Download as pdf or txt
Download as pdf or txt
You are on page 1of 51

UPC – School of Civil Engineering

Master in Structural and Construction Engineering


FOUNDATION STRUCTURES

DEEP FOUNDATIONS
FOUNDATION STRUCTURES
Deep foundations 2

INDEX
STRUCTURAL ASPECTS OF DEEP FOUNDATIONS

1. TYPES
Resisting schemes
Dimensions (diameter)
Materials
Construction procedures and detailing

2. STRUCTURAL ELEMENTS AND ORGANIZATION

3. PILE DESIGN AND STRUCTURAL VERIFICATION


Vertical actions
Horizontal actions
Maximum structural capacity for the design of piles

4. PILE CAP DESIGN AND STRUCTURAL VERTIFICATION


Rigid and flexible pile caps
Strap beams
FOUNDATION STRUCTURES
Deep foundations 3

1. TYPES

MAIN RESISTING SCHEMES

Shaft friction pile End-bearing piles

Pile cap

Terrain with
Soft soil
increasing
resistance
in depth

Load-
bearing
soil
FOUNDATION STRUCTURES
Deep foundations 4

DIAMETER

Micropiles 0.08 m < φ < 0.25 m


Medium diameter piles 0.25 m < φ < 0.80 m
Grand diameter piles φ > 0.80 m

MATERIAL

Shaft:

Steel (steel profiles, empty or


filled tubes)
Concrete (precast, in situ)
Composite (steel profiles
with concrete)
FOUNDATION STRUCTURES
Deep foundations 5

CLASSIFICATION BY CONSTRUCTION PROCEDURE

Driven piles (displacement)


The soil is displaced according to the equivalent volume occupied by the pile. The
soil is displaced radially as the pile shaft penetrates in the ground. First, the
terrain moves up and afterwards the soil is laterally compressed and the pile is
strongly confined. The soil will generally improve due to the compression effect of
the pile.

Bored piles (non-placement)


The terrain is excavated previously to the execution of the pile. The lateral stresses
in the ground are reduced during the excavation and only partly reinstated by the
concreting of the pile.
FOUNDATION STRUCTURES
Deep foundations 6

CLASIFICATION ACCORDING TO CONCRETE STRUCTURAL TYPE


(PRECAST / IN SITU CONCRETE)

Precast piles
They are transported from the factory and are embedded into the soil by
percussion (dropping weight), vibration, with hydraulic jacks or by placing them
in a previous excavation.

“In situ” piles


They are executed in a previous excavation in the terrain. They can be driven
(with pyramidal/conical pile toe, by Franki method, by rotation); bored (with
recoverable casing, with lost casing, without casing but with thixotropic muds);
and auger drilled (without casing, concreting by a central tube in the drilling).

Franki píling System: pressure-injected method used to create expanded base


of cast-in-situ concrete
FOUNDATION STRUCTURES
Deep foundations 21

2. STRUCTURAL ELEMENTS AND ORGANIZATION

Distribution and function of groups of piles, pile caps and strap beams
FOUNDATION STRUCTURES
Deep foundations 22

Normally more than a pile is necessary to receive the load of the pillar and
distribute it to the soil.

The function of the pile caps is to distribute the load of the pillar among the
piles and also to stiffly tie the piles and stabilize them laterally.

The function of strap beams is double: stabilize laterally the pile caps and
avoid the separation of the pile caps.
FOUNDATION STRUCTURES
Deep foundations 23

USING STRAP BEAMS

Strap beams are necessary to grant lateral stability in caps with only one or two
piles. They may be also convenient (even if they may be not strictly necessary) in
other cases.
FOUNDATION STRUCTURES
Deep foundations 24

EXAMPLE OF DEEP FOUNDATION IN A BUILDING ( BASEMENT LEVEL)


FOUNDATION STRUCTURES
Deep foundations 26

DEEP FOUNDATION OF A WALL

Piles distributed so that


they are not placed in a
single vertical plane to
avoid lack of lateral
stability.
FOUNDATION STRUCTURES
Deep foundations 27

3. DESIGN AND STRUCTURAL VERIFICATIONS OF PILES

CALCULATION OF FORCES IN EACH OF THE PILES CONNECTED TO A PILE-CAP

A pillar can apply on a pile cap a vertical force plus two perpendicular moments (in
addition to possible horizontal forces). For the calculation of the vertical forces
experienced by the piles, the pile cap is assumed to be very stiff compared with them.
For a very stiff pile cap, the forces will distribute according to an inclined plane.
FOUNDATION STRUCTURES
Deep foundations 28

