CLIENT:

QUETTA ELECTRIC SUPPLY COMPANY (QESCO)

CONTRACTOR:
FRONTIER WORKS ORGANIZATION (FWO)

CONTRACT NO: IGM/NGS LOT# IV

PROCUREMENT OF PLANT-DESIGN, MANUFACTURE, SUPPLY AND


CONSTRUCTION OF FOUNDATIONS, ERECTION OF TOWERS, INSTALLATION
OF TRANSMISSION LINE CONDUCTOR, HARDWARE, ACCESSORIES,
INSULATORS, STOCK BRIDGE DAMPERS, STRINGING, TESTING AND
COMMISSIONING OF (COASTAL / NON-COASTAL AREAS) FOR
INTERCONNECTION OF ISOLATED GWADAR / MAKRAN AREA WITH
NATIONAL GRID SYSTEM OF PAKISTAN.
1) 132KV D/C TRANSMISSION LINE FROM PANJGOOR-NAG G/S (APPROX 134.5KM)
2) 132KV D/C TRANSMISSION LINE FROM NAG-BASIMA G/S (APPROX 85KM)
3) 132KV D/C TRANSMISSION LINE FROM BASIMA-NAL G/S (APPROX 67KM)
ON AASC “CAIRO’’ CONDUCTOR ON TURNKEY BASIS FOR
INTERCONNECTION OF ISOLATED GWADAR / MAKRAN AREA WITH
NATIONAL GRID SYSTEM OF PAKISTAN, ALONG WITH ALLIED EQUIPMENT

MONTHLY PROGRESS REPORT NO. 2


UPTO 31ST MAY, 2022

Frontier Works Organization. (Headquarter) 758 Construction Team Engineers.


509, Kashmir Road, R. A. Bazar, Basima Camp, Balochistan
Rawalpindi - Pakistan Pakistan
Ph: +92-51-9271301 - 6 Ph: +92-84-7310100
Email: info@fwo.com.pk Email: cte758@hotmail.com
Month Cut-Off Date
Reference No. 2
May, 2022 31st May, 2022

CLIENT:
QUETTA ELECTRIC SUPPLY COMPANY (QESCO)

CONTRACTOR:
FRONTIER WORKS ORGANIZATION (FWO)

CONTRACT: IGM/NGS LOT# IV:


PROCUREMENT OF PLANT-DESIGN, MANUFACTURE,
SUPPLY AND CONSTRUCTION OF FOUNDATIONS, ERECTION
OF TOWERS, INSTALLATION OF TRANSMISSION LINE
CONDUCTOR, HARDWARE, ACCESSORIES, INSULATORS,
STOCK BRIDGE DAMPERS, STRINGING, TESTING AND
COMMISSIONING OF (COASTAL/NON-COASTAL AREAS) FOR
INTERCONNECTION OF ISOLATED GWADAR/MAKRAN AREA
WITH NATIONAL GRID SYSTEM OF PAKISTAN.
(1) PANJGOOR-NAG T/LINE (APPROX 134.5KM),
(2) NAG-BASIMA T/LINE (APPROX 85KM),
(3) BASIMA-NAL T/LINE (APPROX 67KM)
ON AASC “CAIRO’’ CONDUCTOR ON TURNKEY BASIS FOR
INTERCONNECTION OF ISOLATED GWADAR /MAKRAN
AREA WITH NATIONAL GRID SYSTEM OF PAKISTAN, ALONG
WITH ALLIED EQUIPMENT

EMPLOYER: QUETTA ELECTRIC SUPPLY COMPANY LTD. (QESCO)


ENGINEER: M/S ENMASSE (PVT.) LTD.

