Implementation Report Tech Refresh 07-18-2022
Implementation Report Tech Refresh 07-18-2022
PLDT Sta. Maria Tumaga SSA WORK WK June July August Sept Oct Nov PROGRESS
STATUS Dependency
(%)
Item Scope of Work (SOW) PLAN ACTUAL 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47
A. Pre-Implementation Works
1 Material Preparation 3 3 100%
2 Material Delivery 13 13 100%
3 PDAT 1 1 100%
4 Delivery. 2 100%
5 Mobilization 1 1 100% For Request Access Pass
B. Implementation
Relocating of Existing two (2) Battery Bank to give way
1 2 100%
for new Battery Bank 1
2 2 100%
Mounting of 400A Rectifier and 2 x 500AH Battery Bank 1
P.
o.
R
E
L
E
A
S
E
D
IMPLEMENTATION
August September Oct
Week 31 Week 32 Week 33 Week 34 Week 35 Week 36 Week 37 Week 38 Week 39 Week 40
7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8
Backfill
S.O.G.
December
Week 49 Week 50 Week 51 Week 52 PROGRESS
(%) STATUS Dependency
11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1
30%
100%
30%
100%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
WORK WK Jun
PLDT Alimodian 120 Days Nov Dec Jan Feb Mar Apr May
Week 26 Week 27
Item Scope of Work (SOW) PLAN ACTUAL 45 46 47 48 49 50 51 52 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 27 28 29 30 1 2 3 4
A. Pre-Implementation Works
1 Material Preparation 90
2 SKOM (CME) 1
3 Material Delivery 25
4 Mobilization 1
For DDD final approval as per site actual conditon for SFE meeting and approval. SO request for another
B. Implementation survey
B.1 New Equipment Building
1 SITE CLEARING & DEMOLITION WORKS 7
2 EARTH WORKS 7
3 STEEL WORKS 30
4 CARPENTRY WORKS 20
5 CONCRETE POURING WORKS 7
6 MASONRY WORKS 10
7 FINISHING WORKS 10
8 ACCEPTANCE & TURNOVER 5
B.2 FST Shelter
1 EARTH WORKS 7 P.
o.
2 STEEL WORKS 3
3 CONCRETE WORKS 5 R
4 TUBULAR PIPE COLUMN 7 E
L
5 ROOFING WORKS E
6 ACCEPTANCE & TURNOVER A
B.3 Concrete Pavement S
E
1 EARTH WORKS 7 D
2 STEEL WORKS 7
3 CONCRETE POURING WORKS 5
B.3 Cooling System
1 2 x 2.5HP ACCU 3
2 Refrigerant Piping layout. 4
3 Drained Layout 4
4 Electrical Layout 4
5 Mounting and installation of Units. 3
6 Acceptance, test and Commissioning 2
7 PANELS
8 Panel Fabrication 15
9 Delivery on site 25
10 Installation, Mounting of Panels and Submeter 4
11 Cabling and Tapping Works - Electrical Works 4
12 PowerUp 2
C. Demobilization 1
IMPLEMENTATION
July August Se
Week 27 Week 28 Week 29 Week 30 Week 31 Week 32 Week 33 Week 34 Week 35 Week 36
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7
Backfill
30%
100%
30%
0%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
IMPLEMENTATION
WORK WK June July August Sept
PLDT Bayugan 90 Days _ Assu Sep Oct Nov Dec Jan Feb Mar Apr May
Week 22 Week 23 Week 24 Week 25 Week 26 Week 27 Week 28 Week 29 Week 30 Week 31 Week 32 Week 33 Week 34 Week 35 PROGRESS STATUS Dependency
Item Scope of Work (SOW) PLAN ACTUAL 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 (%)
A. Pre-Implementation Works
1 Material Preparation 60 3 100%
2 SKOM 1 1 100%
3 Material Delivery (ACU, & RM)) 25 4 100%
4 Mobilization 1 1 100%
B. Implementation / Concern Battery Lead Time Additonal Scope for DC Upgrade approval ACU punclist with Cost implication
B1 Cooling System
1 3x5TR Floor Delivery and Mounting 14 12 100%
2 Refrigerant Piping layout. 7 6 100%
3 Drained Layout 5 4 100%
4 Electrical Layout 5 4 100%
5 Mounting of Panels and installation of Units. 6 5 100%
6 4 4 100%
StartUp Activity , Testing, Commissioning and Acceptance
B2 Argus (7 Modules)
1 Purchase of Argus rectifier Module 60 65 100%
2 Delivery And installation (plug in) 4 3 100%
3 Acceptance 1 1 100%
B3 2x1000AH Battery Banks ( Additional )
1 Battery Purchase and Delivery Time 90 75 100%
2 Delivery to Site 25 27 100%
3 Laying of DC Cable 3 3 100%
4 Postioning and Mounting of Battery Rack 3 3 100%
5 Cutover Activity / Powerup of battery 3 3 100%
6 Acceptance, test and Commissioning 1 1 100%
C. Demobilization 100%
IMPLEMENTATION
WORK WK June July August Sept
PLDT Cabadbaran 90 Days
Sep Oct Nov Dec Jan Feb Mar April May
Week 22 Week 23 Week 24 Week 25 Week 26 Week 27 Week 28 Week 29 Week 30 Week 31 Week 32 Week 33 Week 34 Week 35 PROGRESS
STATUS Dependency
Item Scope of Work (SOW) PLAN ACTUAL 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 (%)
A. Pre-Implementation Works
1 Material Preparation 90 3 100%
2 SKOM 1 1 100%
3 Material Delivery (STACU, & Rectifier, Battery) 8 4 50%
4 Mobilization 1 5%