DISTRIBUTION OF FORCES IN PILES CONNECTED TO A SINGLE PILE CAP

Case of vertical piles

y ex

ey
O
x

= point of application of vertical load in plan


O = axes origin (reference point in the center of the plan)
FOUNDATION STRUCTURES
Deep foundations 29

Fv My=Fv ex, Mx=Fv ey

Solution for a rigid pile cap:

Fv Mx My
Fiv = + y + x
n ∑ yi 2 i
∑ xi
2 i

n = number of piles
x, y, distances with respect to
reference point O

Fiv
FOUNDATION STRUCTURES
Deep foundations 30

Piles subjected to vertical and horizontal forces and with different transverse sections:
FOUNDATION STRUCTURES
Deep foundations 31

Example of the variation of the bending moment diagram along of the shaft of a pile
subjected to axial and horizontal force.

Horizontal forces will generate


bending moments along the shaft
of the pile

The bending moment will vary


along the shaft and will
experience a reduction in depth
(see figure)

Example:

Diameter of 450 mm

kb= 10000 KPa

fck= 25 N/mm2
FOUNDATION STRUCTURES
Deep foundations 32

INDIVIDUAL PILE- STRUCTURAL MODEL


(1) SHORT PILES (< 10m)

MODEL 1 MODEL 2

• End bearing piles • Floating piles


• Bored Piles • Other cases, without minimum
• Fixed in gravel and dense sand embedded length into resistant soil or not
• With minimum embedded length into resistant soil fixed at bottom into gravel or dense sand.

• The top end of the pile can be considered fixed (constrained rotation) if the pile cap
and the connection between the pile cap and the pile are rigid.
• Minimum embedded length= 6Ø in cohesive terrain, 8Ø in uncohesive terrain
• The effect of buckling must be considered always (and especially in the case of
end-bearing piles)
FOUNDATION STRUCTURES
Deep foundations 33

(2) LONG PILES

The effect of the lateral confinement in the soil has to be taken into account
Consider always buckling (and specially in the case of end-bearing piles)

POSSIBILITIES:

(A) Model the confinement of the terrain as a lateral springs system (Winkler model)
u
F
F = Ku
s
K = sØw Ø=pile diameter

w = coefficient of ballast [N/m3]

(B) Estimate a reduced bending length through empirical formulas


For constant module of clays (E) in depth:
(Ep= Young modulus, Ip Moment of inertia of the pile section)
FOUNDATION STRUCTURES
Deep foundations 34

TENTATIVE CRITERIA FOR PILES SUBJECTED TO HORIZONTAL ACTIONS


If H < 0,05V - horizontal forces may be neglected
If 0,05V < H < 0,10 V - they may be resisted by the piles working in bending
If H > 0,10 V - inclined piles, anchors or passive pressure systems may be necessary

CASES: M V
H
INDIVIDUAL PILE

Fixed or pinned
FOUNDATION STRUCTURES
Deep foundations 35

GROUP OF PILES - CALCULATE AS AN EQUIVALENT FRAME

L ó L’
FOUNDATION STRUCTURES
Deep foundations 36

GROUP OF INCLINED PILES– specific method

ex
y

ey
x

Usually, inclination of the pile< 20º


FOUNDATION STRUCTURES
Deep foundations 37

Fh
Fv Mx=Fvey, My=Fv ex

Fih=Fiv tg(βi)

βi
Fiv
βi
Fi

Fiv
Fv Mx My
Fiv = + y + x Fh = ∑ Fiv tg ( β i ) (βi with its sign)
n ∑ yi 2 i
∑ xi
2 i
FOUNDATION STRUCTURES
Deep foundations 38

DESIGN AND RESISTANCE VERIFICATION FOR A INDIVIDUAL PILE

DESIGN CRITERIA AND MINIMUM STEEL AMOUNTS


(according Eurocode 2, bored piles)

Design as a RC column working in compression and bending

Consider minimal eccentricity =max {Ø/30, 20 mm}

The Buckling Ultimate State has to be verified

A reduced diameter d has to be used in the design calculations.


It is determined as

dnom = nominal diameter, d = reduced diameter


FOUNDATION STRUCTURES
Deep foundations 39

The minimum steel amount depends of the pile cross-


section area (see EC2 clause 9.8.5 and UNE-EN 1536)

As,min = 6 Ø 16 – At least 6 longitudinal bars with minimum


diameter Ø 16mm

Maximum spacing between hoops = 40 cm


(transverse reinforcement)

Minimum concrete cover= 5 cm


FOUNDATION STRUCTURES
Deep foundations 40

Reinforcement detail Pile Cap Pile cap


In piles

Mud slab
Mud slab

Rebar spacer Rebar spacer

Individual hoops or helical


transverse reinforcement.
Transverse reinforcement
necessary to confine the
Vertical section Vertical section
vertical bars against their
buckling or to resist
possible shear forces.

