CRIMSON & PENGUIN RESTAURANT @ MANDAI LAKE

ROAD (MANDAI BIRD PARK)

METHOD STATEMENT
SUBMISSION
For: LPG System Work Installation, Testing &
Commissioning

1|Page
CRIMSON & PENGUIN RESTAURANT @ MANDAI LAKE
ROAD (MANDAI BIRD PARK)
This method statement provides the details of site installation of LPG works for the
project. This method statement outlines the quality procedures for LPG works for the
project. In addition this method statement is made to make the technicians aware of
their exposure to the safety risk identified and explain them how to eliminate or to
reduce the risk in their specific activity.

Required Tools:
 Measuring tape
 Marker pen
 Ladder and accessories
 Pipe cutting machine
 Spanner and standard tool kit
 Manual setting tools
 Hammer drill
 Welding machine
 Pressure gauge
 Welding set c/w cylinder
 Water level

Pre Work Check Up:


1. A check should be made whether drawings are approved by consultant and
authorization is given for the commencement of erection work.
2. A clear designated area will be allocated for the storage of the pipes, elbows,
other fittings and accessories onsite for the execution of LPG works.
3. The required personnel protective equipment (hand gloves, safety goggles,
dust masks, ear plug, safety shoe, etc) will be issued to all the operative staffs
prior to start of installation works. All personnel need to be safety inducted by
main contractor safety officer before commencing work.
4. Permit to work must be obtained from main contractor before start of any
activity onsite and risk assessment made for each activity. Hot work should be
obtained separately for welding of API pipes.
5. All the material used for the LPG services should be checked for their
compliance with the standard and the specifications as mentioned in the
consultant approved material submittals.
6. All the material delivered to the site should be visually inspected and checked
if all complies with the specification. All the pipes are to be stacked in proper
racks and the fittings, flanges, clamps and other accessories are to be stored in
separate area.
7. A copy of the approved drawings is to be given to the foreman, supervisor and
technicians onsite prior to the commencement of work.
8. The site engineer should check the site for the completion of civil works and
the portion of the area cleared for installation of sleeves within concrete.
2|Page
CRIMSON & PENGUIN RESTAURANT @ MANDAI LAKE
ROAD (MANDAI BIRD PARK)

PVC Containment in Wall / Concrete:


 Building work drawings should be produces according to the required
containment for LPG leak detection system.
 All the required containment sleeves to be provided at the site according to the
design & dimensions in the drawings.
 Layout for electrical containment to be provided.

Above ground pipe installations:


 All the pipe routing should be marked and support marking should be done.
 Drilling for the anchor fasteners as per the location of the support have to be
carried out.
 All the threaded rods to be installed and part of the pipe clamp to be erected
along with the thread rods.
 All the pipes, Isolating valves and other accessories are to be installed as per
the approved drawings.
 Pressure test to the complete pipe system to be carried out to 1.5 times the
working pressure. If the pressure testing is successfully completed, then
clearance is given to the contractor.
 Pressure test to be witness by consultant/RTO, pressure gauges used for
monitoring pressure to be provided with calibration cart.

Installation of Regulator, Solenoid Valve & Other Accessories:


 The gas Regulator, Solenoid Valve & other accessories shall be installed after
the completion of all the civil works in kitchen room.
 The Gas leak sensor & interlocking control panel, switch, isolator and gas
detector shall be installation after completing all tiling work for kitchen area
by the civil contractor.
 Final connection of the gas equipment with solenoid valve shall be done after
fixing the gas equipment.
 After fixing the gas system accessories, check the functioning of installed
accessories.
 Seal the joints between fittings and the tiles properly with silicon.
 After completion of the tests, the area can be handed over to the other services
after consultant approval.

Safety Control Measures:


 Prevention of falling materials from height, this would involve toe board on
scaffolding etc.
 All workers to wear appropriate PPE for the task, i.e. goggles, mask, gloves,
ear plug, safety shoe etc. The supervisor should provide all the necessary PPE
and implement the wearing of it.
3|Page
CRIMSON & PENGUIN RESTAURANT @ MANDAI LAKE
ROAD (MANDAI BIRD PARK)
 Electrical power tools shall be check by LEW.
 Fire extinguisher are to be placed within reaching distance any works that is
within risk of a fire.
 Equipment will have RTO inspection certificates and be inspected prior to use.
 All personnel entering the site will wear the appropriate PPE.

Emergency Arrangement:
 The Health & Safety officer will be responsible for coordination the
emergency procedure. If there is an emergency the Health & Safety officer
will be notified immediately.
 The Health & Safety officer will then notify relevant emergency services if
required.
 The required notification, investigation and reporting of the incident will be
conducted in accordance with the site HSE Plan.

Testing and Commissioning Procedure for LPG System:


Testing and Commissioning – Mechanical
 Prior to commencing the commissioning (Installing the Cylinder) of the gas
system the following checks shall be ensured.
 The installation and related pressure tests of the underground and above
ground along with all the fitting should be pressure tested with Air.
 The pressure testing after fitting all the accessories and complete API and GI
piping and welding completely then we have to do the pressure testing at 1.5
times of working pressure.
 Complete system should be tested at 1.5 times of working pressure with Air
before commissioning with cylinders.
 Confirm that the safety links and accessories related to the fire protection and
fire alarm system are tested, approved and put under operation (as per
requirement of Client / Consultant).
 Ensure that the entire above are approved by the consultant.

Testing and Commissioning – Electrical


 Following checks shall be performed to ensure proper installation and wiring
techniques.
 Sensors in kitchen shall be installed at 300mm from the FFL, as per the
standard practice and in such a place there is easy of fresh air.
 Buzzer and emergency switch shall be installed as per approved plan.
 Solenoid valve to be interlinked with Gas Detector and Emergency Switch.
 Power supply (230V AC) to be given at the point of Gas Detector.
 If there is any gas leak inside the kitchen, Gas Detector will give Buzzer and
certain level of gas leak the solenoid valve will cut of and gas flow will be
stopped from cylinder compartment.
4|Page
CRIMSON & PENGUIN RESTAURANT @ MANDAI LAKE
ROAD (MANDAI BIRD PARK)
 Wiring shall be done through proper conduits and shall be connected through
proper connectors.