Tutorial 8 (Scheduling)

1. Find:
a. The network
b. All expected activity times, variances and slacks
c. Critical Path and expected completion time
d. Probability that the project will be done in 23 days
Activity Predecessor a m b
a - 1 4 7
b - 2 2 2
c a 2 5 8
d a 3 4 5
e c, b 4 6 8
f c, b 0 0 6
g d, e 3 6 9

2. With the help of the given data below:


a. Draw a PERT network.
b. Find the Critical Path and the Project Completion Time
c. Prepare an activity schedule showing ES, LS, EF, LF, and slack for each activity.
Exp completion time
Activity Predecessor
(wks)
A NONE 5
B A 2
C A 6
D B 12
E D 10
F D 9
G D 5

Exp completion time


Activity Predecessor
(wks)
H B 9
I C, E 1
J G 2
K F, I, J 3
L K 9
M H, G 7
N M 8
Tutorial 8 (Scheduling)
1. Find:
a. The network
b. All expected activity times, variances and slacks
c. Critical Path and expected completion time
d. Probability that the project will be done in 23 days
Activity Predecessor a m b
a - 1 4 7
b - 2 2 2
c a 2 5 8
d a 3 4 5
e c, b 4 6 8
f c, b 0 0 6
g d, e 3 6 9

2. With the help of the given data below:


d. Draw a PERT network.
e. Find the Critical Path and the Project Completion Time
f. Prepare an activity schedule showing ES, LS, EF, LF, and slack for each activity.
Exp completion time Exp completion time
Activity Predecessor Activity Predecessor
(wks) (wks)
A NONE 5 H B 9
B A 2 I C, E 1
C A 6 J G 2
D B 12 K F, I, J 3
E D 10 L K 9
F D 9 M H, G 7
5 N M 8
G D
3. For the activity relationship given below:
e. Draw an AOA network diagram and number the events.
f. Identify the critical path and calculate the expected project completion time.
g. Determine the probability that the project is completed in 60 days.

Activity Predecessor a m b
A - 10 12 32
B - 4 5 6
C - 6 7 8
D - 11 18 19
E A, B, C, D 5 8 17
F A, B, C, D 3 4 5
G A, B, C, D 3 3 3
H B, C, D 3 4 5
I B, C, D 4 5 6
J B, C, D 7 9 17
K B, C, D 3 3 3
L E, F 15 17 25
M G, H, I 3 4 5
N K 6 6 6
O L, M, J, N 7 9 17

3. For the activity relationship given below:


a. Draw an AOA network diagram and number the events.
b. Identify the critical path and calculate the expected project completion time.
c. Determine the probability that the project is completed in 60 days.

Activity Predecessor a m b
A - 10 12 32
B - 4 5 6
C - 6 7 8
D - 11 18 19
E A, B, C, D 5 8 17
F A, B, C, D 3 4 5
G A, B, C, D 3 3 3
H B, C, D 3 4 5
I B, C, D 4 5 6
J B, C, D 7 9 17
K B, C, D 3 3 3
L E, F 15 17 25
M G, H, I 3 4 5
N K 6 6 6
O L, M, J, N 7 9 17