mezzanine and training areas, as well as shops and storage on the 2nd and 3rd floors. This is an older
D
D
In addition to the review of leasing activity in the subject property, a survey of the marketplace has been lease deal, having commenced in Q4 2009 for a 5 -year term; however, the year 1 base rental rate of
carried out as it relates to the leasing activity in similar industrial developments in Edmonton. The rental $4.00 per sf, is indicative of a price per sf range for industrial facilities which also accommodate the use
market in Edmonton is stable. as an airport hangar. A lower base rental rate is suggested for the subject, given its inferior state of
condition and repair
A review of the market leases considered to be the most comparable to the subject space are presented
in the chart contained in Appendix C. To maintain the confidentiality of the data, specific addresses have Overall, the market rent estimate shown below is generally supported by the results of the market survey.
not been identified and specific details have been retained on file.
CONFIDENTIAL CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB 27 11410 Kingsway NW, Edmonton, AB 28
T
user. The income analysis is based on a triple net lease with the tenant responsible for all operating expenses,
1 including realty taxes and a management fee
Based on the discussion above and the review of the comparable rents outlined in Appendix C, the 2 Incorporates market orientated rents
market rental rate for the subject is estimate at the lower end of the survey range, as outlined below: 4 No vacancy allowance is applied for single-tenant assets
AF
AF
Market Rental Rate Conclusions
No additional revenue streams have been identified for the subject property.
R
R
7.3 Vacancy and Bad Debt Allowance
No vacancy and bad debt allowance has been applied to the subject property, typical of investor attitude
towards single-tenant assets. All sales are analyzed under the same parameters.
D
D
7.4 Recovery Expense Revenue and Operating Expenses
The concluded market rental rate is based upon a net rental term. In this circumstance, the tenant would
be responsible for all operating expenses, including realty taxes and management fees.
CONFIDENTIAL CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB 29 11410 Kingsway NW, Edmonton, AB 30
In order to determine the appropriate yield for the subject property; specifically, the capitalization rate
(CR); the following factors have been considered:
T
The CR selected to value the subject property is expected to be higher than the average yield of 1.77%
indicated by 10-year Canada Bonds as of November 2021. The premium attributable to real estate is
based primarily on the lack of liquidity, increased management and the greater overall risk associated
with real property assets.
AF
AF
Altus InSite Investment Trends Survey
The following are the results of the Altus InSite Investment Trends Survey for the benchmark Single-
Tenant Industrial Building at Q3 2021 in the Edmonton area:
It is acknowledged that the subject property would be ranked as vastly inferior to the comparable 7.6.2 Recent Investment Market Activity
properties utilized for this survey, which would support a CR very much above the top end of the ranges
identified. A review of recent market activity provides additional support for the selection of yields. The most relevant
R
R
transactions that were found are summarized on the following page. To ensure comparability, the same
methodology used for the analysis of the subject property has been applied to the analysis of the
comparable property sales.
D
159
CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB
D
CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB 32
Value Appraisal
DRAFT v.1 - December 13, 2021 DRAFT v.1 - December 13, 2021
The most recent sale, Index 1, involves an 87,743-sf single-tenant industrial facility which was built in
2 Civic Address 11931 145 St Nw Sale Date Apr-20 IRR 8.08%
1997 and is located Great Plains Industrial, Calgary. This manufacturing facility was formerly owned and
Municipality Edmonton, AB Adj Sale Price $7,068,000 TCR 7.50% occupied by Tesco and was sold to an investor in April 2021 at an 8.11% CR. The facility includes
Rentable Area 71,381 sf Price PSF $99 CR 6.85% overhead cranes, good power and secure paved yard. The rentable area includes main and second floor
offices, a shop office, mezzanine, and manufacturing area with full crane coverage (16 cranes total).
There is approximately 20 ft of clear height below the cranes. This facility is superior to the subject in
3 Civic Address 16725 114 Ave Nw Sale Date Feb-20 IRR - terms of age and physical condition and is indicative of a typical yield rate for a functioned industrial
Municipality Edmonton, AB Adj Sale Price $2,200,000 TCR - facility in average physical condition. Given the age and physical condition of the subject, and lack of
T
Rentable Area 20,194 sf Price PSF $109 CR 10.00% attributes typically required by a standard industrial user, a yield rate above this range would be
warranted for the subject.
4 Civic Address 16404-16424 117 Ave Nw Sale Date Sep-19 IRR 8.02%
The upper end of the range is set by Index 3, which transferred in February 2020 at a CR of 10.00%. This
Municipality Edmonton, AB Adj Sale Price $14,100,000 TCR 7.25%
comparable formed part of a 10 property portfolio acquisition and involves a 21,194-sf warehouse facility
AF
AF
Rentable Area 182,859 sf Price PSF $77 CR 7.26%
located in West Sheffield Industrial, Edmonton. The facility is of older vintage, built in 1973, is of concrete
block construction, is demised into two bays (5537sf & 14,657 sf) and contains six (6) overhead grade
5 Civic Address 10303 174 St Nw Sale Date Jul-18 IRR - loading doors. The property was fully leased to two tenants at sale date. It was reported that there was an
Municipality Edmonton, AB Adj Sale Price $2,887,500 TCR - estimated $1,500,000 in deferred maintenance at the date of sale. A CR within this range would be
Rentable Area 27,460 sf Price PSF $105 CR 8.02% suggested for the subject.
The lower end of the range is set by Index 2, which sold in April 2020 at a CR of 6.85%. This comparable
6 Civic Address 4601 99 Street Sale Date Sep-19 IRR 0.00% relates to a 71,381-sf single-tenant warehouse facility located Dominion Industrial, Edmonton. The
Municipality Edmonton, AB Adj Sale Price $3,100,000 TCR 0.00%
building was built in 1973 and is of steel frame and concrete block construction. Rail connectivity is
Rentable Area 23,289 sf Price PSF $133 CR 8.76%
available along the east side of the building. At the date of sale, the facility was fully occupied by Russell
R
R
Food Equipment Ltd., operating as Russell Hendrix (tenant), Canada’s largest supplier of food service
7 Civic Address 9526 Yellowhead Trail Sale Date Jun-17 IRR 0.00%
equipment and food supplies. The remaining lease term was 8.65 years (July 31, 2028), with two (2) 5-
Municipality Edmonton, AB Adj Sale Price $4,550,000 TCR 0.00%
year renewal options, with contractual rental escalations. With a strong tenant profile and lease term in
Rentable Area 48,330 sf Price PSF $0 CR 9.61% place, a CR above this range is warranted for the subject.
The remaining comparable sales support CRs ranging between 7.26% and 9.61%.
D
D
7.6.4 Capitalization Rate Rationalization
In addition to the analysis of alternative investment yields, the Altus InSite Investment Trends Survey and
recent market activity, the following factors have been ranked in order to assist the reader in
understanding the investment yields selected for the subject property. These factors compare the subject
property’s investment attributes with typical characteristics observed in the market for this type of
property. An “average” rating indicates similarity with market expectations.
CONFIDENTIAL CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB 33 11410 Kingsway NW, Edmonton, AB 34
Condition/Appeal Fair condition, with multiple elements This procedure entails three steps:
of deferred maintenance.
The stabilized net operating income (NOI) was determined.
Size 81,913 sf
In this section, the NOI was capitalized at a CR of 10.00%, as determined in the Yield Analysis
Functional Utility Below average, lacking standard section, to estimate the market value based on stabilized occupancy.
industrial improvements such as
This value will be adjusted, if applicable, for rent abatements, above/below market rent, existing
overhead loading door, dock loading
vacancy, short-term leasing costs, capital expenditures and amortized capital expense revenue.
doors and craneways.
T
Limited interior office development 7.7.1 Estimate of Market Value (Direct Capitalization)
AF
1 Total Stabilized NOI $286,696
Financial Occupancy Owner-user occupied Below Average
2 Capitalization Rate 10.00%
Market Rent Low-end of market parameters, at 3 Stabilized Value $2,866,955
$3.50 per sf (NER) 4 Total Adjustments $0
5 Final Value $2,866,955
External Neighbourhood Blatchford Neighbourhood, with Below Average 6 Final Value (Rounded) $2,900,000
exposure and frontage along
Kingsway NW, an arterial roadway of
the inner city.
R
characteristics, as the subject required
a significant amount of capital
investment for elements of deferred
maintenance. Further, the designation
as a Historical Resource is a deterrent
for typical investors, as the bylaw
D
D
imposes limitations with respect to
renovations and/or site-
redevelopment.
CONFIDENTIAL CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB 35 11410 Kingsway NW, Edmonton, AB 36
The subject property is comprised of a total area of 4.88 ac and is afforded frontage along Kingsway NW,
wherein surrounding land uses mainly involve commercial / general business use, as well as industrial
business use.
