Professional Documents
Culture Documents
Isu - Impact of Covid-19 On Ug. Construction
Isu - Impact of Covid-19 On Ug. Construction
Impact of COVID-
19 in Uganda’s
Construction
industry
M.ISU, R.SU
MSc CPM, Loughborough University, BSc (Hons) Building Economics
MRICS
C.IQSK, BORAQs
Director: ICM Consultants Ltd
Currently working as Quantity Surveyor with SSE Enterprise, UK
Overview of Session
• JBCC (Green Book) 2018- EOT Cl 36 …..Upon it becoming reasonably apparent that the progress of the
Works is or is likely to be delayed….. the Contractor shall forthwith give written notice of the cause of the delay……. an
application for adjustment of time shall not be valid unless accompanied by adequate supporting details to the satisfaction of
the Architect. Unlike the above Force Majeure is defined. Cl 36.2.10 Reasons beyond Contractor’s control, Nominated subies,
delay to secure skilled labour due to forces beyond his control. Cl 40.4 Termination by Either Party …..suspension of works for a
Continuous period of 60 days due to Force Majeure…
Contract provisions
• FIDIC- Has been proactive and created guidelines to deal with COVID-19 related issues (obviously no fit it all solution due
to variances created by amendments). The purpose in drafting the guidance memorandum is to help parties to a FIDIC contract
to consider mutually satisfactory solutions and avoid disputes arising between them.
• JCT Contracts- There’s no definition the term ‘force majeure’ and it is instead classified under Clause 2.26 as a
‘Relevant Event’ but not a Relevant Matter. As a relevant event, it potentially entitles the contractor to an extension of time but
will not result in loss and expense (as it is not a Relevant Matter)
• NEC Contracts- Cl 60.1.9 describes Force Majeure in everything except in name. AS a CE, this clause should give rise
to not only an extension of time, but additional monies as well. Under NEC, the Force Majeure Event must stop completion of
the Works, or completion of the Works by the dates shown on the Accepted Programme. EWNs need to be as soon as either the
Contractor or the Project Manager “becomes aware” of any matter which could increase the Prices, delay Completion etc.
• Bespoke/Non-Standard Contracts-
What happens if a contract does not include a force
majeure clause?
• Look at existing provisions in the contract. Look out for terms like ‘unforeseen conditions, prevent, hinder etc.
• Look out for details/entitlements under common clauses like Delays, EOT, termination,
• Doctrine of frustration- In the case of Howard & Co. (Africa) Ltd v. Burton (supra) Sir Daniel Crawshaw, J.A., stated: The onus
of proving frustration is on the party alleging it, and if that is proved, the onus is upon the other party to prove that it was self-
induced. Monday Eliab v Attorney General ((Civil Appeal No 16 Of 2010)) [2011] UGSC 12 (14 November 2011)-”Whether or
not there was frustration of contract is a question of fact and the respondent had a duty to prove it.” It is the respondent who
sought to rely on frustration to justify the termination of the contract. This being so, it was incumbent on the respondent to lead
evidence to prove that the contract was discharged by frustration as a result of the accident”
• If the contract lacks a force majeure clause, no particular relief will necessarily flow from situations the parties might consider
force majeure
• Request suspension by way of a contract variation (renegotiate terms) e.g. payment mechanisms, insurance provisions, etc
• notice periods, acting upon notices,…avoid no justifiable grounds are given for the failure to act.*
• Loss & Expense contract provisions & claims. Expenses the contractor may be entitled to and are not
reimbursable under any other provision of the contract.*
• Fluctuation clauses and escalation clauses. Escalation clauses allow a contractor to receive an increase in
its contract price if the costs go up
Opportunities
• Collaboration and working together*.
• Responsible and fair contractual behaviour- like
– being reasonable and proportionate in responding to performance issues and
enforcing contracts,
– requesting, and giving, relief for impaired performance, including in respect of the
time for delivery and completion
– requesting, and allowing, extensions of time
– making, and responding to, force majeure, frustration, change in law, relief event,
delay event, compensation event and excusing cause claims
– making, payment on time
• Leadership! Jobs- handling claims
• New ideas and innovations
The End