PROVINICAL GOVERNMENT
PROVINCE NO.2
MINISTRY OF PHYSICAL INFRASTRUCTURE DEVELOPMENT
TRANSPORT INFRASTRUCTURE DIRECTORATE
INFRASTRUCTURE DEVELOPMENT OFFICE
BIRGUNJ, PARSA
PILE INTEGRITY TE
REPORT ON
Sansarimai Khola Bridge along Kalay
Contract No. IDO/PAR/NCB/BRIDGE-25/077/078,
Client: INFRASTRUCTURE DEVELOPMENT OFFICE
Office Reg No.: EP043
sd By
Viswa Consult Put Ltd
P.O, Box 4316, Dillibazar, Kathmandu
Tel:-977-1-4533156E mail: viswaconsultlab@gmaiLcom
FALGUN, 2078Project: Construction of Sansarimai Khola Bridge Along Kalayia-Prashtoka Road,Bara
Contract No.: IDO/PAR/NCB/BRIDGE-25/077/078.
Location: Sansarimai Khola, Kalaiya, Bara. (Left Abutment) Date : 2078/11/19
TABLE OF CONTENTS
PAGES
INTRODUCTION & PILE LITERATURE xen
‘BASIC TESTING RECOMMENDATIONS ono
PILE DETAILS AND DATA COLLECTION...
APPENDIX
APENDIX-A: PIT QFV Instruments and Pictorial Representation of the test
‘APENDIX-B: Summary
APENDIX-C: Photo Caption
1[PageProject: Construction of Sansarimai Khola Bridge Along Kalayia-Prashtoka Road,Bara
Contract No.: IDO/PAR/NCB/BRIDGE-25/077/078
Location: Sansarimai Khola, Kalaiya, Bara. (Left Abutment) Date : 2078/11/19
PIT REPORT DesiGn aNo BuiLo oF Construction of Sansarimai Khola Bridge Along Kalayi
Road,Bara
PILE INTEGRITY TEST REPORT ON 20 NOS. BORED CAST-IN-SITU (Left Abutment)
-Prashtoka
1. INTRODUCTION
‘The Pile Integrity Tester (PIT) is an instrument for integrity testing of deep foundations by low-strain surface-
impact methods. It acquires, processes, enhances, and reports data. The test engineer must interpret the data
according to wave propagation theory. The results obtained are only as meaningful and reliable as the testing
engineer's understanding of the physical principles involved
The PIT is avaiiable in four models, namely, PIT-X, PIT-V, PIT-XFV and PIT-FV. The four models can be
distinguished from each other on the basis of their size, portability, number of input data channels and wireless
‘ransmission of data from the sensing device to the electronic units. All PIT models support the “Low Strain
Integrity Test" Method (see ASTM 5882) also called the Pulse-Echo Method (PEM), while PIT-XFV and PIT-
FV additionally support the Trensient Response Method (TRM). The user should become thoroughiy proficient
in PEM and TRM in order to achieve a higher level of confidence needed during data interpretation. Some
theory is discussed in this user manual as it relates to the PIT operation, but this discussion is neither definitive
nor exhaustive.