Land transactions have been researched and sales compiled that show the greatest degree of
comparability to the subject. These are shown in summary form on the table set out below. Full details
T
have been kept on file. AF
R
D
CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB 37
1 5304 Admiral Girouard St Canada Lands Company CLC Ltd. Closed $5,002,500 4.35 ac $1,150,000 per ac General Business
Edmonton, AB Jewel of Griesbach Ltd. Mar-21 CB2
2 12560 Fort Road 539878 Albeta Ltd. Closed $2,380,000 1.56 ac $1,525,641 per ac Industrial Business
T
Edmonton, AB The City of Edmonton Aug-20 IB
3 7430 68 Ave NW Remington Development Corporation Closed $4,200,000 3.68 ac $1,141,304 per ac General Business
Edmonton, AB Stalwart Davies Properties Ltd. Feb-20 CB2
AF
4 403 Mistatim Way Delcon NW Edmonton Lands Ltd. Closed $4,121,600 2.94 ac $1,401,905 per ac General Business
Edmonton, AB Elite Real Estate Investments Inc. Apr-19 CB2
5 12719 156 Street NW Allweather Holdings Ltd. Closed $3,000,000 2.60 ac $1,153,846 per ac Industrial Business
Edmonton, AB Alliance MJ Developments Ltd. Jan-19 IB
6 180 Mistatim Road Delcom NW Edmonton Lands Ltd. Closed $2,968,000 2.12 ac $1,400,000 per ac General Business
Edmonton, AB 2119606 Alberta Ltd. Jun-18 CB2
7 12380 121 Street NW 745284 Alberta Ltd. Closed $5,500,000 4.82 ac $1,141,079 per ac Industrial Business
R
Edmonton, AB The City of Edmonton Sep-18 IB
D
CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB 38
T
AF Subject Index 1
AF
R
R
Index 2 Index 3
D
D
Legend
1 5304 Admiral Girouard St, Edmonton, AB 2 12560 Fort Road, Edmonton, AB 3 7430 68 Ave NW, Edmonton, AB
4 403 Mistatim Way, Edmonton, AB 5 12719 156 Street NW, Edmonton, AB 6 180 Mistatim Road, Edmonton, AB
CONFIDENTIAL CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB 39 11410 Kingsway NW, Edmonton, AB 40
Index 6 Index 7
T
The above summarized land sales illustrate unit rates between $1,141,079 per ac and $1,525,641 per
ac, with site sizes ranging from 1.56 ac to 4.82 ac.
Index 1 represents the most recent sale of the dataset and involves a 4.35-ac parcel of CB2 (General
AF
Business) zoned land, located in the Griesbach neighbourhood of north central Edmonton, approximately
5 km north from the subject. This parcel transferred in March 2021 at a unit rate of $1,150,000 per ac.
The site occupies a corner position, at the intersection of Admiral Girourard Street and 137 Avenue NW,
an east-west arterial roadway of the north Edmonton. This transaction is highly comparable to the subject
and provides a strong indication as to an appropriate unit value for the subject.
The lower end of the range is set by Index 7, at $1,141,079 per ac. This transaction occurred in
September 2018 and involves a 4.82-ac parcel of IB (Industrial Business) zoned land which was acquired
by the City of Edmonton. The site is a corner site with direct access and exposure to Yellowhead Trail,
also located along the northwest periphery of the future Blatchford residential community. Sale details
denote that water and sewer connections were not directly available and the cost to connect services
R
would range between $410,000 and $550,000. The indicated adjusted price per acre would range
between $1,037,344 per ac and $1,066,390 per ac. A similar unit value would be expected for the
subject.
The upper end of the range is set by Index 2 at $1,525,641 per ac. This sale relates to a 1.56-ac parcel of
D
IB (Industrial Business) zoned land, located on Fort Road, in the Yellowhead Corridor East
neighbourhood. The site was acquired by the City of Edmonton in August 2020 for purposes of road
upgrades being completed to the Yellowhead trail. The site has a highly irregular configuration, backs
onto a rail line and a small portion of the site is zoned CB2. Given the difference in site magnitude,
wherein an inverse relationship exists between parcel size and unit rates, a lower unit value would be
expected for the subject.
Remaining comparable sales exhibit unit values ranging from $1,141,304 per ac to $1,401,905 per ac.
CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB 41
Reference is made to Index 4, a 2.94-ac parcel of land which sold in August 2019 for $4,121,600,
reflecting a unit price of $1,401,905 per ac. The site has CB2 zoning and occupies a corner position in
9 Reconciliation and Conclusion – As Is Value
Mistatim Industrial, with frontage along 137 Avenue NW, an east-west arterial roadway of the City. The
purchaser, Elite Real Estate Investments Inc., acquired the site for the purpose of developing three The estimates of value from the approaches used are:
retail/office buildings, totalling ±44,000 sf. Overall, this sale is highly comparable to the subject in terms of
location and potential land use; however, a lower unit rate is warranted for the subject, given that it is Final Value Conclusions
larger in size.
Valuation Methodology Parameters Conclusion
Direct Capitalization Cap Rate 10.00% $2,900,000
Giving consideration to the location, size and condition of the subject property, it is my opinion that the
value of the subject property’s land value would be $1,200,000 per ac. On the basis of the above analysis Direct Comparison Price PSF $35.00 $2,900,000
and discussion, please see the table below for the market value estimate of the excess land of the subject Final Value Conclusion (Rounded) $2,900,000
property. Final Value Conclusion PSF $35.40
Value Conclusion - Site Area In arriving at a final conclusion of market value, the Direct Comparison Approach is accorded the greatest
T
weight given that the subject property is an owner/user property.
AF
VALUE CONCLUSION (ROUNDED)
Further to the analysis of the subject property and of the market data outlined in this report, the current
$5,900,000
market value of the property located at 11410 Kingsway NW, Edmonton, AB as at November 18, 2021,
subject to the Ordinary Assumptions and Limiting Conditions in Appendix A, is:
As Is Value: $2,900,000
Two Million Nine Hundred Thousand Dollars
R
R
An estimated exposure time of 9 to 12 months would have been required prior to the effective date to sell
the subject property at its current market value.
D
D
CONFIDENTIAL CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB 42 11410 Kingsway NW, Edmonton, AB 43
T
A review of the market leases considered to be the most comparable to the subject space once upgrades
It is noted that the Gross Building Area for all scenarios is 8,593 m², or 92,494 sf. are complete, are presented in the chart contained in Appendix C. To maintain the confidentiality of the
data, specific addresses have not been identified and specific details have been retained on file.
For the purpose of this analysis, the net leasable area (NLA) is assumed to be 7,610 m², or, 81,914 sf,
based upon a Facility Condition Report provided by the Client, dated August 2017. For larger warehouse facilities in an average to good state of condition and repair, lease comparables
AF
AF
reflect year 1 base rental rates ranging from $4.45 per sf to $8.50 per sf, with an average of $6.69 per
The redevelopment scenarios and their respective impacts on value are summarized below. sf, for facilities ranging in size from 40,000 sf to 110,000 sf.
Reference is made to Index 3, which involves a 39,965 sf single-tenant warehouse facility located in
10.1 Redevelopment Scenario 1 Dominion Industrial, approximately 4 km west from the subject. This lease involves a new lease deal
commencing in October 2020, for a 12-month term at a year 1 base rental rate of $6.00 per sf. The
Scenario 1 involves a 20-year rehabilitation project. All renovations within this scenario shall follow the property is of older vintage, originally built in 1962, with an office expansion in 1994 and shop expansion
Standards and Guidelines for the Conservation of Historic Places in Canada and comply with Bylaw in 2002. It is noted that major renovations and exterior upgrades were completed in fall 2016. The base
12868, a bylaw designating Hangar #14 (the subject) as a Municipal Historic Resource. The renovations rental rate is based upon main floor area 29,280 sf, as well as a concrete mezzanine area of 10,685 sf.
shall also follow any requirements of Alberta Culture, Multiculturalism and Status of Women through the As an older warehouse that underwent significant renovations, a similar rental rate would be expected for
R
R
Provincial Historic Resource designation (Charter Bylaw 16828). the subject in Scenario 1. However, as a larger facility, where an inverse relationship exists between
building area and achieved rental rates, and given the subject’s lack of standard industrial amenities,
There are two options within Scenario 1; they are as follows: including lack of yard storage due to the historical resource designation, a rate slightly below this range
would be expected.
