Method Statement Submission: For: LPG System Work Installation, Testing & Commissioning
Method Statement Submission: For: LPG System Work Installation, Testing & Commissioning
METHOD STATEMENT
SUBMISSION
For: LPG System Work Installation, Testing &
Commissioning
1|Page
CRIMSON & PENGUIN RESTAURANT @ MANDAI LAKE
ROAD (MANDAI BIRD PARK)
This method statement provides the details of site installation of LPG works for the
project. This method statement outlines the quality procedures for LPG works for the
project. In addition this method statement is made to make the technicians aware of
their exposure to the safety risk identified and explain them how to eliminate or to
reduce the risk in their specific activity.
Required Tools:
Measuring tape
Marker pen
Ladder and accessories
Pipe cutting machine
Spanner and standard tool kit
Manual setting tools
Hammer drill
Welding machine
Pressure gauge
Welding set c/w cylinder
Water level
Emergency Arrangement:
The Health & Safety officer will be responsible for coordination the
emergency procedure. If there is an emergency the Health & Safety officer
will be notified immediately.
The Health & Safety officer will then notify relevant emergency services if
required.
The required notification, investigation and reporting of the incident will be
conducted in accordance with the site HSE Plan.