Concrete Works: Concrete Method Statement No. Cfc/Dtc/Ca007/St/Mst/200017
Concrete Works: Concrete Method Statement No. Cfc/Dtc/Ca007/St/Mst/200017
Concrete Works: Concrete Method Statement No. Cfc/Dtc/Ca007/St/Mst/200017
CFC/DTC/CA007/ST/MST/200017
Department :QC Rev. 01
Title :Concrete Works Date : 04.04.19
CONCRETE WORKS
REVISION HISTORY
0 Revision 01 04.04.2019
CFC-DTC-CA007-ST-MST-200017 Page 1 of 23
CONCRETE METHOD STATEMENT No. CFC/DTC/CA007/ST/MST/200017
Department :QC Rev. 01
Title :Concrete Works Date : 04.04.19
1 CONCRETE WORKS
1.0 OBJECTIVE
1.1 To define the requirements for the supply and execution concrete works for
the constructions of AL-Futtaim Oriana 4 Villas Development’ Phase 1&2-New
Caro Project – New Cairo (Tender Number: CA007P01)
2.0 SCOPE
3.0 REFERENCE
3.6 American Society of Testing and Material (ASTM C 94 , ASTM C 494 , ASTM C
1059 ).
CFC-DTC-CA007-ST-MST-200017 Page 2 of 23
CONCRETE METHOD STATEMENT No. CFC/DTC/CA007/ST/MST/200017
Department :QC Rev. 01
Title :Concrete Works Date : 04.04.19
4.0 PROCEDURE
4.1 The contractor shall obtain approval from consultant for various grades of
concrete as specified in the project specification, the contractor shall arrange for
trial mix at approved concrete batching plant. The contractor shall submit the
results of such trial mixes and obtain approval from consultant.
4.2 The contractor shall obtain approval from consultant for the sources of all
materials used in concrete including the ready mix batching plant by duly
furnishing the valid calibration certificated of the batching plant issued by
approved calibrating agencies and test certificates of all concrete ingredients
form consultant approved independent laboratories.
4.3 Ready mix concrete should conform to ASTM C 94, except for material, testing
and design conform to E.C.P.
4.4 Before concreting, necessary approval for rebar, formwork should be obtained
from consultant engineer. Clearance from electro mechanical shall be obtained.
All the inserts, fixtures are in firmly position.
4.5 Request for Inspection and approval shall be submitted by consultant engineer in
advance clearly mentioning the scope of concreting including the time, date,
grade and quantity of concrete.
4.6 All the equipment necessary for the proposed concrete should be made
available in working condition at site. Proper lighting arrangements should be
made available at concreting location if required.
4.7 Adequate manpower shall be arranged at site for finishing the concrete before it
takes initial setting.
4.8 Ensure that the correct grade and required quantity of concrete is ordered and
the delivery of concrete should not be any time gap which shall lead to cold joints
in the freshly placed concrete.
CFC-DTC-CA007-ST-MST-200017 Page 3 of 23
CONCRETE METHOD STATEMENT No. CFC/DTC/CA007/ST/MST/200017
Department :QC Rev. 01
Title :Concrete Works Date : 04.04.19
4.10 Temperature of concrete should be taken and it shall be within the permissible
limits. If the temperature of concrete exceeds 30°C at the placing point,
Consultant engineer should be informed and create cold joint at the placement if
required.
4.11 Slump test in accordance with BS 5328 should be conducted before placing of
concrete. Tests shall also be conducted when making test cubes and a record
must be kept for all these tests.
4.12 Samples for work cube test shall be taken at the rate of twelve of cubes from
every day pour or each 100 m3 of concrete pour whichever is smaller , from each
sample three cubes shall be tested after seven days , three after 28 days. Test
cubes shall be crushed in presence of Consultant engineer and the results
should be submitted and approved from Consultant , giving the information like
cube specimen mark, date of casting, date of testing, age, dimensions,
compressive strength, weight of the cube etc.
4.13 Concrete shall only be placed on surface ready to receive it. Concrete shall be
placed gently to avoid segregation.
4.14 Concrete shall not be thrown or dropped from a height exceeding 2 m and it shall
be placed in final position.
4.15 Concreting shall be carried out continuously and fresh concrete shall not be
placed against insist concrete, which is more than 30 thirty minutes unless a
construction joint is formed.
4.16 At any case concrete shall not be placed in standing water in the formwork. The
depth of layers and the time between placements of layers can be properly
merged into preceding layer before initial set takes place.
