Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

Inspection & Testing Plan for Installation of GRP pipes

Ref. P1122-0000-GEN-ME-ITP-0150-03 Rev. (03) Form Issue Date: 13/06/2022

Client : ADCOOP Prepared & signed by: Eng.SANDEEP


Project : ADCOOP DISTRIBUTION CENTRE
The Employer : ADCOOP Discipline : MEP Reviewed & signed by: ENG.NAVEEN
Engineer : WINNER ITP Serial No. : P1122-0000-GEN-HV-ITP-0150-03 Approved & signed by: ENG.YOUSUF
Contractor : JAZAL ENGINEERING AND CONTRACTING L.L.C Date : Page :
Item No.

Frequency of Applicable
Inspection THIRD
Inspection / Test to be carried out Test / Acceptance Criteria Specification / Control Data / Forms
Method JEC WINNER PARTY/SITE
Inspection Standard
LAB

1 PREPARATION PHASE (Before Installation)


Specifications/appr Approved Method Statement
oved material Ref. Ref.MS-JECL-MEP-001
Prior to start of
1.1 Method Statement Visula check satisfactory, MS-JECL-MEP-001
proper sizes pipes and accessories free of damage N/A H H N/A
work

Specifications/appr
Prior to start of oved material Ref. Approved Shop Drawings
1.2 Drawings Engineers Approval N/A H H N/A
work JEC-C1040-SD-ME- IFC Drawings
DR-SP-00
Specifications/appr Approved Method Statement
Prior to start of oved material Ref.
1.3 Delivery of GRP pipes Quantity verification Visual R S N/A
work JEC-C1040-SD-ME-
DR-SP-00
Dust and Dirt protection Approved Method Statement
Prior to start of Manufacturer's
1.4 Proper storage and proper cover.Not over Visual W S N/A
work stacking
recommendation
No Damage material, Specifications/appr
Dimensions / Sizes, oved material
Prior to start of
1.5 Material Inspection Marking on material, Material submittal Visual W W N/A
work
As per material
approval

1 BICC-P1122-FM-000 8rev.00
Inspection & Testing Plan for Installation of GRP pipes
Ref. P1122-0000-GEN-ME-ITP-0150-03 Rev. (03) Form Issue Date: 13/06/2022

Client : ADCOOP Prepared & signed by: Eng.SANDEEP


Project : ADCOOP DISTRIBUTION CENTRE
The Employer : ADCOOP Discipline : MEP Reviewed & signed by: ENG.NAVEEN
Engineer : WINNER ITP Serial No. : P1122-0000-GEN-HV-ITP-0150-03 Approved & signed by: ENG.YOUSUF
Contractor : JAZAL ENGINEERING AND CONTRACTING L.L.C Date : Page :
Item No.

Frequency of Applicable
Inspection THIRD
Inspection / Test to be carried out Test / Acceptance Criteria Specification / Control Data / Forms
Method JEC WINNER PARTY/SITE
Inspection Standard
LAB
2 INSTALLATION PHASE
Approved shop
Visual check
drawings/material submittal
satisfactory, proper
GRP pipes are installed in correct location as per As per approved and manufacturer
2.1 For each location size pipes and Visual R S N/A
approved drawings and equipment schedule shop drawings recommendations and check
accessories free of
list Ref. P1122-0000-GEN-
damage
HV-CK-0002
Specifications/appr
Visual check Approved shop
oved material
satisfactory, as per drawings/material submittal
2.2 Below Ground Drainage Gravity test For each location Visual R/W W N/A
approved material and manufacturer
submittal recommendations

Visual check Approved shop


As per approved
satisfactory, as per drawings/material submittal
2.3 2.3a Installation of underground pipes For each location shop drawings/ Visual/Dimension R W N/A
approved SD and and manufacturer
Details drawings
details drawings recommendations

No Damage to manufacturer's
Final inspection of complete installation including pipes/accessories and recomm.,Proj.
2.3 For each location Approved Drawings Visual R H N/A
identification prior to cover up works installed as per Spec., Approved
approved SD SD
Visula check
Approved shop
satisfactory, proper As per approved
drawings/material submittal
2.3 Clearance for civil work For each location sizes pipes and shop drawings/ N/A H H N/A
and manufacturer
accessories free of Details drawings
recommendations
damage
As per approved
complying all the IFC Drawings and
2.3 Review & endorse Red Line drawings For each location shop drawings/ N/A H H N/A
comments specifications
Details drawings

Visual check
Functional testing of complete drainage piping satisfactory, as per Spec. & Local Approved Drawings/Specs/
2.3 Final Hand over Visual H W N/A
system approved SD and Authority Material submittal
details drawings

1 BICC-P1122-FM-000 8rev.00
Inspection & Testing Plan for Installation of GRP pipes
Ref. P1122-0000-GEN-ME-ITP-0150-03 Rev. (03) Form Issue Date: 13/06/2022

Client : ADCOOP Prepared & signed by: Eng.SANDEEP


Project : ADCOOP DISTRIBUTION CENTRE
The Employer : ADCOOP Discipline : MEP Reviewed & signed by: ENG.NAVEEN
Engineer : WINNER ITP Serial No. : P1122-0000-GEN-HV-ITP-0150-03 Approved & signed by: ENG.YOUSUF
Contractor : JAZAL ENGINEERING AND CONTRACTING L.L.C Date : Page :
Item No.

Frequency of Applicable
Inspection THIRD
Inspection / Test to be carried out Test / Acceptance Criteria Specification / Control Data / Forms
Method JEC WINNER PARTY/SITE
Inspection Standard
LAB
Visual check
satisfactory, as per Spec. & Local Approved Drawings/Specs/
2.3 Final connection with Manhole/Infrastructure Final Hand over Visual H R/A A
approved SD and Authority Material submittal
details drawings

Visual check
satisfactory, as per Spec. & Local Approved Drawings/Specs/
2.3 Testing & Comissioning for gravity system For each location Visual H R/W A
approved SD and Authority Material submittal
details drawings

Spec. & Local


Engineers Approval/ Authority & Approved Drawings/Specs/
3 Review as built drawings For each location N/A H R/A N/A
As per site installation approved shop Material submittal
drawings
Note: AAAA: Contractor's Abbreviation, B: Discipline (CIV for Civil, STR for Structural, ELC for Electrical & MEC for Mechanical), ITP: Inspection & Testing Plan, NNN: Form Serial Number, XX: Revision Number,
dd/mm/yyyy: day/month/year , Responsibility: H-Hold, W-Witness, S-Surveillance, R-Review/Record

1 BICC-P1122-FM-000 8rev.00

You might also like