B. Implementation / Concern Contractor Issue Site Issue obstruction encounter, negative for IMC pipe ( Gutter Box for SFE approval )
B1 Cooling System
1 3x5TR Delivery and Mounting 3 5%
2 Refrigerant Piping layout. 2 5%
3 Drained Layout 1 5%
4 Electrical Layout 2 5%
5 Mounting Panels and installation of Units. 1 5%
6 1 5%
StartUp Activity , Testing, Commissioning and Acceptance
B2 DPC Rectifier 2 Set x 600 to 1000A
1 DPC Rectifier Delivery 12 5%
2 Delivery on site 1 5%
3 Installation, Mounting of Rectifier System 3 5%
4 Cabling Works - Electrical Works 3 5%
5 PowerUp / Start up 1 5%
B3 4x500AH Battery Banks
1 Battery Available at WH 1 1 100%
2 Delivery to Site 1 1 100%
3 Laying of DC Cable 3 5%
4 Postioning and Mounting of Battery Rack 2 5%
5 Cutover Activity / Powerup of battery 1 5%
6 Acceptance, test and Commissioning 1 5%
C. Demobilization 1 0%
IMPLEMENTATION
WORK WK June July
PLDT Cavite 14 Days
Aug Sep Oct Nov Dec Jan Feb Mar April May
Week 22 Week 23 Week 24 Week 25 Week 26 Week 27 Week 28 Week 29 Week 30 June July PROGRESS
(%) STATUS Dependency
Item Scope of Work (SOW) PLAN ACTUAL 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 22 23 24 25 26 27 28 29 30
A. Pre-Implementation Works
1 Material Preparation 1 1 100%
2 SKOM 1 1 100%
3 Material Delivery (RM, Battery) 1 1 100%
4 Mobilization 1 1 100%
B. Implementation / Concern Waiting For BAU Rectifier Energization c/o PLDT LM Awarded for Jehan waiting for MOP approval MOP Approved for PHBIA / CMC approval
B1 Argus(9 Modules) 1 1 100%
1 Purchase of Argus rectifier Module 1 1 100%
2 Delivery And installation (plug in) 1 1 100%
3 Acceptance
B2 New Battery (3x500AH)
1 Delivery to Site (rack and battery) 1 1 100%
2 Cabling laying 2 1 100%
3 Positioning and Mounting of Battery Rack 2 1 100%
4 Battery Installation 2 1 50%
5 Battery Migration 1 0% Additional Scope as per PLDT
6 Load Migration 1
7 Test and Commisioning. 1 0%
C. Demobilization 1
WORK WK July
PLDT Isulan 150 Days Jan Feb Mar April May
Week 26 Week 27 Week 28
Item Scope of Work (SOW) PLAN ACTUAL 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
A. Pre-Implementation Works
1 Material Preparation 8
2 SKOM (CME) 1
3 Material Delivery 6
4 Mobilization 1
B1 EQUIPMENT ROOM Contractor issue no PO
1 SITE CLEARING 5
2 EARTH WORKS 7
3 STEEL WORKS 35
4 CARPENTRY WORKS 20
5 CONCRETE POURING WORKS 10
6 MASONRY WORKS 7
7 FINISHING WORKS 7
8 ACCEPTANCE & TURNOVER 5
B2 GENSET SHELTER 1
1 EARTH WORKS 5
2 STEEL WORKS 20
3 CONCRETE WORKS 10
4 TUBULAR PIPE COLUMN 7
5 ROOFING WORKS 7
6 ACCEPTANCE & TURNOVER 5
B3 FST SHELTER
1 EARTH WORKS 7
2 STEEL WORKS 3
3 CONCRETE WORKS 5
4 TUBULAR PIPE COLUMN
5 ROOFING WORKS 7
6 ACCEPTANCE & TURNOVER
5 PowerUp / Start up 1
6 Load Migration from Old Huawei 2
B4 New Battery 4x500AH
1 Battery Available at WH 1
2 Delivery to Site 1
3 Laying of DC Cable 2
4 Postioning and Mounting of 1
Battery Rack
5 Cutover Activity / Powerup of batter 1
6 Acceptance, test and Commissioning 2
7 Load Migration from Old Huawei 1
C. Demobilization 1
IMPLEMENTATION
July August September
Week 29 Week 30 Week 31 Week 32 Week 33 Week 34 Week 35 Week 36 Week 37
18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Backfill
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
IMPLEMENTATION
WORK WK June July
PLDT La Castellana 45 Days
Sept Oct Nov Dec Jan Feb Mar April May
Week 22 Week 23 Week 24 Week 25 Week 26 Week 27 Week 28 Week 29 Week 30 PROGRESS STATUS Dependency
(%)
Item Scope of Work (SOW) PLAN ACTUAL 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
A. Pre-Implementation Works
1 Material Preparation 3 3 100%
2 SKOM 1 1 100%
3 Material Delivery (ACU, & Rectifier, Battery) 8 4 50%
4 Mobilization 50%
B Implementation
B1 Cooling System and CW for WACU wall restorations
1 Wall restoration for 2 x wacu 1 1
2 1x3TR Floor Delivery and Mounting 1 1 100%
3 Refrigerant Piping layout. 3 1 100%
4 Drained Layout 1 1 100%
5 Electrical Layout 1 1 100%
6 Mounting Panels and installation of Units. 1 1 100%
7 StartUp Activity , Testing, Commissioning and Acceptance 1 1 100%
B2 Huawei(2 Modules)
1 Purchase of Huawei rectifier Module 1 5%
2 Delivery And installation (plug in) 1 5%
3 Acceptance 1 5%
B3 DPC Rectifier (300A to 500A)
1 DPC Rectifier delivery 16 4 100%
2 Delivery on site 1 1 100%
3 Installation, Mounting of Rectifier System 2 1 100%
4 Cabling Works - Electrical Works 2 1 100%
5 PowerUp / Start up 1 0%
B4 2x300AH Battery Banks
1 Battery Available at WH 1 1 100%
2 Delivery to Site 1 1 100%