‘Test applications for PIT include integrity andlor length determination of most types of concrete deep
foundations such as drilled shafts or bored piles, Continuous Flight Auger (CFA) or Augured-Cast-in-Place
(ACIP) piles, driven concrete piles, individual concrete wall panels (barrettes), concrete filled pipe piles, and
timber piles. For simplicity we will refer to all of these foundation types as ‘piles’. Please note that the Pulse
Echo Method has pile length limitations which are a function of pile material type, pile uniformity, soil elastic
properties (elastic modulus), soil density etc. Also data taken on cylindrical piles, steel piles, jointed piles and
timber piles have either greater length limitations than solid ones or do not support clear and/or reliable data
interpretation. Similarly individual piles within a bored pile wall or panels of a diaphragm wall usually do not
provide satisfactory integrity assessments with the Pulse Echo Method. Other methods such as the Thermal
Integrity Profiler (TIP) or Cross Hole Sonic Logging are then much more successful,
21PageProject: Construction of Sansarimai Khola Bridge Along Kalayia-Prashtoka Rond,Biara
Contract No.: IDO/PAR/NCB/BRIDGE-25/077/078
Location: Sansarimai Khola, Kalaiya, Bara, (Left Abutment) Date: 2078/11/19
2. PILE LITERATURE
“The Pulse Echo Method has been conceived in the 1970s both in Europe and in the United States (e.g, Steinbach and
Vey, 1975. "Caisson Evaluation by Stress Wave Propagation Method”, Journal of the Geotechnical Engineering Division,
ASCE), However, only after realtime, on-site digital data processing became practical did this method find general
acceptance. Numerous papers describing these developments are available on the PD! website www pile.com; click on
earning Center and select PIT. The PIT user is urged to review these publications starting maybe with following two
papers.
/wrww.pile.com/reference/3rdStresswave/pile inter by low and high strain impacts.péf
bet _nile.com/reference/TransportationResearchBoardAnnualMeeting/AComparisonOfPulseE
choAndTransientRé if
‘Another important reading s also the ASTM 5882 Standard as wel as other applicable
national testing standards or building codes. Some of these are listed in
htto://Avww.pile.com/reference/StressWaveZ008/CH-12-063 -001.puf; however it should be
expected that various code and standards have either been modified or added since the
writing of that paper.
3|PageProject: Construction of Sansarimai Khola Bridge Along Kalayia-Prashtoka Road,Bara
Contract No.: IDO/PAR/NCB/BRIDGE-25/077/078
Location: Sansarimai Khola, Kalaiya, Bara. (Left Abutment) Date: 2078/11/19
3, PIT TEST THEROY
‘light impact is administered to the ple's surface, generally using a special hand-held hammer, and as a result
‘an acoustic wave from the impact propagates down through the pile. Variations in the shape and material quality of the
pile produce reflections of the wave, which are observed as they return to the surface, Surface vibrations are recorded
nti al primary reflections have been observed. Reflections are then interpreted considering their nature and times of
observation to assess pile integrity.
“The surface vibrations are measured by means of an accelerometer attached to the top of the pile. Although the
acceleration curve could be interpreted directly, integration to velocity generally enhances the record by bringing out
details otherwise overlooked. The pile top acceleration signal, a, is therefore digitized and stored in the PIT memory,
‘and itis numerically integrated to produce a velocity signal, v. Note that v is a particle velocity, Le. the actual velocity of
movement of the pile top surface.
‘The deepest reflector is the ple's toe, so its reflection should be the last one observed at the pile top. Given estimates
of the wave speed c and pile length L, the toe reflection is expected at the top at time 2h/¢ after impact. Thus 2L/cis the
‘time it takes the stress wave to travel to the pile bottom and then, after reflection, back to the pile top. Observation,
i.e, measurement, continues until well after this time, but the first 2L/c is the most important part and provides most of
the information about the pile. Note that the wave speed, c, is several orders of magnitudes greater (typically 3,000 to
5,000 m/s than the pile particle velocity, v (typically 1 to 20 mm/s),
‘The signal is acquired as a function of time, and the time scale is known accurately. To facilitate locating the reflectors,
the signal s presented as a function of distance x from the pile top. However, the distance scale completely depends
upon accurate estimation of the wave speed c: x=%¢ t. The distance scale has a physical meaning only for reflectors
within the shaft, not for soil below the toe, nor can it correctly be applied to the impact pulse, which is not strictly 2
reflection.
