Professional Documents
Culture Documents
Open Pit Mining: Mine Planning & Design: Focus On Surface Mining Technology: Lecture 2
Open Pit Mining: Mine Planning & Design: Focus On Surface Mining Technology: Lecture 2
Open Pit Mining: Mine Planning & Design: Focus On Surface Mining Technology: Lecture 2
Course objectives: to bring together aspects of planning & design for mining
highlighting the respective influence on the decision making process. Familialisation
with optimisation of planning & design and its base on net present capital values.
Organisational Structures
Definitions
Engineering: involves the manipulation of nature to create systems for the benefit of at
least some segment of mankind
Options
Expectations for each option
Placement of values on each option
n.b. all decisions are made under conditions of uncertainty. i.e. outcomes cannot be
precisely determined in advance
Technology: ability to make good engineering decisions and to carry them through to
their desired conclusions
Example:
Beans in jar
Issue of option space (+ve integers)
Choosing option space for most engineering systems is complex. There are two tasks:
Design synthesis
Parameterization
Design synthesis: broad configuration of possibilities
Parameterization: parameter alternatives
Consider 2 parallel hafts. One being driven and the other the driver through gears to turn
at ½ the speed of the driving shaft
Options:
Number of teeth on driving gear
Tooth design (straight, helical etc)
Thickness of gears
Driving gear material
Driven gear material
Method of attachment of driving gear to shaft
Method of attachment of driven gear to shaft
Page 2
Idea that planning is future directed with intent focused on determining the
appropriate objectives of an organisation within the context of possible significant
changes in organisation’s operating environment
Planning is flexible, requires planners to anticipate variety of possible scenarios
and develop alternative courses of action to deal with these scenarios and
depending upon environmental opportunities and threats likely to be encountered
select appropriate course of action that can most effectively address organisation’s
concerns
Stories Golden Shaft: Impact of unrelated discrete decisions on the mine and eventual
merger with Mazoe Mine
Gladstone Mine: as for Stories Golden Shaft – merger with Arcturus Mine
Patchway Mine: design shortcomings on mine access. Multiple shaft hoisting and
multi-level tramming on hoisting system. Effect of related manning levels. Remedial
work carried out on material handling. Space handling and impromptu decision on D-
shaft. Eventual merger with Golden Valley Mine
Renco Mine: Effect of low overall productivity per man-hour. Need for decision based
on capacity of deposit, equipment & people. Huge potential of deposit and area.
Comparison with Renstrom Mine in Sweden (equivalent annual tonnages)
Dalny & Venice Mines: Discrete as opposed to continual approach on decisions and
their inter relationships
Emeralds: problems
Buchwa: location
Page 3
Chiquicamata: massive failure of pit wall
Gaths Mine: introduction of false footwall, note also the work now being done on the
dumps albeit the previous acceptance of them
Shabanie: changing the mill from open to covered process under negative pressure in
the mill
Page 4
copper ore
iron ore
6. economics (costs), n.b. 1/100 of discovered deposits become successful
operations
7. closure costs
8. social
9. productivity
10. available information on the deposit (geology)
11. feasibility study
Note:
purpose of mining is to produce metal or mineral as cheaply as possible
ore - material that can be extracted from the ground at a profit today. This
depends on:
geological circumstances
availability of appropriate technology
suitable market
political
social
legal
geographical
topographical
geographical & topographical to include, topography, ground conditions, water
aspects, weather & seasonal variations e.g. 1 in 100-year floods, 1 in 1000-year
floods
slope stability
cost of mining & stripping
Page 5
location of waste dumps
tailings disposal
impact of footprint
dewatering system
tailings stability
surface mining in rainy season, winter for cold areas, etc
geography
geology
mining conditions
ore treatment
economic analysis
legal status
historical, political & sociological factors
they are also dependent on assumptions about methods, equipment and production
schedule.