3 Laying of DC Cable 2 1 100%
4 Postioning and Mounting of Battery Rack 1 1 100%
5 Load Migration 2 100%
6 Acceptance, test and Commissioning 1 100%
C. Demobilization 100%
WORK WK June
PLDT LISP 120 Days Nov Dec Jan Feb Mar April May
Week 26
Item Scope of Work (SOW) PLAN ACTUAL 45 46 47 48 49 50 51 52 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 27 28 29 30 1 2 3
A. Pre-Implementation Works
1 Material Preparation 5
2 SKOM (CME) 1
3 Material Delivery 9
4 Mobilization 1
B. Implementation Contractor issue no PO
B1 EQUIPMENT ROOM
1 SITE CLEARING & DEMOLITION 14
2 EARTH WORKS 7
3 STEEL WORKS 14
4 CARPENTRY WORKS 10
5 CONCRETE POURING WORKS 10
6 MASONRY WORKS 7
7 FINISHING WORKS 14
8 ACCEPTANCE & TURNOVER 5
B2 FST SHELTER
1 EARTH WORKS
P.
7
o.
2 STEEL WORKS 5
3 CONCRETE WORKS 5 R
4 TUBULAR PIPE COLUMN 7 E
L
5 ROOFING WORKS E
6 ACCEPTANCE & TURNOVER A
SERVICE ENTRANCE PEDESTAL S
E
1 EARTH WORKS D
2 STEEL WORKS
3 CONCRETE POURING WORKS
B.3 Cooling System
1 3 x 3TR STACU 2
2 Refrigerant Piping layout. 2
3 Drained Layout 2
4 Electrical Layout 2
5 Mounting and installation of Units. 1
6 Acceptance, test and Commissioning 1
7 PANELS 1
8 Panel Fabrication 2
9 Delivery on site 1
10 Installation, Mounting of Panels and Submeter 1
11 Cabling and Tapping Works - Electrical Works 1
12 PowerUp 1
C. Demobilization 1
IMPLEMENTATION
July August
Week 27 Week 28 Week 29 Week 30 Week 31 Week 32 Week 33 Week 34 Week 35 Week 36
4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6
Backfill
2ND LIFT
IMPLEMENTATION
September October November
Week 36 Week 37 Week 38 Week 39 Week 40 Week 41 Week 42 Week 43 Week 44 Week 45
7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10
30%
100%
30%
0%
3%
3%
3%
3%
3%
3%
3%
3%
3%
3%
3%
3%
3%
3%
IMPLEMENTATION
WORK WK June July
PLDT LUPON PHILCOM 45 Days Week 22 Week 23 Week 24 Week 25 Week 26 Week 27 Week 28 Week 29 Week 30 PROGRESS
(%) STATUS Dependency
Item Scope of Work (SOW) PLAN ACTUAL 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
A. Pre-Implementation Works
1 Material Preparation 6 5 90%
2 SKOM 1 1 100%
3 Material Delivery (ACU, & Rectifier, Battery) 9 5 50%
4 Mobilization 1 1 0%
Space issue NEC for Source out to other
B. Implementation / Concern dismantle project DPC Rectifier
B1 Cooling System
1 3x3TR Ceiling and Floor Delivery and Mounting 2 2 100%
2 Refrigerant Piping layout. 3 2 100%
3 Drained Layout 1 2 100%
4 Electrical Layout 1 2 100%
5 Mounting and installation of Units. 1 2 100%
6 Mounting and Installation of Panels with AC compliments 1 2 100%
7 1 50% 10/02/22
StartUp Activity , Testing, Commissioning and Acceptance 0.5 Sched for SU
B2 DPC Rectifier (300A to 500A)
1 DPC Rectifier Delivery 12 5%
2 Delivery on site 1 5%
3 Installation, Mounting of Rectifier System 2 5%
4 Cabling Works - Electrical Works 2 5%
5 PowerUp / Start up 1 5%
B3 2x300AH Battery Banks
1 Battery Available at WH 1 1 15%
2 Delivery to Site 1 1 100%
3 Positioning and Mounting of Battery Rack 1 5%
4 Cable Ladder Installation 2 5%
5 Laying of DC Cable 2 5%
6 Cutover Activity / Powerup of battery 2 5%
7 Acceptance, test and Commissioning 1 5%
B4 Load Migration
1 Cabling Works 3 5%
2 Termination 1 5%
3 Acceptance, test and Commissioning 1 5%
C. Demobilization 0%
WORK WK
PLDT Mandurriao 120 Days
Sep Oct Nov Dec Jan Feb Mar April May
Item Scope of Work (SOW) PLAN ACTUAL 39 40 41 42 43 44 45 46 47 48 49 50 51 52 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
A. Pre-Implementation Works
1 Material Preparation 5 3
2 SKOM (CME) 1 1
3 Material Delivery 9 3
4 Delivery 1
5 Mobilization 1
B. Implementation Permitting Issue on Site and contractor issue
B1 EQUIPMENT ROOM
1 SITE CLEARING & DEMOLITION 12
2 EARTH WORKS 7
3 STEEL WORKS 21
4 CARPENTRY WORKS 10
5 ROOFING WORKS 10
6 CONCRETE POURING WORKS 7
7 MASONRY WORKS 14
8 FINISHING WORKS 14
9 ACCEPTANCE & TURNOVER 7
B2 UNDERGROUNG FST
1 EARTH WORKS 7
2 STEEL WORKS 5
3 CARPENTRY WORKS
4 CONCRETE WORKS 7
5 ACCEPTANCE & TURNOVER
SERVICE ENTRANCE PEDESTAL
1 EARTH WORKS
2 STEEL WORKS
3 CONCRETE POURING WORKS
B3 Concrete Encasement Handhole
1 Site Clearing and Excavation 7
2 Rebar, Piping 7
3 Gravel Bedding 3
4 Concrete works 2
5 Cable laying ,pulling 5
B4 Argus (4 Modules)
1 Purchase of Argus rectifier Module 1
2 Delivery And installation (plug in) 1
3 Acceptance 1
B5 Electrical works (1x50KVA)
1 General Requirements / Preliminaries
2 Processing and application of Electrical Permit 10
3 Panel boards 10
Backfill
2ND LIFT
P.