Reflections are caused by variations in the pile's impedance. Impedance Z may be calculated as where A is the cross-
sectional area, Eis the elastic modulus and is the mass density of the material of the pile. Thus, reflections can be due to
changes in either the cross-section (siz) or in the elastic modulus or specific weight (quality) ofthe material, A region of
decreasing impedance generates a tensile reflection, producing a velocity peak in the same direction as the impact. A
region of increasing impedance causes a compressive reflection, producing a velocity peak in the direction opposite the
impact.
“The reflections must be interpreted to determine whether the associated changes are acceptable or of serious concern
to the integrity of the shaft. All interpretation should also consider installation records of concrete volume, design
length and other observations
4) PageProject: Construction of Sansarimai Khola Bridge Along Kalayia-Prashtoka Road,Bara
Contract No.: IDO/PAR/NCB/BRIDGE-25/077/078
Location: Sansarimai Khola, Kalaiya, Bara. (Left Abutment) Date : 2078/11/19
4, PROCEDURE OF PILE INTEGRITY TEST
‘The SE method is a low strain integrity test conducted from the top (or upper side) of the shaft as shown in
the figure below. test equipment includes a 3 pound(1.36kg) hammer (instrumented or mechanical),
receiverlaccelerometer and/or geophone) mounted on the top (or upper side) of the shaft, and a data
‘acquisition platform. the test involves hitting the foundation top with the hammer to generate wave energy
that travels to the bottom of the foundation. The wave reflects off irregularities (cracks, necks, bulbs, soil
intrusions, voids, etc.) and/or the bottom of the foundation and travels back along the foundation to the top.
the receiver measures the vibration response of the foundation to each impact. The data collection platform
‘acquires, processes and displays the receiver ouputs. Foundation length and integrity of concrete are
‘evaluated by identifying and analyzing the arrival times, direction and amplitude of reflections measured by
the receivers in time. The Eco Depth (0) is calculated by multiplying the reflection time(t) by the compression
‘wave velocity(V) and dividing this quantity by 2 to account for the fact that the wave has gone down and
reflected back, ie. D=V"t/2.
‘Analysis of the length determination and the integrity evaluation of s foundation with the SE method is based,
‘on the identification and evaluation of reflections. Test results are analysed in the time domain for the SE test.
‘The SE test method Is sensitive to changes in the shaft impedance(shaft concrete area*velocity*mass density
where mass density equals unit weight divided by gravity), which case the reflections of the compression
‘wave energy. Compression wave energy(hammer impact energy) reflects differently from increased shaft
impedance than from decreased shaft impedance. This phenomenon allows the type of reflector to be
identified as follows. Soil intrusions, honeycomb, breaks, cracks, cold koints, poor quality concrete and similar
defects are identified as reflections that correspond to a decrease in shaft impedance. Increases in the shaft
cross-section or the competency of surrounding materials such as bedrock and stiffer soil strata are identified
{3s reflections corresponding to increases in the shaft impedance. A decrease in impedance is indicated by a
downward initial break of a reflection event in an SE record and frequency peaks positioned in 2 record such
that a peak could be extrapolated to be near OHz in the mobility plot. Conversely, an increase in shaft
impedance is identified by an upward initial break for an SE reflector.
‘When length to diameter ratio exceeds 20:1 to 30:1 for shafts in stifer soils/bedrock. the attenuation of
compression wave energy is high and bottom echoes are weak or unidentifiable in SE test results. if the shaft
is embedded in a material which has similar impedance to that of the shaft, it may not be possible to see @
reflection from the bottom of.the-shaft,
5|PageProject: Construction of Sansarimai Khola Bridge Along Kalayia-Prashtoka Road,Bara
Contract No.: IDO/PAR/NCB/BRIDGE-25/077/078
Location: Sansarimai Khola, Kalaiya, Bara. (Left Abutment) Date : 2078/11/19
Velocity ofthe pile top surface isin most instances the most important data collected during 2 pile integrity test. It
requires a light hammer impact and the recording of acceleration. In order to obtain an accurate record of the pile
top surface motion the location where the acceleration is measured has to be a sound, clean pile material
‘Contamination by soil, loose debris or surface layers, poorty hardened pile material a very rough surface are
‘among the conditions that provide poor records which are difficult or in most instances impossible to interpret
clearly. Obviously, the concrete has to be hardened to a point where itis much harder (or having a higher elastic.