CFC-DTC-CA007-ST-MST-200017 Page 4 of 23
CONCRETE METHOD STATEMENT No. CFC/DTC/CA007/ST/MST/200017
Department :QC Rev. 01
Title :Concrete Works Date : 04.04.19
4.18 Vibration of the concrete shall not be applied on reinforcement. The duration of
vibration shall be limited to produce satisfactory compaction without causing
segregation.
4.19 On completion of concreting, the site shall be cleaned and any splashes of
concrete shall be removed..
5: PERSONAL RESPONSIBILITIES
A full and detailed description of the roles and responsibilities of all DETAC staff is included
within the Project Quality Plan. For the works as covered by this method statement, the
following personnel have specific duties.
Ensuring that the project is managed in a safe manner and meets the
requirements of the project documentation.
CFC-DTC-CA007-ST-MST-200017 Page 5 of 23
CONCRETE METHOD STATEMENT No. CFC/DTC/CA007/ST/MST/200017
Department :QC Rev. 01
Title :Concrete Works Date : 04.04.19
Shall refer to the QC Department and the HSE Department for advice
and guidance when required.
Liaison with the senior site staff on health, safety and environmental
related matters.
Ensuring that all required tests are performed and are in compliance
with project specifications.
CFC-DTC-CA007-ST-MST-200017 Page 6 of 23
CONCRETE METHOD STATEMENT No. CFC/DTC/CA007/ST/MST/200017
Department :QC Rev. 01
Title :Concrete Works Date : 04.04.19
6. Equipment:
Concrete Pump.
.Vibrators.
Testing equipment's.
CFC-DTC-CA007-ST-MST-200017 Page 7 of 23
CONCRETE METHOD STATEMENT No. CFC/DTC/CA007/ST/MST/200017
Department :QC Rev. 01
Title :Concrete Works Date : 04.04.19
7. Materials
8. Safety:
Project Safety Plan shall be strictly enforced at all times. All works
shall be regularly monitored to ensure full compliance.
All waste materials (rubbish and debris) shall be removed from the
workplace to a suitable area.
Establish first aid station and maintain adequate first aid supplies.
During casting concrete ensure that Stairs, walkways and work areas
to be free of debris, grease and oil, also provide warning tapes and
signs at potential fall hazard areas.
CFC-DTC-CA007-ST-MST-200017 Page 8 of 23
CONCRETE METHOD STATEMENT No. CFC/DTC/CA007/ST/MST/200017
Department :QC Rev. 01
Title :Concrete Works Date : 04.04.19
Samples for work cube test shall be taken at the rate of twelve of
cubes from every day pour or each 100 m3 of concrete pour
whichever is smaller, from each sample three cubes shall be tested
after seven days, three after 28 days. Test cubes shall be crushed in
presence of Consultant engineer and the results should be submitted
and approved from consultant for giving all data, according to project
specifications division 03 section 33000 part 3.19
9. Submittals:
Reinforcement.
Formwork.
CFC-DTC-CA007-ST-MST-200017 Page 9 of 23
CONCRETE METHOD STATEMENT No. CFC/DTC/CA007/ST/MST/200017
Department :QC Rev. 01
Title :Concrete Works Date : 04.04.19
CFC-DTC-CA007-ST-MST-200017 Page 10 of 23
CONCRETE METHOD STATEMENT No. CFC/DTC/CA007/ST/MST/200017
Department :QC Rev. 01
Title :Concrete Works Date : 04.04.19
CFC-DTC-CA007-ST-MST-200017 Page 11 of 23
CONCRETE METHOD STATEMENT No. CFC/DTC/CA007/ST/MST/200017
Department :QC Rev. 01
Title :Concrete Works Date : 04.04.19
11.2Workability
11.3Preliminary Mixes
One brand of cement throughout the project will be used and the
source of supply for cement shall be subject to the Engineer's
approval, the date of manufacture must be recorded, also follow-up
tests shall be performed.
The supplier of ready mix concrete shall at all times furnish test
certificates and proof that the required standard specification has
been followed.
Cement used in concrete work shall be less than six months old from
date of manufacture.
Aggregates shall not contain harmful materials which may reduce the
strength or durability of concrete nor materials which may attack the
reinforcement.
CFC-DTC-CA007-ST-MST-200017 Page 12 of 23
CONCRETE METHOD STATEMENT No. CFC/DTC/CA007/ST/MST/200017
Department :QC Rev. 01
Title :Concrete Works Date : 04.04.19
Coarse aggregate shall be free from salt, mica, alkali, organic matter
or other deleterious material either free or as adherent coating on
particles.
Coarse and fine aggregate shall comply with ES No. 1109, having
absorption as measured in Accordance with BS 812.