Scenario 1A
Index 13 provides an example of a market rental rate that can be garnered for a newer warehouse facility
D
D
Extends the useful life of the subject for a further term of 20 years, and essentially involves keeping the
building operating ‘as is’ in terms of physical layout and functionality. Scenario 1A incorporates major of similar magnitude. This lease comparable relates to the Discovery Centre, located in Discovery
renovations to the building envelope, mechanical and electrical systems, and the functionally of these Business Park, South Edmonton, involving a newer, single-tenant industrial complex (2019) containing
systems is expected to be fully restored. According to information provided by Altus Cost & Project 113,889 sf of rentable area. The lease commenced in March 2020, for a 10-year term at a year 1 base
Management, the total cost for this redevelopment scenario is estimated to be $23,483,942. rental rate of $8.50 per sf with Amazon Canada Fulfillment Services, ULC. While this lease deal is a
strong comparable for a newer warehouse facility, a year 1 base rental rate below this range would be
expected for the subject, again, given the lack of industrial amenities such as overhead loading doors and
Scenario 1B limitations on yard storage due to the historical designation.
Similar to Scenario 1A, this option extends the useful life of the subject for a further 20 years, by
incorporating major renovations to the building envelope, mechanical and electrical systems; however,
the renovations to these systems are more extensive, with the purpose of reducing Green House Gas
(GHG) emissions by 50%. Based upon information provided by Altus Cost & Project Management, the
total cost for this redevelopment scenario is estimated at $31,576,803.
CONFIDENTIAL CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB 44 11410 Kingsway NW, Edmonton, AB 45
T
for a potential tenant is the same as Scenario 1A. Assuming that the subject’s lease terms are triple net,
the benefit is to the end user, the tenant, as they would incur reduced operating costs in the form of The estimated capitalization rates for Scenario 1 are contained in the chart below:
energy savings. Based upon an energy model provided by Williams Engineering, it is estimated that this
scenario would provide a total energy savings (heating, lights, mechanical systems and hot water) of
approximately 36%. Yield Conclusions - Scenario 1
AF
AF
Scenario Parameter Conclusion
As the end user would incur reduced heating and power costs, it is estimated that a base rental rate
Scenario 1A 8.50%
slightly higher than Scenario 1A could be achieved. As a result, a market rental rate estimated at $6.50 Capitalization Rate (CR)
per sf for Scenario 1B. Scenario 1B 7.50%
The market rental rate conclusions for the subject under Scenario 1 are summarized in the chart below:
10.1.3 Income and Expense Pro Forma
Market Rental Rate Conclusions - Scenario 1 The Stabilized NOIs for Scenarios 1A and 1B are outlined in the tables below. Assuming a triple net
Rental Rate PSF lease, the tenant would be responsible for all operating expenses, including realty taxes and management
R
R
Area Type fees.
(Net Effective)
Alberta Aviation Museum - Scenario 1A $5.50
Alberta Aviation Museum - Scenario 1B $6.50 Stabilized NOI - Scenario 1A: 20-Year Rehabilitation
Line No.
1 Potential Rental Income Rate Area (sf)
D
D
2 Vacant Industrial $5.50 @ 81,914 $450,527
3 Total Potential Gross Revenue $450,527
4 Vacancy Allowance @ 0.00% $0
5 Effective Gross Revenue $450,527
6 Operating Expenses
7 Total Operating Expenses $0
8 Stabilized NOI $450,527
Notes
The income analysis is based on a triple net lease with the tenant responsible for all operating expenses,
1 including realty taxes and a management fee
2 Incorporates market orientated rents
4 No vacancy allowance is applied for single-tenant assets
CONFIDENTIAL CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB 46 11410 Kingsway NW, Edmonton, AB 47
Stabilized NOI - Scenario 1B: 20-Year Rehabilitation with 50% GHG Reduction 10.2 Redevelopment Scenario 2
Line No.
1 Potential Rental Income Rate Area (sf) Scenario 2 involves a 40-year rehabilitation project, with extensive upgrades to the building’s envelope
2 Vacant Industrial $6.50 @ 81,914 $532,441 and mechanical systems. The layout of the facility essentially remains the same; however, the building
envelope and mechanical systems are more efficient, and the overall useful life of the subject is
3 Total Potential Gross Revenue $532,441
4 Vacancy Allowance @ 0.00% $0
extended.
5 Effective Gross Revenue $532,441
Similar to Scenario 1, all renovations in Scenario 2 shall follow the Standards and Guidelines for the
6 Operating Expenses
Conservation of Historic Places in Canada and comply with Bylaw 12868, a bylaw designating Hangar
7 Total Operating Expenses $0
#14 (the subject) as a Municipal Historic Resource. The renovations shall also follow any requirements of
8 Stabilized NOI $532,441
Alberta Culture, Multiculturalism and Status of Women through the Provincial Historic Resource
Notes designation (Charter Bylaw 16828).
The income analysis is based on a triple net lease with the tenant responsible for all operating expenses,
1 including realty taxes and a management fee
2 There are two options within Scenario 2; they are as follows:
T
Incorporates market orientated rents
4 No vacancy allowance is applied for single-tenant assets
Scenario 2A
10.1.4 Estimate of Market Value – Direct Capitalization Extends the useful life of the subject for a further term of 40 years, involving more robust renovations to
the building envelope, mechanical systems and electrical systems, while increasing the useful life of the
AF
AF
The estimate of values, through use of the Income Approach, for Scenarios 1A and 1B, are outlined subject. In Scenario 2, the building upgrades are superior to Scenario 1, with increased efficiency and life
below: span of aforementioned systems, but the layout and physical functionality still remains the same.
According to information provided by Altus Cost & Project Management, the total cost for this
redevelopment scenario is estimated to be $34,372,112.
Direct Capitalization - Scenario 1A: 20-Year Rehabilitation
Scenario 2B ‘
Total Stabilized NOI $450,527
Similar to option 2A, this scenario extends the useful life of the subject for a further term of 40 years, yet
Capitalization Rate 8.50% at the same time reduces Green House Gas (GHG) emissions by 50%. According to information provided
Stabilized Value $5,300,320 by Altus Cost & Project Management, the total cost for this redevelopment scenario is estimated to be
Final Value (Rounded) $5,300,000 $42,372,062.
R
R
Overall, Scenario 2 is similar to Scenario 1, with the exception that the useful life of the subject is
Direct Capitalization - Scenario 1B: 20-Year Rehabilitation extended for an additional 20 years, through a more comprehensive renovation to the building envelope
50% GHG Reduction and mechanical systems.
D
Capitalization Rate 7.50%
Stabilized Value $7,099,217 As previously discussed, with extensive improvements to the building’s physical attributes and efficiency
Final Value (Rounded) $7,100,000 through implementation of Scenario 2, it is expected that the subject could secure an elevated base rental
rate as compared to the market rental rate selected for the ‘as is’ scenario, at $3.50 per sf.
For Scenario 2, the same lease comparable chart contained in Appendix C is referenced (Lease
Comparables – Scenario 1 & 2), wherein comparable lease rates for larger warehouse buildings in
average to good condition ranged from $4.45 per sf to $8.50 per sf.
CONFIDENTIAL CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB 48 11410 Kingsway NW, Edmonton, AB 49
Scenario 2 continues to be impacted by the historical resource designation, which imposes restrictions on 10.2.2 Yield Rate Forecast
the use of yard space for a potential warehouse user. While the upgrades to the building envelope and
mechanical systems are extensive, both of these scenarios maintain some elements of functional The capitalization rates (CRs) indicated by the recent property sales in Section 7.6.5 ranged between
obsolesce, due to the absence of industrial user amenities such as overhead loading doors and truck 6.85% and 10.00%, with an average of 8.37%.
turning capabilities.
The ‘as is’ valuation of the subject concluded a yield rate towards the upper end of the range, with a
The renovation plan is essentially similar under both scenarios, with the exception that Scenario 2 results capitalization rate (CR) of 10.00%.
in a longer useful life. As such, as at year 1 of a typical 10-year investment horizon, the overall physical
condition and quality of the subject under Scenario 1 and 2 would be similar. With both scenarios While extending the useful life of the subject for a further term of 40 years improves a potential investor’s
involving a similar physical condition at the commencement of a lease-term, it is estimated Scenario 2A outlook, the historical resource designation remains, which imposes restrictions on potential future
would achieve a market rental rate similar to Scenario 1A, at $5.50 per sf. renovations, expansion and alterations and forbids demolition. As such, a capitalization rate towards the
upper is still recommended for Scenario 2. Nevertheless, capitalization rates are forecast to be lower than
Scenario 1, given the extension renovations to the subject, which would reduce near-term capital outlay
Conclusion for a potential investor. An additional downward adjustment is considered for Scenario 2B, reflecting the
added ‘green’ features which produce a more attractive investment profile.