o.
R
E
L
E
A
S
E
D
IMPLEMENTATION
September October
Week 35 Week 36 Week 37 Week 38 Week 39 Week 40 Week 41 Week 42 Week 43
29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
30%
100%
30%
2%
1%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
100%
100%
100%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
R
e
c
t
i
f
i
IMPLEMENTATION
WORK WK e June July
PLDT Mintal RSU 45 Days W
r
Week 22 Week 23 Week 24 Week 25 Week 26 Week 27 Week 28 Week 29 Week 30 PROGRESS
aiV STATUS Dependency
Item Scope of Work (SOW) PLAN ACTUAL (%)
tie1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
nn
A. Pre-Implementation Works gd
foo
1 Material Preparation 3 3 rr 100%
2 1 P 100%
SKOM 1 LI
3 8 Ds 50%
Material Delivery (ACU, & Rectifier, Battery) 5 Ts
4 Mobilization Su 5%
pe
B. Implementation / Concern a
cD
B1 Cooling System ee
isl
1 Chipping Works Relocation of WACU 3 sa 100%
uy
2 Cable Works - Electrical Works 2 ee 50%
ad
p
3 1 pd 5%
StartUp Activity , Testing, Commissioning and Acceptance ru
B2 DPC Rectifier (300A to 500A) oe
v
1 DPC Rectifier Delivery 5 alt 5%
o
2 Delivery on site 1 P 5%
3 2 a 5%
Installation, Mounting of Rectifier System n
4 Cabling Works - Electrical Works 2 d 5%
e
5 PowerUp / Start up 1 m 5%
i
B3 2x300AH Battery Banks c
1 Battery Available at WH 5 100%
2 Delivery to Site 1 100%
3 Postioning and Mounting of Battery Rack 1 5%
4 Cable Ladder Installation 1
5 Laying of DC Cable 1 5%
6 Cutover Activity / Powerup of battery 1 5%
7 Acceptance, test and Commissioning 1 5%
B4 Battery and Load Migration
1 Cabling Works 3 5%
2 Termination 1 5%
3 Acceptance, test and Commissioning 1 5%
C. Demobilization 0%
WORK WK
PLDT Pikit 150 Days Sep Oct Nov Dec Jan Feb March April May
7 1
StartUp Activity , Testing, Commissioning and Acceptance
B4 GENSET SHELTER
1 SITE CLEARING & DEMOLITION WORKS 7
2 EARTH WORKS 7
3 STEEL WORKS 35
4 CARPENTRY WORKS 20
5 CONCRETE POURING WORKS 7
6 MASONRY WORKS 10
7 FISNISHING WORKS 10
8 ACCEPTANCE & TURNOVER 5
B5 FST SHELTER
1 EARTH WORKS 5
2 STEEL WORKS 14
3 CONCRETE WORKS 2
4 ROOFING WORKS 2
B6 C.R. 2
6 EARTH WORKS 5
7 STEEL WORKS 7
8 CONCRETE WORKS 5
9 ROOFING WORKS 7
10 SEPTIC TANK WORKS 14
B7 Electrical works (3x75KVA)
1 General Requirements / Preliminaries
2 Processing and application of Electrical Permit 10
50%
100%
30%
40%
On going Limestone soil
100%
100%
100%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
50%
10%
2%
2%
2%
2%
2%
2%
2%
2%
50%
50% OG Limestone
5%
5%
5%
5%
5%
5%
5%
5%
5%
5%
5%
5%
5%
3%
3%
3%
3%
3%
3%
3%
WORK WK
PLDT Pontevedra 90 Days Nov Dec Jan Feb Mar April May
Week 26
Item Scope of Work (SOW) PLAN ACTUAL 45 46 47 48 49 50 51 52 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 27 28 29 30 1 2
A. Pre-Implementation Works
1 Material Preparation 3 3
2 SKOM 1 1
3 Material Delivery (ACU, Panels & Rectifier, Battery) 8
4 Mobilization
B. Implementation / Concern Additonal SOW from site as per actual site condition Contractor issues
100%
100%
50%
50%
100%
100%
100%
100%
100%
100%
3%
3%
3%
3%
3%
3%
3%
3%
3%
3%
3%
3%
3%
WORK WK
PLDT Tacurong 150 Days
Sep Oct Nov Dec Jan Feb Mar April May
Week 26
Item Scope of Work (SOW) PLAN ACTUAL 39 40 41 42 43 44 45 46 47 48 49 50 51 52 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 27 28 29 30 1 2 3
A. Pre-Implementation Works
1 Permitting 5 8
2 Material Preparation 5 3
3 SKOM (CME) 1 1
4 Material Delivery (Rec, battery, ACU, DCPDB) 9 3
5 Mobilization (DC + CME) 1
B. Implementation / Concern Contractor Issue Contractor on hold ( PO issue
6 2
StartUp Activity , Testing, Commissioning and Acceptance
B5 NEW EQUIPMENT BLDG.