Admixtures shall comply with ASTM C 494 and their type and dose
are dependent upon the trail mixes stage where the performance of
concrete can be observed.
Trail mixes for all grades of concrete, slump test and measuring
concrete temperature will be made in attendance of consultant
supervisor.
Six cubes of each concrete grade will be taken for trail mixes of
concrete three cubes will be crushed after seven days and the
another three cubes will be crushed after 28 days for each concrete
grade.
CFC-DTC-CA007-ST-MST-200017 Page 13 of 23
CONCRETE METHOD STATEMENT No. CFC/DTC/CA007/ST/MST/200017
Department :QC Rev. 01
Title :Concrete Works Date : 04.04.19
12. MIXERS
The amount of concrete mixed in any one batch shall not exceed the
rated capacity of the mixer.
All truck mixers are of the revolving drum type, water tight and
equipped with discharge chute.
CFC-DTC-CA007-ST-MST-200017 Page 14 of 23
CONCRETE METHOD STATEMENT No. CFC/DTC/CA007/ST/MST/200017
Department :QC Rev. 01
Title :Concrete Works Date : 04.04.19
13.1Inspection
Verify that the latest approved for construction shop drawings are
used. , according to project specifications division 03 section 33000
part 1.03
Material test Certificates for reinforcement, casting and the like are
checked approved
CFC-DTC-CA007-ST-MST-200017 Page 15 of 23
CONCRETE METHOD STATEMENT No. CFC/DTC/CA007/ST/MST/200017
Department :QC Rev. 01
Title :Concrete Works Date : 04.04.19
Qc site representative
HSE site representative
Site engineer
CFC-DTC-CA007-ST-MST-200017 Page 16 of 23
CONCRETE METHOD STATEMENT No. CFC/DTC/CA007/ST/MST/200017
Department :QC Rev. 01
Title :Concrete Works Date : 04.04.19
Site supervisor
Facility supervisor
Subcontractors
Sufficient number of labors
Proper, safe and clean access for concrete truck to reach the pump.
Forms shall be thoroughly cleaned of all dirt, loose stones etc., and
shall be well soaked with water.
The first concrete delivery onsite for any particular section of the work
shall be held and the concrete slump measured by the independent
laboratory technician. The concrete pour will only commence after this
and the delivery ticket has been verified against the approved mix
design.
CFC-DTC-CA007-ST-MST-200017 Page 18 of 23
CONCRETE METHOD STATEMENT No. CFC/DTC/CA007/ST/MST/200017
Department :QC Rev. 01
Title :Concrete Works Date : 04.04.19
14. COMPACTION
CFC-DTC-CA007-ST-MST-200017 Page 19 of 23
CONCRETE METHOD STATEMENT No. CFC/DTC/CA007/ST/MST/200017
Department :QC Rev. 01
Title :Concrete Works Date : 04.04.19
17. FORMWORK
All formworks must be erected with level and flush surfaces and close
fitting edges with joints fitting sufficiently close to prevent leakage of
concrete, according to project specifications division 03 section 33000
part 3.13
CFC-DTC-CA007-ST-MST-200017 Page 20 of 23
CONCRETE METHOD STATEMENT No. CFC/DTC/CA007/ST/MST/200017
Department :QC Rev. 01
Title :Concrete Works Date : 04.04.19
Forms shall not be removed until the concrete has attained sufficient
strength to ensure structural stability and to carry both dead load and
any construction loads that may be imposed on It .The minimum
period of time that shall elapse between pouring concrete and
removal of forms shall be as follows, , according to project
specifications division 03 section 33000 part 3.13
CFC-DTC-CA007-ST-MST-200017 Page 21 of 23
CONCRETE METHOD STATEMENT No. CFC/DTC/CA007/ST/MST/200017
Department :QC Rev. 01
Title :Concrete Works Date : 04.04.19
Deshuttering for slabs will take place after concrete strength reaches
75% of the specified compressive strength. Deshuttering will not be
allowed till testing of 7 days cubes took place and the results are
satisfactory, and approved by consultant.
18. Finishing
.Concrete surface must be horizontal land level for top and bottom of
slab, top of foundation and beam.
Pre Inspection checklist and other quality forms has been signed off
as complete by construction team, and other package contractors
especially for electromechanical works.
CFC-DTC-CA007-ST-MST-200017 Page 22 of 23
CONCRETE METHOD STATEMENT No. CFC/DTC/CA007/ST/MST/200017
Department :QC Rev. 01
Title :Concrete Works Date : 04.04.19
CFC-DTC-CA007-ST-MST-200017 Page 23 of 23