FIDIC Contracts – An Overview

Roger Button

Head of Middle East Construction

Amereller Legal Consultants

MUNICH │ BERLIN │ BAGHDAD │ BASRA │ERBIL


DUBAI │ CAIRO │ RAS AL-KHAIMAH │ DAMASCUS

1
FIDIC Red Book 1999 (1)

 Most Design by Employer


 Engineer’s Role in Inspection and Certification
 Bills of Quantities or Optional Lump Sum

MUNICH │ BERLIN │ BAGHDAD │ BASRA │ERBIL


DUBAI │ CAIRO │ RAS AL-KHAIMAH │ DAMASCUS
FIDIC Red Book 1999 (2)

 Key Employer Risks:

 Unforeseeable physical conditions


 Forces of Nature
 Employer Design
 War, Riot and Similar Risks

 MDB Edition

MUNICH │ BERLIN │ BAGHDAD │ BASRA │ERBIL


DUBAI │ CAIRO │ RAS AL-KHAIMAH │ DAMASCUS

3
FIDIC Yellow Book - 1999

 Most Design by Contractor


 Type of Project now Irrelevant
 Engineer’s Role in Inspection/Certification
 Lump Sum Basis of Payment
 More Elaborate Testing Procedure
 Similar Risk Profile

MUNICH │ BERLIN │ BAGHDAD │ BASRA │ERBIL


DUBAI │ CAIRO │ RAS AL-KHAIMAH │ DAMASCUS

4
FIDIC Green Book

 Straightforward Projects of Small Capital Value

 No Sub-Contracting Without Consent

 Variety of Pricing Options

 Employer Liabilities

 No Engineer

MUNICH │ BERLIN │ BAGHDAD │ BASRA │ERBIL


DUBAI │ CAIRO │ RAS AL-KHAIMAH │ DAMASCUS

5
FIDIC Blue Book (2006)

 Dredging and Reclamation

 With or Without Design by Contractor

 Variety of Valuation Mechanisms

 Engineer to Inspect and Certify

 Defined Risks

MUNICH │ BERLIN │ BAGHDAD │ BASRA │ERBIL


DUBAI │ CAIRO │ RAS AL-KHAIMAH │ DAMASCUS

6
FIDIC Silver Book (1)

 For Use With BOT/Private Finance Type Projects

 Certainty of Time/Price

 Contractor Takes Almost All Risk

“The Contract Price shall not be adjusted to take


account of any unforeseen difficulties or costs”

MUNICH │ BERLIN │ BAGHDAD │ BASRA │ERBIL


DUBAI │ CAIRO │ RAS AL-KHAIMAH │ DAMASCUS

7
FIDIC Silver Book (2)

 Contractor Risks:
 Fitness for Purpose
 Employer Design
 Site Conditions
 Employer’s Risks:
 Force Majeure
 Changes in Law
 Employer Default
 Limit of Contractor’s Liability
MUNICH │ BERLIN │ BAGHDAD │ BASRA │ERBIL
DUBAI │ CAIRO │ RAS AL-KHAIMAH │ DAMASCUS

8
FIDIC Silver Book (3)

 Employer’s Representative

 Limited Employer Control

 The Market

 Controversy

MUNICH │ BERLIN │ BAGHDAD │ BASRA │ERBIL


DUBAI │ CAIRO │ RAS AL-KHAIMAH │ DAMASCUS

9
FIDIC Gold Book (1)

 Design, Build and Operate Projects

 Contractor Designs, Manufactures and Installs Project

 Operates Completed Project for 20 Years

MUNICH │ BERLIN │ BAGHDAD │ BASRA │ERBIL


DUBAI │ CAIRO │ RAS AL-KHAIMAH │ DAMASCUS

10
FIDIC Gold Book (2)

 Design-Build Period – Risk Profile Very Similar to Yellow


Book

 Complex Design Review Provisions

 Compensation to Employer for Design Rework

 Adjustment for Changes in Technology

 Lump Sum Price – Possibly Subject to Indexation


MUNICH │ BERLIN │ BAGHDAD │ BASRA │ERBIL
DUBAI │ CAIRO │ RAS AL-KHAIMAH │ DAMASCUS

11
FIDIC Gold Book (3)

 Operation Service Period


 All Risks Arising From Design or Construction of
the Works (Apart From Employer’s Design)
 All Risks Arising From Operation and Maintenance
of the Works Apart from Employer’s Risks

 Asset Replacement Fund

 Maintenance Retention Fund

MUNICH │ BERLIN │ BAGHDAD │ BASRA │ERBIL


DUBAI │ CAIRO │ RAS AL-KHAIMAH │ DAMASCUS

12
FIDIC White Book - 2006 Edition

 Re-arrangement of Layout

 Consultant Only Liable if Lack of Skill, Care and Diligence

 Impedance: ‘Scope, Cost or Duration’ of the Services

 Varied Services – Agreement First

 Currency Risk

MUNICH │ BERLIN │ BAGHDAD │ BASRA │ERBIL


DUBAI │ CAIRO │ RAS AL-KHAIMAH │ DAMASCUS

13
FIDIC Sub-Contract (1)

 For Use With FIDIC Red Book Only

 Sub-Contractor Assumes All Liabilities of Main Contractor


Under the Main Contract, Subject to Certain Exceptions

 Any Design By Sub-Contractor to be Fit for Any Purpose


Indicated by or to be Inferred From the Sub-Contract

 ‘Pay When Paid’

MUNICH │ BERLIN │ BAGHDAD │ BASRA │ERBIL


DUBAI │ CAIRO │ RAS AL-KHAIMAH │ DAMASCUS

14
FIDIC Sub-Contract (2)

 Claims Back to Back With Main Contract

 Sub-Contractor Takes Risk of Sub-Contract Works Until Take Over


Under Main Contract

 Defects Notification Period Expires as per Main Contract

MUNICH │ BERLIN │ BAGHDAD │ BASRA │ERBIL


DUBAI │ CAIRO │ RAS AL-KHAIMAH │ DAMASCUS

15
FIDIC Sub-Contract (3)

 Liability for LADs Limited – 10% of Sub-Contract Sum in


Default

 Extension of Time and Cost for Non-Cooperation by Other


Sub-Contractors

MUNICH │ BERLIN │ BAGHDAD │ BASRA │ERBIL


DUBAI │ CAIRO │ RAS AL-KHAIMAH │ DAMASCUS

16
FIDIC: Remaining Publications

 Joint Venture Agreement (1992)

 Sub-Consultancy Agreement (1992)

 Model Representative Agreement (1994)

 Contracts Guide

MUNICH │ BERLIN │ BAGHDAD │ BASRA │ERBIL


DUBAI │ CAIRO │ RAS AL-KHAIMAH │ DAMASCUS

17
Thank you very much for your attention