‘modulus) than the surrounding soil
For clean impact pulses without ringing of other spurious signals the impact surface also has to be of clean and
preferably smoothened. Thus, grinding down to good concrete several impact and accelerometer locations is the
best assurance to obtain meaningful results. t saves on data interpretation time and/or a repeat trip to the site.
‘The accelerometer should be bonded to the pile top surface with a thin layer ofa “sticky” material. Depending on
pile temperature and/or moisture content, different materials may have to be tried. Under no circumstances
should a thick layer of bonding material separate the sensor from the pile material. In fact, pressing the
accelerometer down far enough until one feels it touching the concrete makes for the best records,
Ideally, the hammer impact would cause the whole pile diameter to achieve a uniform axial motion. However, only
a small pile top area is subjected to the impact causing a non-plane deformation of the pile cross sections below
‘the pile top. Thus, testing on the westside of the pile top will not reveal what is happening on the east side within
one or two pile diameters below the pile top and for larger pile it is therefore strongly recommended that the pile
top is tested and impacted at several locations. Ideally impacting and testing is done at the third points of the pile
‘top surface. The worst location for testing is the edge of the pile,
However, the larger the pile diameter the greater the motions generated at the pile top by shear (or Rayleigh)
waves. These pile top motions may appear as noise in the basic compressive wave record. Spurious record
components can also be created by reinforcement extending above the pile toe or small cracks within a short
distance below the pile top. Larger hammers or more cushioned hammers possibly improve the record appearance
in such cases.
Longer ples produce weaker pile toe signals than shorter ones because of losses of wave energy due to pile
internal or soil external damping. However, hammer impact pulses with lower frequency contents (those that have
longer lasting impact pulses either because of a greater hammer weight or a softer cushioning) travel longer
distances with less energy dissipation than those that are sharper
‘And shorter. Unfortunately, the smoother longer pulses do not allow for as clear a resolution as the sharper ones.
Itis best practice, therefore, ta test with several hammers, for example, using hammer weights of 5, 10, 30.N (0.5,
11, and 3 kg or 1, 2 and 6 Ib) for more and clearer information,
6[PageProject: Construction of Sansarimai Khola Bridge Along Kalayia-Prashtoka Road,Bara
Contract No.: IDO/PAR/NCB/BRIDGE-25/077/078
Location: Sansarimai Khola, Kalaiya, Bara. (Left Abutment) Date : 2078/11/19
6. PILE DETAILS AND DATA COLLECTION
‘The Pile integrity Test was conducted at Sansarimai Khola, Kalaiya, Bara. The pile graphs had
measured diameter of 800 mm and was reported of having depth of 18.00 m at Left Abutment
which is the basis of this report.
20 piles were tested from foundation at 18.00 m at Left Abutment from the PCC
level.
Respective Engineer and technicians were on site in order to perform the PIT test from 2078-
41-04 to 2078-11-05. All field records were transferred to computer at office. Then necessary
filtering, magnification was done to data and corresponding velocity curves were plotted. The
shafts were processed using a concrete wave speed of 3400 m/this to 4000 m/s range of wave
speed variations (as the lower range of wave speed was recorded) is within the +/- 4% which may
be encountered at site.
TlPageProject: Construction of Sansarimai Khola Bridge Along Kalayi-Prashtoka Road,Bara
Contract No.: [DO/PAR/NCB/BRIDGE-25/077/078.
Location: Sansarimai Khola, Kalaiya, Bara, (Left Abutment) Date : 2078/11/19
7.LIMITATION OF PIT
Limitation of Pile Integrity Test are as follows:
1) Pile Integrity Test does not provide any information on the load bearing capacity
of piles and deep foundations.
