Professional Documents
Culture Documents
Development, Installation, and Effect of An Underground Crushing and Conveying System
Development, Installation, and Effect of An Underground Crushing and Conveying System
NUMBER
J. C. Irvine
Mine Engineer
Meramec Mining Company
Sullivan, Missouri
11
72-AU-69
by
J. C. IRVINE
MINE ENGINEER
MERAMEC MINING COMPANY
INTRODUCTION
Corporation and St. Joe. Minera.ls Corporation, is engaged in the mining, con-
centrating, and pelletizing of iron ore from the Pea Ridge Mine located near
Sullivan, Missouri, about 70 miles southwest of St. Louis. The orebody was
cover new lead orebodies. An airborne magnetometer survey which was run by
the U. S. Geological Survey, the Missouri Geological Survey. and severa.l min-
ing companies was published in 1950 and showed an anomaly in the Pea Ridge
area. '!-est holes drilled in 1953 and 1954 revealed the presence of a large ore-
1957 and shaft sinking began in the latter part of that year.
The Pea Ridge orebody lies under about 1300 feet of sediments. It is
tabular, about 2600 feet long and up to 600 feet thick, and lies in an approxi-
depth. The ore is primarily high grade magnetite with smaller zones of spec-
in diameter and 2500 feet deep. No. 1 shaft, equipped with an "AI! type head-
72-AU-69
-2-
frame and conventional cylindrical drum hoists, handles men, materials, and
waste rock; it is also the downcast air shaft. No.2 shaft utilizes tower-
mounted friction hoists to handle the two production skips, each with 24-ton
counterweights, and a small man cage. The mine exhaust passes through this
pillar recovery; it is loaded into Swedish-type railroad cars either by LHD units
or by slushers.
When the mine came into production in 1964, ore was hauled on four
fed raises into scraping trenches in two loading stations. Then, ISO-horsepower
double-drum slushers were used to pull ore into a pair of small steel hoppers
tons of broken ore, have hydraulically operated gates which dump ore into the
two skips. The hoists are independent of each other; thus two skips can be
hoisted from either loading station or one from each station, depending on the
hoisting efficiency in three ways .. First, it would reduce time spent on se,?ond-
ary breakage at the loading station whicl?- was causing delays in hoisting while
the crews blasted. Second, it would reduce the amount of damage caused by
boulders to the hoppers, gates, and skips which required more frequent 'major
repairs and overhauls than desired. Third, the system would eliminate the use
ground crushing and conveying system established on a new, lower level of the
72-AU-69
-3-
level. The- manufacturer agreed to split the top shell, making it possible to
lower such a large crusher down No. 1 shaft. This is fed by a 72-inch wide by
20-foot long reciprocating feeder which empties the ore pass system from the
four Swedish-style dumps above, as shown in Figure 1. Liner wear in the re-
thickness. The crusher drops Ore into a small surge bin and then onto a 60-inch
wide by l6-foot long vibrating feeder with a 4-foot long grizzly end which in turn
feeds the conveyor. Feed rate is monitored by the crusher operator via closed
circuit TV. The conveyor, shown in Figure 2, has a distance of 1750 feet be-
tween the head and tail pulleys with a slope of 9-1/2 degrees, and a vertical lift
of 291 feet. The conveyor is level at the loading point; at 20 feet from there it
curves upward on a 575-foot radius until it achieves the 9_1/20 slope. It has a
belt speed of 450 feet per minute and a capacity of up to 1000 tons per hour.
The troughing and return idlers are mounted on roof suspended 3/4-inch (6 x 19)
cadmium-coated plow steel cable (see Figure 3). The belt itself is 42 inches
wide, 5-ply rayon-nylon cord construction, and has a 3/8-inch top cover and
3/32-inch bottom cover. Fifty-foot sections of l-inch hoses hooked into the
permanent water line in the main conveyorway (see Figure 4) every 1000 feet
the belt with high-pressure water. It is driven through a parallel shaft speed
A 100-foot raise beneath the conveyor provides room for a gravity takeup.
The operator's control room houses the main control panel which by
means of push buttons, indicator lights, alarm panels, motor ammeters, and
closed circuit television allows total monitoring of the system up to the tops of
the ore bins. This control room also contains all of the 480-volt motor controls
for the crushing station. Starting equipment for the 4l60-volt crusher motor
and conveyor drive is located separately from the control room for safety
reasons.
starting for all equipment. All motor drives are single-speed type except the
vibrating feeder under the crusher which is a wound-rotor type to allow bin
The ore is either fed directly into No. lore bin or onto a lOS-foot long,
42-inch shuttle conveyor which then conveys the ore to No. 2 ore bin. This
rail-mounted truss which can move itself to intercept the trajectory of ore
coming off the main belt. The ore bins, 28 feet in diameter and 90 feet deep,
single 60-inch by l2-foot vibrating feeder onto a 48-inch conveyor 157 feet long.
and fed as needed by the feeders. Feed is remotely controlled by the skip
loader and metered by electronic scale. Ore is generally fed two skip loads
at a time into the measuring hoppers and then loaded into the skips.