T
Scenario 2A
Based upon the foregoing discussion and the market rent comparables contained in Appendix C, it is The estimated capitalization rates for Scenario 2 are contained in the chart below:
concluded that under Scenario 2A, the subject would achieve a market rental rate towards the lower end
of the range at $5.50 per sf. This market rental rate considers the extensive renovations to the as is
format of the subject, which will result is a more physically attractive warehouse facility; however, still Yield Conclusions
AF
AF
lacking standard sought-after industrial amenities, and impacted by the presence of the historical Scenario Parameter Conclusion
resource designation.
Scenario 2A 7.00%
Capitalization Rate (CR)
Scenario 2B 6.50%
Scenario 2B
Assuming a triple net lease, the addition of green features to the building’s envelope and mechanical
system essentially has a financial impact on the end user, the tenant, who would incur reduced energy
10.2.3 Income and Expense Pro Forma
costs in the form of operating expense recoveries. Based upon an energy model provided by Williams
Engineering, it is estimated that this scenario would provide a total energy savings (heating, lights, The Stabilized NOIs for Scenarios 2A and 2B are outlined in the tables below. Assuming a triple net
mechanical systems and hot water) of approximately 36%. lease, the tenant would be responsible for all operating expenses, including realty taxes and management
R
R
fees.
As such, it is estimated that a base rental rate slightly higher than Scenario 2A could be achieved, with a
market rental rate estimated at $6.50 per sf. Stabilized NOI - Scenario 2A: 40-Year Rehabilitation
Line No.
The market rental rate conclusions for the subject under Scenario 2 are summarized in the chart below:
1 Potential Rental Income Rate Area (sf)
D
D
2 Vacant Industrial $5.50 @ 81,914 $450,527
Market Rental Rate Conclusions - Scenario 2 3 Total Potential Gross Revenue $450,527
Rental Rate PSF 4 Vacancy Allowance @ 0.00% $0
Area Type
(Net Effective) 5 Effective Gross Revenue $450,527
Alberta Aviation Museum - Scenario 2A $5.50 6 Operating Expenses
Alberta Aviation Museum - Scenario 2B $6.50 7 Total Operating Expenses $0
8 Stabilized NOI $450,527
Notes
The income analysis is based on a triple net lease with the tenant responsible for all operating expenses,
1 including realty taxes and a management fee
2 Incorporates market orientated rents
4 No vacancy allowance is applied for single-tenant assets
CONFIDENTIAL CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB 50 11410 Kingsway NW, Edmonton, AB 51
Stabilized NOI - 40-Year Rehabilitation with 50% GHG Reduction 11 Redevelopment Scenario 3
Line No.
1 Potential Rental Income Rate Area (sf) Redevelopment Scenario 3 involves the demolition of the existing improvements, and construction of a
2 Vacant Industrial $6.50 @ 81,914 $532,441 brand new, zero emissions warehouse facility of similar size and design.
3 Total Potential Gross Revenue $532,441
4 Vacancy Allowance @ 0.00% $0 The design and size of the new warehouse building is to be similar to the existing facility; however,
5 Effective Gross Revenue $532,441 physically, it is to be of high-quality, built to achieve zero emissions and entail slightly different proportions
6 Operating Expenses of warehouse and office. The new facility would be equipped with 14 overhead doors (11 ft. wide by 11 ft.
7 Total Operating Expenses $0
high), as well as 14 single overhead doors, for a total of 28 loading doors.
8 Stabilized NOI $532,441
The gross building area of the new facility is set to be similar to the existing facility, at 8,593 m², or 92,495
Notes
The income analysis is based on a triple net lease with the tenant responsible for all operating expenses,
sf; however, incorporates a slightly higher office ratio, at 38%, versus an office ratio of 32% in the existing
1 including realty taxes and a management fee facility.
2
T
Incorporates market orientated rents
4 No vacancy allowance is applied for single-tenant assets It should be noted to the reader that the valuation analysis herein is base upon an assumed net leasable
area (NLA) of 7,610 m², or 81,914 sf, based upon a Facility Condition Report provided by the Client,
dated August 2017.
10.2.4 Estimate of Market Value (Direct Capitalization)
It is further assumed that the new facility would not be encumbered by Bylaw 12868, designation of
AF
AF
The estimate of values, through use of the Income Approach, for Scenarios 2A and 2B, are outlined
below: Hangar #14 (the subject) as a Municipal Historic Resource, nor Charter Bylaw 16828, a designating the
subject as a Provincial Historic Resource. As such, the usage of yard space would be ameliorated with
under Scenario 3, and potential investors would have the ability to perform future renovations, alterations
Direct Capitalization - Scenario 2A: 40-Year Rehabilitation
or expansion.
Line No.
1 Total Stabilized NOI $450,527 Scenario 3 also incorporates the City of Edmonton’s Climate Resiliency Policy (Policy C485C), which is a
2 Capitalization Rate 7.00% revised Energy Transition Strategy adopted by council in April 2021. The policy aligns with the City’s Big
3 Stabilized Value $6,436,103 City Move of Greener as we Grow, a part of the City Plan which overall, stipulates that the City is
4 Total Adjustments $0 committed to reducing GHG emissions by 35% in 2025, 50% by 2030 and carbon neutral by 2050. In
5 Final Value $6,436,103 addition, the new build adheres to City Policy C458C – Percent for Art to Provide and Encourage Are in
R
R
6 Final Value (Rounded) $6,400,000 Public Areas.
As a zero-emission facility, both scenarios result in a total energy savings of 75%, compared to the as is
Direct Capitalization - Scenario 2B: 40-Year Rehabilitation with 50% GHG Reduction scenario of the subject, based upon an energy model provided by Williams Engineering.
Line No.
1 Total Stabilized NOI $532,441 There are two options within Scenario 3; they are as follows:
D
D
2 Capitalization Rate 6.50%
3 Stabilized Value $8,191,404 Scenario 3A
4 Total Adjustments $0 Produces a new, high-quality 20-year zero-emission warehouse with a total of 28 loading doors and is
5 Final Value $8,191,404 assumed to provide for adequate yard usage and truck turning capabilities. According to information
6 Final Value (Rounded) $8,200,000 provided by Altus Cost & Project Management, the total cost for this redevelopment scenario is estimated
to be $33,197,408.
Scenario 3B
Produces a new, high-quality 40-year zero emission warehouse with a total of 28 loading doors and is
assumed to provide for adequate yard usage and truck turning capabilities. According to information
provided by Altus Cost & Project Management, the total cost for this redevelopment scenario is estimated
to be $36,558,264.
CONFIDENTIAL CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB 52 11410 Kingsway NW, Edmonton, AB 53
The market rent analysis for the subject under Scenario 3 is based upon the following assumptions: Scenario 3 A&B
The subject contains a NLA of 81,914 sf (7,610 m²) Based upon the foregoing discussion and the market rent comparables contained in Appendix C, it is
concluded that under Scenario 3A, the subject would achieve a market rental rate towards the upper end
The subject includes 2nd storey office space and has an office ratio of 38% of the range at $11.00 per sf for a standard warehouse bay, and $14.00 per sf for standard suburban
office space.
As the building footprint remains similar under Scenario 3, truck turning capabilities and vehicle
maneuverability is regarded as below average.
This market rental rate considers that the subject will be a brand new warehouse facility which is
It is assumed that the subject can be demised into a multi-tenant facility, accommodating several
functional for a standard industrial warehouse/office user. Further, assuming a triple net lease, as a zero-
smaller warehouse bays ranging in size from 10,000 sf to 50,000 sf.
emission facility, a tenant would incur reduced operating cost recoveries, in the form of energy savings,
The market rent analysis assumes a net effective rent with a standard 5-year lease for an industrial and as such, a rental rate towards the upper end of the range could be secured.
warehouse / office user with an average tenant profile.
As mentioned, Scenario 3B is essentially the same as Scenario 3A in terms of physical attributes and
T
A review of the market leases considered to be the most comparable to the subject, as a brand new zero- functionality. The main difference is that the useful life of the building is extended for an additional 20
emission warehouse of similar magnitude, are presented in the chart contained in Appendix C. To years. That said, the physical use of the building for a potential tenant is the same as Scenario 3A. As a
maintain the confidentiality of the data, specific addresses have not been identified and specific details result, a market rental rate estimated for Scenario 3B is estimated to be the same as Scenario 3A.
have been retained on file.