Horizontal section Horizontal section


FOUNDATION STRUCTURES
Deep foundations 41

ALTERNATIVE APPROACH FOR THE PILE DESIGN AND VERIFICATION


ESTIMATION OF MAXIMUM STRUCTURAL CAPACITY
(Approach not recognized in geotechnical standards but commonly used in practice)

The maximum applicable load on a pile can be obtained as:


Te = α · fyk ·Sa + β · fck · Sb + χ · fyk’ · Sc

Where: Sa, Sb, Sc are the steel, concrete and steel casing sections
fyk, fck, fyk’ are the characteristic resistances of the materials.

Orientatively, the following maximum strength values may be considered:

Laminated profiles or tubes fyk= 400 N/mm2


Reinforcement of steel fyk= 500 N/mm2
Precast concrete fck= 40 N/mm2 Definitive
Precast concrete fck= 35 N/mm2 Provisional
In situ concrete fck= 25 N/mm2
FOUNDATION STRUCTURES
Deep foundations 42

α, β, χ are coefficients indicated in the table:

α β χ
• Steel
Profiles 0.35
Tubes 0.40 0.25 0.35
• Precast concrete 0.40 0.25
• In situ concrete
With lost casing 0.40 0.25 0.35
With recoverable casing 0.35 0.22
Dry, without casing 0.35 0.20
Using bentonite mud 0.32 0.20
Through auger drilling 0.30 0.30
FOUNDATION STRUCTURES
Deep foundations 43

In a simplified way, the structural capacity can be estimated by considering the


following admissible average stresses:

< 4.5 N/mm2 Wooden piles


7.0-11.0 N/mm2 Precast concrete piles
3.0-3.5 N/mm2 In situ concrete piles (under water)
3.5-4.0 N/mm2 In situ concrete piles (without water)
FOUNDATION STRUCTURES
Deep foundations 44

4. DESIGN AND STRUCTURAL VERIFICATIONS OF PILE CAPS

Flexible pile caps

v ≥ 2h v

h
FOUNDATION STRUCTURES
Deep foundations 45

If v ≥ 2h (flexible case) the pile cap can be calculated as a conventional RC beam

V Mf
FOUNDATION STRUCTURES
Deep foundations 46

The distribution or forces, the calculation criteria and methods and the
reinforcement details are the same as for a flexible footing. The ULS of bending,
shear and punching are to be verified.
FOUNDATION STRUCTURES
Deep foundations 47

Punching verification around pile. Definition of critical perimeter.

Overlap

Pile
Pile
Critical perimeter

Critical perimeter in punching for the


individual pile and critical perimeter, with
overlapping, of groups of close piles
FOUNDATION STRUCTURES
Deep foundations 48

Rigid pile cap

v < 2h
v

h
FOUNDATION STRUCTURES
Deep foundations 49

If v < 2h (rigid case) the general methods for calculation of beams are not valid.
The strut and tie method must be used.

(1) (2)

(1) Simple model, insufficient (risk of fragile failure due to excessive secondary
tensile stress).

(2) A detailed model which describes the opening of the bottleneck-shaped strut and
the necessary reinforcement to resist the secondary tensile stress. Horizontal
and vertical secondary reinforcement will be necessary.
FOUNDATION STRUCTURES
Deep foundations 50

Rigid pile cap on 2 piles- Calculation strut-and-tie model

Minimum depth H ≥ 40 cm N d (v + 0.25a )


=
z = 0.85d (d=effective depth, z=level arm) T1d = As f yd
0.85d
FOUNDATION STRUCTURES
Deep foundations 51

Model for moment applied on the cap in addition to vertical force (two
different forces applied by the pillar are considered)
The model works as the superposition of two basic models.
Take Nd as the maximum force in the two piles.
FOUNDATION STRUCTURES
Deep foundations 52

Main reinforcement (a) : T N d (v + 0.25a )


= 1d = As f yd
0.85d
When calculating with the strut
b and tie method take fyd ≤ 400
≥T1d /10 N/mm2

≥4‰
a
T1d
Secondary reinforcement: (b-c-d)
c
If the width exceeds half of the depth,
the reference section is taken with a
width equal to half of the depth in
≥4‰ order to calculate the minimum
amount of secondary reinforcement
FOUNDATION STRUCTURES
Deep foundations 53

