TB. KANAKA 09 - Overhaul AE Kiri.
TB. KANAKA 09 - Overhaul AE Kiri.
SN. 4B12G002282
No. Doc
OHR
OVERHAUL REPORT
Start Date Time Finish Date Time Mach. Status ⃝ Breakdown ⃝ Operation
Diagnose ticket Trouble Date:
Waiting part Bk’down start date time
Target ticket/lama kerja Ready for use date time
A. LIST OF WORK
No Description
I. Engine Over Houl (work standards based on manual book)
1. Checking
2. Measuring
3. Service
4. Replacement Parts
5. Assembly
6. Running Test
1. Checking and measuring
Main bearing journal out side diameter
Main bearing journal nominal diameter
Main bearing clearance
Crank shaft end ply
Crank pin out side diameter
Con rod bearing journal diameter
Con rod clearance
Con rod end ply
Piston out side diameter
Piston ring grove clearance
Piston con rod bush diameter
Piston pin out side diameter
Piston pin bush diameter
Cylinder liner inside diameter
Prostution cylinder liner
Crank shaft deflexion
Piston ring gap
Cam shaft journal diameters
Cam shaft bearing out side diameters
Cam lobe
No. Doc
OHR
OVERHAUL REPORT
Vessel Name : TB. KANAKA 09 Cost center :
Customer : PT. KANAKA WO date : No :
Machine/Model : DEUTZ TD226B-4CD1 Application : Auxiliary Engine kiri
Serial No. : 4B12G002282 HM # : Unit no. # : Asset no. :
Factory dealer : Rig # : Location :
Contact Person : HP : Customer engineer :
Start Date Time Finish Date Time Mach. Status ⃝ Breakdown ⃝ Operation
Diagnose ticket Trouble Date:
Waiting part Bk’down start date time
Target ticket/lama kerja Ready for use date time
A. LIST OF WORK
No Description
Cylinder head
Valve seat
Diameter valve stems
Inside diameter valve guide
2. Replacement Parts
Replace all gaskets (overhaul gasket kit)
Replace parts based on result of measurement
3. Assembly Parts
Installation’s method based on manual book
Tight of bolt suitable with manual book
4. Service – Generals
Injection Pump → Check pressure, volume → Calibration
Injector → Test pressure → Calibration
Adjust valve clearance
Cleaning and service dynamo starter
Cleaning and service alternator
New water cooler (AH 300)
Check, service and cleaning oil cooler
Check and test thermostat
Service / recondition / reseal fresh water pump and sea water pump
Check housing Replace mechanical seal
Check shaft Coupling
Check impeller
Replace radiator coolant
Replace oil filter
Replace fuel filter and fuel filter separator
Replace air cleaner
Replace all fan belt
No. Doc
OHR
OVERHAUL REPORT
Vessel Name : TB. KANAKA 09 Cost center :
Customer : PT. KANAKA WO date : No :
Machine/Model : DEUTZ TD226B-4CD1 Application : Auxiliary Engine kiri
Serial No. : 4B12G002282 HM # : Unit no. # : Asset no. :
Factory dealer : Rig # : Location :
Contact Person : HP : Customer engineer :
Start Date Time Finish Date Time Mach. Status ⃝ Breakdown ⃝ Operation
Diagnose ticket Trouble Date:
Waiting part Bk’down start date time
Target ticket/lama kerja Ready for use date time
A. LIST OF WORK
No Description
Check and repair control indicator / engine panel
Oil pressure, water temperature, battery charge, etc
Check foundation and foundation’s bolts
Check coupling to generator
Check exhaust line, flexible, until output exhaust
Instal sea water cooling
5. Running Test
IDLE
1500 Rpm without load
Load test ± 6 hours (gradually and recorded)
Make a result report and the condition of engine (record all of engine control system and
generator)
MAIN BEARING CLEARANCE
A
C B
B C
A
NO I II III IV
A 0.065 0.063 0.063 0.063
1 B 0.076 0.076 0.076 0.076
C 0.063 0.063 0.063 0.063
A
C B
B C
A
NO I II III IV
A 0.020 0.021 0.025 0.020
1 B 0.025 0.025 0.025 0.025
C 0.021 0.020 0.020 0.021
INSIDE CYLINDER LINER DIAMETER
F
1 2 3 4
P S
F-A
NO I II III IV
1 105.00 105.00 105.00 105.00
2 105.00 105.00 105.00 105.00
3 105.00 105.00 105.00 105.00
4 105.00 105.00 105.00 105.00
P-S
NO I II III IV
1 105.00 105.00 105.00 105.00
2 105.00 105.00 105.00 105.00
3 105.00 105.00 105.00 105.00
4 105.00 105.00 105.00 105.00
GAP
DIVISION
TOP RING
2ND RING
OIL RING
F
1 2 3 4
P S
F-A
NO I II III
1 104.25 104.25 104.25 104.25
2 104.80 104.80 104.80 104.80
3 104.80 104.80 104.80 104.80
4 104.94 104.94 104.94 104.94
P-S
NO I II III
1 104.25 104.25 104.25 104.25
2 104.80 104.80 104.80 104.80
3 104.74 104.74 104.74 104.74
4 104.94 104.94 104.94 104.94
Alat yang Digunakan :
2. Micro meter
3. Dial gauge
4. Plastik gauge
Dokumentasi :
Pelaksana :
Eko Purwanto