List of Deleted Works

South Eastern Railway

(Confirmed only) (Deletion Date BETWEEN 01/01/2022 AND 16/06/2022)


(Cost In Thousands of Rs.)
Sr. Plan Division Balance to Reas
Rly Project ID. Name of Work Cost
No. Head Complete on*
1 SER 17 12.03.17.18 Kharagpur Divn : Implementation of Integrated KGP 1920 520 A
.4.52.002 Running Room Occupancy Management System
with dedicated railnet connection to server of each
R/room.
2 SER 17 12.04.17.18 Replacement of Phase-IV UTS equipment-50 nos. RNC 1366 66 A
.4.53.001 Thin Client for UTS locations in Ranchi Division

3 SER 17 12.04.17.21 Procurement of 90 nos. of UTS Ticket Printers. RNC 1393 0 A


.4.53.001
4 SER 17 12.00.17.19 Replacement of Hardware and Networking 1161 119 A
.3.16.001 equipment of computerization of refund Coaching
system at PCCM office.
5 SER 33 12.01.33.17 ADA Division:- Dual detection SSDAC(Single ADA 24886 443 A
.3.50.001 Section Digital Axle Counter) in ADA-MDN
section.
6 SER 33 12.01.33.17 Adra - Chandil:- Dual detection SSDAC(Single ADA 27704 0 A
.6.50.001 Section Digital Axle counter) in ADA-CNI section.

7 SER 33 12.02.33.17 CKP Division:- Dual LVCD/Axle counter in IBs on CKP 27964 20743 A
.6.51.001 OFC through dedicated E1 in RKSN-GX section.

8 SER 33 12.02.33.18 Provision of Maintenance Free Earthing for CKP 2395 31 A


.4.51.001 stations in CKP division
9 SER 33 12.02.33.18 Mini IPS & RTU at NOMD-BJMD IBH. CKP 2290 267 A
.4.51.002
10 SER 33 12.02.33.18 Bondamunda~~Bondamunda~~Provision of CKP 9694 1105 A
.4.51.003 Railnet through OFC at all important offices and
officer's residences at Bondamunda of
Chakradharpur Division.
11 SER 33 12.03.33.17 Provision of dual detection of LVCD in KGP - KGP 30811 2514 A
.3.52.007 TATA -NMP-HIJ & KGP-MDN section in KGP
Division .
12 SER 33 12.03.33.17 Provision of Dual detection of LVCD in KGP-BTS KGP 29779 1333 A
.3.52.008 section of KGP Division.
13 SER 33 12.03.33.17 Provision of dual detection in KGP -BHC & ROP- KGP 31281 2287 A
.3.52.009 VZR sections in KGP Division .
14 SER 33 12.03.33.17 Provision of dual detection of LVCD in BTS-BHC KGP 29274 628 A
.3.52.010 section of KGP Division (6 IBS)
15 SER 33 12.03.33.17 Provision of Dual detection of LVCD in KGP-TATA KGP 29672 3705 A
.3.52.012 section of KGP Division ( 7 IBS)
16 SER 53 12.01.53.09 GBA-Replacement of existing FOB with wider one ADA 13980 580 A
.4.50.029 connecting platform and circulating area ( Both
ends)
17 SER 53 12.01.53.09 Sudamdih- Provision of new FOB Estt no- ADA 9034 2291 A
.4.50.060 357/ADA/10
18 SER 53 12.01.53.09 Replacement of existing FOB with wider one, ADA 13985 4239 A
.4.50.065 connecting to all platforms at Bhaga Station
19 SER 53 12.01.53.15 Garhjaipur~~Proposal for provision of RDSO type ADA 2392 10 A
.4.50.028 shelter with Light, Fan & Water facility.
20 SER 53 12.01.53.17 Garhjaipur~~Construction of Waiting Hall and ADA 1246 345 A
.4.50.006 renovation of Existing Booking Office
21 SER 53 12.01.53.17 Midnapur~~Chandil~~20 numbers of ‘BUS ADA 6018 1033 A
.4.50.008 STAND’ type PF shed at 14 stations of Adra
division.
22 SER 53 12.01.53.17 Kotshila jn~~Provision of Boundary wall on PF No ADA 1613 1395 A
.4.50.010 -1 at kotshila station.

Page : 1 of 3 As on : 16/06/2022 1:49:46 PM


Sr. Plan Division Balance to Reas
Rly Project ID. Name of Work Cost
No. Head Complete on*
23 SER 53 12.01.53.17 Bankura jn.~~Construction of New Booking Office ADA 1885 2 A
.4.50.023 at Bankura South side.
24 SER 53 12.02.53.14 Rairangpur :- Development of station as Adarsh CKP 15229 4669 A
.3.51.002 Station.
25 SER 53 12.02.53.15 Extension of DN platform at GOL station. CKP 3773 2505 A
.4.51.005
26 SER 53 12.02.53.15 Extention of PF No. 1 at Gua Station. CKP 7031 1993 A
.4.51.008
27 SER 53 12.02.53.15 Replacement of existing luminaires by LED based CKP 3693 1832 A
.4.51.022 luminaires at TATA & ROU
28 SER 53 12.02.53.16 Tatanagar~~Rourkela~~Rourkela~~Austhetic look CKP 2860 1860 A
.4.51.003 of TATANAGAR & ROURKELA station
29 SER 53 12.02.53.16 Tatanagar~~Tatanagar~~ Provision of 6men CKP 1869 1869 A
.4.51.008 capacity Elevator at PF No. 3 at TATA
30 SER 53 12.02.53.17 Jharsuguda - Improvement of PF surface of PF CKP 24015 872 A
.3.51.003 no.2/3 and 4/5.
31 SER 53 12.02.53.17 Rourkela~~Provision of 13men capacity Elevator CKP 2284 192 A
.4.51.003 in 2nd Entry at ROURKELLA
32 SER 53 12.03.53.11 Hijli - Development of modern station building with KGP 139486 0 A
.1.30.001 passenger amenities, circulating area etc.

