Professional Documents
Culture Documents
On The Implementation of A Hysteretic Reactor Mode
On The Implementation of A Hysteretic Reactor Mode
On The Implementation of A Hysteretic Reactor Mode
net/publication/228874038
CITATIONS READS
11 522
6 authors, including:
Some of the authors of this publication are also working on these related projects:
Lightning experiment-protection of line 110 kV Ston-komolac against lightning by line surge arresters View project
All content following this page was uploaded by Manuel Martinez on 13 May 2014.
Sébastien Dennetière1, Jean Mahseredjian1 , Manuel Martinez2, Michel Rioual2, Alain Xémard2,
Patrick Bastard3
(1)IREQ / Hydro-Québec (2)Électricité de France (3)Supélec
1800 Lionel-Boulet Direction des Études et Recherches Plateau de Moulon
Varennes, Québec, 1 ave. du Général de Gaulle 3 Rue Joliot-Curie
Canada, (jeanm@ireq.ca) 92141 Clamart Cedex 91190 Gif-sur-Yvette Cédex, France
1
International Conference on Power Systems Transients – IPST 2003 in New Orleans, USA
Shv 8
1
The Chyst defines the hysteresis effect curvature. The re- 3
(3)
2
International Conference on Power Systems Transients – IPST 2003 in New Orleans, USA
C. Initialization
Before starting the time loop solution, it is needed to
initialize the reversal points stack. The first 2 points of this IV. IMPLEMENTATION IN EMTP
stack are initialized with very high flux ( 1010 Wb) for de-
fining the borders of the major loop. The remaining vari- A. The fitter
ables depend on the type of initialization. As a first step it is required to provide a fitting method
If ‘manual’ initial conditions (manual remanent flux for determining the parameters of equations (1) and (2).
φ0 ) are used then the initialization proceeds as shown in The new fitter uses a least-squares method for finding the
Fig. 4. Point 2 (current i 2 ) is arbitrarily chosen for a cur- saturation function parameters of equation (1). The pa-
rent 50 times the coercive current. The next step is to de- rameter Shv of equation (2) is also determined by this
termine equation (2) for a trajectory passing through φ0 method since during the fitting process λ unsat is replaced
which will give point 1. It is assumed that the trajectory by Shvi . The remaining parameters of equation (2) are
between the last reversal point and φ0 is a downward tra- determined from minor loop data. The coercive current is
jectory if φ0 ≥ 0 and upward trajectory if φ0 < 0 . Such determined from the major loop data or can be entered
manually when only a centered raw data is available. The
behavior is consistent with the deenergization pattern of a
user is allowed to visualize the fitting results and improve
transformer. The point 2 is chosen sufficiently high to en-
them by manipulating parameters.
able placing φ0 on the upper trajectory between 2 and 1
Fig. 6 compares a case of raw data with fitted data. The
when φ0 ≥ 0 and on the lower trajectory when φ0 < 0 . If requisite symmetry of the hyperbolic curves complicates
this condition is not satisfied then point 2 must be moved. the fitting if the available characteristic has a lack of sym-
The same technique is applicable to φ0 = 0 . metry. It also noticed that the fitting could have been im-
proved if 3rd or 4th order equations were used instead of the
λ unsat quadratic model of equation (1).
1010 3
80
1
φ0
70
i2
60 Raw data
i
Flux (Wb)
50 Fitted data
2
40
4 −1010
30
20
Fig. 4 Reversal points stack for manual initial conditions 10
If it is chosen to connect the reactor during the steady- 0
state phasor solution, one option is to use an inductance 0 50 100 150 200 250 300 350
value taken from the slope of the major hysteresis loop at i (A)
zero flux. In this case the initialization points are given in Fig. 6 Fitting example
Fig. 5. Points 3 and 4 are defined using 10φss . The choice
of 10φss (where φss is the flux at t=0 from the steady- B. Equivalent circuit
state phasor solution) is again arbitrary, but has been found The new hysteretic reactor has been implemented into
acceptable in most cases. a new EMTP code, named EMTP-RV [11][12]. To allow a
λ unsat
completely general solution where nonlinear model func-
1010 5 tions can be solved without topological restrictions,
3
EMTP-RV uses an iterative setup with the entire system of
linear equations. Nonlinear devices are required to simply
φss 1 return their discretized Norton equivalent through lineari-
zation at the given operating point for time-point t . This
−φss i
2 constitutes a Newton method.
4
The topological restrictions due to the compensation
method are eliminated, since there is no need to calculate a
−1010
Thevenin network equivalent as seen by the reactor.