The blended market rental rate conclusions for the subject under Scenario 3 are summarized in the chart
AF
AF
The comparable leases involve two datasets. The first dataset pertains to multi-tenant below:
warehouse/distribution centres, mainly involving flex buildings / business centres, which were in an
average to good state of condition and repair at the commencement of the lease term. The lease Market Rental Rate Conclusions - Scenario 3 A&B
comparables reflect year 1 base rental rates ranging from $9.50 per sf to $12.50 per sf, with an average
of $10.71 per sf, for facilities ranging in size from 4,500 sf to 65,000 sf. Rental Rate PSF
Area Type Area (SF)
(Net Effective)
As the subject contains a large office ratio, with 2nd storey office space, a secondary dataset is included Scenario 3A - Warehouse $11.00 50,787
which pertains to suburban office leases for Class A and B office facilities located within the Edmonton Scenario 3A - Office $14.00 31,127
region. These lease comparables reflect year 1 base rental rates ranging from $12.00 per sf to $17.000 Blended Market Rent PSF $12.14 81,914
per sf, with an average of $14.85 per sf, for rental units ranging in size from 700 sf to 7,000 sf. Blended Market Rent PSF (Rounded) $12.00 81,914
R
R
Overall, the data suggests that the subject could support a market rental rate in the range of $10.00 per sf
to $12.00 per sf for a standard warehouse bay of average to good quality, and a rental rate ranging from 11.1.2 Yield Rate Forecast
$12.00 per sf to $16.00 per sf for suburban office space. The sales data chart previously referenced in Section 7.6.5 highlighted capitalization rates (CRs) ranging
between 6.85% and 10.00%, with an average of 8.37%. The ‘as is’ valuation of the subject concluded a
A blended market rental rate will be applied to the subject under scenario 3, given the high proportion of
D
D
yield rate towards the upper end of the range, with a capitalization rate (CR) of 10.00%.
2nd storey office space.
In addition to the yield sales summarized in Section 7.65, the following recent transactions are
highlighted, which involve newer, single-tenant facilities of similar magnitude to the subject:
CONFIDENTIAL CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB 54 11410 Kingsway NW, Edmonton, AB 55
Recent Investment Market Activity 11.1.3 Income and Expense Pro Forma
Rate
The Stabilized NOIs for Scenarios 13A and 3B are outlined in the tables below. Assuming a triple net
Index Building Details Sale Details Summary
lease, the tenant would be responsible for all operating expenses, including realty taxes and management
1 Civic Address 6600 72 Avenue SE Sale Date Jun-21 IRR 5.50% fees.
Municipality Calgary, AB Adj Sale Price $37,000,000 TCR 5.00%
Rentable Area 498,816 sf Price PSF $134 CR 4.84%
Stabilized NOI - Scenario 3A: 20-Year, New Zero-Emission Warehouse
Line No.
2 Civic Address Confidential Sale Date Dec-21 IRR 5.22% 1 Potential Rental Income Blended Rate Area (sf)
Confidential Municipality Edmonton, AB Adj Sale Price $118,000,000 TCR 5.00% 2 Vacant Industrial $12.00 @ 81,914 $982,968
Rentable Area 488,949 sf Price PSF $241 CR 4.81% 3 Total Potential Gross Revenue $982,968
4 Vacancy Allowance @ 0.00% $0
5 Effective Gross Revenue $982,968
6 Operating Expenses
T
Index 1 relates to the August 2021 off market sale which transaction with a capitalization rate of 4.84%.
This sale related to a 498,816 sf single-tenant industrial facility located in Great Plains Industrial, Calgary. 7 Total Operating Expenses $0
The warehouse was built in 2019, has a clear height of 36 ft and at the date of sale, the tenant has signed 8 Stabilized NOI $982,968
a new 5-year lease at a lease rate of $6.50 per sf. Notes
The income analysis is based on a triple net lease with the tenant responsible for all operating expenses,
1 including realty taxes and a management fee
AF
AF
Index 2 involves a portfolio transaction involving three, single-tenant warehouse facilities located in
2 Incorporates market orientated rents
Edmonton, ranging in size from 113,889 sf to 193,397 sf. This December 2021 sale transacted at an
4 No vacancy allowance is applied for single-tenant assets
overall capitalization rate of 4.81%. Two of the three facilities were newly built in 2020, with the third
facility built in 2000 with expansion / renovation in 2012/13.
Stabilized NOI - Scenario 3B: 40-Year, New Zero Emission Warehouse
In selecting appropriate yield rates for Scenario 3 A&B, the following factors are considered: Line No.
The subject involves a brand-new warehouse facility, which is assumed to have an average level 1 Potential Rental Income Blended Rate Area (sf)
of functionality for an industrial user 2 Vacant Industrial $12.00 @ 81,914 $982,968
3 Total Potential Gross Revenue $982,968
The subject involves a zero-emission facility is an attractive feature for a potential investor 4 Vacancy Allowance @ 0.00% $0
R
R
The subject is equipped with a total of 28 loading doors, with 14 overhead doors (11 ft. wide by 5 Effective Gross Revenue $982,968
11 ft. high), as well as 14 single overhead doors 6 Operating Expenses
7 Total Operating Expenses $0
With Scenario 3 having the same building footprint as the existing facility, truck turning, and
8 Stabilized NOI $982,968
vehicle maneuverability is regarded as below average.
Notes
The subject has a relatively high office ratio, of 38%. The income analysis is based on a triple net lease with the tenant responsible for all operating expenses,
D
D
1 including realty taxes and a management fee
The building has the potential to be demised into multiple warehouse bays, ranging in size from 2 Incorporates market orientated rents
The estimated capitalization rates for Scenario 3 A&B are contained in the chart below. As Scenario 3B
11.1.4 Estimate of Market Value – Direct Capitalization
increased the useful life of the building for an additional 20 years, a downward adjustment is applied for
this option, as building efficiency is more robust by extending its useful life. The estimate of values, through use of the Income Approach, for Scenarios 3A and 3B, are outlined
below:
Yield Conclusions
Scenario Parameter Conclusion
Scenario 3A 6.00%
Capitalization Rate (CR)
Scenario 3B 5.50%
CONFIDENTIAL CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB 56 11410 Kingsway NW, Edmonton, AB 57
Direct Capitalization -Scenario 3B: 1A 20-Year Rehabilitation $5.50 8.50% $5,300,320 $5,300,000
40-Year, New Zero Emission Warehouse 1B 20-Year Rahabilitation w/ 50% GHG Reduction $6.50 7.50% $7,099,217 $7,100,000
T
2B 40-Year Rahabilitation w/ 50% GHG Reduction $6.50 6.50% $8,191,404 $8,200,000
Capitalization Rate 5.50%
3A 20-Year, New Zero-Emission Warehouse $12.00 6.00% $16,382,808 $16,400,000
Stabilized Value $17,872,154
Final Value (Rounded) $17,900,000 3B 40-Year, New Zero Emission Warehouse $12.00 5.50% $17,872,154 $17,900,000
AF
AF
R
R
D
D
CONFIDENTIAL CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB 58 11410 Kingsway NW, Edmonton, AB 59
12 Certification In my opinion, the current market value of the fee simple interest in the subject property, subject to the Ordinary Assumptions and
Limiting Conditions in Appendix A, as at November 18, 2021, is:
T
► I am not in a conflict of interest to undertake this assignment.
► I have no bias with respect to the property that is the subject of this report or to the parties involved with this assignment.
► My engagement in and compensation for this assignment was not contingent upon developing or reporting predetermined
Angela Barron, AIC Candidate Member Mike deJong, AACI
results, the amount of the value estimate, or a conclusion favouring the client.
AIC Member #: 907395 AIC Member #: 901817
AF
AF
► My analyses, opinions and conclusions were developed, and this report has been prepared, in conformity with the Canadian
Signing Date: DRAFT
Uniform Standards of Professional Appraisal Practice, Valuation - Professional Standards of the Royal Institution of Chartered
Attachments and Appendices
Surveyors and the International Valuation Standards.
► I have the knowledge and experience to complete this assignment competently, and where applicable, this report is co-signed
in compliance with Canadian Uniform Standards of Professional Appraisal Practice, Valuation - Professional Standards of the
Royal Institution of Chartered Surveyors and the International Valuation Standards.
► The subject property was inspected by Angela Barron, AIC Candidate Member and Mike deJong, AACI on November 18,
2021. The inspection was considered sufficient to assist the author in describing the real estate, developing an opinion of
highest and best use and making meaningful comparisons with other market data. A detailed inspection to report building
condition is beyond the scope of this assignment.
R
► As of the date of this report, Mike deJong, AACI and Angela Barron, AIC Candidate Member have fulfilled the requirements of
The Appraisal Institute of Canada Continuing Professional Development Program for designated and candidate members,
and are members in good standing of the Appraisal Institute of Canada.
► I, Mike deJong, AACI, directly supervised the appraiser who prepared this appraisal report and, having reviewed the report,
agrees with the statements and conclusions of the appraiser, agrees to be bound by the appraiser's certification and I am
D
D
taking full responsibility for the appraisal and the appraisal report.
