CONTRACTOR:
FRONTIER WORKS ORGANIZATION (FWO)
CLIENT:
QUETTA ELECTRIC SUPPLY COMPANY (QESCO)
CONTRACTOR:
FRONTIER WORKS ORGANIZATION (FWO)
DATED: 01 - 06 - 2022
Table of Contents
1 PROJECT BRIEF...................................................................................................................... 5
2 EXECUTIVE SUMMARY: ...................................................................................................... 6
2.1 Brief Description of Project: .................................................................................................. 6
2.2 Location of Sites: ................................................................................................................... 6
2.3 Scope of Work: ...................................................................................................................... 6
3 OVERALL PROGRESS OF WORKS....................................................................................... 7
3.1 132KV D/C T/LINE FROM PANJGOOR TO NAG GRID STATION - (LINE#4) ................ 7
3.2 132KV D/C T/LINE FROM NAG TO BASIMA GRID STATION - (LINE#5) ..................... 7
3.3 132KV D/C T/LINE FROM BASIMA TO NAL GRID STATION - (LINE#6) ..................... 7
4 LINE WISE PROGRESS .......................................................................................................... 8
4.1 132KV D/C T/LINE FROM PANJGOOR TO NAG GRID STATION - (LINE#4) ................ 8
4.2 132KV D/C T/LINE FROM NAG TO BASIMA GRID STATION - (LINE#5) ................... 10
4.3 132KV D/C T/LINE FROM BASIMA TO NAL GRID STATION - (LINE#6) ................... 12
5 PLAN FOR NEXT 30 DAYS: ................................................................................................. 15
5.1 132KV D/C T/LINE FROM PANJGOOR TO NAG GRID STATION - (LINE#4) .............. 15
i. Foundation Work ................................................................................................................. 15
ii. Erection Work ..................................................................................................................... 15
iii. Stringing of Conductor ........................................................................................................ 15
iv. Stringing of Earthwire ......................................................................................................... 15
5.2 132KV D/C T/LINE FROM NAG TO BASIMA GRID STATION - (LINE#5) ................... 15
i. Foundation Work ................................................................................................................. 15
ii. Erection Work ..................................................................................................................... 15
iii. Stringing of Conductor ........................................................................................................ 15
iv. Stringing of Earthwire ......................................................................................................... 15
5.3 132KV D/C T/LINE FROM BASIMA TO NAL GRID STATION - (LINE#6) ................... 15
i. Foundation Work ................................................................................................................. 15
ii. Erection Work ..................................................................................................................... 15
iii. Stringing of Conductor ........................................................................................................ 15
iv. Stringing of Earthwire ......................................................................................................... 15
6 COMPARISON OF THE PLANNED VS ACTUAL PROGRESS: ......................................... 16
6.1 132KV D/C T/LINE FROM PANJGOOR TO NAG GRID STATION - (LINE#4) .............. 16
i. Foundation Work: ................................................................................................................ 16
ii. Erection Work: .................................................................................................................... 16
iii. Stringing of Conductor: ....................................................................................................... 16
iv. Stringing of Earthwire: ........................................................................................................ 16
6.2 132KV D/C T/LINE FROM NAG TO BASIMA GRID STATION - (LINE#5) ................... 16
i. Foundation Work: ................................................................................................................ 16
ii. Erection Work: .................................................................................................................... 16
iii. Stringing of Conductor: ....................................................................................................... 16
iv. Stringing of Earthwire: ........................................................................................................ 17
6.3 132KV D/C T/LINE FROM BASIMA TO NAL GRID STATION - (LINE#6) ................... 17
i. Foundation Work: ................................................................................................................ 17
ii. Erection Work: .................................................................................................................... 17
iii. Stringing of Conductor: ....................................................................................................... 17
iv. Stringing of Earthwire: ........................................................................................................ 17
7 MATERIAL STATUS ............................................................................................................ 18
7.1 132KV D/C T/LINE FROM PANJGOOR TO NAL G/S - (LINE#4,5,6) ............................. 18
i. Stubs and Cleats: ................................................................................................................. 18
ii. Tower Material: ................................................................................................................... 18
iii. Stringing Material: ............................................................................................................... 18
8 CONTRACT & FINANCE ..................................................................................................... 19
9 PROGRESSIVE PROGRESS REPORT .................................................................................. 19
9.1 132KV D/C T/LINE FROM PANJGOOR TO NAG GRID STATION - (LINE#4) .............. 19
9.2 132KV D/C T/LINE FROM NAG TO BASIMA GRID STATION - (LINE#5) ................... 19
9.3 132KV D/C T/LINE FROM BASIMA TO NAL GRID STATION - (LINE#6) ................... 19
10 SITE PHOTOGRAPHS........................................................................................................... 20
10.1 EXCAVATION ACTIVITY ................................................................................................ 20
10.2 CONCRETE ACTIVITY..................................................................................................... 21
1 PROJECT BRIEF
All materials, tools, equipment and services, necessary for the reliable and safe operation of the
transmission line.
