Professional Documents
Culture Documents
Evaluation of The Introduction of A Hydrogen Supply Chain Using A Conventional Gas Pipelinee A Case Study of The QinghaieShanghai Hydrogen Supply Chain
Evaluation of The Introduction of A Hydrogen Supply Chain Using A Conventional Gas Pipelinee A Case Study of The QinghaieShanghai Hydrogen Supply Chain
Evaluation of The Introduction of A Hydrogen Supply Chain Using A Conventional Gas Pipelinee A Case Study of The QinghaieShanghai Hydrogen Supply Chain
ScienceDirect
highlights
Introductory method of a hydrogen supply chain using gas pipeline was shown.
Economic and environmental benefits were clarified from the energy flow.
Potentiality of a large-scale clean energy using hydrogen was suggested.
Gas pipeline currently installed between Qinghai and Shanghai was analyzed.
Article history: A large-scale hydrogen supply chain is an alternative for the transportation of energy
Received 6 July 2020 generated from a renewable energy source. Utilizing this technology would drastically
Received in revised form improve the generation of clean energy. Therefore, an analysis method to estimate the
14 August 2020 economic and environmental benefits of the introduction of a hydrogen supply chain using
Accepted 2 September 2020 an existing pipeline is developed. The proposed method first estimates the energy and
Available online 29 September 2020 exergy flows in the system to calculate the overall efficiency of these quantities. Afterward,
the payback period is estimated based on the overall energy efficiency using the discounted
Keywords: cash flow (DCF) method. The overall efficiency of the system, based on the energy analysis
Hydrogen presented, would seem to be the final delivered electrical, fuel and useable heat energy
Supply chain delivered to end use divided by the input solar and wind energy. Furthermore, the envi-
Economic gain ronmental effects due to the introduction of the systems are evaluated considering the
Environmental impact reduction of global warming and air pollution gases, such as CO2 and PM2.5. The proposed
China analysis method was applied considering a natural gas pipeline that connects Qinghai and
Shanghai. As a result, conversion ratios of 24.9% for electricity and 17.5% for heat were
achieved, with the overall efficiency of the system of 42.4% based on the electricity ob-
tained from photovoltaics. 3.02 Gt of CO2, 104 kt of SOx, and 134 kt of NOx, which represent
3.3%, 0.5%, and 0.6% of the annual discharge in China, respectively, and 8.66 kt of PM2.5
would be reduced every year. Furthermore, a reduction of 953 Mt in coal consumption is
expected. The payback period of the proposed system using the DCF method is 4.17 and
* Corresponding author.
E-mail address: obara@mail.kitami-it.ac.jp (J. Li).
https://doi.org/10.1016/j.ijhydene.2020.09.009
0360-3199/© 2020 Hydrogen Energy Publications LLC. Published by Elsevier Ltd. All rights reserved.
i n t e r n a t i o n a l j o u r n a l o f h y d r o g e n e n e r g y 4 5 ( 2 0 2 0 ) 3 3 8 4 6 e3 3 8 5 9 33847
2.28 years for the two alternatives evaluated in this work. The cash flow of the DCF is
influenced by installation cost and operation cost of equipment.
© 2020 Hydrogen Energy Publications LLC. Published by Elsevier Ltd. All rights reserved.
electrolyzer, p_hg; 2 , could be quantified, as shown in Eq. (2). electrolyzer. P1 [Pa] and P2 [Pa] in Eq. (6) are the pressures
Furthermore, the enthalpy of the hydrogen outputted from the before and after the compression of the gas, respectively, n is
water electrolyzer, p_hg; 3 , was obtained based on the efficiency the polytropic index, n1 is the volume flow before compres-
of the water electrolysis, h_ we , and p_hg; 2 , as shown in Eq. (3): sion, and ha is the overall adiabatic efficiency. The actual
power consumption to compress the gas, Dp_cp , was evaluated
p_hg; 1 ¼ h_ wp ,p_wp þ h_ pv ,p_pv ¼ p_hg; wp;1 þ p_hg; pv;1 (1) when the total efficiency of the compressor and motor, rep-
resented as hgt , was considered, as indicated in Eq. (7):
!