The shafts are 2500 feet deep, but to try to establish a new level from
72-AU-69
-5-
site near both No. 1 sha"ft and the waste dump system was chosen, and on April
Since the eventual mucking vehicle was to be a 5-yard LHD unit and
because it was desired to accommodate any vehicle that might use it in the
future, the size of the decline was set at 12 feet high by 15 feet wide. Drifting
was started with three"-man crews using three jackleg drills, a crawler-mounted
overshot loader and two I-yard 3-wheeled diesel trucks. A typical drift round
in this porphyry was 8 feet deep with a burn cut and 40 1-3/8-inch holes. The
upper part of this round was drilled off a removable wooden platform set on the
body of one of the trucks. AN/FO was used in all holes but the lifters and
bottom relievers, except when the decline passed through a few wet areas.
Typical times for the first 200 feet of decline driven with the truck-
With bolting and pumping times considered, the average 8-foot round
took 1. 3 shifts. This time increased as the face moved away from the waste
dump. In August, 1966 a 5-yard LHD unit replaced the overshot loader and
trucks (one truck was retained for drilling): Mean mucking time was reduced
was almost 900 feet and mucking time continued to increase arithmetically as
carrier supplanted the jackleg drills. The remaining three-wheeled truck was
converted into a roof-bolting rig. Drift round depth was increased to 10 feet.
Coincident with the arrival of the LHD unit, a second drift was started toward
the projected location of the bottoms of the crushed ore bins. The jumbo did
not appreciably decrease the drilling time, but it did allow the crew to drill one
face with two men on the jumbo and muck the other face with one man on the
LHD unit. The equipment had, in essence, doubled the footage capacity of a
three-man crew.
In April, 1967 the decline bottomed out and level development began
toward both the crusher site and toward the No. 1 shaft. Simultaneously, from
another advantageous point on the 227S-foot level, a second crew started driving
the 16.80/0 decline which was to be the 1920-foot long conveyorway. About 1370
feet of the 9 -foot high by l4-foot wide decline was driven downhill with jacklegs,
overshot loader, and three-wheeled trucks. The 300-foot section of the convey-
orway above the starting point was scraped into rail cars with a 50-horsepower
slusher, and the SOO-foot section adjacent to and below the 247S-foot level was
In April, 1968 the primary objectives -- the crushing station and the
crushed ore bin sites -- were reached and excavation began. The dimensions
of the crushing station were determined at 20 feet wide by 27 feet 9 inches high
by 102 feet long. In order to excavate the station, one end was slotted and the
width was entirely overcut to permit excavation by longhole drilling. The over-
72-AU-69
-7-
cut, as illustrated in Figure 5, allowed us to bolt, fence, and apply two inches
inch bore drifter was used to drill 2-l/4-inch diameter holes 22 feet deep. The
holes were on a 4-foot by 4-foot pattern with the toes of the holes angled 10 0
toward the slot. Blasting was done with AN/FO. Fragmentation was good and
overqreak was minimal, requiring only routine scaling and bolting to secure the
walls. The chamber in the floor of the crushing station which would contain the
crusher was cut with longholes utilizing a longhole or "drop" raise as the cut.
A 21-foot diameter cylinder with a l4-foot wide by 17 -foot 8-inch long "tail" was
undercut by the conveyor drift below. The "drop" raise (6 feet x 6 feet) was
blasted through in six shifts by keeping the burn one 5-foot segment ahead of the
rest of the round. The remainder of the "keyhole", drilled with a wagon drill
carrying a 4-l/2-inch drifter, was blasted with AN/FO quickly and without
incident.
The ore bins, each 28 feet in diameter and 90 feet deep, were cut in
much the same manner as the crusher chamber. Undercutting the bins reduced
inch diameter holes were spaced 3 feet apart around the periphery of the bins.
Timing the line holes last in groups of 6 to 8, as pie -shaped sections of the bin
were blasted out, left well delineated, stable walls which required only a minor
CONCRETING TECHNIQUES
was batched on the surface 3 yards at a time, agitated briefly, and then dropped
directly to the 2475-foot level through a 6-inch diameter pipe set in the shaft.
72-AU-69
-8-
At the 2475-foot level, the concrete went through a discharge box into th"
bucket of the LHD unit, and was then trammed 2200 feet to the crushing station.
Practically no segregation occurred during the trip, but to guard against any
possibility, the concrete was agitated in the bucket with compressed air through
4810 psi.
