Professional Documents
Culture Documents
Method Statement For General Door-Window Fitting-Replacement
Method Statement For General Door-Window Fitting-Replacement
Method Statement For General Door-Window Fitting-Replacement
Table of Contents
Scope 3
Objective.................................................................................................................................................................. 3
Term & Definitions...................................................................................................................................................3
Key Plant and Tools Required:..................................................................................................................................3
Key Materials Required:...........................................................................................................................................4
Other Essential Equipment:......................................................................................................................................4
Specific Identified Residual Hazards:........................................................................................................................4
Responsibilities.........................................................................................................................................................4
Site Supervisor..................................................................................................................................................5
Site Worker.......................................................................................................................................................6
HSE Officer........................................................................................................................................................6
Specific Staff Training Requirements:...............................................................................................................6
Submission Documents............................................................................................................................................7
Delivery, Storage and Handling................................................................................................................................7
Site Conditions.........................................................................................................................................................7
The sequence of Window Installation Operations:..................................................................................................7
Temporary Supports and Props needed to facilitate the works:..............................................................................8
Fall Protection Measures:.........................................................................................................................................9
Required Personnel Protective Equip.:.....................................................................................................................9
Emergency Procedures:............................................................................................................................................9
First Aid Facilities:.....................................................................................................................................................9
Other Information & Comments:...........................................................................................................................10
Quality Control & Assurance..................................................................................................................................10
Health, Safety & Environment................................................................................................................................11
Below are some COVID-19 Safety precautionary measures to be followed:..........................................................12
Manpower Resourcing...........................................................................................................................................12
Appendices (As Applicable)....................................................................................................................................12
METHOD OF STATEMENT Page 3 of 12
(General Door/Window Fitting/Replacement)
Company Doc. No. Date Revision
Contractor Ref. No.
0
Scope
The scope of the written Method of Statement for General Door/Window Fitting/Replacement. Works are
executed following the Contract Specification and safety requirements, related hazards and concerns are
analyzed and safety precautions are implemented throughout the progress of the work.
Objective
Strict compliance to this method of statement is the most essential to the health and safety of all
manpower engaged in the installation and maintenance work.
Any deviation must first be authorized by the site supervisor.
Work safely throughout the entire process.
Responsibilities
Ensure strict compliance with PTW and procedure.
Deploy competent and certified staff.
Conduct pre-job briefings/toolbox talk/Hazard Communication.
Ensure proper coordination with plant supervisor/operator
Ensure usage of correct tools and equipment.
Ensure to keep away from other equipment or wires/cables not related to the job.
Maintain good housekeeping at all times.
The site Engineer will be managing the activities to execute the works as detailed in MOS with safe
practice and procedure
The performer must get the work permit approved before starting the work, and close the work permit
after completion of the work
The contractor should strictly follow plant rules and regulations while doing the job.
The performer and Plant supervisor/Operator have to discuss and understand the scope before
proceeding to the job.
METHOD OF STATEMENT Page 5 of 12
(General Door/Window Fitting/Replacement)
Company Doc. No. Date Revision
Contractor Ref. No.
0
Any damage to the plant property while doing the work will be fixed by the contractor on his expenses
The contractor should strictly follow plant rules and regulations while doing the job.
The performer and Plant supervisor/Operator have to discuss and understand the scope before
proceeding to the job.
Responsible for overall projects executions
Adapt a leading role concerning contractor’s quality and safety procedures
Always be informed of the task to the plant responsible person
Supervise the works.
Make sure all the labourers adhere to the HSE policies ex. Use safety restraints, safety harnesses...etc.
Directly monitor the repairing activities at the site.
Report on the spot any non-conformance to the Plant Supervisor.
Provide all necessary tools, equipment, and material required at the site.
Stop all unsafe work activities.
Ensure availability of all required tools to maintain a safe working environment.
Ensure compliance with procedures concerning equipment and related certification and permits.
Ensure that the workers under his command fully understand the hazards and risks involved in the job
and are responsible to ensure they work in a safe environment.
The service technician, in attendance, must sign into the plant room, where applicable and make the site
manager or site representative, aware of the works to be undertaken and the areas in which the worker
wishes to work before commencing with any works.
The site team must aware of the worker about fire, health and safety and specific site requirements. As
the workers will be working within unfamiliar buildings, they must also be made aware of the positions
of fire alarm call points, fire evacuation assembly points, fire extinguishers or blankets and the nearest
fire escape routes.