CONTRACTOR: FRONTIER WORKS ORGANIZATION (FWO)

ISSUED BY: 758 CTE, FRONTIER WORKS ORGANIZATION (FWO)

DATED: 01 - 06 - 2022
Table of Contents
1 PROJECT BRIEF...................................................................................................................... 5
2 EXECUTIVE SUMMARY: ...................................................................................................... 6
2.1 Brief Description of Project: .................................................................................................. 6
2.2 Location of Sites: ................................................................................................................... 6
2.3 Scope of Work: ...................................................................................................................... 6
3 OVERALL PROGRESS OF WORKS....................................................................................... 7
3.1 132KV D/C T/LINE FROM PANJGOOR TO NAG GRID STATION - (LINE#4) ................ 7
3.2 132KV D/C T/LINE FROM NAG TO BASIMA GRID STATION - (LINE#5) ..................... 7
3.3 132KV D/C T/LINE FROM BASIMA TO NAL GRID STATION - (LINE#6) ..................... 7
4 LINE WISE PROGRESS .......................................................................................................... 8
4.1 132KV D/C T/LINE FROM PANJGOOR TO NAG GRID STATION - (LINE#4) ................ 8
4.2 132KV D/C T/LINE FROM NAG TO BASIMA GRID STATION - (LINE#5) ................... 10
4.3 132KV D/C T/LINE FROM BASIMA TO NAL GRID STATION - (LINE#6) ................... 12
5 PLAN FOR NEXT 30 DAYS: ................................................................................................. 15
5.1 132KV D/C T/LINE FROM PANJGOOR TO NAG GRID STATION - (LINE#4) .............. 15
i. Foundation Work ................................................................................................................. 15
ii. Erection Work ..................................................................................................................... 15
iii. Stringing of Conductor ........................................................................................................ 15
iv. Stringing of Earthwire ......................................................................................................... 15
5.2 132KV D/C T/LINE FROM NAG TO BASIMA GRID STATION - (LINE#5) ................... 15
i. Foundation Work ................................................................................................................. 15
ii. Erection Work ..................................................................................................................... 15
iii. Stringing of Conductor ........................................................................................................ 15
iv. Stringing of Earthwire ......................................................................................................... 15
5.3 132KV D/C T/LINE FROM BASIMA TO NAL GRID STATION - (LINE#6) ................... 15
i. Foundation Work ................................................................................................................. 15
ii. Erection Work ..................................................................................................................... 15
iii. Stringing of Conductor ........................................................................................................ 15
iv. Stringing of Earthwire ......................................................................................................... 15
6 COMPARISON OF THE PLANNED VS ACTUAL PROGRESS: ......................................... 16
6.1 132KV D/C T/LINE FROM PANJGOOR TO NAG GRID STATION - (LINE#4) .............. 16
i. Foundation Work: ................................................................................................................ 16
ii. Erection Work: .................................................................................................................... 16
iii. Stringing of Conductor: ....................................................................................................... 16
iv. Stringing of Earthwire: ........................................................................................................ 16
6.2 132KV D/C T/LINE FROM NAG TO BASIMA GRID STATION - (LINE#5) ................... 16
i. Foundation Work: ................................................................................................................ 16
ii. Erection Work: .................................................................................................................... 16
iii. Stringing of Conductor: ....................................................................................................... 16
iv. Stringing of Earthwire: ........................................................................................................ 17
6.3 132KV D/C T/LINE FROM BASIMA TO NAL GRID STATION - (LINE#6) ................... 17
i. Foundation Work: ................................................................................................................ 17
ii. Erection Work: .................................................................................................................... 17
iii. Stringing of Conductor: ....................................................................................................... 17
iv. Stringing of Earthwire: ........................................................................................................ 17
7 MATERIAL STATUS ............................................................................................................ 18
7.1 132KV D/C T/LINE FROM PANJGOOR TO NAL G/S - (LINE#4,5,6) ............................. 18
i. Stubs and Cleats: ................................................................................................................. 18
ii. Tower Material: ................................................................................................................... 18
iii. Stringing Material: ............................................................................................................... 18
8 CONTRACT & FINANCE ..................................................................................................... 19
9 PROGRESSIVE PROGRESS REPORT .................................................................................. 19
9.1 132KV D/C T/LINE FROM PANJGOOR TO NAG GRID STATION - (LINE#4) .............. 19
9.2 132KV D/C T/LINE FROM NAG TO BASIMA GRID STATION - (LINE#5) ................... 19
9.3 132KV D/C T/LINE FROM BASIMA TO NAL GRID STATION - (LINE#6) ................... 19
10 SITE PHOTOGRAPHS........................................................................................................... 20
10.1 EXCAVATION ACTIVITY ................................................................................................ 20
10.2 CONCRETE ACTIVITY..................................................................................................... 21
1 PROJECT BRIEF

