Professional Documents
Culture Documents
Development of West Cliff Extended Project
Development of West Cliff Extended Project
EXTENDED PROJECT
By
K. TALBOTI
r ----- :
(
,
PACIFIC
OCEAN
SEA
LEGEND
MIiTAGONG
LOCALITY PLAN o 20
._------- FIGURE
The mine has not achieved planned 1980 Darkes Forest Mine, 3rd
production levels due to market Prize, Wollongong
constraints. Gardening Competition
West Cliff Extended Mine is being (Industrial Section)
developed to extract coal reserves
1981 Darkes Forest Mine, 2nd
located in the eastern sector of the
Prize, Wollongong
current West Cliff Mine Holding. The
Gardening Competition
proposed mine would also share a
(Industrial Section)
common boundary with Darkes Forest
Mine Holding. West Cliff Extended 1982 Darkes Forest Mine, 1st
Mine will provide replacement capacity Prize, Wollongong
for Coal Cliff Mine and ultimately Gardening Competition
additional capacity to meet long (Industrial Section)
term market demand.
GEOLOGY
The new mine is being developed
The proposed West Cliff Extended
in two stages. Development works on
Lease contains about 51 million tonnes
Stage I commenced in January 1982
in situ of high grade coking coal
and consist of the sinking of two
from the Bulli Seam. A total of 14
shafts to the Bulli Seam, associated
boreholes were sunk to prove the
seam development and gas drainage
reserves. The geological programme
works. Stage 11 consists of the
was also assisted by various seismic,
upgrading of the project into a
resistivity and magnetometer surveys.
separate operating mine capable of
The premium coal seam in the
producing up to 2 million tonnes per
Illawarra measures is the Bulli Seam
annum of run-of-mine coal.
which is the uppermost seam. Depth
Kembla Coal and Coke is justifi-
of the Bulli Seam is about 460m.
ably proud of the environmental record
The reserves are suitable for
achieved at its mines. For its high
continuous miner and longwall
environmental standards, the Company
operations and will support efficient
has been awarded various environmental
productivity levels. The pit bottom
prizes:-
area is being developed under
1977 West Cliff Mine Pollution
competent sandstone roof.
Control Abatement Award,
All projected geological faulting
2nd Prize, awarded by the
is oriented in a north-west south-east
Minister for Planning and
direction. The throw of the faults
Environment
range from 60m in the Stokes and
1979 Darkes Forest Mine, 4th Scarborough Faults down to 5m. The
Prize, Wollongong Gardening Stokes Fault and Scarborough Fault
Comp~tition (Industrial will provide natural lease boundaries
Section) to the west and the north respectively.
AC"7JVITY J 9PC
---
HPJ
- -
J 9£~
A
J I' ~ ~ J J
"5 o " D J I' ~. " ~ .J J A 5 0
I
" D
J F ~ 1< ~ : J 1< f
Co "
D
Develooment Consent
I I
I
Conpilation of E.1.5. -- I I
I
Site visit. - D.E.r.
,.ollondi J ly Counci 1 • . I
I I
I
Accej) ance of E.1.5. by
-l- I
I
D.E.P.
I I
O<"ve]opment. Application
lodged I
. I
I I
Advcrti6ing E.1.5. I - I I
·E.I.S. placed on
publlc dispJay
I - I
,..I I
I
Com=,i]a~ion of Environ-
mental Impact Assessment :tl
I
I
. D.E.P.
~
Pl:bl1~
(\0,'01
Inquiry
J on gong )
'"
~I
<::
..I
.~ w
v.
<:.
j
Cor:-l ssicner' ~ Report on '-' ,..j ~c
:;1
PUt:-llC Inc;'u~ry
~ ~
z
~I ..
~'"
Granting of Development
Consent Do
..,\ ~
....<::Z! '1 ~
::JI
l':~nina Pt;rooses Leases >:
I I
Ap;:-lications for
.M.P.L. 's lodged
. z,
gl
~I
I I
I
Notification of Develop- '" I I
I
r
.
ment. Consent
I I
Referencing
[Jrdfting of M.P.L.'s
I -'-
-- I I
P-';. r .L .• s sIgned by the
I I I
~lnister of the Depart-
I I -
ment of Mineral Resources I
~.P.L. '5
Officials
signee by Company
J
1
I
I
.I
~.P.L. '5 signed by 1
I
Governor I
1
Issuing of M..P.Lls
I I
A
I I I
I I
FIG.2
500 00
~otal [ ~(O\ alion I4B6i - -- -"0E tpl/ - -
f1I
~'"
0,"
IV> ~II
~I/ /
,- ~
l/ I
[Sump
Inset
400 V
/ l/
11
11
l:ri
Ir:--
400
/
/ ~
/
/ I
-E V / lu
/
~
/ d
300
No 3 bHJ FT /
/
:1 11: ~
300
j 13
7 Srn ~ /
:r:
~
0..