Section A-A

Column Confinement hoops in


anchor zone

Piles

For large concentration of principal bottom reinforcement it is good practice to approach


the transverse hoops In the anchorage regions
FOUNDATION STRUCTURES
Deep foundations 54

Rigid pile cap on 4 piles

Compression
For different forces in the piles take Nd as
Tension
the maximum force
FOUNDATION STRUCTURES
Deep foundations 55

Main reinforcement:
Nd Nd
T1d = (0,50l1 − 0,25a1 ) T2 d = (0,50l2 − 0,25a2 )
0,85d 0,85d
The main bottom reinforcement is placed in bands over the piles
FOUNDATION STRUCTURES
Deep foundations 56

Secondary reinforcement: the


Main
reinforcement
minimum reinforcement capacity in
each direction is ¼ of the main
reinforcement
Secondary
reinforcement

Main
reinforcement

Strip width
Reinforcement
Secondary centroid
reinforcement Main
Main
reinforcement reinforcement

Secondary Mud slab


reinforcement
Pile cap
bottom bottom
Pile

The strip where the main reinforcement is to be contained


is defined as the line that connect the pile axes and has a
Main width equal to the pile diameter plus two times the
reinforcement distance between the pile top section and the barycenter
of the main reinforcement in the tie.

The secondary reinforcement includes horizontal bars


between strips and vertical transverse reinforcement
(hoops) confining the main reinforcement.
Section A-A
FOUNDATION STRUCTURES
Deep foundations 57

Pile cap for 3 piles (rigid):

Nd
=Td 0, 68 (0,58l − 0,=
25a ) As f yd
d

Compression
Tension

where Nd is the design axial force for the most loaded pile
FOUNDATION STRUCTURES
Deep foundations 58
FOUNDATION STRUCTURES
Deep foundations 59

Pile caps on multiple piles


The vertical secondary reinforcement in rigid pile caps on multiple piles is
calculated with reinforcement capacity ≥ Nd/(1.5n) (n= number of piles ≥ 3)
with Nd equal to the axial force applied by the pillar.

The role of the secondary vertical reinforcement is to resist the secondary tensile
stresses produced by the opening of the diagonal struts. The minimum reinforcement
is provided to resist force T2d (assumed equal to 0.3Cd with θ=45º)
FOUNDATION STRUCTURES
Deep foundations 60

Deep foundation for running wall

Principal and secondary reinforcements are needed.


FOUNDATION STRUCTURES
Deep foundations 61

Reinforcement anchorage and construction details in rigid pile cap.

40cm
h min ≥ 
 φp

Vertical
h anchorage

≥ 25cm

Anchorage by
welding
Øp
Bar spacing ≤ 30 cm
φbar ≥ 12 mm
FOUNDATION STRUCTURES
Deep foundations 62

PILE CAPS REINFORCEMENT DETAILS FOR MULTIPLE PILES

Moderately loaded Heavily loaded

Three piles

Reinforcement
along sides

Reinforcement in strips

Four piles
Reinforcement
along diagonals

Reinforcement in strips
FOUNDATION STRUCTURES
Deep foundations 63

Five piles

Reinforcement in
strips

Reinforcement
Reinforcement distributed in star
in strips

Six piles

Reinforcement in strips

Reinforcement along diagonals


FOUNDATION STRUCTURES
Deep foundations 64

Example of reinforcement detailing for a cap on two piles


Column reinforcement

Pile reinforcement
Mud slab

CUT B-B CUT A-A


FOUNDATION STRUCTURES
Deep foundations 65

Strap beams
Nd Nd

Md Md

Width: b>l/20
Depth: h>l/12

M1d=± (Md+Nde) V1d=M1d/l


M2d=± ql2/12 V2d=ql/2 q=10 kN/m

As=As’=Md/d’
FOUNDATION STRUCTURES
Deep foundations 66

BIBLIOGRAPHY
J. M. Rodríguez Ortiz, J. M. Serra y C. Oteo. Curso aplicado de
cimentaciones. COAM, Madrid, 1989

T. Davidian. Pilotes y cimentaciones sobre pilotes. ETASA, Barcelona 1982

J. A. Jiménez Salas (y otros autores). Geotécnica y cimientos (3 tomos). Ed.


Rueda, Madrid, 1980.

Technical standards

• EN 1992-1-1: Eurocode 2: Design of concrete structures


• EN 1997-2 -Eurocode 7: Geotechnical design
• EHE - Instrucción de Hormigón Estructural. Artículo 58º. Ministerio de
Fomento, 2008
• Código Técnico de la Edificación – Documento Básico SE-C – Seguridad
estructural Cimientos
• Normas Tecnológicas de la Edificación – Cimentaciones - Pilotes

You might also like