2) Integrity Testing cannot be conducted over pile caps
3) Integrity testing of cross sections below a major crack (that crosses the entire
cross-sectional area) is not possible.
4) This test is not effective in piles with highly variable cross sections.
5) Itis not effective in evaluating sections of piles below cracks that crosses the
entire cross-sectional area of the pile.
6) Pile integrity is generally not suitable for testing steel sheets, H-section, or
unfilled pipe piles.
7) When the toe reflection is not evident, integrity evaluation may not be
conclusive.
8) In some cases, its difficult to distinguish the soil response, and the (pile) toe
response.
9) Presence of water in site during testing affects good data acquisition.
‘The records were evaluated for reflections from the shaft toe and for variations in the
impedance above the shaft toe
‘The depth accuracy may vary from +/- 4% due to site conditions or human error or machine error
Bl PageProject: Construction of Sansarimai Khola Bridge Along Kalayia-Prashtoka Road,Bara
Contract No.: IDO/PAR/NCB/BRIDGE-25/077/078
Location: Sansarimai Khola, Kalaiya, Bara. (Left Abutment) Date : 2078/11/19
CONCLUSION:
‘The wave speed for this report is from 3400-4000 m/s. 20 piles were tested from PCC level. The
concrete grade is M25.
From above report it can be deduced for Left Abutment the maximum diameter is 1.13 at 5.44 m of
pile 19a, The minimum diameter 0.89 at 6.80 m of pile 1. The maximum depth is found out to be
118.35 m of pile 3a and minimum depth is 17.60 of pile 8b.
‘The PIT as stated above has many limitations also the field conditions and technicians are
responsible for quality of the data taken. Also, PIT doesn’t give any information regarding the
bearing capacity of the pile. It only gives the structural integrity of the pile structure.
Considering all of these no major cracking was observed in the field data. Slight bulging of piles was
observed. As per International Journal of GEOMATE, July 2018 vol 15 and DOR requirement the
beta analysis is within the limits.
Keeping in mind the relevant code that has been followed and the guidelines of 1S code and
ASTM code it can be safe to say the 20 Piles recorded do not show any major defects.
9) PageAPENDIX-A: PIT
QFV Instruments
and Pictorial
Representation of
the test1A SANE
(sav) suo sire A
(su ova) w sees eo 50
—r00
| I
. a 2hO
Mid Brivo: zeoeaue spud
‘SHWE b Dd ceil
26002 eIold i rH Valid
2z02/91/2 ‘payayoy bid eld ay
ez0zeie ‘PHT Ag JINSUOD eMs|A,worere ‘yale uM
960
Wwoo01 001 :eubid xen
00: seany "onsisu0g
004 :10A yonAsUeD
850 "TOA SMBH
(ave'0) snuo vBV0 A
mH Lu8e wory yoonenn
Ne Sr'soie 2e02/9H2
26002 80d
2z0ZI9LIZ ‘PaWAIOD
zz0z/ere
azaid
Q@ Fld 29d AV
‘PHT a aNsUCO BMSIA,weost e960 tHo%d wi
‘WQ0'018 00" :euOle ¥EVN
Oot seaxy pmsueD
OO #10A yonsU0D
96
fon eneeu
ws |
180 \
°
ea
+ fi
wby
(esz0) suo esz0 A (sw oore) w seat aio i
|
—s00-
|
i —s00
> aro
Wa Heco:e zz0er94e sub
zw:0-PC aTId [Olle
76002 Aid : eae
Zz0z/94/2 ;PAIEIIOD beeper
pr Wad UNSUOD EMsIA
zzoziere‘yas Ue
‘
Wirrie sot eyoid xen
Oot seeny voneuen
(001 H10A ‘pAHsueD,
Zot ejaMeey
(209) $49 veLZ A (sy oove) ws oV'@H! ated soe
|
“a
ot
18
Wa ¥9:80: zz02/0172 ial
S#¢-9p aid :0lld
6002 aNOId raid
ZZOZI9LIE ‘PEDALS,
zzoziee
2p ald “ld ay
“PHL Ad UNsUOD EMSADOL :1eA vensisu0D
950 “TOA aNIEeR
I wos
i 160
°
' eed
+ 1 ToT t
I woe we = wos SE :
(ror'0) 80 v6K'0 A: {enw oore) w 0z84 Sead ae 10
i
+120
Wn ogee zz0z/01 sun
Twounngy y= bea e-a9 311d 20d
26002 140d 9g Fld
COLLIE PeAIOD 9g aiid ad av
zeousele
PLT Td JIMSUOD EMSA,wgorieeso elves uv
UIEDEI OL ood xe
004 ayy yonisu0D
(00's "eq yonasu09
560 "TON eneeH
listo) sau esr0 A.