p_hg; 2 ¼ hadc , p_hg;wp;1 þ hddc , p_hg;pv;1 ,hpcn (2) n1
1 n P2 n
Lc ¼ , , P1 , n1 , 1 (6)
ha n 1 P1
compressor was expressed by Eq. (11), while the enthalpy of Meanwhile, Eq. (16) represents the thermal power from the
hydrogen at the outlet, exj , was considered in Eq. (12): heat storage tank, p_h;out ; based on the efficiency of the backup
boiler, hbkb :
l,Lj ,W_ 2
Dp_hgc;exj ¼ Dp_hgp;exj Dp_hcp;exj (12) Eq. (17) indicates the energy balance in the SOFC, considering
the internal reforming of methane, where m_ is the molar flow
Energy flow on the demand side rate of fluid, h is the molar-specific enthalpy, rad is the reaction
rate in the anode, and m_ hm;in is the molar flow rate from the
Fig. 4 shows a diagram representing the energy flow on the heating medium. The terms on the left-hand side of this
demand side. The output of the fuel cell (SOFC), p_sofc;e , can be equation represent the enthalpy change in the anode, cath-
adjusted by controlling the convective heat transfer of the ode, and heating medium (to control the temperature of the
heating medium (air), Dp_sofc;tc . Air was supplied to the cathode fuel cell), and the energetic change of the chemical reaction,
of the SOFC as an oxidizer (p_sofc;cm ). Moreover, some of the respectively. In contrast, the right-hand side of the equation
represents the energy generated by the supplied hydrogen.
unused hydrogen (p_sofc;uh ), which is discharged from the
The working temperature of the SOFC is defined through Eq.
anode of the SOFC, was recovered and used as a fuel in the off-
(17). In situations in which the load changes, the operation
gas boiler. The heat generated from this combustion was,
temperature must be controlled.
therefore, combined with the high-temperature exhaust heat
(p_sofc;ofg ) of the SOFC. The thermal energy (p_ogb;h ) of the off-gas X
N XN
m_ ad;in;i , had;in;i hi þ m_ cd;in;i , hcd;in;i hi
boiler was, thereafter, stored in the heat storage tank, where it
i¼1 i¼1
could be supplied through the backup boiler (p_h;out ). In XM
contrast, the electric power (p_sofc;e ) of the SOFC was supplied þ m_ hm;in , hhm;in hhm;out þ hrc; j , rad;j
j¼1
through the power conditioner (p_e;out ).
¼ p_sofc;e þ Dp_sofc;rad þ p_sofc;ofg þ p_sofc;h þ Dp_sofc;tc
Economic gain
Exergy flow
In this study, the return of investment of the system is esti-
Exergy is the theoretical maximum workload that could be mated through the dynamic payback period, which was
obtained from a particular state until a steady state is reached. calculated with the DCF method. A discount rate was applied
As a result, the calculation of exergy considers environmental to account for the uncertainty of a future positive balance. As
quantities, such as the ambient temperature, T0 , and pressure, a result, this rate was positively affected by the risk of the
P0 . operation, reducing economic gain. The future cash flow and
the investment of the project were evaluated at the present, to
Heat flow rate enable the development of a cash flow plan. The net present
value (Vnpv ) and dynamic payback period (Pdb ) were taken into
When the logarithmic mean temperature difference, Tm , of an consideration by the DCF method.
object with temperature change is used, the exergy, e_h , obtained, Eq. (24) was used to calculate the years required to recover
considering the energy absorbed by the object, p_abs , is calculated the present value, Vnpv . Furthermore, t is the year of the project
by Eq. (20), which also represents the work of a Carnot cycle. period and n is the total project period, ðCin;t Cout;t Þ is a term
representing the difference of cash inflows, Cin;t , and outflows,
T0
e_h ¼ 1 ,p_abs (20) Cout;t , at t, and i is the discount rate:
Tm
n h
X i
t
Chemical reaction Vnpv ¼ Cin;t Cout;t ð1 þ iÞ (24)
t¼1
At the initial state, a substance of enthalpy, H_ 0 , entropy, S_0 , T* was defined as the year of the first positive balance, which
and flow rate, m_ g , reacts under temperature, T, generating a was used to calculate Pdb , as indicated in Eq. (25). Furthermore,
substance with output enthalpy, H_ p , and entropy, S_p . Vnpv were also considered to evaluate the Pdb . As the Vnpv is
Assuming this scenario, Eq. (21) can describe the maximum modified through the years, Pdb is a more accurate quantity to
work, e_heat;T , that can be extracted from this chemical reaction: estimate the years required to recover the investment when
compared with Vnpv .
e_heat;T ¼ m_ g , H_ 0 H_ p T , S_0 S_p (21) TX
* 1 .
Pdb ¼ T* 1 þ Vnpv Vnpv;T* (25)
Furthermore, Fig. 5 shows a chemical reactor in which t¼1
Case study
Table 5 e Specifications of the heat supply system. Owing to the high levels of solar radiation, as shown in Fig. 8
Off-gas boiler 90% [20], the introduction of photovoltaic energy generation in the
Heat storage tank 95% surrounding area of Qinghai is profitable. As a result, the
Backup boiler 92%
proposed hydrogen production plant was assumed to be
installed in Qinghai. Furthermore, the water used in the
result, this area is suitable for photovoltaic generation. In electrolysis process was supplied by a nearby river.
contrast, Shanghai is a large commercial town, with a popu-
lation of 24, 280, 000 people; therefore, it is a prominent energy Analysis setup
demand of China.
