Part A (5 X 2 = 10 Marks)
(Answer All Questions)
Part 8 (2 x 15 = 30 Marks)
(Answer All Questions)
6. (a) What are the various types of charts used in project management? Explain detail.
(OR)
(b) Write short notes on
i) PERT network (8)
ii) Role of project managers (7)
7. (a) Construct a network diagram from the information given below and find the critical path ,
arliest finish date for the project, total and free floats for activities.
Activity Immediate Duration (Days)
redecessors
A - 4
B - 8
C A 6
D A 8
E B 6
F B 5
G C 5
H D,E 3
(OR)
(b) Follow ing is the data assoc iated with PE RT projec
t
Activi ty A B C
I D E F G
Prece di n -- -- A B A B C&D
activi ty
To (days ) 6 5 4 4 4 2 4
Tm 9 8 7 7 7 5 10
ays)
Tp (days ) 12 7 22 16 10 8 22
z -3 -2 -1 0 1 2 3
P(%)·-- 0.13 2.28 15.87 50 84.13 97.72 99.87
Part C (1 x 10 = 10 Marks)
(Answer All Questions)