CONFIDENTIAL CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB 60 11410 Kingsway NW, Edmonton, AB 61
T
Appendix A - Altus’ Terms of Reference
AF
AF
Appendix B - Visual Identification Appendix A Altus’ Terms of Reference
Appendix C - Comparable Lease Data
Ordinary Assumptions and Limiting Conditions
Definitions
R
R
D
D
Appendices
Ordinary Assumptions and Limiting Conditions in the report. It is an assumption of this report that the property complies with all regulatory requirements concerning environmental,
chemical and biological matters, and it is assumed that the property is free of any detrimental environmental, chemical legal and biological
conditions that may affect the market value of the property appraised. If a party relying on this report requires information about or an
The following Ordinary Assumptions and Limiting Conditions apply to real estate appraisals prepared by Altus Group ("Altus"). Any Special assessment of detrimental environmental, chemical or biological conditions that may impact the value conclusion herein, that party is
Conditions have been added as required. advised to retain an expert qualified in such matters. The author expressly denies any legal liability related to the effect of detrimental
environmental, chemical or biological matters on the market value of the property.
The certification that appears in this appraisal report is subject to compliance with the Personal Information and Electronics Documents Act
(PIPEDA), Canadian Uniform Standards of Professional Appraisal Practice (CUSPAP), Professional Standards of the Royal Institution of 9. The analyses set out in this report relied on written and verbal information obtained from a variety of sources the author considered
Chartered Surveyors (RICS), International Valuation standards (IVS), published by the International Valuation Standards Council and any other reliable. Unless otherwise stated herein, the author did not verify client-supplied information, which the author believed to be correct.
Appraisal Organization to which the author is a member and the following conditions.
10. The term “inspection” refers to observation only as defined by CUSPAP and reporting of the general material finishing and conditions
1. This report is prepared only for the client and authorized users specifically identified in this report and only for the specific use identified observed for the purposes of a standard appraisal inspection. The inspection scope of work includes the identification of marketable
herein. No other person may rely on this report or any part of this report without first obtaining consent from the client and written characteristics/amenities offered for comparison and valuation purposes only.
authorization from the authors. Liability is expressly denied to any other person and, accordingly, no responsibility is accepted for any
11. The opinions of value and other conclusions contained herein assume satisfactory completion of any work remaining to be completed in a
damage suffered by any other person as a result of decisions made or actions taken based on this report. Liability is expressly denied for
good and workmanlike manner. Further inspection may be required to confirm completion of such work. The author has not confirmed
any unauthorized user or for anyone who uses this report for any use not specifically identified in this report. Payment of the appraisal fee
that all mandatory building inspections have been completed to date, nor has the availability/issuance of an occupancy permit been
T
has no effect on liability. Reliance on this report without authorization or for an unauthorized use is unreasonable.
confirmed. The author has not evaluated the quality of construction, workmanship or materials. It should be clearly understood that this
2. Because market conditions, including economic, social and political factors, may change rapidly and, on occasion, without warning, this visual inspection does not imply compliance with any building code requirements as this is beyond the professional expertise of the
report cannot be relied upon as of any date other than the effective date specified in this report unless specifically authorized by the author.
author.
12. The contents of this report are confidential and will not be disclosed by the author to any party except as provided for by the provisions of
3. The author will not be responsible for matters of a legal nature that affect either the property being appraised or the title to it. The property the CUSPAP and/or when properly entered into evidence of a duly qualified judicial or quasi-judicial body. The author acknowledges that
AF
AF
is appraised on the basis of it being under responsible ownership. Unless otherwise stated in this report, no registry office search has the information collected herein is personal and confidential and shall not use or disclose the contents of this report except as provided for
been performed and the author assumes that the title is good and marketable and free and clear of all encumbrances. Matters of a legal in the provisions of the CUSPAP and in accordance with the author’s privacy policy. The client agrees that in accepting this report, it shall
nature, including confirming who holds legal title to the appraised property or any portion of the appraised property, are outside the scope maintain the confidentiality and privacy of any personal information contained herein and shall comply in all material respects with the
of work and expertise of the author. Any information regarding the identity of a property’s owner or identifying the property owned by the contents of the author's privacy policy and in accordance with the PIPEDA.
listed client and/or applicant provided by the author is for informational purposes only and any reliance on such information is
13. The author has agreed to enter into the assignment as requested by the client named in this report for the use specified by the client,
unreasonable. Any information provided by the author does not constitute any title confirmation. Any information provided does not
which is stated in this report. The client has agreed that the performance of this report and the format are appropriate for the intended
negate the need to retain a real estate lawyer, surveyor or other appropriate experts to verify matters of ownership and/or title.
use.
4. Verification of compliance with governmental regulations, bylaws or statutes is outside the scope of work and expertise of the author. Any
14. This report, its content and all attachments/appendices and their content are the property of the author. The client, authorized users and
information provided by the author is for informational purposes only and any reliance is unreasonable. Any information provided by the
any appraisal facilitator are prohibited, strictly forbidden, and no permission is expressly or implicitly granted or deemed to be granted, to
author does not negate the need to retain an appropriately qualified professional to determine government regulation compliance.
modify, alter, merge, publish (in whole or in part) screen scrape, database scrape, exploit, reproduce, decompile, reassemble or
R
R
5. No survey of the property has been made. Any sketch in this report shows approximate dimensions and is included only to assist the participate in any other activity intended to separate, collect, store, reorganize, scan, copy, manipulate electronically, digitally, manually or
reader of this report in visualizing the property. It is unreasonable to rely on this report as an alternative to a survey, and an accredited by any other means whatsoever this appraisal report, appendices, all attachments and the data contained within for any commercial, or
surveyor ought to be retained for such matters. other, use.
6. This report is completed on the basis that testimony or appearance in court concerning this report is not required unless specific 15. If transmitted electronically, this report will have been digitally signed and secured with personal passwords to lock the appraisal file. Due
arrangements to do so have been made beforehand. Such arrangements will include, but not necessarily be limited to: adequate time to to the possibility of digital modification, only originally signed reports and those reports sent directly by the author can be reasonably relied
upon.
D
D
review the report and related data, and the provision of appropriate compensation.
7. Unless otherwise stated in this report, the author has no knowledge of any hidden or unapparent conditions (including, but not limited to: 16. Where the intended use of this report is for financing or mortgage lending or mortgage insurance, it is a condition of reliance on this report
its soils, physical structure, mechanical or other operating systems, foundation, etc.) of/on the subject property or of/on a neighbouring that the authorized user has or will conduct lending, underwriting and insurance underwriting and rigorous due diligence in accordance
property that could affect the value of the subject property. It has been assumed that there are no such conditions. Any such conditions with the standards of a reasonable and prudent lender or insurer, including but not limited to ensuring the borrower’s demonstrated
that were visibly apparent at the time of inspection or that became apparent during the normal research involved in completing the report willingness and capacity to service his/her debt obligations on a timely basis. Liability is expressly denied to those that do not meet this
have been noted in the report. This report should not be construed as an environmental audit or detailed property condition report, as condition. Any reliance on this report without satisfaction of this condition is unreasonable.
such reporting is beyond the scope of this report and/or the qualifications of the author. The author makes no guarantees or warranties,
17. Unless specifically stated, the value conclusions contained in this report applies to the real estate only, and does not include personal
express or implied, regarding the condition of the property, and will not be responsible for any such conditions that do exist or for any
property, machinery and equipment, trade fixtures, business value, goodwill or other non-realty items. This report is limited to surface
engineering or testing that might be required to discover whether such conditions exist. The bearing capacity of the soil is assumed to be
rights only and does not include any inherent subsurface or mineral rights. Income tax considerations have not been included or valued
adequate.
unless so specified in this report. No representations are made as to the value changes that may be attributed to such considerations.
8. The author is not qualified to comment on detrimental environmental, chemical or biological conditions that may affect the market value of
18. It is assumed that legal, engineering, or other professional advice, as may be required, has been or will be obtained from properly
the property appraised, including but not limited to pollution or contamination of land, buildings, water, groundwater or air which may
qualified legal professional sources and that this report will not be used for guidance in legal or technical matters such as, but not limited
include but are not limited to moulds and mildews or the conditions that may give rise to either. Any such conditions that were visibly
to, the existence of encroachments, easements or other discrepancies affecting the legal description of the property. It is assumed that
apparent at the time of inspection or that became apparent during the normal research involved in completing the report have been noted
CONFIDENTIAL CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB 11410 Kingsway NW, Edmonton, AB
there are no concealed or dubious conditions of the subsoil or subsurface waters including water table and flood plain, unless otherwise
noted.
Definitions
19. It is assumed that any and all liabilities that might accrue against the real estate such as taxes, hypothecs, contracts or services of any
kind, are paid when due. Taxes and other fees (e.g. broker commissions) incurred during the hypothetical sale of the real estate are not Altus InSite Investment Trends Survey
addressed in this report.