1.1. Contract No. : IGM/NGS LOT# IV


1.2. Project Title : PROCUREMENT OF PLANT-DESIGN,
MANUFACTURE, SUPPLY AND CONSTRUCTION
OF FOUNDATIONS, ERECTION OF TOWERS,
INSTALLATION OF TRANSMISSION LINE
CONDUCTOR, HARDWARE, ACCESSORIES,
INSULATORS, STOCK BRIDGE DAMPERS,
STRINGING, TESTING AND COMMISSIONING OF
(COASTAL/NON-COASTAL AREAS) FOR
INTERCONNECTION OF ISOLATED
GWADAR/MAKRAN AREA WITH NATIONAL
GRID SYSTEM OF PAKISTAN.
(4) PANJGOOR-NAG T/LINE (APPROX 134.5KM),
(5) NAG-BASIMA T/LINE (APPROX 85KM),
(6) BASIMA-NAL T/LINE (APPROX 67KM)
ON AASC “CAIRO’’ CONDUCTOR ON TURNKEY
BASIS FOR INTERCONNECTION OF ISOLATED
GWADAR /MAKRAN AREA WITH NATIONAL
GRID SYSTEM OF PAKISTAN, ALONG WITH
ALLIED EQUIPMENT

Vide PD QESCO letter no. 01-06/PD/GSC/QESCO/QTA


1.3. Notification of Award :
dated 03-01-2022

1.4. Date of signing of Contract


Agreement between Frontier
Works Organization and : Signed on 22-02-2022
Usman and Company (Pvt.)
Ltd.

1.5. Commencement date : 22-02-2022

1.6. Contractual Completion Date : 22-06-2023

1.7. Completion Period : 480 Days

1.8. Design and Engineering : By M/S Frontier Works Organization (FWO)

i. EPC Based Project


ii. Transmission Line material i.e. stubs, grounding sets,
1.9. Material Procurement :
towers, conductor, OPGW, insulators and line hardware
to be supplied by Frontier Works Organization (FWO)
2 EXECUTIVE SUMMARY:
The work was awarded to M/S Frontier Works Organization (FWO) by Quetta Electric Supply
Company (QESCO) vide letter no. 01-06/PD/GSC/QESCO/QTA dated 03-01-2022. The project
progress details have been given in the next sections with issues required to be addressed for the
timely completion of work.
The construction activities are being performed in accordance with the contract requirements and
provisions for satisfactory completion, testing and commissioning of the plant.

2.1 Brief Description of Project:

CONSTRUCTION OF FOUNDATIONS, ERECTION OF TOWERS, INSTALLATION OF


TRANSMISSION LINE CONDUCTOR, HARDWARE, ACCESSORIES, INSULATORS,
STOCK BRIDGE DAMPERS, STRINGING, TESTING AND COMMISSIONING OF
(COASTAL / NON-COASTAL AREAS) FOR INTERCONNECTION OF ISOLATED
GWADAR / MAKRAN AREA WITH NATIONAL GRID SYSTEM OF PAKISTAN.

