REPUBLIC OF THE PHILIPPINES

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS

CAVITE-LAGUNA EXPRESSWAY (CALAX) PROJECT


CAVITE SECTION
STA. 0+720 TO STA. 27+900
PROVINCE OF CAVITE

WEEKLY PROGRESS REPORT


(November 20 - 26, 2020)

INDEPENDENT CONSULTANT

United Technologies Consolidated Partnership and


Foresight Development and Surveying Company

CONTRACTOR
WEEKLY PROGRESS REPORT
CAVITE-LAGUNA EXPRESSWAY PROJECT (Cavite Segment)

Reference No. : Period Covered :


Cut-off Date :

CONTRACT DETAILS
Owner MPCala Holdings Inc. Grantor DPWH Construction Manager (ECDLCC) Antonio P. Aguilar

Principal Contractor E.C. de Luna Construction Corp. Independent Consultant UTCP/FDSC Start Date

Designer DCCD Engineering Corporation Client Representative Danilo R. Ignacio Finish Date 30-Dec-99

WEATHER

Legend

12
11 1

27 28 29 30 1 2 3 10 2
Fair Shower

9 1 3

4 Cloudy Rain
8

FRIDAY SATURDAY SUNDAY MONDAY TUESDAY WEDNESDAY THURSDAY 7 5


6
November 27, 2020 November 28, 2020 November 29, 2020 November 30, 2020 December 1, 2020 December 2, 2020 December 3, 2020 Night

Day Date

HEALTH & SAFETY ENVIRONMENTAL ISSUES


Toolbox Topic This Week : 0
Previous Report
1 This Period Total To-Date Previous Report This Period Total To-Date
Lost Workday Cases (LWDC) : - - -
Restricted Workday Cases (RWDC) - - - Major Environmental Incident
(MAJENV)
First Aid (FA) : - - -
Major Property Damage (MAJPD) : - - - Minor Environmental Incident
(MINENV)
Minor Property Damage (MINPD) : - - -
Near Miss Incidents : - - -
Contract Man-Hours : 0 0 0
Accident Free Man-Hours : 0 0 0

PROJECT ACCOMPLISHMENT SUMMARY

Project Start Date :

Project Finish Date : Previous This Period To Date

Project Duration : Planned - - -


Cut-off Date : Actual - - -
Days Ellapsed : Variance - - -
Days To-Go :

100%

Pl
90% an
Fo
80% re
ca
st
70%

60%

50%

40%

30%

20%

10%

0%
08-Aug-15

08-Nov-15
12-Nov-15

22-Dec-15
26-Dec-15
11-Jul-15
15-Jul-15
19-Jul-15
23-Jul-15
27-Jul-15
31-Jul-15
04-Aug-15

12-Aug-15
16-Aug-15
20-Aug-15
24-Aug-15
28-Aug-15
01-Sep-15
05-Sep-15
09-Sep-15
13-Sep-15
17-Sep-15
21-Sep-15
25-Sep-15
29-Sep-15
03-Oct-15
07-Oct-15
11-Oct-15
15-Oct-15
19-Oct-15

04-Nov-15

16-Nov-15
20-Nov-15
24-Nov-15
28-Nov-15
02-Dec-15
06-Dec-15
10-Dec-15
14-Dec-15
18-Dec-15

30-Dec-15
03-Jan-16
07-Jan-16
11-Jan-16
15-Jan-16
19-Jan-16
23-Jan-16

04-Feb-16
08-Feb-16
12-Feb-16
23-Oct-15
27-Oct-15
31-Oct-15

27-Jan-16
31-Jan-16

Project S-Curve

F-CON-004 Rev 3 Dec 02, 2020 Page 2 of 17


WEEKLY PROGRESS REPORT
CAVITE-LAGUNA EXPRESSWAY PROJECT (Cavite Segment)

Reference No. : Period Covered :


Cut-off Date :

HIGHLIGHTS OF EVENTS AND ACTIVITIES


ROADWORKS

No. Particulars Remarks


1.)
2.)
3.)
4.)
5.)

MISCELLANEOUS

No. Particulars Remarks


1.)
2.)
3.)
4.)
5.)