1 SITE CLEARING & DEMOLITION WORKS 7
2 EARTH WORKS 14
3 STEEL WORKS 30
4 CARPENTRY WORKS 20
5 CONCRETE POURING WORKS 10
6 MASONRY WORKS 7
7 FISNISHING WORKS 7
8 SEPTIC TANK WORKS 14
9 ACCEPTANCE & TURNOVER 5
B6 GENSET SHELTER
1 SITE CLEARING 7
2 EARTH WORKS 14
3 STEEL WORKS 30
4 CARPENTRY WORKS 20
6 CONCRETE POURING WORKS 10
7 MASONRY WORKS 7
8 FINISHING WORKS 7
9 ACCEPTANCE & TURNOVER 5
B7 FST SHELTER
1 EARTH WORKS 7
2 STEEL WORKS 5
3 CONCRETE WORKS 5
4 TUBULAR PIPE COLUMN 14
5 ROOFING WORKS
6 ACCEPTANCE & TURNOVER
SERVICE ENTRANCE PEDESTAL
1 EARTH WORKS
2 STEEL WORKS
3 CONCRETE POURING WORKS
B8 Electrical works (3x37.5KVA)
1 General Requirements / Preliminaries
2 Processing and application of Electrical Permit 10
100% LGU's
30%
100%
30%
1%
15%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
2%
IMPLEMENTATION
WORK WK July August September October November December
PLDT Talisay 120 Days
Aug Sep Oct Nov Dec Jan Feb Mar April May
Week 26 Week 27 Week 28 Week 29 Week 30 Week 31 Week 32 Week 33 Week 34 Week 35 Week 36 Week 37 Week 38 Week 39 Week 40 Week 41 Week 42 Week 43 Week 44 Week 45 Week 46 Week 47 Week 48 Week 49 Week 50 Week 51 Week 52 PROGRESS STATUS Dependency
(%)
Item Scope of Work (SKOM, DATE DURATION) PLAN ACTUAL 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1
A. Pre-Implementation Works
1 Material Preparation 6 7 100%
2 SKOM 1 1 100%
3 SKOM (CME) 1 1 100%
4 Material Delivery 1 1 100%
5 Delivery. 1 1 100%
6 Mobilization (DC + CME) 2 2 100%
B. Implementation / Concern Site Issue Contractor Issue Contractor and PO Issue Contractor Issue for CW and Waiting for Additional Materials
B1 Acbel (10 Modules)
1 Purchase of Argus rectifier Module 2 2 100%
2 Delivery And installation (plug in) 1 1 100%
3 Acceptance 1 1 100%
B2 New Battery 2x1000AH
1 Delivery to Site (rack and battery) 2 2 100%
2 Laying of Additonal Cable 2 2 100%
3 Postioning and Mounting of Battery Rack 1 1 100%
4 Test and Commisioning. 1 1 100%
B3 NEW GENSET SHELTER P.
1 SITE CLEARING & DISMANTLING WORKS 7 o.
2 EARTH WORKS 7
R Backfill
3 STEEL WORKS 5 E
4 CARPENTRY WORKS 10 L Formworks and Scaffolds
E
5 CONCRETE POURING WORKS 7
A
2ND LIFT 3rd Lift S.O.G.
