Professional Documents
Culture Documents
Ch-7 Project Assessment 2
Ch-7 Project Assessment 2
Background
➢ The use of the cost of capital to calculate the net present value
in screening projects ensures that only projects that will enhance
the return to shareholders are taken on, provided that the cost
of capital is adjusted to reflect the project risk.
➢ The historical costs of the company’s existing capital is
irrelevant. What is important is the current cost of raising
incremental capital for the company to carry out the project.
➢ This cost is the rate of return which needs to be earned on the
capital if the existing shareholders are to be no better or no
worse off.
➢ If all the capital were to be raised from internal reserves or by a
rights issue, the cost of capital would be equal to the total rate of
return which could be expected to be earned by the
shareholders on their existing shares.
➢ If, however, the whole of the capital were to be raised from
fixed-interest borrowing, it would be the net cost of that
borrowing after allowing for tax reliefs and likely future inflation,
which would need to be taken as the cost of capital.
➢ If part of the capital were raised through equity and part through
borrowing, we would need to look at the weighted average cost.
➢ The WACC varies with the level of gearing and hence the optimal
capital structure will be that which minimises the WACC and
maximises the value of the company.
➢ The cost of debt capital should be taken as the cost in real terms
of new borrowing by the company. This is calculated by taking an
appropriate margin over the current expected total real return
on index-linked bonds, having regard to the company’s credit
rating, and multiplying by (1 – t), where t is the assumed rate of
corporation tax.
➢ The cost of equity capital should be taken as the current
expected total real return on index-linked bonds plus a suitable
margin to allow for the additional return which equity investors
seek to compensate them for the risks they run.
CAPM-based approach
➢ The CAPM model can be used to estimate the returns required
from a capital project.
➢ This required rate of return can then be used as a risk discount
rate to price the project.
➢ The project beta measures the systematic risk of the project and
so the above equation gives a higher/lower risk discount rate for
projects with a higher/lower level of systematic risk.
Ch-7 Project Assessment 2 Page 4
projects with a higher/lower level of systematic risk.
Practical experience
➢ Many companies apply the same cost of capital to all projects.
This can lead to wrong decisions being made if the systematic
risk of different projects is substantially different.
➢ It has been found that use of different costs of capital can lead to
internal friction within a company which can, along with the
complexity of the method, mean that the theoretically correct
approach is often ignored.
➢ It is not uncommon for companies to use very high discount or
hurdle rates when appraising proposed projects.
➢ Use of a very high discount rate could lead to the danger of the
incorrect acceptance of a risky project with a high apparent NPV
or the incorrect rejection of a low-risk project with a negative
NPV, which would have a positive NPV if this were calculated on
a lower but more appropriate discount rate.
➢ In any case it would usually be appropriate to carry out the NPV
calculations on two alternative discount rates, and if both results
are satisfactory, then there is no need to worry too much about
Ch-7 Project Assessment 2 Page 5
are satisfactory, then there is no need to worry too much about
determining the most appropriate discount rate precisely
➢ The use of a risk discount rate for establishing the present value
of future project cashflows combines the two elements of time
value of money and the level of risk associated with the
cashflow.
➢ As the level of risk may vary according to the nature of the item
being assessed, we should strictly use a different risk discount
rate for each element.
➢ To avoid this, we replace the individual (risky) projected
cashflows with their certainty equivalents.
➢ In this way we produce a series of ‘certain’ cashflows that can
then be discounted at a uniform rate of return.
➢ With any project there are risks and these can be divided into
two types:
1. Systematic: ‘in the system’ and which affect the whole area of
the business into which the project falls, eg price of land for a
building project.
2. Specific: ‘specific to the project’ and which can be diversified
away by the company, eg the risk of a cold summer reducing ice-
cream sales diversified by also selling hot dogs
Risk matrices
➢ These are helpful in the identification and analysis of risks.
➢ The basic idea is to construct a table or tables with different
generic categories and sub-categories of risk as the column and
row headings.
➢ One method by which to categorise risks is according to:
i. the cause of the risk (eg as columns)
ii. the stage of the project at which the risk arises (eg as rows).
Causes of Risk
i. political
ii. business
iii. economic
iv. project
v. natural
vi. financial
vii. crime.
➢ Having identified the risks inherent in the project, the next step
is to attempt to quantify their impact upon the financial returns
yielded by the project.
➢ Once the identification process is regarded as complete, an
analysis of the risks is done to ascertain the frequency of
occurrence and the consequences if the risk event occurs.
➢ The analysis will concentrate on the independent risks and
regard the dependent risks as consequences of them.
➢ The risks could be classified according to four different
dimensions:
i. Frequency of occurrence – the perceived likelihood that the
particular risk will occur. The categories used might vary from
‘very likely’ to ‘very unlikely
ii. Impact – the effect on the cashflows. The occurrence of a risk
with a major negative impact upon the project could lead to its
cancellation.
iii. Degree of dependence – of the various risks. Categories here
could range from ‘very high degree’ to ‘very low degree’.
iv. Controllability – the extent to which the impact of the risk can
be mitigated or managed. Here the categories could range from
‘can be completely mitigated’ to ‘very uncontrollable’. The cost
of control might also be considered here.
➢ The risk(s) in each cell of the risk matrix are therefore essentially
awarded a score for each of the above dimensions and the most
important risks in terms of their likely financial impact are
thereby identified.
➢ The most crucial aspect of risk is probably the absolute
magnitude of the financial impact.
1. Scenario Analysis
➢ The first is to construct a series of future scenarios, each
representing a combination of possible outcomes for the major
risk events and each having its own probability of occurrence,
obtained by combining the probabilities of the various
independent component risks.
➢ The outcomes selected for the scenario analysis will in practice
often be the mid-points of a range of possible values. For
example, if there is an 80% chance that the capital cost will lie
between £40m and £42m, and a 20% chance that it will lie
between £42m and £50m, one might model two sub-scenarios,
the first having a capital cost of £41m with an 80% probability
and the other having a capital cost of £46m with a 20%
probability. If each of these 2 sub-scenarios for capital cost were
to be combined with (say) 4 sub-scenarios on gross revenue and
3 sub-scenarios on running costs, we would generate a total of 2
* 4 * 3 = 24 scenarios.
➢ For each scenario the probability of occurrence and the NPV if it
occurs are calculated.
➢ Assuming that the scenarios cover all possible outcomes, at least
in principle, the result will be an approximate probability
distribution of the NPVs of the project.
Unfavourable NPVs
Example 1