I) The Network Flow Diagram of The Project Is Given Below

You might also like

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 2

Task A B C D E F G H I

Time(Days) 8 10 8 10 16 17 18 14 9

i) The network flow diagram of the project is given below:

E = 28 L = 28
5
10 17
E = 18 B F E = 45
3 J 7
0
E=0 E = 8 10 L = 18 9 E = 54
L = 45
D I
1 A 2 1
8 0
E E = 24 E = 50 L
L = 54
L = 8 16 0
L=0 4 9
E = 32 L = 50
18
C G
L = 24
8 6 K 0
H
L = 32
14 8 E = 46
L = 46

Here the activity J, K and L are the dummy activities.

The Early Start time, Early Finish time, Late Start time and Late Finish time for all nodes
are given below,

Activity Early Start Early Finish Late Start Late Finish


A (1-2) 0 8 8 16
B (3-5) 18 28 28 38
C (4-6) 24 32 32 40
D (2-3) 8 18 18 28
E (2-4) 8 24 24 40
F (5-7) 28 45 45 62
G (6-9) 32 50 50 68
H (6-8) 32 46 46 60
I (7-10) 45 54 54 63
J (3-7) 18 18 18 18
K (8-9) 46 46 46 46
L (9-10) 50 50 50 50

You might also like