Page 6
Inclined drift has optimum gradient determined by:
Production requirements
Development requirements
Operating costs
Additive effect of higher operating costs per hour & lower production as gradient
increases, optimum usually 8%-10%)
Recovery
Grade control
Economics (costs)
Flexibility of operation
Safety
Environment (work & effects on environment)
Social
Foot print
The various factors that influence the design are dependent on the capacity of the deposit
represented by:
Assay results
Geology
Extent of ore reserves
Topography
Mining equipment
Economic factors of operating costs
Capital requirements
Profit
Types of ore
Pit limits
Cut-off grades
Stripping ratios
Rate of production
Pit slopes
Bench heights
Road grades
Ore metallurgical characteristics
Hydrological conditions
Property lines
Marketing considerations
Page 7
Key elements for open-pit design
Stripping ratio
Pit slope angle
Cut-off grade
Use vertical sections to approximate and fix limits in the design. Horizontal sections and
plans used to optimize the pit design (long ore-bodies rely on vertical sections)
Production Engineering:
Solution of day to day production issues
Short term planning
Each item has a relationship to the value determine for each option & therefore each
expected outcome.
The actual design is defined and limited by, slopes, rock and ore characteristics, water
conditions, cut-off grade etc.
The size and number of machines are indirectly proportional i.e. in general terms,
capacity increase relates to a decrease in the number of pieces of equipment.
Bench height:
Is determined by:
Vertical distribution of ore
Production requirements and therefore equipment sizing
Page 8
Existing equipment and availability of new equipment
Other factors
Feasibility Studies
Aim:
Consider consequences of different options
Find the best option
Describe in greater detail the feasibility, or profitability
Provide recommendation for decision
Page 9
Pre-feasibility – at early stages of project. Uncertainty of the order of ±30%. To
obtain base for decision on more detailed study
Feasibility study:
Base for preliminary decision to realise project. Uncertainty ±20%
Definitive estimate:
Uncertainty ± 10%. Provides base for final decision for project go ahead
Procedure:
Determine annual production rates, taking into account: market; size of ore reserve;
capacity restrictions; investment requirement of plant; mine and infrastructure, labour
requirements; costs and revenues
Optimize mine layout e.g. optimal location of haulages system; optimisation of the
number of ore passes; location of shafts; dumps and processing plant
Optimisation of ore processing: e.g. best method, how much should be outsourced etc.
Consider use of contractors and leased equipment against owner owned or operated.
Other issues to consider are due diligence studies and acceptance of studies as bankable
projects.
Page 10
TUTORIAL EXAMPLES.
Example 1.
An ore body amenable to open pit mining contains Cu – ore with a small amount of gold
(0.25g/t ore) and silver (5.0g/t ore)
There is 400Mt waste and overburden inside the final pit limits.
Page 11
Silver $6.20 million
Assume an even feed to the concentrating plant and calculate for (a) and (b)
respectively:
SOLUTION
Break-even cut-off grade Mining cost/t ore + concentrating cost per tonne ore
=
(Metal price per tonne – SRM costs per tonne metal) x
recovery
Mining cost per tonne ore = Mining cost per tonne material x (1 +
stripping ratio)
Mining cost per tonne ore = $54 250
($21 700(1+1.5)
Concentrating cost per tonne ore = $77 500
Metal price per tonne = $68.2 million
SRM costs per tonne metal = $17.05 million
Recovery = 88%
Page 12
= 77500 = 0.17%
(68.2 million – 17.05 million) x 0.88
SOLUTION TO 2.0
a) b)
Total tonnes material 900 900
Total tonnes ore 400 300
b) 900-300 = 2:1
300
Head grade = average grade of blocks above cut-off grade. N.b. all blocks are the same
size. Therefore, average grade is the same as the arithmetic mean.
a) 25 200 tonnes
b) 25 200 tonnes
Annual production of copper metal = (Daily ore production) x (Head grade) x (Working
days per year) x Recovery =
Mineable ore reserves = all ore tonnages above or equal to cut-off grade
Page 13
a) = 400 Mt
b) = 300Mt
Annual ore production = Daily ore production x working days per year
Mine life =
a) 400 million = 52.9 years
7.56 million
Marginal stripping ratio = Recoverable value/tonne ore – production cost/ tonne ore
Stripping cost/tonne waste
SRM costs per tonne ore = head grade x recovery x SRM costs/tonne metal
Example No 2
Consider the deposit shown below. The copper content varies in different blocks,
ranging from less than 0.25% Cu to over 2.5% Cu. The depiction can be a section of a
Page 14
horizontal deposit suitable for surface mining or a plan/section through a deposit to be
mined underground. It is assumed that any part of deposit can be mined independently of
the adjoining parts. There are 30 blocks or areas in the deposit, each with 1Mt of ore.