Wid oo 8e°4 zz0er9/e
waunnay Wer
26002 Sod
ZzOZI9LIZ ‘DEI
ze0ziele
lew e-e9 31ld “elle
100
sy 700
e9 31d
29 Fld Ald 9ay
PIT Vid aNsUED EMSIA,weer e60
Wor 00
00)
oot
180
wen wre
lo
=
:
t ott ttt
Sea
(eve'0) SMD EEO A (Snu Ove) WOO'SL 986°0 860 650 ‘460 950860 zz
i
1
a
sla
iif ivbeseowiate aus
sheers ceoss-peawaiond
2-600 B1YOld PL ad
ZzOzIOLIe ‘Pee
zzoziere
PL Ald ‘ltd 'oay
‘PIT Ae HNSUOD EMSA,wizztie 160 eho
wzg pie cot “Odd xe
00°4 ay YonNSUID
zvo) 2 120 A
(su oose) 1 09°24
aqua?
a Love zzo291
Tusuanay 1246-48 ANd ‘ll
26002 101d Hi i a3 Sid
zZOZIOLIZ PEED ee ak
Feozere PIT Ad JINSUOD EMSIA,wggzieoot — “ouoid UW
weLere SO eivald xen
(Oot seary wonasu0D
001 “10A vonsisu0D
yO "WA @MBOH
(zv'0) $140 0¢+'0 A (srw ove) w 00°84) v0
—s10
“sro
9r0
WW eOPL:2 ZzozIshe a
ce €- G6 Fld ‘ltd
96 ad
96 31ld lid ‘Sav
ze00e Bod
ZZOZI9LIZ PAID
zzoziee
“PIT Wad NSUED EMSIAea
1 T :
wou way |
(i¥00) sto o»00 A (snaore) wove 160 $60 i
—sr0-
| |
500
i 300
mowiz — wow reronem “svo
Wha ion zz0zre12 aie
weuandy ve 6420-80 Bld lle
EE 201 ald
20} 31d ‘ld ‘OV
IT Wd ¥MSUOD ENSIA
F800 S1NSid
zz0z/91/2 PaHeIOD
ezozserewep of
tyoid
ayo EW
Go swany vnasu09
OO “Ion nnsu0D
960 "1en@nEIee
ozo) sme 2670 A
(srw gore) w oo Bt
ae
| —s00-
—90
abo
wa es:ieu ezozene ane
wounay We oee-Gh) ald Od
F6002 SHOld
Zz0UISb/Z ‘PAPAICD aL atid
TZOCEIE ‘PIT Wd UNSUOD EMS!TOA Yonutsuoy
@izo suozizo A
Ne Lee 2202/01
wuauangy Ye
wen |
380 |
°
weg
tt ;
wewes
(1 00¥6) 06:28 96.0650
oro
no
0
|
|
ua”?