1) 132KV DC T/LINE FROM PANJGOOR-NAG G/S (APPROX 134.5KM)


2) 132KV DC TRANSMISSION LINE FROM NAG-BASIMA G/S (APPROX 85KM)
3) 132KV DC TRANSMISSION LINE FROM BASIMA-NAL G/S (APPROX 67KM)

ON AASC “CAIRO’’ CONDUCTOR ON TURNKEY BASIS FOR INTERCONNECTION OF


ISOLATED GWADAR / MAKRAN AREA WITH NATIONAL GRID SYSTEM OF
PAKISTAN, ALONG WITH ALLIED EQUIPMENT

2.2 Location of Sites:


Panjgoor, Nag, Basima, Nal in Balochistan, Pakistan.

2.3 Scope of Work:


The scope of the work to be executed under this Contract comprises of following:

1- Construction of foundations, Erection of Towers, Installation of Transmission Line


conductor, Hardware, accessories, Insulators, Stock bridge dampers, Stringing, Testing and
Commissioning of 132kV D/C Panjgoor to Nag Transmission Line (Approx. 134.5km) on
AASC Cairo conductor.

2- Construction of foundations, Erection of Towers, Installation of Transmission Line


conductor, Hardware, accessories, Insulators, Stock bridge dampers, Stringing, Testing and
Commissioning of 132kV D/C Nag to Basima Transmission Line (Approx. 85km) on AASC
Cairo conductor.

3- Construction of foundations, Erection of Towers, Installation of Transmission Line


conductor, Hardware, accessories, Insulators, Stock bridge dampers, Stringing, Testing and
Commissioning of 132kV D/C Basima to Nal Transmission Line (Approx. 67km) on AASC
Cairo conductor.

All materials, tools, equipment and services, necessary for the reliable and safe operation of the
transmission line.
3 OVERALL PROGRESS OF WORKS
3.1 132KV D/C T/LINE FROM PANJGOOR TO NAG GRID STATION - (LINE#4)

Actual Completion Percentage


Sr. No. Activities Name
Work Status Completion
1 Tower/Poles Stacking (Nos.) 513 - -
2 Tower/Poles Released (Nos.) 513 - -
3 Excavation (Nos.) 513 - -
4 Concrete (Nos.) 513 - -
5 Backfilling (Nos.) 513 - -
7 Tower Erection/Poles (Nos.) 513 - -
8 Stringing of Conductor (Km) 134.50 - -
9 Stringing OPGW (Km) 134.50 - -

3.2 132KV D/C T/LINE FROM NAG TO BASIMA GRID STATION - (LINE#5)

Actual Completion Percentage


Sr. No. Activities Name
Work Status Completion
1 Tower/Poles Stacking (Nos.) 320 176 58.08%
2 Tower/Poles Released (Nos.) 320 - -
3 Excavation (Nos.) 320 - -
4 Concrete (Nos.) 320 - -
5 Backfilling (Nos.) 320 - -
7 Tower/Poles Erection (Nos.) 320 - -
8 Stringing of Conductor (Km) 85 - -
9 Stringing OPGW (Km) 85 - -

3.3 132KV D/C T/LINE FROM BASIMA TO NAL GRID STATION - (LINE#6)

Actual Completion Percentage


Sr. No. Activities Name
Work Status Completion
1 Tower/Poles Stacking (Nos.) 270 250 100%
2 Tower/Poles Released (Nos.) 270 155 62%
3 Excavation (Nos.) 270 90 36%
4 Concrete (Nos.) 270 13 5.2%
5 Backfilling (Nos.) 270 - -
7 Tower/Poles Erection (Nos.) 270 - -
8 Stringing of Conductor (Km) 67 - -
9 Stringing OPGW (Km) 67 - -
Note:
1. ROW issue from Tower 31 – 39 Basima to Nal Section (T/Line # 6)
2. Excavation work stopped near Nal Grid Station due to cultiviated zone (ROW) and non-
availability of release from T#49-142.
3. Inspection of 400 Towers being carried out at M/S Spleen Manufacture (Pvt) Ltd
4 LINE WISE PROGRESS

4.1 132KV D/C T/LINE FROM PANJGOOR TO NAG GRID STATION - (LINE#4)

Total No of Towers/Poles = 513 Nos.