Site Supervisor
The carrying-out of work and the proper distribution of all the available resources in coordination with
the Site Engineer daily.
Daily reports of the works are achieved and coordinated for future planning with the Site Engineer.
Incorporate all the QA/QC and Safety requirements as requested by the concerned Engineer.
Meeting with any type of unforeseen incident or requirement and reporting the same to the Site
Engineer immediately.
Should acquire any necessary civil works clearances and coordination.
The identified HSEQ aspects and TBT are briefed to the working crew before the starting of the job and
its HSE Officer/Representative shall be responsible for the safe executing of the above activities in strict
compliance with approved MOS/TRA via Control, supervise and record toolbox meetings.
Ensure that all HSE requirements are met and implemented while executing the works.
METHOD OF STATEMENT Page 6 of 12
(General Door/Window Fitting/Replacement)
Company Doc. No. Date Revision
Contractor Ref. No.
0
Site Worker
Maintenance of all materials associated with fire protection systems and in line with [Company/client]’s
SOW
Following approved checklists for service and maintenance of the assets.
Handling of the site materials, accessories, tools and equipment.
Ability to perform routine maintenance on equipment and determine when and what kind of
maintenance is needed.
Maintaining circuits and sensors, following wiring and system specifications.
Performing other related activities as instructed by the Superior.
HSE Officer
The implementation of all safety measures following the HSE plan and that the whole workforce is
aware of its proper implementation.
The implementation of safety measures is adequate to maintain a safe working environment on the
maintenance activity.
Inspection of all the site activities and training personnel in accident prevention and its proper reporting
to the Maintenance Manager.
The site is maintained in a clean and tidy manner.
Ensure only trained persons shall operate the power tools.
Ensure all concerned personals shall use PPE and all other items as required.
Ensure high risk elevated areas are provided are barricades, tape, safety nets and provided with ladders.
Ensure service area/inspection area openings are provided with barricades, tape, and safety nets.
Ensure safe access to site work at all times.
Submission Documents
Technical Data: technical data, test certificates, installation instructions and valid Bomba’s certificates for fire-
rated assemblies for approval before commencement of work will be provided by the manufacturer.
Site Conditions
Install work only in areas closed and protected against the weather. Provide appropriate Ventilation &
Dehumidification (VD) to eradicate extreme moisture in the areas of work to ensure appropriate drying, curing
of the compounds.
Try to never install such type of work in any area unless convinced that the work accomplished has dried out and
that no more installation of damp materials is proposed.
1The old windows and frames will be removed from the site and disposed of via a licensed waste carried for
disposal at a licensed waste site.
All work will generally be carried out from the inside of the property, however, where work is being carried out on
floors other than the ground floor, or where work is carried out on the ground floor and level of the ground outside
of the window is more than 1.5m below the sill height and where the internal sill height is less than 910mm (or
950mm on properties constructed after April 2005) above the internal floor level, then additional measures must be
implemented to safeguard against falls through the open window aperture. This is to ensure compliance with the
Work at Height Regulations 2005. In such instances where the sill height is below 910 mm (or 950mm on new
properties) either a temporary handrail at 950 mm must be erected, or those carrying out the works must wear a full-
body harness with a lanyard attached to a suitable anchor point.
Before the fitting of the new window and window frame, the walls must be checked to ensure that they are sound
and that any old fixings have been removed and disposed of. Where sections of the wall have been damaged or are
not suitable, the area should be made good or alternative fixings used.
Clean the area and prepare the recess for the installation of the new windows. Fit the new window frame into
position, ensuring a tight fit and ensuring that the frame is plumb and square.
Use packers were necessary to secure the frame in position and then drill through the frame into the masonry wall
for the frame fixings. A minimum of 2 frame fixings should be used on each element of the window frame, though
for long windows additional fixings will be required.
Once the frame fixings have been inserted and securely fixed /tightened, the back of the frame should be filled with
expanding foam to provide added protection against the weather, water ingress and unwanted noise.
Where applicable the individual window openings can be inserted and fixed to the window frame with the hinges.
Generally, all windows and frames should be supplied pre-assembled before arriving on site.
Once the windows and frames have been installed, the glazing units can be inserted. Each unit should be installed
and secured into position with the appropriate beading/seals. The glazed panels can then be carefully lifted into
position, grip gloves should be worn at all times when lifting glazed units and for large panels, a minimum of 2
persons should be used to lift and secure the
panels in place. The use of suction lifters should also be used to provide a safe and secure grip when lifting large and
heavy glass panels/units.