In the investigations of the energy and exergy flows of the
Energy network in China proposed system, the following hypotheses were assumed:
A high-voltage transmission line between the eastern and - The maximum efficiency of the equipment was obtained
western areas of China is not installed; Fig. 6 shows the main considering the rated power.
33854 i n t e r n a t i o n a l j o u r n a l o f h y d r o g e n e n e r g y 4 5 ( 2 0 2 0 ) 3 3 8 4 6 e3 3 8 5 9
Equipment costs
Transportation cost
- The system was in a rated operation. compressors, power conditioners, and heat equipment in
- The heat loss of the SOFC due to radiation was considered Table 5 were also quantified considering that they were
in the electric generation efficiency. general-purpose products.
The volume flow of the hydrogen transported was Facilities cost and finance
assumed to be the same as that of the present natural gas Table 6 shows the installed capacity and cost of the equip-
under the same pressure. As a result, a flow of 1.071 108 t/ ment used in the proposed facility, while Table 7 shows the
year could be achieved, resulting in 1.519 1013 MJ/year values used in the DCF method to evaluate the finances of
(4.16 1010 MJ/day) when the heat generated by the hydrogen the operation [5]. The other operating costs and the con-
was calculated. Furthermore, an area of approximately struction cost in Table 6 were obtained based on the differ-
25 km 25 km (equivalent to 120 GW) for a photovoltaic power ence of system capacity of reference [5] and the capacity of
plant was required to achieve these values. the proposed system. Section Energy network in China,
Section Analysis setup, and Section Environmental benefits
Photovoltaics and water electrolyzer has described the value of others in Table 6. The total proj-
The cost of photovoltaic facilities was assumed to be USD 250/ ect period was estimated to be 22 years, which was
kW [21]. Furthermore, an outdoor air temperature of 295 K and composed of the construction period (2 years) and the
a pressure of 0.101 MPa were considered the standard condi- operation period (20 years). The price of the SOFC cogene-
tions of the system when the electricity of photovoltaics was ration was evaluated considering the Japanese industrial
supplied to the water electrolyzer through a DCeDC converter. SOFC cogeneration as a reference. The pipeline pressure
The output pressure of the water electrolyzer, which worked drop was 7.93 kPa/km, and the pressure ratio of the
with a proton exchange membrane, was 0.1 MPa (gauge). compressor station, where the inlet pressure was approxi-
Table 3 indicates the efficiencies of the electrical system and mately 7 MPa, was 1.4. As a result, a compressor station was
water electrolyzer, which were assumed considering they
were commercial products.
Table 7 e Financing costs [5].
SOFC and heat supply system Discount rate 8%
Tables 4 and 5 show the setting conditions of the SOFC and Loan interest 5%
Equity/debt 30%/70%
heat supply system. Although the percentages of outputted
Repayment period 10 years
electricity and heat of the SOFC differ based on the operation
Operation period 20 years
method, a fixed value was used in this case study to simplify Value-added tax rate 8.50%
the calculations. The efficiencies of the inverters, Income tax rate 20%
i n t e r n a t i o n a l j o u r n a l o f h y d r o g e n e n e r g y 4 5 ( 2 0 2 0 ) 3 3 8 4 6 e3 3 8 5 9 33855
installed every 378 km, leading to seven compressor stations satisfactory [19], the pipeline's improvement cost does not
in the operation. The energy loss due to the compression in take into consideration.
the 3000-km gas pipeline was approximately 2.8%, which The period to pay the fixed cost was 10 years and large-
was similar to a reference value of approximately 1% of scale maintenance was assumed to be implemented in 10
energy per thousand kilometers. The installation cost of the years after the start of commercial operation. Moreover, the
booster compressor is taking into consideration. Moreover, discount rate of a renewable energy project in China usually
API-X70 pipeline's hydrogen embrittlement is almost varies from 6% to 10%. The value-added tax rate was half the
sum in the price of the renewable energy project, which is a cogeneration were sold to the consumer. Meanwhile, in the
commonly applied rate in China for this type of project. gas alternative system, the selling price of hydrogen was
Meanwhile, the income tax rate was estimated based on the determined based on the same quantity-of-heat unit price of
government tax rate in China for the renewable energy the previously used natural gas.