ee -GZL ad 20lld
Z-600e A0Id
ZzOzIgLIe ‘Pee
zeoziee
et Td
ZL 31d “lle '9av
PIT Wad YNSUED EMSIA,“Stole WN
680
weer zo) oid xen
05 :eary venssv00
(001 0A verwsv0D
Oot Ten anneee
i eg
t b
| woo
(e1v0) sma eivo A (nu pore) w 5624! 650 Pee
| oe:
|
! ovo
(
| ovo
|
|
meee = wo90 orem eo
Wa es'6r 2202/012 ”
‘waunngy 4= ee ic- GEL Bd lle
E8002 ayoid ‘Ge 311d
Zz0zI9LI ‘PaaS
zeozieie
el ld ‘eld ‘9aV
PIT a UNsuED EMSA,(020) su voz'0 A
oro
—s00
I 00°
i
i
i
(smu ove) w 00 @1
910"
Wid se'geu ze0zoVe we
‘wounngy 47 se#¢-GpL TTId lid
E6002 aW0Id ‘Oph aid
220Z/9H/Z ‘PaAIOD pL Fld ld 9qv
zzozsere YT Aa jinsuog ems,wos
oo
t °
I Pe
1 iat ete, ;
wg wer wee, Sor woss worwez
G4v0) su2 140 A——— (euoore) woes) 980 860 OHO 9600 650 850 eee
soo
—s00
|
oro
sno
wa vee 2202/1 Mu
‘wouanay vr cow e-QSL Td Old
ast aid
26002 S0Id
Zz0z/9L/z ‘Pa!eaOD
zzose/e
G1 31d ‘elld ‘oay
"PIT 3g INSUOD EMsIA,Tob "eA ante
| wrol
| 980 i
I °
ea
T 1 i
(00) 8740 5020, ——— woot
4 <0
(1a ne) wor ai
\
|
coo
|
00
* ea
00
wa ose zeozne sus
wounnay We) se '¢-B9) Bld “elle
01 Fd
26002 SHOld
ZZOZ/OLIZ ‘PAINCD
zzozrere
29) 31ld lid OAV
PIT Ad YNSUOD EMsIA,wep
waver aso “aod wn
Wyle LOL ood xeW
D0 seary vonwsued
| eee
| to
(ecz0) sno 9020 A ceo ‘S60
z | 960
| ae a)
| |
| —100
i
(su 000s) woos
aH Pe woot reionenn +90
wa eziozie 2207/92 sal
wouanay Y= se w'e-QLb ald 20d
600 Sold pole
ZZOZ9LIZ P2ANCD
zzoziele
LL ad id av
“PHT Ina tInsUoD EMsIAst o
OR aaneiou
(sro) suo esto A (sn ose) w oo 8b
|
|
: ; ah
| |
I |
i |
| | —se0
|
ti
|
| —eeo
| |
|
|
we
5
wa zzz ez0z/eue oe
veauninay Y= 61 #°¢- PBL Bld 20lld
76002 @1Od - 8h Tid
IL/z ‘PRIOR|IOD 81 Tid eld ‘av
eevee on hea trsieg enonwopove 00+ auld UI
Ot “Ten antes
(es0'0) snue gg00 A
8
1 T ;
\ gut wee |
a 0 950
(score) 00 cs
1 lege
240058 wio0z yeronenn a)
Wie bois 2202081 swe
nueuanay We LL: B6L Fld 29d
76002 ed 86 Tid
861 Fld ‘Alld ‘Odv
2z0z/91/2 ‘PAPAIOD
zz0z/ee
"prT Wad ANSUOD EMSIA,were
woeeie 960 “ayola uN
woeSIE LOT ood xen
00+ eany yonvjsu0p
901 "TeA ypnuisU0D
660" TPASNIOIRL
(2500) sno e600 A
(score w 00 i
ao
|
1 HO
ae ws
rasan a
27-6002 A}Old 902 Sid
2ZOZ/OL/Z ‘PROD 90Z Fd Ald ‘ay
ez0z/e/e
YT Ad NsuoD eMs!A,APENDIX-B:
SummaryOre
(acy 395 sea} yer0 30 96ys wos Aven Aes 19) a4 J 4AOp 94: 3LON
—worswe0 [arse mt J
cost | _wazereoot | _weszrvesot |
cost] _werewaso | wrcewrot |
oer | worstwaso | _wasceeot |
arena [—azrereceo | eset |
wmmgr [-esereyy Af Yes pourgunfreseN gj) ¢ AOHDEAHUOD,
outvscot : ea wsang‘funig 99yJ0 Wwoudojpsag aumonsystsuy
mung'proy Eoystad-eIepey BuoLY apg wOUN HuUNLESUES Jo WoHIMASHOS + 199ford
Joys ATeuMNg
OSTEEHE-I-LLG *X¥A 9S)
npueuney “ezequITC “91h X08 “O'd
“GLT “LAd LTASNOO VMSIAIt fs assumed that the wave transmission is one-dimensional. This requires that the ple is long
‘compared withthe diameter. For large diameter shafts, a defect near the tcp might be missed ifthe
‘accelerometer is attached far from the defect, and thus several locations for each large shaft should
be tested. The PIT units with the force-measuring option allow better defniion of shaft properties