6
Thevenin impedance or admittance conditioning problems
[9] are avoided. Since there is no separation between the
Fig. 5 Reversal points stack initialization from steady-state linear and nonlinear network (see [9] for details) solutions
3
International Conference on Power Systems Transients – IPST 2003 in New Orleans, USA
and all nonlinear functions are always present, there are no set of two interconnected target transformers (three-pole
restrictions on mixing nonlinear functions of various types. 3x360 MVA and three-phase 2x29 MVA) when a second
Contrary to the previous type-92 model, one can place the 600 MVA transformer has been already energized through
nonlinear hysteretic reactor in parallel with a nonlinear a long line. The generator at the sending end is a 900 MW
arrester model or use several combinations of nonlinear machine, which is modeled as an ideal source behind its
reactors without restrictions on voltage loops [9]. subtransient reactance. The long line and the interconnect-
In EMTP-RV, the hysteretic reactor is a flux- ing cables are modeled using pi-sections. The detailed case
input/current-output element. At each solution time-point it includes a total of 5 transformers: an autotransformer at
is converted into the Norton equivalent shown in Fig. 7. the receiving end of the line, the step-up transformer at the
This is similar to the nonlinear inductance model. The flux source end, the load transformer at the source end, the
φ(t j) (at time-point t and iteration j) is first found from the step-down target transformer and the second load trans-
former at the target. The target transformers (target is used
network voltage v(t j) using the trapezoidal integration here to denote the energized transformers) are modeled
method with time-step ∆t : using the hysteretic reactor model presented in this paper.
This approach allows to account for remanent flux at ener-
∆t ( j)
φ(t j) = v + φhistory (3) gization. All other transformers contain a nonlinear induc-
2 t tance. All nonlinear models are solved simultaneously with
This flux is entered into equation (1) as λ sat to find the linear network using the techniques developed in
EMTP-RV [11].
λ unsat and then into equation (2) to find the current on the
undertaken trajectory and φ(qj) (ordinate at the origin of
t
+
the operating segment) in:
φ(t j) = Κq( j)i t + φq( j) (4)
1
P Q
t t
2
The calculation of Κ(qj) requires the differentiation of both
t
(1) and (2):
+
∂φ ∂λ unsat 2
K (qj) = (5) 1
t ∂λ unsat φ( j) , λ ( j) ∂i λ ( j) ,i( j) + CP
t unsat t unsat t t
3
into:
it =
∆t
2Κ(qj)
vt +
1
Κq( j)
(φhistory − φ(qj)t ) (6) +
t t
2
RN P Q
+
Fig. 8 Simulated case
+
4
International Conference on Power Systems Transients – IPST 2003 in New Orleans, USA
x 10
5
VII. REFERENCES
5
4 [1] Electromagnetic Transients Program (EMTP), EMTP-
3 V3, Development Coordination Group of EMTP.
2
1
[2] A. Narang, E. P. Dick, R. C. Cheung “Transformer
Voltage (V)
800
[6] D. N. Ewart, “Digital Computer Simulation Model of
a Steel-Core Transformer”, IEEE, Transactions on
600 Power Delivery, Vol. PWRD-1, No. 3, July 1986, pp.
174-183.
Flux (Wb)
400
[7] A. Wright, A. and Carneiro Jr., S. - "Analysis of
200
Circuits Containing Components with Cores of
0 Ferromagnetic Material" - Proceedings IEE, Vol 121,
n 12, December 1974, pp. 1579-1581.
-200
[8] H. W. Dommel, “Nonlinear and time-varying
-1 0 1 2 3 4 5 elements in digital simulation of electromagnetic
i (A) transients”, IEEE Transactions, Vol. PAS-90, 1971,
Fig. 10 Hysteresis trajectories for phase-a of reenergized target pp. 2561-2567
transformer
[9] J. Mahseredjian, S. Lefebvre and X.-D. Do : “A new
method for time-domain modeling of nonlinear
It is valuable to mention that the mean number of itera- circuits in large linear networks”. 11th Power Systems
tions per time-point is about 2.21 and the total CPU time is Computation conference (PSCC), Proceedings Vol. 2,
60 s for a simulation interval of 3 s using ∆t = 50µs on a August 1993, pp. 915-922.
Pentium-4 computer of 1.7 GHz. The complete network [10] A. Semlyen and A. Castro : “A digital transformer
contains a total of 200 nodes and 250 devices. The simula- model for switching transient calculations in three
tion time is dramatically reduced by the ability of the setup phase systems”, PICA Conference Proceedings, New
to achieve steady-state conditions at simulation startup. Orleans, June 1975, pp. 121-126
5
View publication stats