Solution:
If one mined out all parts, the total profit will be:
$1.42trillion-$1.2Trillion = $220Billion where, $1.42 trillion is given by:
(1.34% Cu x 90% x ($12 million - $3.6 million -$1.5 million) - $24 000 - $12 000) x
30Mt
But to avoid mining those parts not worth mining, the cut-off grade must be found. It
will be 0.58% Cu, given by:
X x 90% x ($12 million -$3.6 million - $1.5 million) - $24 000- $12 000) = 0
There are six areas with less than 0.58% Cu. These are thus not worth mining and can be
excluded from the ore reserve estimation. By excluding the 6 non-profitable parts, the
average copper content will increase from 1.34% to 1.57%.
Page 15
(1.57% Cu x 90% x ($12 million - $3.6 million - $1.5 million) -$24 000 - $12 000) x 24
Mt
In the above example, it is assumed that the mining of one area could be done
independent of the other areas. However, let us assume that the picture through the ore
body above was a cross section through a deposit, which could be mined entirely by open
pit mining, as shown below.
i.e. what is the cut-off grade above, assuming the same costs etc as in the latest example?
Solution:
The cut-off grade will be 0.39% Cu given by:
X x 90% x ($12 million -$3.6 million -$1.5 million) -$24 000 = 0
All rock mined with more than 0.39% Cu should therefore be taken into the plant. There
are only three areas out the 30 that are not worth taking into the plant.
In an underground mine, production is at 1Mt of ore. The ore reserve is 10Mt. The
market demand limits the ore to 1Mtpy. The total production cost is $60 000/t
And the revenue is $90 000/t.
The company has just found a smaller deposit of 1Mt in the hanging wall. This deposit
must be mined immediately or left and cannot be mined in the future because of the
caving hanging wall. The revenue will be the same as for the main deposit, but the
mining cost will be higher at $75 000/t
Page 16
The discount rate has been determined to be 15%.
Solution:
The revenue for the smaller deposit is $90 000/t and the total cost only $75 000 per tonne.
One may therefore easily assume that the smaller deposit is worth mining. This should
only follow if mining the smaller deposit results in increased sale in the near future, but
this in not possible because of the market restriction.
Mining of the smaller deposit will thus result in higher costs during the first year. The
revenues will show up during the 11th year. The net present capital value is:
X: 1mtpy x (90 000-60 000) $/t x 5.02 = $150.6 billion
Y: (1mtpy x 90 000-75 000) $/t/ (1+0.15)) +150.6billion/ (1+0.15) =$144 billion
The conclusion is that the small deposit should not be mined because the NPV decreased.
The conclusion however, strongly depends upon what discount rate is used and how
much ore is left in the main deposit. Use of discount rates of 5% and 10% gives a totally
different picture.
An ore deposit contains 100 million tonnes of ore. Revenues and operating costs will be:
The investment in mining and processing equipment etc to get production started will be
higher if a high annual production is chosen and can be split up like this:
What is the optimal annual production level? The discount rate has been determined to
be 10%
Solution:
Page 17
The table below shows calculation of the net present capital value of the deposit for
different annual production rates. An annual production of approximately 5Mtpy yields
the highest value and should therefore be chosen.
Page 18
NET PRESENT CAPITAL VALUE (10%0 OF A DEPOSIT FOR DIFFERENT
ANNUAL PRODUCTION RATES
This applies when a decision has to be made on which deposit to mine first. Should the
largest deposit have to be mined first or the richest? Is it the deposit that yields the
lowest cost?
The mining sequence that yields the highest net present capital value of the whole ore
field supplies the best combination.
