8 - C - Project Scheduling PERT
8 - C - Project Scheduling PERT
1. Find:
a. The network
b. All expected activity times, variances and slacks
c. Critical Path and expected completion time
d. Probability that the project will be done in 23 days
Activity Predecessor a m b
a - 1 4 7
b - 2 2 2
c a 2 5 8
d a 3 4 5
e c, b 4 6 8
f c, b 0 0 6
g d, e 3 6 9
Activity Predecessor a m b
A - 10 12 32
B - 4 5 6
C - 6 7 8
D - 11 18 19
E A, B, C, D 5 8 17
F A, B, C, D 3 4 5
G A, B, C, D 3 3 3
H B, C, D 3 4 5
I B, C, D 4 5 6
J B, C, D 7 9 17
K B, C, D 3 3 3
L E, F 15 17 25
M G, H, I 3 4 5
N K 6 6 6
O L, M, J, N 7 9 17
Activity Predecessor a m b
A - 10 12 32
B - 4 5 6
C - 6 7 8
D - 11 18 19
E A, B, C, D 5 8 17
F A, B, C, D 3 4 5
G A, B, C, D 3 3 3
H B, C, D 3 4 5
I B, C, D 4 5 6
J B, C, D 7 9 17
K B, C, D 3 3 3
L E, F 15 17 25
M G, H, I 3 4 5
N K 6 6 6
O L, M, J, N 7 9 17