Length of Line = 134.50 KM

i. Foundation Work:

Foundation Work Progress


Foundation Work Completed by the End of Previous Month Yet to start
Foundation Work Completed in this Month Yet to start
Foundation Work Completed by the End of this Month Yet to start

Work Done during this month:

Foundation work for this month.

Tower Foundation
Sr. No. Tower No. Tower Type Completion Date
Type / Drawing No.
1.
2.

Total to Date Foundation work:

Tower Foundation
Sr. No. Tower No. Tower Type Completion Date
Type / Drawing No.
1.
2.

ii. Erection Work:

Erection Work Progress


Erection Work Completed by the End of Previous Month Yet to start
Erection Work Completed in this Month Yet to start
Erection Work Completed by the End of this Month Yet to start

Work Done during this month:

Erection work for this month.

Sr. No. Tower No. Tower Type Tower Makeup Completion Date

1.
2.
Total to Date Erection work:

Sr. No. Tower No. Tower Type Tower Makeup Completion Date

1.
2.

iii. Stringing Work Of Conductor:

Conductor Stringing Work Progress


Conductor Stringing Work Completed by the End of Previous Month Yet to start
Conductor Stringing Work Completed in this Month Yet to start
Conductor Stringing Work Completed by the End of this Month Yet to start

Work Done during this month:

Conductor stringing work for this month.

Setup No. Tower Stretch No. Kilometers (Km) Completion Date


1.
2.

Total to Date Conductor Stringing work:

Setup No. Tower Stretch No. Kilometers (Km) Completion Date


1.
2.

iv. Stringing Work Of Earthwire:

Earthwire Stringing Work Progress


Earthwire Stringing Work Completed by the End of Previous Month Yet to start
Earthwire Stringing Work Completed in this Month Yet to start
Earthwire Stringing Work Completed by the End of this Month Yet to start

Work Done during this month:

Earthwire stringing work for this month.

Setup No. Tower Stretch No. Kilometers (Km) Completion Date


1.
2.
Total to Date Earthwire Stringing work:

Setup No. Tower Stretch No. Kilometers (Km) Completion Date


1.
2.

4.2 132KV D/C T/LINE FROM NAG TO BASIMA GRID STATION - (LINE#5)

Total No of Towers/Poles = 320 Nos.


Length of Line = 85 KM

i. Foundation Work:

Foundation Work Progress


Foundation Work Completed by the End of Previous Month Yet to start
Foundation Work Completed in this Month Yet to start
Foundation Work Completed by the End of this Month Yet to start

Work Done during this month:

Foundation work for this month.

Tower Foundation
Sr. No. Tower No. Tower Type Completion Date
Type / Drawing No.
1.
2.

Total to Date Foundation work:

Tower Foundation
Sr. No. Tower No. Tower Type Completion Date
Type / Drawing No.
1.
2.

ii. Erection Work:

Erection Work Progress


Erection Work Completed by the End of Previous Month Yet to start
Erection Work Completed in this Month Yet to start
Erection Work Completed by the End of this Month Yet to start
Work Done during this month:

Erection work for this month.

Sr. No. Tower No. Tower Type Tower Makeup Completion Date

1.
2.

Total to Date Erection work:

Sr. No. Tower No. Tower Type Tower Makeup Completion Date

1.
2.

iii. Stringing Work Of Conductor:

Conductor Stringing Work Progress


Conductor Stringing Work Completed by the End of Previous Month Yet to start
Conductor Stringing Work Completed in this Month Yet to start
Conductor Stringing Work Completed by the End of this Month Yet to start

Work Done during this month:

Conductor stringing work for this month.

Setup No. Tower Stretch No. Kilometers (Km) Completion Date


1.
2.