6 MASONRY WORKS 5 S
7 FINISHING WORKS 7 E
8 ACCEPTANCE & TURNOVER 7 D
B4 AC Upgrade Internal
1 Fabrication of PanelBoard / PDI and Delivery on Site 100%
2 Installation of PanelBoard. 100%
3 Electrical works and Grounding Works 3 30% On going Waiting for 60mm, Grounding wires
4 Additional Pullbox and Gutter Box Materials 2 5% On going On going Fabrication / IMC pipe not workable apsc
5 Waterproofing works, elastomeric membrane 2 5%
Installation of louver access door steel type louver door
6 (double swing steel type) 1 5%
A. Pre-Implementation Works
1 Material Preparation 7 7 100%
2 SKOM 1 1 100%
3 Panel Board Fabrication 7 7 100%
4 Material Delivery (Panels) 1 1 10%
5 Mobilization 1 1 100%
Replaced
B. Implementation / Concern Contractor Issue Site Issue TAP Request Delayed Contractor Iand PO issue and TAP approval c/o security
Partners
1 Main Cable Roughing Ins and IMC pipe installation 2 2 50% excavation (Cable Trench) ( Additional as per Fasman)
2 Rebars and Formworks. 3 3 100% Concrete Encasement Re-route
3 Piping Layout 2 2 100% Concrete Encasement Re-route
4 Handhole provisioning 1 1 100% Concrete Encasement Re-route
5 Concreting / Pouring 2 100% Concrete Encasement Re-route
6 Cabling Works / Pulling. 2 50% Concrete Encasement Re-route
7 Installation and Mounting of Panels 3 100%
8 Terminations. 1 80%
9 Testing and Commissioning 1 0%
C. Demobilization 1 0% 73%
Items Site Name Forecast Timeline
1 PLDT Sta. Maria Tumaga SSA WK 44
2 PLDT Tangub Wk 16
3 PLDT Talisay WK 17
4 PLDT Calinan RSU WK 47
5 PLDT Cavite WK 16
6 PLDT LUPON PHILCOM WK 17
7 PLDT Mambusao WK 39
8 PLDT Manapla WK 16
9 PLDT Mintal RSU WK 16
10 PLDT Cabadbaran WK 16
11 PLDT La Castellana WK 16
12 PLDT Bayugan WK 16
13 PLDT Tacurong WK 17
14 PLDT Pikit WK 17
15 PLDT ALABEL SSA WK 17
16 PLDT ALIMODIAN WK 18
17 PLDT MANDURRIAO WK 18
18 PLDT PONTEVEDRA WK 18
19 PLDT DAPITAN WK 2, 2022
20 PLDT LISP WK 18
21 PLDT ISULAN WK 18
22 PLDT BAYAWAN WK 19
23 PLDT SILAY WK 20
24
25
Status
Done
Done
Subcon issue
Done
Waiting for MOP c/o PLDT
ACU Done/ for DC
Done
Done 27-May-22
Waiting for DC space issue
Waiting for ACU
CME and DC Done/for RM/TVSS
ACU/Battery Migration Done/Load Migaration
On Going CME
On Going CME
Site Plan Revision for SFE approval
For SFE approval
On going for Permitting and for Subcon prep
Waiting for BOQ canvass sheet approval
Done
Partners Bond Issue
Waiting for Subcon
Done 18-May-22
Done 21-May-22
20
Item
No. Site Name Scope
CW
DC
1 PLDT Alabel
ACU
AC
CW
ACU
2 PLDT Alimodian AC
DC
ACU
3 PLDT Bais AC
DC
4 PLDT Bayawan
DC
DC
DC
5 PLDT Bayugan DC
AC
ACU
DC
6 PLDT Cabadbaran
AC
ACU
DC
AC
DC
8 PLDT Cavite
DC
9 PLDT Daanbantayan
DC
10 PLDT Dapitan 2 SSA DC
DC
CW
DC
ACU
11 PLDT ISULAN
AC
CW
DC
12 PLDT La Castellana
ACU
AC
DC
PLDT Lupon Philcom
13
Valencia Bukidnon AC
ACU
CW
ACU
14 PLDT LISP
AC
14 PLDT LISP
AC
CW
15 PLDT Mambusao ACU
CW
DC
16 PLDT Manapla
AC
AC
ACU
CW
DC
DC
17 PLDT Mandurriao
AC
DC
18 PLDT Mintal RSU
AC
ACU
DC
19 PLDT Oroquieta ACU
AC
CW
DC
ACU
20 PLDT Pikit
AC
CW
21
PLDT Pontevedra
21 DC
AC
ACU
DC
23 PLDT Sta. Maria Tumaga
SSA
CW
DC
ACU
24 PLDT Tacurong
AC
CW
25 PLDT Talisay DC
AC
CW
26 PLDT Tangub AC
DC
27 PLDT Silay DC
SKOM NTP
Scope of Work (Date) (Date)
3 x 2.5hp WACU
10-May-21 12-May-21
1 x ACU Panel
1 x 2.5HP WACU
EE Panels and AC Compliments
9 x 75A Rectifier Modules Argus
Load Migration (NEC to BAU Recti)/ Battery Migration
Sept 1 2021 Sept 1 2021
(NEC tp Argus)
New Battery 3X500AH
4 x 125A Rectifier Modules Acbel
02-May-21 24-May-21
15 x 30A Rectifier Modules Acbel
New Rectifier 1x150A ext 300A
DCPDB (wall mounted) 19-Nov-21 None
Load Migration
New Equipment Bldg.
New Genset Bldg
New FST Shelter
New Rectifier 2x1000A
New Battery 4x500AH
New 1xDCPDB and 1xOBR
Load Migration (Huawei to New DPC)
2 x 5TR
24-Jan-22 28-Feb-22
MCB, MDP,MTS-1, MTS-G, Mobile box, EMDP, MDP-
2,ELPP,ELP,EPR-1,EPR-2,ACU Panel, 2xECB(FCU),