Altus InSite undertakes a survey of the Canadian real estate industry to determine the informed
20. This report may contain estimates of future financial performance, estimates or opinions that represent the author's view of reasonable consensus opinion on investment performance trends and valuation parameters from Canada's key
expectations at a particular point in time, but such information, estimates or opinions are not offered as predictions or as assurances that investors, lenders and other opinion leaders. The results of this quarterly survey are presented online as
a particular level of income or profit will be achieved, that events will occur, or that a particular price will be offered or accepted.
a series of data reports and charts for the Office, Retail, Industrial and Multiple Unit Residential asset
Actual results achieved during the period covered by our prospective financial analyses will vary from those described in this report, and
classes for seven major markets across Canada.
the variations may be material.
21. This report assumes that the property will be competently managed, leased and maintained by financially sound owners over the Highest and Best Use
expected period of ownership. This engagement does not entail an evaluation of management's or owner's effectiveness, nor is the
Highest and best use may be defined as:
author or Altus responsible for future marketing efforts and other management or ownership actions upon which actual results will
T
depend.
“The reasonably probable use of a property, that is physically possible, legally
22. The value is based on the purchasing power of the Canadian dollar as of that date. permissible, financially feasible and maximally productive, and that results in the highest
value.” 1
23. The issuance of a draft report is for the initial review of findings by the client and is provided provisionally and subject to completion of the
final report.
AF
AF
The highest and best use of both land as though vacant and the property as developed must meet four
It is on no account to be published or disclosed or used for any other purpose than review by the client. criteria. The highest and best use must be:
Altus accepts no liability for the misuse of a draft report.
Physically Possible: The size, shape, terrain and soil conditions of a parcel of land
Amendments to the report may be considered if new information subsequently comes to light, although additional fees may accrue in the affect its physical utility and adaptability. The size, design and condition of an improved
analysis of this information. property may suggest that rehabilitation, conversion or demolition is in order
If within one week of delivery of the draft PDF there have been no further comments or queries, the author and Altus Group considers
this as The City of Edmonton’s tacit approval of the contents and opinions expressed therein and the final report will be issued Legally Permissible: Depends on public restrictions such as zoning, building codes,
accordingly. historic preservation regulations and environmental controls, as well as the private or
contractual restrictions found in deeds and long-term leases
R
R
Financially Feasible: Uses that should produce returns that exceed the income
required to satisfy operating expenses and debt service (interest and amortization)
Maximum Return: Among financially feasible uses, the use that produces the highest
price or value consistent with the rate of return warranted by the market.
D
D
Fee Simple 2
An interest consisting in absolute ownership unencumbered by any other interest or estate, subject only
to the limitations imposed by the governmental powers of taxation, expropriation, police power and
escheat.
1
Canadian Uniform Standards of Professional Appraisal Practice, Appraisal Institute of Canada. 2020. Section 3.30
2
The Appraisal of Real Estate: 3rd Canadian Edition. Vancouver. University of British Columbia Real Estate Division. 2010.
Section 6.2
CONFIDENTIAL CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB 11410 Kingsway NW, Edmonton, AB
Leased Fee 3
An ownership interest held by the landlord with the rights of use and occupancy conveyed by the lease to
others. The rights of the lessor (the leased fee owner) and the leased fee are specified by contract terms
contained with the lease.
Leasehold 4
The interest held by the lessee (the tenant or renter) through a lease conveying the rights of use and
occupancy for a stated term under certain conditions.
Market Value
Market Value is defined by the Appraisal Institute of Canada in the Canadian Uniform Standards of
Professional Appraisal Practice as:
T
“The most probable price, as of a specified date, in cash, or in terms equivalent to cash, or in
other precisely revealed terms for which the specified property rights should sell after reasonable
exposure in a competitive market under all conditions requisite to a fair sale, with the buyer and
seller each acting prudently, knowledgeably, and for self-interest, and assuming that neither is
AF
AF
under undue duress.” 5
Appendix B Visual Identification
Implicit in this definition are the consummation of a sale as of a specified date and the passing of title
from seller to buyer under conditions whereby:
Photographs of Subject Property
► buyer and seller are typically motivated;
► both parties are well informed or well advised, and acting in what they consider their best Municipal Map
interests;
► a reasonable time is allowed for exposure in the open market;
► payment is made in terms of cash in Canadian dollars or in terms of financial arrangements
R
R
comparable thereto; and
► the price represents the normal consideration for the property sold, unaffected by special or
creative financing or sales concessions granted by anyone associated with the sale.
Exposure Time
D
D
Exposure Time is an estimate of the length of time that the property interest being appraised would have
been offered on the market before the hypothetical consummation of a sale at the estimated value on the
effective date of the appraisal.
Exposure Time is a retrospective estimate based upon experience and the opinions gathered from real
estate brokers active in the field. The estimate of time period for reasonable exposure is not intended to
be a prediction, but is an estimate of the amount of time that the property would have required to be
exposed for sale on the open market in an appropriate manner, and using an experienced broker.
3
The Appraisal of Real Estate: 3rd Canadian Edition. Vancouver. University of British Columbia Real Estate Division. 2010. Section
6.4
4
Ibid.
5
Canadian Uniform Standards of Professional Appraisal Practice, Appraisal Institute of Canada. 2020. Section 3.44
CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB
T
Subject Exterior – South Elevation Subject Exterior – East Elevation Interior View – Display Area Interior View – Display Area
AF
AF
R
R
Subject Exterior – South Elevation Subject Exterior – South & West Elevation Interior View – Restoration Area Interior View – Cadet / Hall Area
D
D
Subject Exterior – West Elevation Subject Exterior – North Elevation Interior View – Mechanical Room Interior View – Standard Classroom
CONFIDENTIAL CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB 11410 Kingsway NW, Edmonton, AB
Municipal Map
Subject
T
AF
AF
Appendix C Comparable Lease Data
R
R
D
D
Source: The City of Edmonton
CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB
1 Q4 2018 New Lease (Net) - - $5.00 - Warehouse / Distribution - 1 Q2 2020 Renewal (Net) - $3.81 $7.50 $6.50 Warehouse / Distribution -
55,000 Warehouse / Distribution $1.75 $5.40 - - 90,000 Warehouse / Distribution $0.50 $7.60 $8.05 28 ft
120 - - 60 - $1.55
2 Q2 2020 New Lease (Net) - $2.62 $4.45 - Warehouse / Distribution 5% 2 Q1 2022 New Lease (Net) - $7.12 $7.50 $5.74 Warehouse / Distribution -
55,000 Warehouse / Distribution $1.00 $4.45 - 28 ft 50,000 Warehouse / Distribution $2.84 $7.50 $9.71 28 ft
60 - - 120 - $3.97
3 Q1 2020 New Lease (Net) - - $2.50 - Manufacturing - 3 Q4 2020 New Lease (Net) - - $6.00 - Warehouse / Distribution 15%
25,000 Manufacturing $1.75 $2.80 - 24 ft 40,000 Warehouse / Distribution $1.00 - - 14 ft - 21 ft
96 - - 12 - -
4 Q1 2015 New Lease (Net) - - $4.34 $4.54 Freezer / Refrigeration - 4 Q4 2018 New Lease (Net) - - $5.00 - Warehouse / Distribution -
65,000 Freezer / Refrigeration $1.00 $4.34 $4.54 18 ft - 32 ft 55,000 Warehouse / Distribution $1.75 $5.40 - -
359 - - 120 - -
T
5 Q4 2018 New Lease (Net) - - $3.00 $4.87 Warehouse / Distribution - 5 Q2 2020 New Lease (Net) - $2.62 $4.45 - Warehouse / Distribution 5%
25,000 Warehouse / Distribution $1.00 $4.20 $9.21 - 55,000 Warehouse / Distribution $1.00 $4.45 - 28 ft
120 - $4.34 60 - -
6 Q2 2011 New Lease (Net) - - $4.25 $3.40 Warehouse / Distribution 10% 6 Q4 2021 Renewal (Net) - - $6.50 $6.82 Warehouse / Distribution 11%
65,000 Warehouse / Distribution $1.00 - $3.40 24 ft 90,000 Warehouse / Distribution $1.00 $6.90 $11.34 28 ft
AF
AF
15 - - 84 - $4.52
7 Q2 2010 New Lease (Net) - - $5.75 $5.43 Manufacturing 0% - 10% 7 Q2 2020 New Lease (Net) - - $5.75 $5.44 Warehouse / Distribution -
70,000 Manufacturing $1.00 - $9.01 20 ft - 30 ft 50,000 Warehouse / Distribution $1.00 - $9.80 -
37 - $3.58 46 - $4.36
8 Q1 2010 Renewal (Net) - - $4.85 $5.08 Warehouse / Distribution - 8 Q2 2021 New Lease (Net) - $2.83 $7.25 $6.37 Warehouse / Distribution 0% - 4%
65,000 Warehouse / Distribution $0.50 $5.25 $7.63 0 ft - 28 ft 55,000 Warehouse / Distribution $1.00 $7.35 $9.80 0 ft - 28 ft
60 - $2.55 60 - $3.43
9 Q1 2010 New Lease (Net) Edmonton - $4.00 $4.19 Warehouse / Distribution 5% 9 Q3 2019 New Lease (Net) - $1.97 $7.75 $7.13 Warehouse / Distribution -
15,000 Warehouse / Distribution $1.00 $4.50 $6.19 22 ft 70,000 Warehouse / Distribution $1.00 $7.90 $10.49 28 ft
60 - $2.00 60 - $3.36
10 Q1 2010 New Lease (Net) - $4.75 $4.76 Warehouse / Distribution 20% 10 Q2 2019 Renewal (Net) - - $7.25 $7.06 Warehouse / Distribution 4%
R
R
75,000 Warehouse / Distribution $1.00 $5.04 $4.76 22 ft 55,000 Warehouse / Distribution $0.50 - $10.42 28 ft
60 - - 36 - $3.36
D
100,000 Manufacturing $0.50 $5.50 $5.32 -
70,000 Transportation Repair Facility $1.00 $4.00 - 0 ft - 35 ft
60 - -
60 - -
13 Q1 2020 New Lease (Net) - $5.00 $8.50 $7.34 Warehouse / Distribution 10%
13 Q3 2007 New Lease (Net) - - $4.65 - Warehouse / Distribution -
110,000 Warehouse / Distribution $2.50 $8.50 $10.55 28 ft
85,000 Warehouse / Distribution $2.50 $4.95 - -
123 - $3.21
123 - -
MINIMUM - YEAR 1 BASE RENT $4.45 MINIMUM - YEAR 1 BASE RENT
14 Q3 2018 Renewal (Net) - - $5.00 $5.32 Manufacturing - MAXIMUM - YEAR 1 BASE RENT $8.50 MAXIMUM - YEAR 1 BASE RENT
100,000 Manufacturing $0.50 $5.50 $5.32 - AVERAGE - YEAR 1 BASE RENT $6.69 AVERAGE - YEAR 1 BASE RENT
60 - - ¹ Total Incentives do not include Landlord's Work.
