Professional Documents
Culture Documents
Method Statement for Tugboat Berth Pile Driving (缺附件A)
Method Statement for Tugboat Berth Pile Driving (缺附件A)
NIGERIA
Method statement for Tugboat berth pile
driving
Contract No. Doc No. LDSPP-Q-02.03-05-0001 Page 1 / 19
Document No : LDSPP-Q-02.03-05-000?
Revision: C01
D ate of Issue : 15 Jan. 2021
Table of Contents
1. General............................................................................................................................... 3
2.1 Definition.................................................................................................................... 5
3. Scope of Works................................................................................................................. 5
4. Standards & References...................................................................................................6
5. Materials & Equipment......................................................................................................6
6. Manpower.......................................................................................................................... 7
7. Construction Flow Chart...................................................................................................7
8. Construction Methodology...............................................................................................8
8.1 Temporary Steel Trestle.............................................................................................8
8.2 Pile casing driving....................................................................................................12
8.3 Tubular pile driving...................................................................................................14
9. Quality Control................................................................................................................ 16
9.1 Overall Quality Control Measures.............................................................................16
9.2 Quality Control Measures for Key Sub-items............................................................16
10. Health, Safety, Security and Environment...................................................................17
10.1 HSE Measures.......................................................................................................17
10.2 Reference............................................................................................................... 18
11. Appendix........................................................................................................................ 18
Appendix A - Lifting Plan for Tugboat berth Pile driving.................................................18
Appendix B - Pile Driving Record Form..........................................................................25
1. General
The purpose of this method statement is to provide construction method and
resource deployment for Tugboat berth pile driving.
The Tugboat berth pile is Φ1000mm steel tubular pile.
2.1 Definition
Project Lekki Deep Water Port Project NIGERIA
Works Method Statement for Tugboat berth pile driving
Employer LEKKI PORT LFTZ ENTERPRISE (LPLE)
Contractor CHEC
3. Scope of Works
This method statement is applicable to the Tugboat berth pile driving. The
quantity of pile driving is following:
Design documents
No. Item Unit Quantity Single(T) Remarks
number
7 Excavator CAT330 1
8 Generator SP500 1
9 GPS ZHD-V60 1
11 Optical Level / 2
6. Manpower
The manpower required for the execution of the works includes the following
personnel:
Table 2: List of Manpower
1 Site engineer 2
2 Equipment engineer 2
3 QA/QC engineer 2
4 Surveyor 2
5 HSE officer 2
6 Rigger 2
7 Labor 20
8 Operator 7
8. Construction Methodology
Manpower, materials, and construction equipment shall be deployed, prepared
before commencement of works.
(1)First step would be to excavate the existing ground and pour the concrete
retaining wall for Temporary Steel Trestle as shown in the below picture. A layer of 1-
100kg rock shall be placed and roller compacted for foundation of concrete retaining
wall before its casting.
Figure 8-3: RETAINING WALL
(2) The piles for Temporary Steel Trestle will be driven first and double I-beam
56a will be installed by the crane and then the precast concrete beam will be installed
using crane as shown in the below picture..
(1)The protective measures of anticorrosive coating must be taken when the pile
is transporting, storing, and driving. The contact part between the pile and its
supports shall be covered with cloth cushion to prevent the coating damage.
(2)The Anticorrosive coating which use for pile must have a certificate of
compliance.
(3)Check the integrity of the coating before pile driving, if there is any coating
damage, the damaged part shall be repaired again.
Pile driving control
(1)Surveyors shall monitor pile deviation constantly during pile driving to correct
deviation.
Appendix A
Lifting Plan for Tugboat berth Pile driving
Appendix B
project date
Stroke
weather temperature Model
height(cm)
Average Pile tip
reading Embedded
Material NO. frequency penetration elevation others
rulers depth(m)
pile (cm) (m)
parameter diameter 1
serial of pile 2
start time 3
7
8
9
10
11
12
13
14
15
16
17
18
19
Pile tip
elevation(m)
20
Pile top 21
elevation(m)
Inclination deviation of pile
east others
south
Deflection of
pile(cm) west
north Surveyor Recorder checker