Example:
A mining company has located 4 different deposits, A-D. Each one is too small to carry
the cost of a processing plant. A new processing plant with an annual capacity of 1 mtpy
of crude ore will be constructed in the middle of the ore field and can be supplied with
crude ore transported from the different mines. Find out the best sequence for mining the
deposits?
Ore grades, costs and possible annual crude ore productions are different and summarized
in the table below:
A B C D
Crude ore tonnage, Mt 5.0 5.0 2.5 2.5*
Possible & recommended annual crude 1.0 0.5 0.5 0.5
ore production, Mtpy
% Cu in crude ore 2.0 0.5
% Pb in crude ore 1.0 4.0 3.0
%Zn in crude ore 2.0 2.5 6.0
Mining operating cost ($/t)# 12 000 12 000 12 000 12 000
Mine investment ($billion) 120 60 60 90
Page 19
The investment in the processing plant will be $300 billion
The annual cost for processing, administration etc is independent of ore processed and
will total $60 billion/year. Three different types of concentrates can be extracted from
the crude ore: copper, lead and zinc concentrate. The metal recovery will be 90% for
each metal.
After smelting and refining, refined copper, lead and zinc are produced. The metal
recovery is 90% for each metal. The cost for transportation to the smelter for smelting
and refining is:
Find the optimal mining sequence within the ore field and the cash flow for the whole
venture. The discount rate is 10%.
Solution:
The table below summarises the annual amount of refined metals for sale, annual
revenues and costs and finally, the net present capital value of each deposit at the point in
time when mining starts in the deposit without considering the costs for processing:
Page 20
A B C D
Life time for each mine (Yrs) 5 10 5 5
Metals for sale per year
Copper, thousand tonnes 16.2# 2.0
Lead, thousand tonnes 8.1 16.2 12.1
Zinc, thousand tonnes 8.1 10.1 24.3
Revenues ($billion/Yr)
Copper 194.4 24.0
Lead 48.6 97.2 72.6
Zinc 72.6 90.6 219
243.0 169.8 163.2 243.0
Operating cost ($billion/Yr), excl. processing
Mining 12.0 6.0 6.0 6.0
Smelt. & refining
Copper 73.2 9.0
Lead 12.0 24.0 18.0
Zinc 19.2 24.0 58.2
96.0 49.2 48.0 73.2
Mine investment ($billion) 120.0 60.0 60.0 90.0
Capital value(10%) of each deposit, when
mining starts on it:
(243-96)x3.79-120.0 437.1
(169.8-49.2)x6.14-60.0 680.4
(163.2-48.0)x3.79-60.0.0 376.8
(243-73.2)x3.79-90.0 553.8
Where 3.79 and 6.14 are Uniform Series Present Value factors for 10% and 5 and 10
years respectively.
# given by 1 Mtpy x 2% x 0.9 x 0.9 = 16.2 tonnes. Similarly for other values.
The total ore reserve is 15million tonnes of crude ore. This will give a total lifetime of
15 years.
The first thing to do is to check if there are any restrictions to consider which will limit
the number of combinations. They are:
When A is mined, only A has to be mined to feed the plant with crude ore during
5 years.
When B is mined during 10 years, two other deposits, C & D must also be after
each other, each lasts 5 years.
Page 21
The only possible combinations are now:
a) A is mined during 5 years. B is then mined in parallel with D during the first
five years and after that in parallel with C during the next 5 years.
b) B is mined parallel with D during 5 years, followed by B in parallel with C
during the next five years, after that A is mined during 5 years.
where 0.62 and 0.39 are single payment present value factors for 5 and10 years
respectively for 10%.
The cash flow for the whole ore field will be like this:
Page 22
The mining and processing cost have bee assumed to be constant for simplicity. These
vary considerably between different deposits.
The net present capital value for the whole ore field can be calculated. It will be $880
billion given by:
The net present capital value is positive and it will be profitable to open this ore field.
This shows how bottlenecks and the size of the ore reserve will affect optimal cut-off
grade in an underground mine in which for low-grade ore not mined, it will not be
possible to recover it in the future.