2xECB(ACCU)
External 3x37.5KVA
Internal 1x125KVA Genset
200L Daytank
1500L FST
1 x 400Amps ATS
WACU wall restoration
New Rectifier 1x300
New Battery 2x300AH
Load Migration
w/1xModified Rack Sept 8 2021 Sept 15 2021
2 x 4KW Rectifier Modules Huawei
TVSS 1 Phase
1 x 2.5HP STACU, SP @Recti Room
EE Panels and Ac Compliments
New Rectifier 1x300A ex to 500A
New Battery 2x300AH
Load Migration (Huawei to New DPC) Sept 1 2021 Sept 1 2021
EE Panels and AC Compliments
2 x 3TR STACU
New FST Shelter
EE-Genset room expansion
Service entrance pedestal
3 x 3TR STACU
1x80KW Genset (Enclosed Type) 24-Nov-21 15-Dec-22
1500L FST
24-Nov-21 15-Dec-22
22-Oct-21 05-Nov-21
New Rectifier 2x200A exp to 500A
New Battery 2x200AH w/2xModified Rack 22-Oct-21 05-Nov-21
Load Migration (Delat &Acbel to New DPC)
MDP, ACU PANEL, EPR
2 x 2.5HP WACU
6 x 75A Rectifier Modules Argus (System A) None None
6 x 75A Rectifier Modules Argus (System B)
1 x 400A exp to 500A Rectifier
2 x 500AH Battery Bank Jul 7 2021 Aug 17 2021
Load Migration
New Equipment Building
New Genset Shelter
New Fuel Storage Tank Shelter
New Rectifier 2x1000A Sept 15 2021 15-Nov-21
New Battery 4x500AH
New 2xDCPDB and 1xOBR
Load Migration (Delta & GP to New DPC)
2 x 5TR STACU
New 3x37.5KVA Transformer
New 1x100KW Genset
New 1x2000L FST
New 1x300L Daytank
New 1 x 400Amps ATS
1xMDP, 1xMCB OD, 1xATS, 1xMTS-1, 1xMTS-G, 1xMB,
1xEMDP, 1xACU Panel, 2xECB ID, 2xECBxECB OD, PR
Panel, 1xEPR-1, EPR-2, 1xELPP, 1xELP
3x 160KA TVSS
Genset shelter (Open Type), pipe trench and cable
Aug 27 2021 Sept 6 2021
concrete encasement
10 x 55A Rectifier Modules Acbel Aug 16 2021 Aug 16 2021
2 x 1000AH Battery Bank Aug 16 2021 Aug 16 2021
1x500L Daytank Sept 6 2021 Sept 6 2021
1x250KW Genset (Enclosed Type) Sept 6 2021 Sept 6 2021
Handhole and Cable concrete Encasement
MCB,ECB,MTS-1, Mobile box Jul 22 2021 Aug 17 2021
Load Migration
None None
Batteries and DPC rectifier from BAYAWAN
Percentage per Week
Implem Start Implem Start
STATUS Plan Actual WK 22 WK 23
Revised (OBO req't) SFE Approval Wk 8 10% 10%
For Mobilization Wk 8 5% 5%
For Mobilization
On Hand Wk 8 10% 10%
On Hand Wk 8 20% 20%
For Manufacturing Wk 8 5% 5%
For Mobilization Wk 10 5% 5%
For Fabrication Wk 10 5% 5%
For Manufacturing WK 18 2% 2%
For Manufacturing WK 18 2% 2%
For Manufacturing WK 18 2% 2%
For Manufacturing WK 18 2% 2%
For Manufacturing WK 18 2% 2%
Completed Wk 45 Wk 47 100% 100%
Completed Wk 10 Wk 3 100% 100%
Completed Wk 10 Wk 3 100% 100%
Completed Wk 8 Wk 3 100% 100%
Completed Wk 45 Wk 3 100% 100%
For Manufacturing Wk 45 15% 15%
For Manufacturing Wk 45 15% 15%
Completed Wk 45 Wk 47 100% 100%
Completed Wk 45 Wk 47 100% 100%
On Hand WK 35 WK 48 15% 15%
On Hand 50% 50%
For Manufacturing Wk 15 5% 5%
For Mobilization (Services) Wk 15 5% 5%
Completed WK 32 WK 32 100% 100%
Completed 100% 100%
Completed WK 36 WK 20 100% 100%
Completed WK 36 WK 20 100% 100%
Completed Wk 50 Wk 5 100% 100%
Completed Wk 50 Wk 5 100% 100%
Completed Wk 45 Wk 47 100% 100%
Completed Wk 45 Wk 47 100% 100%
Completed Wk 45 Wk 47 100% 100%
For Mobilization (Services) Wk 10 3% 3%
For Fabrication Wk 10 5% 5%
For Fabrication Wk 50 5% 5%
For Fabrication Wk 50 15% 15%
For Manufacturing Wk 50 5% 5%
On Hold Wk 9 2% 2%
For Plan approval Wk 10 2% 2%
On Hand Wk 9 5% 5%
On Site Wk 9 5% 5%
Panels on Site Wk 9 2% 2%
On Going Implementation Wk 9 7% 7%
For Manufacturing Wk 9 5% 5%
For Manufacturing Wk 9 5% 5%
5% 5%
2% 2% For MOB
2% 2% WK 35 For MOB
2% 2% For MOB
2% 2% For MOB
2% 2% For MOB
2% 2% For MOB
2% 2% For MOB
2% 2% For MOB
100% 100% Wk 50 Wk 2 For COD
100% 100% WK 4 WK 9 For COD
100% 100% WK 4 WK 9 For COD
100% 100% WK 4 WK 9 For COD
100% 100% WK 4 WK 9 For COD
15% 15% WK 18 Existing Model Phase Out
15% 15% WK 18
100% 100% Wk 50 Wk 2 For COD
100% 100% Wk 50 Wk 2 For COD
15% 15% WK 20 For Delivery on site
50% 50% On Hand
5% 5% For MOB
5% 5% Wk 15 For MOB