MANPOWER AND EQUIPMENT

Manpower Monitoring Equipments & Tools


Description Req'd Fri Sat Sun Mon Tue Wed Thu Description Active Idle Total Remarks
Office/Indirect Staff A. PLANTS 0
Quantity Engineer Crushing/Screening Plants 150 t/hr 0
Office Engineer Screening/Washing Plant 150 t/hr 0
Autocad Operators Concrete Batch Plant 60 cu. m/hr 0
Direct Staff/Supervision Asphalt Batching Plant 120 t/hr 0
Project Manager B. HEAVY EQUIPMENT 0
Road Manager Bulldozer Crawler 302 hp
Field Engineer Wheel Loader 3.50 cu. M
Direct Workers/Labors Concrete Paver/Finisher 2-6m width and 400mm thk
Operators Asphalt Paver/Finisher 2.55m-6.5m width
Mason Asphalt Distributor/Tanker 12,500 lit
Welder Motor Grader 155 hp-195 hp
Mechanics/Electricians Backhoe Excavator 1.60 cu. M
Laborers Backhoe with Hydraulic breaker 1.50 cu. M
Office Support/Others Pneumatic Roller 10 ton, 100 hp
Material Engineer Vibratory Drum Roller 12 ton
Surveyor Vibratory Plate Compactor 5hp
Survey Aides Drill Rig, Mechanical Rotary 600-2000mmØ
Health & Safety Officer Truck Mounted Crane, Hydraulic Telescopic Boom
Environmental Officer Pile Vibratory Hammer
Administrative Assistant C. LIGHT EQUIPMENT
Warehouse In Charge Dump Truck/Tipper or Side Tippers 12-14 cu. M
Warehouseman Fuel Truck
Batching Plant Operator Transit Mixer 6 cu. M
Plant Clerk Service Vehicle
Equipment Clerk TOTAL 0 0 0
Payroll Clerk
Document Controller
Warehouse Clerk
Laboratory Technician
Lab. Encoder
Laboratory Aide
Drivers 0
Conveyor/Slammer
Timekeeper
Security
TOTAL

TWO WEEKS LOOK-AHEAD SCHEDULE

See attachment for Two Weeks Look-Ahead Schedule

SITE ISSUES AND CONCERN


CONSTRUCTION MATTERS
No. Particulars Remarks/Plan of Action

DESIGN ISSUES
No. Particulars Remarks/Plan of Action

Prepared by: Reviewed by: Checked by: Noted by:

Office Engineer Quantity Engineer Materials Engineer II Project Manager


F-CON-004 Rev 3 Dec 02, 2020 Page 3 of 17
WEEKLY PROGRESS REPORT
CAVITE-LAGUNA EXPRESSWAY PROJECT (Cavite Segment)

Reference No. : Period Covered :


Cut-off Date :

F-CON-004 Rev 3 Dec 02, 2020 Page 4 of 17


WEEKLY PROGRESS REPORT
CAVITE-LAGUNA EXPRESSWAY PROJECT (Cavite Segment)

Reference No. : Period Covered :


Cut-off Date :

SITE PHOTOS

F-CON-004 Rev 3 Dec 02, 2020 Page 5 of 17


Click here for
Instructions & Menu
Click here for
Instructions & Menu
Click here for
Instructions & Menu
Click here for
Instructions & Menu
Click here for
Instructions & Menu
Click here for
Instructions & Menu
Click here for
Instructions & Menu
Staffing Plan and Forecast Schedule 7
DD-200 Attachment 7-8
Month/Year

Click here for


Instructions & Menu
l
i
c
k

H
e
r
e 21-Nov-20
Click here for
Instructions & Menu 13
t Week No 13 To
o To
Actions Equipment
Forecast
E
n
l
a
r
g
e

o
n

S
c
r
e
e
n
Click here for
Instructions & Menu
Click here for
Instructions & Menu
MANPOWER EQUIPMENT

Resource Resource Description UOM Resource Resource Description UOM

Project Managemnt Non-Manual LP01 Contracts Manager m/w P01 Excavator No.
LP02 Project Manager m/w P02 JCB 4xC No.
LP03 Construction Manager m/w P03 Shovel No.
LP04 Commercial Manager m/w P04 Roller No.
LP05 Project Director m/w P05 Grader No.
P06 Tipper Trucks 10-30 m3 No.
Engineering Non-Manual LE01 Engineering m/w P07 Compactor No.
LE02 Chief Surveyor m/w P08 Dumpers No.
P09 Trailer No.
Construction Non-Manual LC01 Senior Engineer m/w P10 Compressor No.
LC02 Site Engineer m/w P11 Steel Cutting & Bending No.
LC03 QA/QC Engineer m/w P12 Water Tanker No.
LC04 Safety Officer m/w P13 Generators No.
LC05 Planner m/w P14 Asphalt Pavers No.
LC06 Surveyor m/w P15 Pickups No.
LC07 Site Clerk m/w P16 Transport Buses No.
LC08 Foreman m/w P17 Mobile Crane No.
LC09 Quantity Surveyor m/w P18 Dozer D9 No.
LC10 Safety Staff m/w P19 Dozer
LC11 Technical Staff m/w P20 CSD
LC12 Admin. Staff m/w P21 TSHD
P22 Crane Barge
P23 Booster
Manual LC50 Bricklayer m/w P24 Tugs / Launches
LC51 Carpenter m/w P25 Survey Launch
LC52 Steel Fixer m/w P26 Multicat
LC53 Laborer m/w P27 Dump Truck
LC54 Plant Operator m/w P28 Wheel Loader
LC55 Driver m/w
LC56 Roofer m/w
LC57 MEP Skilled m/w
LC58 Store/Time Keeper m/w
LC59 Equipment Operator m/w
LC60 Mantenance Crew m/w
LC61 Painter m/w
LC62 Skilled Labor m/w
LC63 Captain/Chief - Skipper m/w
LC64 Ship Officers m/w
LC65 Skilled Crew m/w
LC66 Semi Skilled Crew m/w
LC67 Semi-skilled Labor
LC68 Unskilled Labor