Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 5

Matara- Kataragama Railway Extension Project (Phase 1) Sri Lanka Matara-Beliatta

Sector
Matara-Kataragama Railway Extension Project

Matara-Beliatta Sector (Phase 1)

(DK0+44 ~ DK26+461)

Method Statement for chemical anchoring of reinforcement on piles

MS-76
Rev. 0

Contractor : China National Machinery Imp. & Exp. Corp.


No Date Prepared Checked Approved Remark

REV.0 2015.02.02 Namal Sujeewa Zhong Xiang He Peizhi

Ref.Letter No :
Matara- Kataragama Railway Extension Project (Phase 1) Sri Lanka Matara-Beliatta
Sector
CONTENT

1.0 Purpose of Method Statement


2.0 Responsibilities for activity Describe within this Method Statement
3.0 Materials and equipment
4.0 Detailed method of carrying out&method statement activity
5.0 HSE measures
Matara- Kataragama Railway Extension Project (Phase 1) Sri Lanka Matara-Beliatta
Sector
1.0 Purpose of Method Statement

While proceeding the hacking, the reinforcements (upper most portions) of some piles have
been damaged in Nilwala bridge no 02 and failed to provide the required anchorage to the
pile cap. If the number of bars (damaged) is one or two, then chemical anchoring is
proposed to provide the required anchorage. So, this method statement describes the details
of the materials and the procedure for chemical anchoring.

2.0 Responsibilities for activity Describe within this Method Statement

QAQC manager, Section Engineer and other relevant personnel within whose scope of
works shall be responsible for referred this rectification.

3.0 Materials and equipment

HIT-RE 500 injection adhesive, reinforcement bars (T16), drill, blow-out pump, cleaning
brushes

4.0 Detailed method of carrying out method statement activity

Most of the piles are consisted with one or two damaged reinforcement bars (listed in Table
1). For those piles, at the close proximity of the damaged re bar, a new re bar consisted with
required anchorage length will be chemically anchored to the pile head as follows;

a) Installation points of reinforcement will be marked on the pile head.

b) Holes will be prepared in required diameter and depth as per the setting details of the
enclosed datasheet.

c) After having a proper cleaning, HIT-RE 500 injection adhesive will be injected in to the
holes using the dispenser.

d) Reinforcement bars will be inserted up to the required depth and kept undisturbed on
curing for duration as mentioned in the manufacturer’s literature.

1 /2
Matara- Kataragama Railway Extension Project (Phase 1) Sri Lanka Matara-Beliatta
Sector
Table 1

Pile no No of damaged re bars


P06P02 2
P23P04 1
P24P04 1
P25P03 2
P27P03 1
P27P04 1
P28P01 1
P28P02 1
P28P03 2
P28P04 2
P29P01 2
P29P03 1
P29P04 1
P30P02 2
P30P03 2
P31P01 2
P32P02 1
P32P03 1
P32P04 2
P33P04 1
P35P01 1
P36P01 1
P36P03 1
P37P02 1
P37P04 1
P40P03 2
A02P03 2

2 /2
Matara- Kataragama Railway Extension Project (Phase 1) Sri Lanka Matara-Beliatta
Sector
Comments

For planting bars- Depth of anchor 320mm+5mm (For full development of tensile
capacity
For existing bars- Minimum lap length >= 800mm
So Above both condition should be satisfied to development of full tensile capacity.

However, the lap length could be reduced considering coexisting tensile force at the pile /
pile cap interface.

3 /2

You might also like