100% 100% WK 41 For Billing-COD Submitted
100% 100% For Billing-COD Submitted
100% 100% WK 20 WK 21 For COD
100% 100% WK 20 WK 21 For COD
100% 100% WK 20 WK 21 For COD
100% 100% WK 21 WK 21 For COD
100% 100% Wk 17 Wk 13 For COD
100% 100% Wk 17 Wk 13 For COD
100% 100% Wk 17 Wk 13 For COD
3% 3%
10% 10%
5% 5% On Hand
5% 5% Wk 15
15% 15% Wk 15
5% 5% Wk 15
2% 2% On Going with Issue
2% 2%
5% 5% Wk 5 Barrowing from another proj
5% 5% Delivered on site
2% 2% Delivered on Site
7% 7%
10% 10% Wk 15
5% 5% Wk 15
5% 5% Wk 15
20% 20% Wk 15 On Going Fabrication
5% 5% Wk 15
5% 5% Wk 15
CW
DC
1 PLDT Alabel
ACU
AC
CW
DC
AC
CW
DC
7 PLDT La Castellana
ACU
AC
CW
8 PLDT LISP
CW
8 PLDT LISP ACU
AC
DC
CW
DC
AC
CW
CW
DC
13 PLDT Pontevedra DC
AC
ACU
CW
DC
DC
15 PLDT Talisay
AC
CW
16 PLDT Tangub AC
SKOM NTP
Scope of Work (Date) (Date)
For Mobilization Wk 19 5% 5% 5%
5% Wk 35
Final Inspection w/ SO done
5% Wk 35 Final Survey Done
5% Wk 35 SO request for another Survey
5% Wk 35
100% WK 2 WK 2 For COD
100% Wk 23 Wk 12 For COD
50% Wk 10
100% Wk 15 Wk 15 Accepted
100% Wk 15 Wk 15 Accepted
10% WK 27 New ETA Status tobe confirm
20% WK 27 Waiting for TAP approval
20% Wk 25 For Mob ACU Ser: Wk 45
Item
No. Site Name Scope
AC
1 PLDT Tangub CW
DC
2 PLDT Talisay AC
CW
DC
PLDT LUPON
3
PHILCOM AC
ACU
CW
DC
16 PLDT Manapla
AC
AC
ACU
DC
5 PLDT Mintal RSU
ACU
DC
6 PLDT Cabadbaran
ACU
DC
7 PLDT La Castellana
ACU
CW
AC
DC
DC
8 PLDT Bayugan AC
ACU
DC
ACU
AC
9 PLDT Tacurong
9 PLDT Tacurong
CW
DC
ACU
AC
10 PLDT Pikit
CW
DC
ACU
11 PLDT Alabel AC
AC
CW
CW
ACU
AC
12 PLDT Alimodian AC
CW
DC
DC
AC
13 PLDT Mandurriao AC
AC
CW
DC
DC
CW
14 PLDT Pontevedra CW
AC
ACU
DC
15 PLDT ISULAN
ACU
15 PLDT ISULAN AC
CW
DC
16 BAYAWAN DC
DC
17 SILAY DC
SKOM NTP
Scope of Work (Date) (Date)
EE Panels and AC Compliments Jul 22 2021 Aug 17 2021
Handhole and Cable concrete Encasement
10 x 55A Rectifier Modules Acbel Aug 16 2021 Aug 16 2021
2 x 1000AH Battery Bank Aug 16 2021 Aug 16 2021
1x250KW Genset (Enclosed Type) and 500L DT Sept 6 2021 Sept 6 2021
Genset shelter (Open Type), pipe trench and cable concrete
Aug 27 2021 Sept 6 2021
encasement
New Rectifier 1x300A ex to 500A Sept 1 2021 Sept 1 2021
New Battery 2x300AH
EE Panels and AC Compliments
3 x 3TR STACU
Concerete Pedestal and Handhole
New Rectifier 1x300A
New Battery 2x 200AH
w/1xModified Rack Aug 17 2021 Sept 15 2021
EE Panels
AC upgrade ( Additional )
2x2.5HP WACU (Standby) @Rectifier Room
New Rectifier 1x300A exp. to 500A, SP Sept 8 2021 No NTP
New Battery 1x200AH battery
1 x 2.5HP WACU
New Rectifier 2x600A exp to 1000A Sept 9 2021 Sept 15 2021
New Battery 4x500AH
3 x 5TR STACU
New Rectifier 1x300 Sept 8 2021 Sept 15 2021
New Battery 2x300AH
Load Migration
w/1xModified Rack
2 x 4KW Rectifier Modules Huawei
1 x 2.5HP STACU, SP @Recti Room
WACU wall restoration
EE Panels and Ac Compliments
7 x 75A Rectifier Modules Argus Sept 8 2021 Sept 15 2021
2x1000AH LI ( Additional )/ Migration
Panels and AC Compliments
3 x 5TR STACU
New Rectifier 2x1000A Sept 15 2021 15-Nov-21
New Battery 4x500AH
New 1xDCPDB and 1xOBR
2 x 5TR STACU
New 3x37.5KVA Transformer
New 1x100KW Genset
New 1x1500L FST and 1x300L Daytank
New 1 x 400Amps ATS
EE Panels
3x 160KA TVSS
New Equipment Building
New Genset Shelter
New Fuel Storage Tank Shelter
4 x 2KW Rectifier Modules Argus Sept 15 2021 08-Nov-21
New 1xDCPDB and 1xOBR
1 x 3TR STACU
1 x 2.5HP WACU
New 3x75KVA Transformer
New 2x200KW Genset
New 1x3000L FST and 1x500L Daytank
New 1 x 700Amps ATS
EE Panels
1x 160KA TVSS
24-Jan-22 28-Feb-22
2 x 5TR
AC compliments
External 3x37.5KVA ( 3x50KVA) 24-Jan-22 28-Feb-22
Internal 2x125KVA
1 x 400Amps ATS
New Equipment Bldg. and Genset Shelter
New FST Shelter
Load Migration
NA NA
Dismantling Batteries and DPC rectifier
Load Migration
NA NA
Batteries and DPC rectifier from BAYAWAN
Implem Start Implem Start
STATUS Plan Actual WK 23 WK 24 WK 25
For Mobilization Wk 10 5% 5% 5%