Professional Documents
Culture Documents
Weekly Progress Report: Department of Public Works and Highways
Weekly Progress Report: Department of Public Works and Highways
Weekly Progress Report: Department of Public Works and Highways
INDEPENDENT CONSULTANT
CONTRACTOR
WEEKLY PROGRESS REPORT
CAVITE-LAGUNA EXPRESSWAY PROJECT (Cavite Segment)
CONTRACT DETAILS
Owner MPCala Holdings Inc. Grantor DPWH Construction Manager (ECDLCC) Antonio P. Aguilar
Principal Contractor E.C. de Luna Construction Corp. Independent Consultant UTCP/FDSC Start Date
Designer DCCD Engineering Corporation Client Representative Danilo R. Ignacio Finish Date 30-Dec-99
WEATHER
Legend
12
11 1
27 28 29 30 1 2 3 10 2
Fair Shower
9 1 3
4 Cloudy Rain
8
Day Date
100%
Pl
90% an
Fo
80% re
ca
st
70%
60%
50%
40%
30%
20%
10%
0%
08-Aug-15
08-Nov-15
12-Nov-15
22-Dec-15
26-Dec-15
11-Jul-15
15-Jul-15
19-Jul-15
23-Jul-15
27-Jul-15
31-Jul-15
04-Aug-15
12-Aug-15
16-Aug-15
20-Aug-15
24-Aug-15
28-Aug-15
01-Sep-15
05-Sep-15
09-Sep-15
13-Sep-15
17-Sep-15
21-Sep-15
25-Sep-15
29-Sep-15
03-Oct-15
07-Oct-15
11-Oct-15
15-Oct-15
19-Oct-15
04-Nov-15
16-Nov-15
20-Nov-15
24-Nov-15
28-Nov-15
02-Dec-15
06-Dec-15
10-Dec-15
14-Dec-15
18-Dec-15
30-Dec-15
03-Jan-16
07-Jan-16
11-Jan-16
15-Jan-16
19-Jan-16
23-Jan-16
04-Feb-16
08-Feb-16
12-Feb-16
23-Oct-15
27-Oct-15
31-Oct-15
27-Jan-16
31-Jan-16
Project S-Curve
MISCELLANEOUS
DESIGN ISSUES
No. Particulars Remarks/Plan of Action
SITE PHOTOS
H
e
r
e 21-Nov-20
Click here for
Instructions & Menu 13
t Week No 13 To
o To
Actions Equipment
Forecast
E
n
l
a
r
g
e
o
n
S
c
r
e
e
n
Click here for
Instructions & Menu
Click here for
Instructions & Menu
MANPOWER EQUIPMENT
Project Managemnt Non-Manual LP01 Contracts Manager m/w P01 Excavator No.
LP02 Project Manager m/w P02 JCB 4xC No.
LP03 Construction Manager m/w P03 Shovel No.
LP04 Commercial Manager m/w P04 Roller No.
LP05 Project Director m/w P05 Grader No.
P06 Tipper Trucks 10-30 m3 No.
Engineering Non-Manual LE01 Engineering m/w P07 Compactor No.
LE02 Chief Surveyor m/w P08 Dumpers No.
P09 Trailer No.
Construction Non-Manual LC01 Senior Engineer m/w P10 Compressor No.
LC02 Site Engineer m/w P11 Steel Cutting & Bending No.
LC03 QA/QC Engineer m/w P12 Water Tanker No.
LC04 Safety Officer m/w P13 Generators No.
LC05 Planner m/w P14 Asphalt Pavers No.
LC06 Surveyor m/w P15 Pickups No.
LC07 Site Clerk m/w P16 Transport Buses No.
LC08 Foreman m/w P17 Mobile Crane No.
LC09 Quantity Surveyor m/w P18 Dozer D9 No.
LC10 Safety Staff m/w P19 Dozer
LC11 Technical Staff m/w P20 CSD
LC12 Admin. Staff m/w P21 TSHD
P22 Crane Barge
P23 Booster
Manual LC50 Bricklayer m/w P24 Tugs / Launches
LC51 Carpenter m/w P25 Survey Launch
LC52 Steel Fixer m/w P26 Multicat
LC53 Laborer m/w P27 Dump Truck
LC54 Plant Operator m/w P28 Wheel Loader
LC55 Driver m/w
LC56 Roofer m/w
LC57 MEP Skilled m/w
LC58 Store/Time Keeper m/w
LC59 Equipment Operator m/w
LC60 Mantenance Crew m/w
LC61 Painter m/w
LC62 Skilled Labor m/w
LC63 Captain/Chief - Skipper m/w
LC64 Ship Officers m/w
LC65 Skilled Crew m/w
LC66 Semi Skilled Crew m/w
LC67 Semi-skilled Labor
LC68 Unskilled Labor