Total to Date Conductor Stringing work:

Setup No. Tower Stretch No. Kilometers (Km) Completion Date


1.
2.

iv. Stringing Work Of Earthwire:

Earthwire Stringing Work Progress


Earthwire Stringing Work Completed by the End of Previous Month Yet to start
Earthwire Stringing Work Completed in this Month Yet to start
Earthwire Stringing Work Completed by the End of this Month Yet to start
Work Done during this month:

Earthwire stringing work for this month.

Setup No. Tower Stretch No. Kilometers (Km) Completion Date


1.
2.

Total to Date Earthwire Stringing work:

Setup No. Tower Stretch No. Kilometers (Km) Completion Date


1.
2.

4.3 132KV D/C T/LINE FROM BASIMA TO NAL GRID STATION - (LINE#6)

Total No of Towers/Poles = 276 Nos.


Length of Line = 67 KM

i. Foundation Work:

Foundation Work Progress


Foundation Work Completed by the End of Previous Month Nil
Foundation Work Completed in this Month 13 Nos.
Foundation Work Completed by the End of this Month 13 Nos.

Work Done during this month:

Foundation work for this month.

Tower Foundation
Sr. No. Tower No. Tower Type Completion Date
Type / Drawing No.
1. 243 PDW/TC-198/20o ZM-1 22-05-2022
2. 242 PDW/TC-198/20o ZM-1+3 25-05-2022
3. 241 PDW/TC-198/20o ZM-1+3 25-05-2022
4. 237 PDW/TC-198/20o ZM-1 25-05-2022
5. 236 PDW/TC-198/20o ZM-1 25-05-2022
6. 240 PDW/TC-198/20o ZM-1 26-05-2022
7. 235 PDW/TC-198/20o ZM-1 27-05-2022
8. 234 PDW/TC-198/20o ZM-1+3 28-05-2022
9. 232 PDW/TC-198/20o ZM-1+3 28-05-2022
10. 230 PDW/TC-198/20o ZM-1 30-05-2022
11. 231 PDW/TC-198/20o ZM-1 30-05-2022
12. 226 PDW/TC-198/20o ZM-1+6 31-05-2022
13. 229 PDW/TC-198/20o ZM-1 31-05-2022
Total to Date Foundation work:

Tower Foundation
Sr. No. Tower No. Tower Type Completion Date
Type / Drawing No.
1. 243 PDW/TC-198/20o ZM-1 22-05-2022
2. 242 PDW/TC-198/20o ZM-1+3 25-05-2022
3. 241 PDW/TC-198/20o ZM-1+3 25-05-2022
4. 237 PDW/TC-198/20o ZM-1 25-05-2022
5. 236 PDW/TC-198/20o ZM-1 25-05-2022
6. 240 PDW/TC-198/20o ZM-1 26-05-2022
7. 235 PDW/TC-198/20o ZM-1 27-05-2022
8. 234 PDW/TC-198/20o ZM-1+3 28-05-2022
9. 232 PDW/TC-198/20o ZM-1+3 28-05-2022
10. 230 PDW/TC-198/20o ZM-1 30-05-2022
11. 231 PDW/TC-198/20o ZM-1 30-05-2022
12. 226 PDW/TC-198/20o ZM-1+6 31-05-2022
13. 229 PDW/TC-198/20o ZM-1 31-05-2022

ii. Erection Work:

Erection Work Progress


Erection Work Completed by the End of Previous Month Yet to start
Erection Work Completed in this Month Yet to start
Erection Work Completed by the End of this Month Yet to start

Work Done during this month:

Erection work for this month.

Sr. No. Tower No. Tower Type Tower Makeup Completion Date

1.
2.

Total to Date Erection work:

Sr. No. Tower No. Tower Type Tower Makeup Completion Date

1.
2.
iii. Stringing Work Of Conductor:

Conductor Stringing Work Progress


Conductor Stringing Work Completed by the End of Previous Month Yet to start
Conductor Stringing Work Completed in this Month Yet to start
Conductor Stringing Work Completed by the End of this Month Yet to start

Work Done during this month:

Conductor stringing work for this month.