Example:
The deposit considered is a hypothetical copper deposit. The technique applied can be
used for any type of deposit.
The deposit is almost vertical, with a length of 400 metres and an average width of 50
metres. The depth is believed to be 500 metres.
The ore grade is highest close to the footwall, where 20 metres have an average of 2%
Cu. The copper content decreases towards the hanging wall.
How large a portion of this deposit will it be possible to mine profitable with depth?
Mining method:
This deposit is assumed to be mined by underground. The ore body is divided into levels,
each 100 metres high.
A drilling level is developed at the top of each level from which long parallel large
diameter holes are drilled into the ore body for blasting.
A loading level is developed at the bottom of each level from where LHD equipment
clean blasted ore from draw points into trucks for haulage through an inclined ramp up to
a primary crusher at a higher level.
Page 23
There will be five levels as the deposit is 500 metres deep.
Ore quantity:
The total amount of recoverable ore in one level is 6 million tones of which there are:
Mining plans:
The basic alternative is to produce 600 000 tonnes of ore per year from the high-grade
part close to the footwall. This will give a life of 4 years per level.
A lower cut-off grade will result in changed yearly ore production and/or changed life.
a) mining of low-grade ore can be used to increase the total mine production
and keep the lifetime of each level as well as the whole mine constant.
b) There is a bottleneck in the hoisting system or the processing plant such
that the mining of low grade ore results in high grade ore being replaced
by low grade ore or making the lifetime longer.
These are extreme alternatives. Different combinations should also be studied in a real
life situation to get a fuller picture.
A copper concentrate is obtained following grinding and floatation and is sent to the
smelter for production of refined copper for sale.
Page 24
MINING PLANS
CUT-OFF GRADE (%Cu)
2.0 1.5 1.0 0.5
Average Cu content % 2.0 1.83 1.62 1.40
A: Increased mine production and
constant lifetime
Lifetime (years/level) 4 4 4 4
Ore (million tonnes /year) 0.6 0.9 1.2 1.5
B: constant mine production
Ore (million tonnes/year) 0.6 0.6 0.6 0.6
Life time (years/level) 4 6 8 10
Underground development: $30 billion. $35 billion, $40 billion and $45 billion
respectively, this will increase by 10% per level on depth.
Mining operating cost: $30 000/tonne of ore mined respectively, which will increase by
10% per level
Extra cost for pillar recovery: $6 billion, $8 billion, $10 billion and $12 billion
respectively which will increase by 10% per level with depth
Ore beneficiation: $6 billion per year + $20 000 per tonne ore milled.
Copper price: $12 000/kg refined copper, of which the smelter to cover its costs will keep
30%.
OPTIMISATION
To find the optimal cut-off grade, the net present capital value for different cut-off grades
will be calculated and compared. The cut-off grade that gives the highest net present
value is the cut-off grade that should be chosen. A real interest rate of 15% is assumed.
The optimal cut-off grade must be found before the first block is developed. The next
table shows net present value of all costs (excl. investment) and revenues associated with
the first level at constant lifetime.
The table shows that a cut-of grade of 1.0% will yield the highest value. A cut-off grade
of 1.0% Cu should therefore be chosen if there is only one level.
Page 25
NET PRESENT CAPITAL VALUE OF ONE LEVEL AT CONSTANT LIFE TIME
The next table shows the same calculation if there is a bottleneck. The bottleneck results
in constant mine production of crude ore per year.
The table shows that a cut off grade of 1.5% will yield the highest value. A cut-off grade
of 1.5% should therefore be used.
Page 26
The final conclusion is therefore that the existence of a bottleneck means a higher cut-off
grade.
The two tables also show that a bottleneck will reduce the profitability. The net present
capital value will decrease from $169 billion to $117 billion.
# uniform series present value factors, 15% and a life for a level of 4, 6, 8 and 10 years.
* single payment present value factors, 15%
Page 27
THE EFFECTS OF THE SIZE OF THE ORE RESERVE
The question arises; does that mean that all parts in the whole deposit with 1.5% Cu or
more should mined?
The answer is : only if this level (level 1) is the only level we have.