‘ear the top of the shaft during the width of the hammer signal, and thus is @ definite improvement
‘over systoms lacking this capably (s00 also a. above.)
It should be clearly understood that the main purpose of this test is to locate piles with serious
defects. Minor defects could easily be missed (and may not be important anyway to the overall load
Carrying performance ofthe pile shaft as the soll resistance is usualy the limiting factor inthe pile
cepacity)
Classification of PIT Records
‘Adopting @ cassificaton system forthe PIT records is highly recommended, both as a guideline to
‘inal nterpretaton and as an indication ofthe capabilites and limitations ofthe method. Diferent
Classification systems have been adopted by codes and specifications around the world. The
Classification system below is provided 2s an example only
‘AA Sound shaft integrity indicated: a clear toe reflection can be ideniied corresponding to tho
reported length and wave speed within acceptable range: records in this category may indicate
normally accepted variations of size or material quality.
AB _No major defect indicated; the records indicate neither reflections from significant
reductions of pile size or material quality nor a clear toe response. Records inthis category do not
sive indications of a significant deficiency, however, nelther do they yield posite evidence of the
‘haf being lawless over its full length.
ABX No major defect indicated to a depth of x ft (mm). because of method limitations
interpretation of the record for the full length is not possible. For example, long pies or shafts and
‘those with high sol resistance and/or major bulges fall under this category
PFx Indication of a probable flaw at an approximate depth of x ft (m); a toe reflection Is
‘apparent in addition to at least one reflection corresponding to an unplanned reduction of size or
material quality. Additional quanttative analysis may help identify the severity of the apparent flaw.
PDx Indication of a probable defect at an approximate depth of x ft (m; the records show a
strong reflection corresponding to a major reduction of size or material qualty Occurring, a clear toe
reflection is net apparent.
Vx _Inconelusive record below depth of x ft (m) due to spurious vibrations; data is
inconclusive due to vibrations generated by construction machinery or heavy reinforcement
‘extending above the pile top concrete; retestng is advisable under certain ckcumstances,
IR inconclusive record; data is inconclusive, possibly for reasons such as:
* poor pileishaft top quality or low concrete strength (lest has been conducted too early);
retestng after walting and/or pile top cleaning is advisable,
‘planned impedance changes or joints generate signals which prevent toe signal
‘entfication.APENDIX-C: Photo
Caption(@39NGNOD ONI3E 1S3L ALIHDAINI 31d
‘S3AILVLN3S2¥d3¥ YOLDVYLNOD ONY NOISIAIC 4O SON3SRNd 3HL NI G3LINGNOD ONI3S 1S3LG219NGNOD ONI3E 1531 ALIYOIINI Tid