Setup No. Tower Stretch No. Kilometers (Km) Completion Date


1.
2.

Total to Date Conductor Stringing work:

Setup No. Tower Stretch No. Kilometers (Km) Completion Date


1.
2.

iv. Stringing Work Of Earthwire:

Earthwire Stringing Work Progress


Earthwire Stringing Work Completed by the End of Previous Month Yet to start
Earthwire Stringing Work Completed in this Month Yet to start
Earthwire Stringing Work Completed by the End of this Month Yet to start

Work Done during this month:

Earthwire stringing work for this month.

Setup No. Tower Stretch No. Kilometers (Km) Completion Date


1.
2.

Total to Date Earthwire Stringing work:

Setup No. Tower Stretch No. Kilometers (Km) Completion Date


1.
2.
5 PLAN FOR NEXT 30 DAYS:

5.1 132KV D/C T/LINE FROM PANJGOOR TO NAG GRID STATION - (LINE#4)

i. Foundation Work
 Yet to start
ii. Erection Work
 Yet to start
iii. Stringing of Conductor
 Yet to start
iv. Stringing of Earthwire
 Yet to start

5.2 132KV D/C T/LINE FROM NAG TO BASIMA GRID STATION - (LINE#5)

i. Foundation Work
 Depends on release of tower foundation types.
ii. Erection Work
 Yet to start
iii. Stringing of Conductor
 Yet to start
iv. Stringing of Earthwire
 Yet to start

5.3 132KV D/C T/LINE FROM BASIMA TO NAL GRID STATION - (LINE#6)

i. Foundation Work
 130 Nos.
ii. Erection Work
 Yet to start
iii. Stringing of Conductor
 Yet to start
iv. Stringing of Earthwire
 Yet to start
6 COMPARISON OF THE PLANNED VS ACTUAL PROGRESS:

6.1 132KV D/C T/LINE FROM PANJGOOR TO NAG GRID STATION - (LINE#4)

i. Foundation Work:
Planned Vs Actual Works
Total Foundation Work 513 Nos.
Planned work for May 2022 Yet to start
Achieved work for May 2022 Yet to start

ii. Erection Work:


Planned Vs Actual Works
Total Erection Work 513 Nos.
Planned work for May 2022 Yet to start
Achieved work for May 2022 Yet to start

iii. Stringing of Conductor:


Planned Vs Actual Works
Total Length 134.50 Km
Planned work for May 2022 Yet to start
Achieved work for May 2022 Yet to start

iv. Stringing of Earthwire:


Planned Vs Actual Works
Total Length 134.50 Km
Planned work for May 2022 Yet to start
Achieved work for May 2022 Yet to start

6.2 132KV D/C T/LINE FROM NAG TO BASIMA GRID STATION - (LINE#5)

i. Foundation Work:
Planned Vs Actual Works
Total Foundation Work 320 Nos.
Planned work for May 2022 Yet to start
Achieved work for May 2022 Yet to start

ii. Erection Work:


Planned Vs Actual Works
Total Erection Work 320 Nos.
Planned work for May 2022 Yet to start
Achieved work for May 2022 Yet to start

iii. Stringing of Conductor:


Planned Vs Actual Works
Total Length 85 Km
Planned work for May 2022 Yet to start
Achieved work for May 2022 Yet to start
iv. Stringing of Earthwire:
Planned Vs Actual Works
Total Length 85 Km
Planned work for May 2022 Yet to start
Achieved work for May 2022 Yet to start

6.3 132KV D/C T/LINE FROM BASIMA TO NAL GRID STATION - (LINE#6)

i. Foundation Work:
Planned Vs Actual Works
Total Foundation Work 276 Nos.
Planned work for May 2022 Nil
Achieved work for May 2022 13 Nos.

ii. Erection Work:


Planned Vs Actual Works
Total Erection Work 276 Nos.
Planned work for May 2022 Yet to start
Achieved work for May 2022 Yet to start

iii. Stringing of Conductor:


Planned Vs Actual Works
Total Length 67 Km
Planned work for May 2022 Yet to start
Achieved work for May 2022 Yet to start

iv. Stringing of Earthwire:


Planned Vs Actual Works
Total Length 67 Km
Planned work for May 2022 Yet to start
Achieved work for May 2022 Yet to start
7 MATERIAL STATUS

7.1 132KV D/C T/LINE FROM PANJGOOR TO NAL G/S - (LINE#4,5,6)

i. Stubs and Cleats:

Total Qty. Total Qty. Balance to be


Sr. No. Description Unit
Required Allocated Allocated

1 ZM-1 Stubs and Cleats Nos. 3420 400 3020

2 ZM-30 Stubs and Cleats Nos. 472 - 472

3 ZM-60 Stubs and Cleats Nos. 216 - 216

4 Grounding Material Nos. 2289 300 737

ii. Tower Material:

Sr. Total Qty. Total Qty. Balance to be


Description Unit
No. Required Allocated Allocated

Tower Type ZM-1

i. Basic Body Nos. 855 - 855


01
ii. Leg Extension (3.0m) Nos. 1284 - 1284

iii. Leg Extension (6.0m) Nos. 92 - 92

Tower Type ZM-30


02 i. Basic Body Nos. 118 - 118
ii. Leg Extension (3.0m) Nos. 160 - 160

Tower Type ZM-60


03 i. Basic Body Nos. 54 - 54
ii. Leg Extension (3.0m) Nos. 56 - 56

SPA Pole
04
i. Basic Body Nos. 02 - 02
SPG Pole
05
i. Basic Body Nos. 07 - 07

SPD Pole
06
i. Basic Body Nos. 01 - 01

iii. Stringing Material:

 Yet to be allocated
8 CONTRACT & FINANCE

 Mobilization advance payment amounting Rs 880.21 Mn paid by QESCO to M/S FWO.

9 PROGRESSIVE PROGRESS REPORT

9.1 132KV D/C T/LINE FROM PANJGOOR TO NAG GRID STATION - (LINE#4)

Total Towers
= 474 Nos. Progress till previous Progress during the Total at the end of the
Total Poles Month month under-report month under-report
= 10 Nos. Percentage (%) Percentage (%) Percentage (%)
Line Length
= 134.5km ---- ---- ----
1.
---- ---- ----
a. Tower Staking Work ---- ---- ----
b. Foundation Work
c. Erection Work ---- ---- ----
d. Stringing of Conductor
---- ---- ----
e. Stringing of Earthwire

9.2 132KV D/C T/LINE FROM NAG TO BASIMA GRID STATION - (LINE#5)

Total Towers Progress till previous Progress during the Total at the end of the
= 303 Nos. Month month under-report month under-report
Line Length Percentage (%) Percentage (%) Percentage (%)
= 85km
44.22 13.86 58.08
1.
a. Tower Staking Work ---- ---- ----
b. Foundation Work
c. Erection Work ---- ---- ----
d. Stringing of Conductor ---- ---- ----
e. Stringing of Earthwire
---- ---- ----

9.3 132KV D/C T/LINE FROM BASIMA TO NAL GRID STATION - (LINE#6)

Total Towers Progress till previous Progress during the Total at the end of the
= 250 Nos. Month month under-report month under-report
Line Length Percentage (%) Percentage (%) Percentage (%)
= 67km
98.79 1.21 100
1.
a. Tower Staking Work 0 5.2 5.2
b. Foundation Work
c. Erection Work
---- ---- ----
d. Stringing of Conductor ---- ---- ----
e. Stringing of Earthwire
---- ---- ----
10 SITE PHOTOGRAPHS

10.1 EXCAVATION ACTIVITY


10.2 CONCRETE ACTIVITY