3 OVERALL PROGRESS OF WORKS
3.1 132KV D/C T/LINE FROM PANJGOOR TO NAG GRID STATION - (LINE#4)
3.2 132KV D/C T/LINE FROM NAG TO BASIMA GRID STATION - (LINE#5)
3.3 132KV D/C T/LINE FROM BASIMA TO NAL GRID STATION - (LINE#6)
4.1 132KV D/C T/LINE FROM PANJGOOR TO NAG GRID STATION - (LINE#4)
i. Foundation Work:
Tower Foundation
Sr. No. Tower No. Tower Type Completion Date
Type / Drawing No.
1.
2.
Tower Foundation
Sr. No. Tower No. Tower Type Completion Date
Type / Drawing No.
1.
2.
Sr. No. Tower No. Tower Type Tower Makeup Completion Date
1.
2.
Total to Date Erection work:
Sr. No. Tower No. Tower Type Tower Makeup Completion Date
1.
2.
4.2 132KV D/C T/LINE FROM NAG TO BASIMA GRID STATION - (LINE#5)
i. Foundation Work:
Tower Foundation
Sr. No. Tower No. Tower Type Completion Date
Type / Drawing No.
1.
2.
Tower Foundation
Sr. No. Tower No. Tower Type Completion Date
Type / Drawing No.
1.
2.
Sr. No. Tower No. Tower Type Tower Makeup Completion Date
1.
2.
Sr. No. Tower No. Tower Type Tower Makeup Completion Date
1.
2.
4.3 132KV D/C T/LINE FROM BASIMA TO NAL GRID STATION - (LINE#6)
i. Foundation Work:
Tower Foundation
Sr. No. Tower No. Tower Type Completion Date
Type / Drawing No.
1. 243 PDW/TC-198/20o ZM-1 22-05-2022
2. 242 PDW/TC-198/20o ZM-1+3 25-05-2022
3. 241 PDW/TC-198/20o ZM-1+3 25-05-2022
4. 237 PDW/TC-198/20o ZM-1 25-05-2022
5. 236 PDW/TC-198/20o ZM-1 25-05-2022
6. 240 PDW/TC-198/20o ZM-1 26-05-2022
7. 235 PDW/TC-198/20o ZM-1 27-05-2022
8. 234 PDW/TC-198/20o ZM-1+3 28-05-2022
9. 232 PDW/TC-198/20o ZM-1+3 28-05-2022
10. 230 PDW/TC-198/20o ZM-1 30-05-2022
11. 231 PDW/TC-198/20o ZM-1 30-05-2022
12. 226 PDW/TC-198/20o ZM-1+6 31-05-2022
13. 229 PDW/TC-198/20o ZM-1 31-05-2022
Total to Date Foundation work:
Tower Foundation
Sr. No. Tower No. Tower Type Completion Date
Type / Drawing No.
1. 243 PDW/TC-198/20o ZM-1 22-05-2022
2. 242 PDW/TC-198/20o ZM-1+3 25-05-2022
3. 241 PDW/TC-198/20o ZM-1+3 25-05-2022
4. 237 PDW/TC-198/20o ZM-1 25-05-2022
5. 236 PDW/TC-198/20o ZM-1 25-05-2022
6. 240 PDW/TC-198/20o ZM-1 26-05-2022
7. 235 PDW/TC-198/20o ZM-1 27-05-2022
8. 234 PDW/TC-198/20o ZM-1+3 28-05-2022
9. 232 PDW/TC-198/20o ZM-1+3 28-05-2022
10. 230 PDW/TC-198/20o ZM-1 30-05-2022
11. 231 PDW/TC-198/20o ZM-1 30-05-2022
12. 226 PDW/TC-198/20o ZM-1+6 31-05-2022
13. 229 PDW/TC-198/20o ZM-1 31-05-2022
Sr. No. Tower No. Tower Type Tower Makeup Completion Date
1.