Concreting the crushing station began in February 1969 and was com-
pleted in February 1970. During that year 930 cubic yards of concrete were
poured and 32,500 pounds of reinforcing steel were set. The entire concreting
ope ration including forming, pouring, and stripping took 1626 manshifts. All
of the forming was done on site with plywood and timber except the top 13 feet
of the crusher chamber which was formed with a couple of sections of OUr steel
shaft forms. This was done to achieve a cylindrical throat for the crusher feed
levels above at the same time. Meramec's dumps are shown in Figure 6 and
control chutes in Figure 7. These were done in sequence from the lowest level
plywood forms for the upper (and complicated) part of one dump was prefabricated
in the carpenter shop. This was used, carefully stripped, and re-used On the
subsequently constructed dumps. Concrete for the dumps was dropped down the
shaft into 3-yard agitator carS and hauled to the construction site. Then, where
it couldn't be poured, it was blown into the forms with a one-yard pressure-pot-
type placer. A total of 1944 cubic yards of concrete and 3687 manshifts were
CONCLUSION
The crusher went on stream on April 1, 1970, with feed from the lower
two dumps. In August 1970 the fourth dump was completed and the system began
operation in its entirety. Since initial operation, it has handled 4,500,000 tons,
which is 96"/0 of the mine's total production during that period. The only major
haulage. As illustrated in Figure 8, a shift foreman now has the option of dump-
ing in the original dump if the new dump is full or requires repair. This has re-
duced the loss of haulage due to full dumps to practically nil. Scheduled main-
tenance on dumps and chutes now means rerouting rather than loss of haulage.
The two-bin system has similarly aided haulage. When maintenance is required
on one bin, the other is used and ore flow continues normally. If, at any time
hoisting is shut down, the Ore passes and bins can almost always provide a
The successful planning, design and construction of this system was due
In the 18 months that the full system has been in operation, Meramec
Mining Company's daily hoisted tonnage has increased by 12.6%. The major
conveying system.
72-AU-69
-10 -
I
(10) f-'
f-'
COMPONENT DESCRIPTION I
(1) 8 ft. diameter ore pas s to haulage levels above.
(2) 72 in. x 20ft. long reciprocating feeder. (II)
(3) Crushing station showing access from 2475-ft. level.
(4) 42 in. gyratory crusher belt driven by 300 H. P. motor.
(5) Vibrating grizzly end feeder, 60 in. x 16 ft. long (30 H. P. motor).
(6) 1750 ft. roof-suspended belt at 9-1/20 slope; 42 in. wide with 35 0 troughing. (12)
(7) 105 ft. long shuttle conveyor.
(8) Ore bin with 5,000 ton capacity; 28 ft. in diameter, 90 ft. high.
(9) Vibrating feeder 60 in. x 12 ft. long.
(10) 160 ft. long 48 in. belt, 8 0 slope with 1200 tph capacity.
(11) Skip loading station with measuring hoppers.
(12) No.2 shaft with 2 friction hoists. -.J
I\)
I
<t
BELT
I 14'-0
4'- 3 <0'-0
I
2'-0 2!O
1
'\
~()HT
\
FI XTUR.E.
(E.VER'" 2A')
- CASU.
lZTAAY I
AIR
LlNES
.$WAT~8 :1N
- 0
.-- -'m
ryI ./)
wfO Gk'ADE PLUG-..-5
o
...!!!!!r
~
v ~ -I
~-Zt ROPE
1-
Q
-'I/) tc=Ll}=If=U}=(J . - Q
.!t
;t In
0
~
-v'
I
i
I
FIGURE 4.- Typical Conveyorway Section
1.) Drive 24CSD 20' wide x 12' high until face is 3D' from 24CEl.
2.) Drive 8' x 8' raise from end of 24 CSD until back is 27' -9" above floor of 24 CSD.
3.) Develop 8' wide x 20' long slot opening by slabbing into raise from both sides.
\
\
\ \
\ \
\ \
\ \
\ I
} \ I f-'
-----_../ L __ -.J W
I
/~~
24 CSD I
~+ '\
-!-]--
CRUSHER ":;:::>'-_/
5.) Develop 8' high, 21' wide, 94' long upper level by slabbing 6i' x 8' from both sides into pilot
drift.
6.) 4i' from end of upper level, cut a slot out of back to be loi wide, 19' long, 6' higher than
back of pilot drift. This back should be about 33'-9" above the floor of 24 CSD.
4- ll' 19'
~m~I-
"
__
II
1.
l
9~' I
I
I-'
-I=:"
I
-..:J
i\l
8.) Drive 24 CSD 20' wide x 12' high far enough to connect with 24 CE 2.
!'i_ 70 l Z '
19'
rl-~---T-~--~----- I 8'_.I_ 2.Z'
I
Il-~l ______________ ~~ I \9
I _ @$@ '~l io I ~ ~
~~JlllL~J]]JlllIJnlrf~ ==cp ~ ~
I
f-'
\Jl
I
, I
--.l
t\.l
FIGURE 5 (c):- Underground Crushing Station I
:J:>
'f
0'1
Excavation Sequence \.0
72-AU-69
- 16-
STATIONARY
Il(UERSE~
SlOE RAILS ON
CARS ANO
[lOCOMOTIVE
\ RERAllERS
- 17-
\------~~ ~QOT~L-----\\
-- ----------~,,=~~\
\ "r~-------------\\
212<;:> FOOT LE.VEL
S"I"I'-TICN .--5
~::x:
cIJ
\
-----------==-Q\ \
2'ZiS FOOT LEVE.L \ (IJ
1
o
z
~ \ \ \
\1 \ \\
~
2415 FOOT LEVEL
U ORE BINS ;3M
""KIP LOADING
STATiON