Time
NO JOB DESC / MAINTENANCE ITEMS Work Scope WORKDAY
Start End 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
V MONITORING OPERATION
2
COMPLETED
MONITORING OPERATION OPERATOR 8:00 AM 8:00 PM →
1 GENERAL COMPLETION O/M 8:00 AM 8:00 PM
4 2nd INSTALL GAS SUPPLY VALVE UPPER SIDE MECHANIC/ELECTTRIC 8:00 AM 8:00 PM
24 TURBO CHARGER GAS OUTLET GUIDE & ASSESORIES MECHANIC/HELPER 8:00 AM 8:00 PM
22 RETIGHTENING CRANKPIN CAP & BEARING SHELL UPPER LOWER MECHANIC/HELPER 8:00 AM 8:00 PM
21 1st_INSTAL PISTON COMPLETE - RING SET & CONECTING ROD MECHANIC/HELPER 8:00 AM 8:00 PM
19 INPECTION - MEASUREMENT - PT - COLOUR CHECK AROUND CYLINDER COVER MECHANIC/HELPER 8:00 AM 8:00 PM
17 REMOVE - TAKE OFF MAIN & SLOW STARTING VALVE MECHANIC/HELPER 8:00 AM 8:00 PM
II AUXILIARY ENGINE
13 DRAIN - FILL OIL GENERATOR BEARING N/D MECHANIC + HELPER 8:00 AM 8:00 PM
9 RUNING TEST INSIDE FILTER SUCTION TURBOCHARGER MECHANIC + HELPER 8:00 AM 8:00 PM
7 RE_SEAL - RENEW BEARING - OVERHAUL MOTOR VENT BLOWER - MOTOR EXHAUST FAN MECHANIC/ELECTRIC 8:00 AM 8:00 PM
6 CHECK - CLEANING PUMP - COUPLING - MOTOR SECONDARY CW MECHANIC + HELPER 8:00 AM 8:00 PM
5 REMOVE - TAKE OFF PUMP - COUPLING - MOTOR PRIMARY CW MECHANIC + HELPER 8:00 AM 8:00 PM
13 MOTOR AUXILIARY - MOTOR FAN RADIATOR - VENT BLOWER - WIRING ELECTRICAL + HELPER 8:00 AM 8:00 PM
10 RUNING TEST PANEL HV 20KV - MV 11KV - WIRING ELECTRICAL + HELPER 8:00 AM 8:00 PM
9 INSULATION TEST & FUNCTION TEST PANEL LOW VOLTAGE 400V - WIRING ELECTRICAL + HELPER 8:00 AM 8:00 PM
8 INSTALL - RETIGHTENING - GREASE_UP PANEL ESP/CONTROL ENGINE & GCP - WIRING ELECTRICAL + HELPER 8:00 AM 8:00 PM
7 INPECTION - CLEANING CABLE - SOCKET INSTRUMENT - WIRING ELECTRICAL + HELPER 8:00 AM 8:00 PM
6 REMOVE - TAKE OFF SPARK PLUG MOUNT - SENSOR - WIRING ELECTRICAL + HELPER 8:00 AM 8:00 PM
5 PREPARE PICK UP SENSOR - PRESSURE SENSOR - THERMOCOUPLE - WIRING ELECTRICAL + HELPER 8:00 AM 8:00 PM
3 PM CLINIC & TAKE DATA BEFORE SOH ELECTRICAL + HELPER 8:00 AM 8:00 PM