² Represents Year 1 Face Rent net of applicable operating costs for gross and semi-gross leases.
CONFIDENTIAL CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB 11410 Kingsway NW, Edmonton, AB
Lease Comparables - Scenario 3 - Warehouse / Distribution Lease Comparables - Scenario 3 - Suburban Office
Lease Type District / Node Incentives¹
Lease Type District / Node Incentives¹
Lease Area (Approx.) Building Type Leasing Y1 Base Rent² NER Office Ratio
Index Start Date Lease Term (Months) Tenant Type Total Exp. Avg. Y1-5 Rent GER Building Type Clear Height
Lease Area (Approx.) Building Type Leasing Y1 Base Rent² NER
Index Start Date Lease Term (Months) Tenant Type Total Exp. Avg. Y1-5 Rent GER Building Type
1 Q1 2021 Renewal (Net) - - $12.00 $11.48 Warehouse / Distribution -
5,500 Warehouse / Distribution $0.50 - $17.15 20 ft 1 Q2 2021 Renewal (Net) Suburban Edmonton / South Side - $13.00 $12.71 Class A
12 - $5.67 1,500 Class A $1.50 $13.10 $27.72
60 Hi Tech & Telecommunications $15.01
2 Q1 2021 Renewal (Net) - - $10.00 $9.71 Warehouse / Distribution -
4,500 Warehouse / Distribution $0.50 $10.07 $9.71 13 ft
2 Q4 2020 Renewal (Net) - - $15.00 $14.62 Class B
76 - -
700 Class B $1.50 $15.00 $14.62
3 Q3 2021 Renewal (Net) - - $11.00 $11.30 Warehouse / Distribution - 60 Other - See Comments -
20,000 Warehouse / Distribution $0.50 $11.00 $11.30 -
120 - - 3 Q4 2019 New Lease (Net) - - $15.00 $15.28 Class B
20,000 Class B $3.00 $15.00 $15.28
4 Q3 2020 New Lease (Net) - - $10.00 $9.45 Warehouse / Distribution -
120 Other - See Comments -
5,000 Warehouse / Distribution $1.00 - $13.94 24 ft - 28 ft
24 - $4.49
4 Q3 2020 New Lease (Net) - - $12.00 $11.58 Class B
5 Q1 2021 Renewal (Net) - $2.00 $9.50 $9.14 Warehouse / Distribution 0% - 20% 5,000 Class B $3.00 $12.40 $11.58
30,000 Warehouse / Distribution $0.50 $9.80 $15.15 0 ft - 26 ft 60 Other - See Comments -
60 - $6.01
T
5 Q1 2020 New Lease (Net) - - $14.00 $12.85 Class B
6 Q4 2020 New Lease (Net) - - $9.50 $7.30 Warehouse / Distribution -
15,000 Warehouse / Distribution $1.00 - $11.84 25 ft 8,500 Class B $3.00 - $12.85
24 - $4.54 36 Unknown -
7 Q3 2020 Renewal (Net) - - $11.00 $10.11 Cross Dock 18% 6 Q3 2020 Renewal (Net) - - $14.00 $13.96 Class B
65,000 Cross Dock $0.50 - $13.96 24 ft
1,500 Class B $1.50 $14.40 $13.96
36 - $3.85
60 Other - See Comments -
AF
AF
8 Q1 2020 Renewal (Net) - - $12.00 $11.48 Warehouse / Distribution -
5,500 Warehouse / Distribution $0.50 - $16.35 20 ft 7 Q3 2019 New Lease (Net) - - $16.00 $15.84 Class A
12 - $4.87 2,500 Class A $3.00 $16.00 $31.83
84 Law $15.99
9 Q4 2019 New Lease (Net) - - $11.00 - Manufacturing 10%
35,000 Manufacturing $1.00 $11.00 - 30 ft
8 Q3 2020 New Lease (Net) - - $17.00 $16.24 Class A
60 - -
4,000 Class A $3.00 $17.00 $30.52
10 Q3 2020 Renewal (Net) - - $12.00 $11.29 Warehouse / Distribution 0% - 20% 60 Government $14.28
10,000 Warehouse / Distribution $0.50 $12.20 $15.25 0 ft - 28 ft
60 - $3.96 9 Q3 2019 New Lease (Net) - - $16.00 $16.28 Class A
7,000 Class A $3.00 $16.00 $32.15
11 Q3 2020 New Lease (Net) - - $9.75 $9.92 Warehouse / Distribution -
7,000 Warehouse / Distribution $1.75 $9.95 $15.18 24 ft
120 - $15.87
120 - $5.26
10 Q3 2019 Renewal (Net) - - $15.00 $14.62 Class B
12 Q3 2021 New Lease (Net) - - $10.00 $9.54 Warehouse / Distribution 20% 1,500 Class B $1.50 $15.00 $14.62
R
R
10,000 Warehouse / Distribution $1.00 $10.00 $14.66 26 ft
60 Insurance -
60 - $5.12
13
11 Q3 2019 Renewal (Net) - - $15.00 $14.62 Class B
Q1 2020 New Lease (Net) - - $9.75 $10.13 Warehouse / Distribution -
20,000 Warehouse / Distribution $1.75 $10.05 $10.13 24 ft - 28 ft 3,500 Class B $1.50 $15.00 $14.62
120 - - 60 Real Estate & Pension -
14 Q3 2019 New Lease (Net) - $15.16 $12.50 $8.50 Warehouse / Distribution - 12 Q3 2019 Renewal (Net) - - $15.00 $14.62 Class B
20,000 Warehouse / Distribution $1.75 $12.70 $12.40 24 ft - 28 ft
2,500 Class B $1.50 $15.00 $14.62
84 - $3.90
D
D
60 Resources -
MINIMUM - YEAR 1 BASE RENT $9.50 MINIMUM - YEAR 1 BASE RENT
MAXIMUM - YEAR 1 BASE RENT $12.50 MAXIMUM - YEAR 1 BASE RENT
13 Q4 2019 Renewal (Net) - - $16.00 $15.62 Class B
AVERAGE - YEAR 1 BASE RENT $10.71 AVERAGE - YEAR 1 BASE RENT
1,500 Class B $1.50 $16.00 $15.62
60 - -
CONFIDENTIAL CONFIDENTIAL
11410 Kingsway NW, Edmonton, AB 11410 Kingsway NW, Edmonton, AB
T
AF
R
D
altusgroup.com