TOPIC 4 : PILING
by
azwani@utar.edu.my
Ms. Ibtisam Azwani Room 46, zone 2,
level 8
Precast prestressed
concrete sheet piles
● Precast concrete sheet piles
Steel H-piles Interlocking steel
Steel pipe piles sheet piles
• Concrete Pouring
caissons
M3
M4
Depth driven shall be measured from
the cut-off level to the toe level
M5
The concrete lengths of cast in place
concrete piles shall be measured from
the cut-off level to the toe levels.
Sample description:
Sample description:
Moving and handling of all piling plant and equipment within the Site
and from location to location as often as is, and whenever necessary
for the execution of the whole piling operation.
Sample description:
Bored Depth
Toe Level/bottom
driven
Bored Depth
Rock
Toe Level/bottom
driven
HOW TO MEASURE BORING THROUGH ROCK
MS. IBTISAM AZWANI
H2*3: BORED PILES – permanent casing-
m
H2*3 : permanent casing (if applicable or stated in
drawing)
•D1 – Usually permanent steel casing classified as driven cast in-situ
piles where the piles are designed for the load to be carried on the
concrete
•A12 – in description for permanent casings, state materials,
thickness and details of treatments and coating
Permanent
Permanent casing for
casing for bored pile
driven cast in
situ
12Y12 – 450
H = pitch (spacing/centre to
centre)
L = 0.7728m
Jointing in
number
(nr)
H261-Supply length
A4- Shall identify in description initial or extension piles.
Detail for driving head and shoe shall be so stated in
description
Initial pile
Extension pile
Supply length =
35.00 – 15.00 =
Depth driven
20.00m
Toe Level
TL= 15.00
0.00
6.00
Supply length =
35.00 – 15.00 =
6.00
Depth driven
20.00m
9.00
Toe Level
TL = 15.00
Example
Supply length for initial pile used 9.00m long
Supply length for extension pile used 6.00 long
Depth driven =
35.00 – 15.00 Supply length
– 0.60 =
19.40m
Toe Level
15.00
0.00
6.00
Supply length =
35.00 – 15.00 =
6.00
Depth driven
20.00m
9.00
9.00
Toe Level
15.00
Example
Supply length for initial pile used 9.00m long
Supply length for extention pile used 6.00 long