33 SER 53 12.03.53.14 Kokpara : Provision of Deep Tube of size 150mm KGP 1611 1024 A
.4.52.011 X 75mm including construction of Pump House
under the jurisdiction of ADEN/JGM.

34 SER 53 12.03.53.15 Provision for P.F Shelter,Water Tap, Urinal, KGP 24304 0 A
.3.52.007 Lavatory .of MEA Under ADEN/West/KGP
35 SER 53 12.03.53.15 Haldipada : High level platform No.1, 2/3 & 4. KGP 24292 1825 A
.3.52.011
36 SER 53 12.03.53.16 Howrah - Kharagpur : Repl of washable aprons KGP 66048 24339 B
.1.52.001 with ballastless track (4 platforms)
37 SER 53 12.03.53.16 Kharagpur - Bhadrak Setion : Electrical work for KGP 2510 427 A
.4.52.011 passenger amenities work.
38 SER 53 12.03.53.16 Girimaidan : Resurfacing of Platform No. 1. KGP 2502 2502 A
.4.52.012
39 SER 53 12.03.53.16 Kharagpur - Tatanagar Section : Electrical work KGP 2580 280 A
.4.52.014 for passenger amenities work.
40 SER 53 12.03.53.17 Balasore : Construction of AC paid lounge. KGP 675 675 A
.4.52.014
41 SER 53 12.03.53.18 Rupsa, Basta, Amarda Road & Markona : KGP 5560 2549 A
.4.52.014 Provision of Train Indication Board (TIB).
42 SER 53 12.03.53.18 Santragachi : Engineering work for Provision of KGP 11320 70 A
.7.52.007 Escalators (2 Nos) & development of surrounding
area.
43 SER 53 12.03.53.19 Soro:- Improvement of PF surface, circulating KGP 28789 3634 A
.3.52.001 area & improvement of approach road.
44 SER 53 12.04.53.18 RNC: Redevelopment of Ranchi Railway station. RNC 141854 33472 A
.3.53.001
45 SER 53 12.04.53.18 RNC ; Raising and Resurfacing of platform No. 1 RNC 48131 14678 A
.3.53.002 ,1A & Saloon Siding to high level at Ranchi
station.
46 SER 53 12.04.53.18 Ranchi jn.:- Extension of 6mtr. Wide FOB from PF RNC 28939 9838 A
.3.53.005 No.2 & 3 to circulating area on north side at
Ranchi station.
47 SER 53 12.04.53.18 Muri jn~~Augmentation of local Power supply at RNC 2417 1358 A
.4.53.001 MURI
48 SER 53 12.04.53.18 Improvement to station approach road, circulating RNC 21903 17439 A
.4.53.003 area with boundary wall and drain at SSIA and
LTMD station.
49 SER 53 12.04.53.18 Muri jn~~Setting up of Quick watering RNC 24427 4663 A
.7.53.001 arrangement at Muri Station-SER..

Page : 2 of 3 As on : 16/06/2022 1:49:46 PM


Sr. Plan Division Balance to Reas
Rly Project ID. Name of Work Cost
No. Head Complete on*
50 SER 53 12.04.53.18 Ranchi jn.~~Ranchi Station~~Setting up of Quick RNC 23083 4774 A
.7.53.002 watering arrangement at Ranchi Station-SER..

51 SER 53 12.04.53.19 Ranchi Division-Provision of GPS Clock(Digital) at RNC 4387 1555 A


.4.53.003 46 stations and provision of Television with Setup
Box and Ranchi & Hatia Station.

52 SER 64 12.01.64.16 Purulia Jn.~~Construction of community Hall at ADA 3000 1945 A


.4.50.002 Purulia.
53 SER 64 12.00.64.17 Garden Reach -Renovation and improvement to GRC 10322 65 A
.6.12.001 at 2nd floor & 3rd floor of Engg section of GM
building/ Head office at North colony
54 SER 64 12.06.64.16 GRC:Renovation of different offices of S & T GRC 7046 2695 A
.3.12.003 Department Elect. department and finance store
section at NAB building, Garden Reach..

55 SER 64 12.03.64.17 Nimpura : Modification of Nimpura running room KGP 1973 100 A
.4.52.001 into cubical type by accommodates 2(two) Nos of
beds norms & renovation of toilet & bath rooms

56 SER 64 12.04.64.16 Hatia~~Provision of sports hostel at newly RNC 9726 7673 B


.6.53.001 constructed Astro Turf Hockey Stadium at Hatia.

57 SER 64 12.04.64.20 Hatia~~Provision of 30 Nos. of video surveillance RNC 1594 0 A


.4.53.001 system
TOTAL 1,00,09,76 19,70,28

*Note -
A - Work financially closed or completed
B - Work short closed/reduced in scope, retaining productivity
C - Work closed as progress is NIL/negligible
D - Do not Delete
E - Work is duplicate
F - Other Reasons
G - Work(I1) not included in Latest Pink Book

Page : 3 of 3 As on : 16/06/2022 1:49:46 PM