The windows should then be tested to ensure that they open and close smoothly without rubbing or catching, if
necessary, the hinges should be adjusted to ensure a suitable fit.
The window frame should then be trimmed and sealed both internally and externally and the area made good.
Upon completion of the works, [Client/Contractor/Company Name] will remove all rubbish, scrap and waste
materials/packaging from the premises and dispose of them appropriately. Thoroughly vacuum and clean through
the area and all transit routes leaving the property in a clean and tidy state.
Care must be taken to ensure that the glass is not broken and that when handling glass and windows, those
appropriate gloves are worn
1. [Client/Contractor/Company Name] has a policy of a Tidy Site is a Safe Site and in this respect all employees are
required to remove and dispose of waste as it is generated, leaving a clean and
2. tidy site at all times. All waste is to be segregated where applicable and placed into the appropriate waste
containers/skips. At the end of each working day, a check is to be made to ensure that all
METHOD OF STATEMENT Page 9 of 12
(General Door/Window Fitting/Replacement)
Company Doc. No. Date Revision
Contractor Ref. No.
0
3. waste has been removed from the site and placed into the appropriate waste containers/skips and that the site is left
in a clean and tidy state.
4. At the end of each shift, ensure that all working areas are left tidy, safe and secure and remove or cover anything
which may constitute a trip hazard, or result in a danger to other workers/persons.
5. Method of Access and Egress to the work area:
6. Access and egress to the working area will be via the front/rear doors of the premises, access to the first floor will be
via the internal staircase.
7. In areas where external access is needed all work will be carried out from full access scaffolds or tower scaffolds,
the use of ladders will not be permitted for use as a working platform.
Do not store tools or materials on top of working platforms or around holes in the floor when working above ground level.
Exclusion zones shall also be established in the area beneath all such works, to protect others from the risk of falling tools,
equipment and materials etc. Access scaffolds are to be used for all external work at height to provide a safe working
platform and protection from falls, all scaffolds will be provided with close boarded platforms, toe boards and double
handrails in full accordance with the Work at Height Regulations 2005.
Emergency Procedures:
Call 999 and advise the appropriate emergency services Isolate any plant, machinery or other equipment.
Do NOT move the injured person unless it is necessary and they are in
danger by remaining where they are.
Keep the injured person warm and dry. Inform the site manager and head office.
The use of low vibration tools will be utilized where possible, only low vibration models will be purchased and when tools
are being hired, consideration is to be given to lower vibration models.
As with vibration, low noise tools will be selected where appropriate, consideration has been given to the selection of
appropriate tools in this method statement and quieter methods of working are selected where appropriate.
Identify the processes needed for achieving quality service and product as per client satisfaction and
applicable standards.
Determine the sequence and interaction of the execution processes, and determine criteria and
methods required to ensure the effective operation and control of these processes.
Ensure the availability of information necessary to support the operation and monitoring of these
processes i.e., project specifications/method statements.
Measure, monitor and analyze these processes by following the work and service plans.
Implement actions necessary to achieve the planned results and continual improvement.
Identify QHSE hazards associated with its activities and planning for risk control.
Established to maintain quality of the works following specification and standard.
Materials to be inspected by Plant Supervisor/Operator after delivery to site.
Works shall be inspected by the Plant Supervisor/operators at every stage.
To ensure that quality is maintained, we will coordinate with the on-site [Client’s] team regularly.
The plant Supervisor/operator and the Client’s representative shall inspect the materials and
workmanship
Approval by the supervisor or the operator in charge during the time of work will be accepted as
sufficient evidence that arrangements for manufacture and quality comply with these requirements.
Always inspect the job by supervisor/operators on each step of the work progress.
METHOD OF STATEMENT Page 11 of 12
(General Door/Window Fitting/Replacement)
Company Doc. No. Date Revision
Contractor Ref. No.
0
29. All employees shall attend a safety induction Training Course to identify all hazards associated with this
work.
30. The workers will be made aware of safety requirements related to this activity through daily toolbox and
safety talks.
31. All required work permits will be acquired and kept available at respective work sites hanged clearly in
plastic folders.
32. Access and good housekeeping should be maintained in all working areas.
33. Waste management should be strictly enforced by site supervision.
34. All workers shall be provided with proper tools & equipment’s to execute the work safely.
Manpower Resourcing
Number of
S. N. Position
Employees
1 Project Engineer
2 Site Supervisor
3 Site worker
Total