/ /
/
:1 ""-
ual-V// 11 1-0
lLJ
0 Ac
~
/
200 / / 11 200
lI'r nde ed
11
11
I
I
/
// 1
I
I
100
/
/ /J /
1
1
I
I
100
N
I
0/
0/
- - .- - ~ V 1 I Collar
10 20 30 TIME 40 50 60 70 76 BO
(wee ksl ,
500 ITotal x(av ~tlon 497-C - . - - - ~- / 500
~E
-'"
0,"
:I:V> ~ V r ---
I
--~ - Inset
5u~1'
~,
/
,,
/
/
, /
400 00
~
/
/
-
E
I /
/
I~
~
No 4 ;HP FT / /
/
/
~
300 300
13
/
/
:r: 61rn ~ , /
~
~
I1
0.. ,
lLJ
0 AduCl ,, 1-0
200
~ 200
V/ I
! "
I
I/,::'T eInd er ed I
100
I' I
100
/
If I
I
/
~
~
~ ~
V I
I ollar
0 10 20 30 TIME 40 50( wee k s)60 70 7B 80
day basis was justified with Joy 12CM Continuous Miner and two Joy
performances surpassing those achieved 22 sic Shuttle Cars.
on West Cliff Mine's No. 2 shaft: Coal is being hoisted to the
No. 2 shaft was sunk in 1976 with an surface using the contractor's
average shaft sinking rate of 12.8ml sinking headframe and winder which has
week on a three shift per day basis. a capacity of about 100 tonnes per
The shaft sinking method employed hour. It is proposed to retain both
at Nos. 3 and 4 shafts comprised sinking headframes and winders on
blasting using electric delay site until Stage II development
detonators and AN gelignite 60, commences.
mucking using dual cryderman grabs GAS DRAINAGE
and lining of the shaft walls using a Gas drainage technology was
suspended form arrangement. pioneered in Australia at West Cliff
The survey tolerance on each Mine by Company staff in conjunction
shaft was !25mm on the radius of the with the Commonwealth Scientific and
shaft. The contractor achieved Industrial Research Organisation,
contractual surveying and engineering the Australian Coal Industry Research
quality standards. .Laboratories and the Department of
Both shafts were largely free of Mineral Resources/~hdustrial Relations.
water and geological anomalies. A The success of the gas drainage
trace of gas was detected when programme culminated in the
negotiating the Bald Hill Claystones commissioning of Australia's first
at a depth of 160 to 180 metres. No surface gas drainage station in
further gas was detected until the March, 1980.
Bulli Seam was encountered. Currently, gas drainage at West
SEAM DEVELOPMENT Cliff Mine is being achieved by:-
Development of the in-seam Installing 100m drainage
connection linking the two shafts is holes into blocks of virgin
currently being undertaken. Two coal (pre-drainage),
headings are being driven in parallel Installing drainage holes
and pillars formed to assist with into the coal seams under-
ventilation of the working face. lying the Bulli Seam
Development is proceeding on a one (pre-drainage and post-
shift per day basis. drainage), and
On completion of the in-seam Post-drainage from sealed
connection, it is planned to develop goaf areas.
pit room to the north for at least It is proposed to drain gas in a
500 metres to allow for gas drainage similar manner at West Cliff Extended
works. It is then planned to develop and to install a similar gas drainage
pit room to the south and ultimately station. Research and development of
in the east and west directions. longhole drilling technology is
Under Stage I, about 160,000 currently being conducted to extend
tonnes of coal will be mined using a ·the effectiveness of pre-drainage.
Since 1980 coal sale revenues GAS DRAINAGE & GAS UTILISATION
have not matched inflation rates and Drainage of methane gas will be
mining costs have exceeded the similar to the arrangement operating
national inflation rate. An example at West Cliff Mine. A separate
of increasing mining costs is the gas drainage plant will be commissioned
January 1982 Award negotiation. The at West .Cliff Extended.
result of the January 1982 Award It is estimated up to 10 megawatts
negotiation was about $109 per man of electrical energy can be generated
per week when all benefits were by utilising the drained methane gas.
translated to dollar equivalents. . The arrangement for gas utilisatio~
The Award variation meant an increase cannot be finalised until the pilot
in operating costs of about $3 to $4 plant study at West Cliff Mine is
per tonne to the average mlne completed. Gas drained at West
operator. Cliff Extended could be either
Capital costs since 1980 have utilised on site or reticulated to
also increased significantly. In West Cliff to be used in a central
1980 the estimated cost of Stage I gas utilisation plant.
works was $14.5 million. In today's
CONCLUSIONS
dollars the estimate is about
Development of any new Mine
$22.5 million.
requires a long lead time. In the
Development of the project into
Illawarra area west of the escarpment
a separate operating mine is now not
the lead time is increasing due to
sufficiently viable to permit any
the need to pre-drain gas from the
contribution to transport infra-
coal seam prior to production mining.
structure.
The cost of conducting gas
COAL TRANSPORT drainage works in advance of the mine
The Company has previously generating a positive cash flow
proposed a scheme that avoided road provides an additional economic
haulage to Port Kembla. The scheme burden to the development of a new
comprised:- mine. The mine planner must quantify
(a) A conveyor transport drift the risks and incorporate technology
through the Illawarra into the mine design in an effort to
escarpment to Coal Cliff achieve productivity levels
rail siding, and sufficient to permit capital costs
(b) Ultimately an overland to be amortized.
conveyor linking K.C.C. The economics of a new mine
mines west of the escarpment development are further eroded by the
with the drift portal. inordinately long lead time for
The Company can no longer afford statutory approval in New South Wales.
to construct the transport infra- While external and domestic
structure. markets for coal remain uncertain, it
is still necessary to develop replace-
ment mines such as West Cliff Extended