It is apparent that there are 5 levels in the deposit and it is necessary to take them all into
account.
The next table shows the capital value of each level at the point in time when mining of
that level starts.
# is given by: 105 – (1.104 – 1) x (18.0 x 2.85 + 30 + 3), and similarly for other values.
This table shows how the longer haulage distance to surface will reduce the profitability
at deeper levels.
To find the optimal cut-off grade on each level, it is necessary to start with a study of the
deepest level.
The table shows that in the future when someone has to decide the cut-off grade of level
5, it is necessary to choose a cut-off grade of 1.5% Cu.
To find the optimal cut-off grade for level 4, it is necessary to add the value of level 5
because the lifetime of block 4 will increase from 4 to 6 years if all the ore with 1.5% Cu
or more will be mined and similarly for other cut-offs.
The capital value of level 4 & 5 when mining of level 4 starts is:
Value with cut-off grade @ 2.0% Cu: 77 +66 x 1.15-4 =$115 billion
Value with cut-off grade @ 1.5% Cu: 82 +68 x 1.15-6 =$111 billion
Page 28
It is apparent that only ore with 2.0% Cu should be mined from level 4 for profit
maximisation. Similar conclusions can be made for block 1-3.
The table below shows the total net present capital value assuming the same cut-off grade
all the lifetime.
# given by: $66 billion x 0.107, where 0.107 is the single value factor for 15%
and 16 years. ( mining of level 5 starts after 4 x 4 = 16 years).
The above table shows that a use of 2.0% Cu cut-off grade will yield the highest value for
the deposit.
Conclusions:
Such a study shows that a combination of increased mine production and increased
sinking rate will, if possible, be the most profitable way to increase the value of this
mine.
Page 29
Optimal number of ore-passes in a steeply dipping mine
Find the optimal number of ore-passes between 4, 6, 8, and 10 ore-passes per level. N.b.
each ore-pass serves an area on either side of it (scale drawing will indicate the haul
distances)
Number of ore-passes
4 6 8 12
Average haul distance for LHD single way (metres)
In crosscut 25 25 25 25
In drift 63 42 31 21
To ore-pass 25 25 25 25
total 123 92 81 71
A decision to deepen an open pit would normally result in increased waste rock or low-
grade material removal. Waste rock removal often precedes mining of corresponding ore
below it. Investment in waste removal needs to be paid back through higher internal rate
of return from future incomes.
Waste removal pushes up operating costs up to a limit that the operation can no longer
sustain. This is the ideal ultimate pit depth.
Page 30
The ultimate pit depth must be obtained early as it determines the size of the ore reserve
and ultimately maximum crude ore production and mine life. It is also the base for waste
removal for different push backs.
Ore grades can differ over the ore-body and influence economics
Interest rate costs can be high as stripping can occur many years prior to mining
ore
Value of ore can differ.
Procedure:
Establish the ultimate pit depth and design of a hypothetical deposit:
The deposit is steeply dipping with a length of 1000m and a width of 50-250m.
Study each cross section and establish the ultimate depth in the section
Even out the preliminary depths taking note of the final slope in all directions
Finally connect the final depths to establish the whole pit layout (incl. Haul roads)
Page 31
One Section through the ore body showing Cu%
Surface baseline
0.50 1.00 0.50 0.50 1.00
1.00 0.50 0.50 1.50 0.50 100m
1.50 0.50 0.50 1.00 2.00
200m 1.00 0.50 0.50 1.50 0.50
1.50 0.50 0.50 1.00 2.00
300m 0.50 0.50 1.00 0.50 1.50
0.50 1.00 0.50 0.50 1.00
400m 1.50 0.50 0.50 1.00 2.00
1.50 0.50 0.50 1.00
500m 0.50 1.00 0.50
P1 P2 P3 P4 P5 P6
Page 32
0.50 1.00 0.50 0.50 1.00
Calculation of the value of each tonne of rock for various copper grades based on:
P1 P2 P3 P4 P5 P6
Page 33
16.00 1.00 1.00 9.00 24.00 -2 -2 -2
References:
Page 34