2.
Sr. No. Tower No. Tower Type Tower Makeup Completion Date
1.
2.
iii. Stringing Work Of Conductor:
5.1 132KV D/C T/LINE FROM PANJGOOR TO NAG GRID STATION - (LINE#4)
i. Foundation Work
Yet to start
ii. Erection Work
Yet to start
iii. Stringing of Conductor
Yet to start
iv. Stringing of Earthwire
Yet to start
5.2 132KV D/C T/LINE FROM NAG TO BASIMA GRID STATION - (LINE#5)
i. Foundation Work
Depends on release of tower foundation types.
ii. Erection Work
Yet to start
iii. Stringing of Conductor
Yet to start
iv. Stringing of Earthwire
Yet to start
5.3 132KV D/C T/LINE FROM BASIMA TO NAL GRID STATION - (LINE#6)
i. Foundation Work
130 Nos.
ii. Erection Work
Yet to start
iii. Stringing of Conductor
Yet to start
iv. Stringing of Earthwire
Yet to start
6 COMPARISON OF THE PLANNED VS ACTUAL PROGRESS:
6.1 132KV D/C T/LINE FROM PANJGOOR TO NAG GRID STATION - (LINE#4)
i. Foundation Work:
Planned Vs Actual Works
Total Foundation Work 513 Nos.
Planned work for May 2022 Yet to start
Achieved work for May 2022 Yet to start
6.2 132KV D/C T/LINE FROM NAG TO BASIMA GRID STATION - (LINE#5)
i. Foundation Work:
Planned Vs Actual Works
Total Foundation Work 320 Nos.
Planned work for May 2022 Yet to start
Achieved work for May 2022 Yet to start
6.3 132KV D/C T/LINE FROM BASIMA TO NAL GRID STATION - (LINE#6)
i. Foundation Work:
Planned Vs Actual Works
Total Foundation Work 276 Nos.
Planned work for May 2022 Nil
Achieved work for May 2022 13 Nos.
SPA Pole
04
i. Basic Body Nos. 02 - 02
SPG Pole
05
i. Basic Body Nos. 07 - 07
SPD Pole
06
i. Basic Body Nos. 01 - 01
Yet to be allocated
8 CONTRACT & FINANCE
9.1 132KV D/C T/LINE FROM PANJGOOR TO NAG GRID STATION - (LINE#4)
Total Towers
= 474 Nos. Progress till previous Progress during the Total at the end of the
Total Poles Month month under-report month under-report
= 10 Nos. Percentage (%) Percentage (%) Percentage (%)
Line Length
= 134.5km ---- ---- ----
1.
---- ---- ----
a. Tower Staking Work ---- ---- ----
b. Foundation Work
c. Erection Work ---- ---- ----
d. Stringing of Conductor
---- ---- ----
e. Stringing of Earthwire
9.2 132KV D/C T/LINE FROM NAG TO BASIMA GRID STATION - (LINE#5)
Total Towers Progress till previous Progress during the Total at the end of the
= 303 Nos. Month month under-report month under-report
Line Length Percentage (%) Percentage (%) Percentage (%)
= 85km
44.22 13.86 58.08
1.
a. Tower Staking Work ---- ---- ----
b. Foundation Work
c. Erection Work ---- ---- ----
d. Stringing of Conductor ---- ---- ----
e. Stringing of Earthwire
---- ---- ----
9.3 132KV D/C T/LINE FROM BASIMA TO NAL GRID STATION - (LINE#6)
Total Towers Progress till previous Progress during the Total at the end of the
= 250 Nos. Month month under-report month under-report
Line Length Percentage (%) Percentage (%) Percentage (%)
= 67km
98.79 1.21 100
1.
a. Tower Staking Work 0 5.2 5.2
b. Foundation Work
c. Erection Work
---- ---- ----
d. Stringing of Conductor ---- ---- ----
e. Stringing of Earthwire
---- ---- ----
10 SITE PHOTOGRAPHS