Hydro Test Procedure
Hydro Test Procedure
Injection, Source Water Supply Wells and Oil Wells at Ghani Field" Sheet No.: Page 1 of 5
HYDROTEST PROCEDURE
TABLE OF CONTENTS
1. GENERAL.........................................................................................................................................................................3
Project: Wells Flow Lines Replacement and Repair for Water Injection, Source Water Supply Wells and Oil Wells at Ghani Field
CONTRACT NUMBER REV. NO.
1. GENERAL
1.1 General Description
Harouge Oil Operations (HOO) (hereinafter called COMPANY) has identified BaderOya Oilfield Services
(BOS) (hereinafter called CONTRACTOR) as one of a potential bidder in the Tender for “Wells Flow
Lines Replacement and Repair for Water Injection, Source Water Supply Wells and Oil Wells at Ghani
Field”.
1.2 Scope
CONTRACTOR shall perform Construction Work at Ghani field, consisting of Supply all Field Engineering
Services, Testing Services, Labour, Equipment and Consumables Materials necessary to install and tie-
in new Flow Lines for number of Ghani & Zenad Wells and replacement of the damaged piping sections
of Zenad & RRR-17 manifolds at Ghani field in accordance with Scope of Work and Specifications as
outlined in Sections I and II of this Schedule and Company Project Drawings and Documents attached
to the Scope Of Work.
Project: Wells Flow Lines Replacement and Repair for Water Injection, Source Water Supply Wells and Oil Wells at Ghani Field
CONTRACT NUMBER REV. NO.
Project: Wells Flow Lines Replacement and Repair for Water Injection, Source Water Supply Wells and Oil Wells at Ghani Field
CONTRACT NUMBER REV. NO.
• Water filling valve shall be closed, connection between test pump and test section shall be
removed,
• manifold valve shall be plugged,
• Inspect system for leaks and verify pressure stability
• Start the pressure recorder with the chart, Check and records pressure and temperature
each 30 min interval.
3. ASSESSMENT OF TEST
• The hydrostatic test shall be considered as positive if pressure was constant throughout the
test duration, except for change due to temperature effects. Such changes shall be
evaluated.
• The test shall be considered as acceptable if the difference is less than or equal to 0.3 bar.
In case of doubt, the testing period shall be extended by 4 hours.
• If test section fails to maintain the specified test pressure after isolation, Contractor shall
determine the location of leakage or failure. For leak and failure within the pipe or weld
seams shall be repaired by replacement of entire joint or joints in which leakage or failure
occurs. The method of repair shall be determined by the Company and hydrostatic test
shall be repeated in accordance to this procedure.
• After the positive result of testing and all the data have been collected, test records and
charts shall be signed by the Company representative and final test REPORT shall be issued
with Pre-commissioning PACKAGE.
• Test piping shall be slowly depressurized at a moderate and constant rate under
supervision of Company.
Project: Wells Flow Lines Replacement and Repair for Water Injection, Source Water Supply Wells and Oil Wells at Ghani Field