Submitting herewith Contractor’s Weekly Activities/Accomplishment covering from the
period Monday to Saturday May 30, to June 4, 2022.
Thank you.
_____________________________________________________________________________________________________________________________
Consulting Services for the Construction Supervision of the Construction of Roads and Bridges under Improving Growth Corridors in Mindanao Road Sector
Project (IGCMRSP) ADB Loan No. 3631-PHI
Pages 1
In Joint Venture with
As Sub-Consultant
3. BRIDGES
LITUBAN BRIDGE-GIRDER- FABRICATION & INSTALLATION OF RSB
Location: Lituban Bridge Area
Name of Equiments: Minor Tools
Manpower: 5 workers
Length=30.00 mts
5. FABRICATION OF RCPC
Location: China wuyi Camp Area
Name of Equiments: Minor Tools
Manpower: 4 workers
6. FABRICATION OF GIRDER
Location: Lituban Bridge Area
Name of Equiments: Minor Tools
Manpower: 5 workers
5. HAULING QUARRY
Location: Brgy. New Sagay Area
Name of Equiments: 2 Dumptrucks, 1 Backhoe
Manpower: 5 workers
_____________________________________________________________________________________________________________________________
Consulting Services for the Construction Supervision of the Construction of Roads and Bridges under Improving Growth Corridors in Mindanao Road Sector
Project (IGCMRSP) ADB Loan No. 3631-PHI
Pages 2
In Joint Venture with
As Sub-Consultant
5. STONE MASONRY
Item #: 506(1)
Station: K1847+390 to K1847+420 L/S
Name of Equiments: Minor Tools
Manpower: 5 workers
6. FABRICATION OF RCPC
Location: China wuyi Camp Area
Name of Equiments: Minor Tools
Manpower: 4 workers
7. FABRICATION OF GIRDER
8. HAULING QUARRY
Location: Brgy. New Sagay Area
Name of Equiments: 2 Dumptrucks, 1 Backhoe
Manpower: 5 workers
_____________________________________________________________________________________________________________________________
Consulting Services for the Construction Supervision of the Construction of Roads and Bridges under Improving Growth Corridors in Mindanao Road Sector
Project (IGCMRSP) ADB Loan No. 3631-PHI
Pages 3
In Joint Venture with
As Sub-Consultant
4. FABRICATION OF RCPC
Location: China wuyi Camp Area
Name of Equiments: Minor Tools
Manpower: 4 workers
5. FABRICATION OF GIRDER
Item #- 404(1)b
Location: Lituban Bridge Area
Name of Equiments: Minor Tools
Manpower: 5 workers
6. HAULING QUARRY
Location: Brgy. New Sagay Area
Name of Equiments: 2 Dumptrucks, 1 Backhoe
Manpower: 5 workers
7. INSTALLATION OF RCPC
Item #: 500(1)a6
Station: 1850+460 L/S
Name of Equiments: 1 Backhoe. Minor Tools
Manpower: 6 workers
_____________________________________________________________________________________________________________________________
Consulting Services for the Construction Supervision of the Construction of Roads and Bridges under Improving Growth Corridors in Mindanao Road Sector
Project (IGCMRSP) ADB Loan No. 3631-PHI
Pages 4
In Joint Venture with
As Sub-Consultant
4. FABRICATION OF RCPC
Location: China wuyi Camp Area
Name of Equiments: Minor Tools
Manpower: 4 workers
5. FABRICATION OF GIRDER
Item #: 406(1)f8
Location: Lituban Bridge Area
Name of Equiments: Minor Tools
Manpower: 5 workers
6. HAULING QUARRY
Location: Brgy. New Sagay Area
Name of Equiments: 2 Dumptrucks, 1 Backhoe
Manpower: 5 workers
7. INSTALLATION OF RCPC
Item #: 500(1)a6
Station: 1850+460 L/S
Name of Equiments: 1 Backhoe. Minor Tools
Manpower: 6 workers
_____________________________________________________________________________________________________________________________
Consulting Services for the Construction Supervision of the Construction of Roads and Bridges under Improving Growth Corridors in Mindanao Road Sector
Project (IGCMRSP) ADB Loan No. 3631-PHI
Pages 5
In Joint Venture with
As Sub-Consultant
Manpower: 2 workers
1. FABRICATION OF GIRDER
Item #: 406(1)f8
Location: Lituban Bridge Area
Name of Equiments: Minor Tools
Manpower: 5 workers
3. HAULING QUARRY
Location: Brgy. New Sagay Area
Name of Equiments: 2 Dumptrucks, 1 Backhoe
Manpower: 5 workers
4. INSTALLATION OF RCPC
Item #: 500(1)a6
Station: 1850+460 L/S
Name of Equiments: 1 Backhoe. Minor Tools
Manpower: 6 workers
2. FABRICATION OF RCPC
Item #- 500(1)a6
Location: China wuyi Camp Area
_____________________________________________________________________________________________________________________________
Consulting Services for the Construction Supervision of the Construction of Roads and Bridges under Improving Growth Corridors in Mindanao Road Sector
Project (IGCMRSP) ADB Loan No. 3631-PHI
Pages 6
In Joint Venture with
As Sub-Consultant
4. FABRICATION OF GIRDER
Item #- 406(1)f8
Location: Lituban Bridge Area
Name of Equiments: Minor Tools
Manpower: 5 workers
5. HAULING QUARRY
Location: Brgy. New Sagay Area
Name of Equiments: 2 Dumptrucks, 1 Backhoe
Manpower: 5 workers
6. INSTALLATION OF RCPC
Item #: 500(1)a6
Station: 1850+460 L/S
Name of Equiments: 1 Backhoe. Minor Tools
Manpower: 6 workers
_____________________________________________________________________________________________________________________________
Consulting Services for the Construction Supervision of the Construction of Roads and Bridges under Improving Growth Corridors in Mindanao Road Sector
Project (IGCMRSP) ADB Loan No. 3631-PHI
Pages 7
In Joint Venture with
As Sub-Consultant
_____________________________________________________________________________________________________________________________
Consulting Services for the Construction Supervision of the Construction of Roads and Bridges under Improving Growth Corridors in Mindanao Road Sector
Project (IGCMRSP) ADB Loan No. 3631-PHI
Pages 8
In Joint Venture with
As Sub-Consultant
_____________________________________________________________________________________________________________________________
Consulting Services for the Construction Supervision of the Construction of Roads and Bridges under Improving Growth Corridors in Mindanao Road Sector
Project (IGCMRSP) ADB Loan No. 3631-PHI
Pages 9