industry. Fig. 12 compares the economic gain results of both alter-
Water electrolyzer is interconnecting with electricity gen- natives. By integrating the cost, income, and expenditure, the
eration of the photovoltaics. Therefore, the capacity factors of simple cumulative cash flow and cumulative cash flow by net
the water electrolyzer and photovoltaics is 15%. The capacity present value were obtained, as shown in Fig. 12(a). As the
factors of the fuel cell differ with operating pattern by the discount rate included the risk of investment in the cumula-
demand side. In this analysis example, the capacity factors tive cash flow of the net present value, the results of this cu-
(60%) of a home cogeneration is applied. mulative cash flow were lower than those of the simple
cumulative cash flow. After the project is finished (22 years),
Analysis results the simple cumulative cash flow would be approximately 2.8
and 2.4 times higher than the cumulative cash flow with the
Energy and exergy flows net present value in the power plant and gas alternatives,
Figs. 9 and 10 show the analysis results of the energy and the respectively.
exergy flow distributions, respectively. According to Fig. 9, with The time to recover the investment, considering the simple
the proposed hydrogen supply chain, 24.9% and 17.5% of the cumulative cash flow, was 2 years for both systems, and
photovoltaic generation could be converted into electricity and profits occur from after the third year, as shown in Table 8. In
heat, respectively, corresponding to the overall efficiency of the contrast, the time to recover the investment when using the
system of 42.4%. Meanwhile, Fig. 11 shows the magnitude of the net present value was 3 and 2 years, with the power plant and
energy and exergy losses. As a result, the conversion loss of gas alternative systems, respectively. Moreover, Pdb was 4.17
water electrolysis (16%) represented the largest loss, followed by and 2.28 years, for each alternative, respectively. These values
the DCeDC converter of photovoltaics (10%) and power condi- were significantly different when compared to the difference
tioner (9%). In contrast, the highest exergy losses were due to the of years to recover the investment calculated from the simple
water electrolyzer (16%), DCeDC converter (10%) of photovoltaic cumulative cash flow; therefore, the economic gain of the
generation, power conditioner (9%), hydrogen compressor system should be carefully evaluated.
(11.4%), and booster compressors (9%). As a result, the large As compared with the economical efficiency result of the
exergy losses in the system were attributed mostly to natural gas transportation containing hydrogen by Liu et al.
electricesubstance (water electrolyzer), electriceelectric [5], the result of the dynamic payback period of this study is 1/
(DCeDC converter and power conditioner), and electricework 4 to 1/3. The efficiency of the fuel cell cogeneration introduced
(compressor) conversions. Moreover, the final exergy effi- into urban areas was high, and the price of electricity and heat
ciency obtained from the proposed system was 19.4% and 18.4% supply was more inexpensive than the conventional method.
considering the output of electricity and heat, respectively. Fig. 12(b) shows the variations in the cost components
One possibility to improve the efficiency of the proposed considering the project period, while Fig. 12(c) shows the sum
system is to reduce the loss of the electrical machinery and of the costs of Fig. 12(b). Where, some taxes are not included in
apparatus (DCeDC converter and power conditioner) coupled Fig. 12 (b). The fixed cost was paid in the first 10 years and the
with photovoltaic generation by using the exhaust heat of the large-scale maintenance was implemented 10 years after the
electrical machinery and apparatus. A technique or system initialization of commercial operation. The cost of the SOFC
configuration that results in an efficiency of water electrolysis was the largest (53.5%) for the power plant alternative system,
above 80% was not found in the literature; however, most while the water electrolyzer represented the largest values
improvements in the efficiency of the process have focused on (36.7%) for the town gas alternative system. The cost per-
the utilization of exhaust heat. centage of hydrogen compression (including the booster
compressor) was 4% and 8.6% in the power plant and town gas
Economical gain alternative systems, respectively. The personnel expenses
By examining the economic gain, electricity generation and were 3.2% in the power plant alternative system and 7% in the
waste heat management are analyzed considering the power town gas alternative system. From these results, the costs of
plant alternative system and a scenario in which the hydrogen the energy equipment, such as the SOFC, and the water
supplied is used to generate heat (gas alternative system). In electrolyzer, influenced the economic efficiency significantly.
the first case, both electricity and heat generated from SOFC Furthermore, although the SOFC is not manufactured globally,
the reduction of its future price is estimated and required to
increase the economic gain of this project.
Table 8 e Analytical results of the payback period.
Power plant Town gas Environmental benefits
alternative alternative The standard coal-fired power generation in China may be
system system replaced by the town gas alternative of the hydrogen power
Simple cumulative cash flow 2 years 2 years supply chain that connects Qinghai to Shanghai.
Net present value (NPV, Vnpv ) 16,850 M$ 5800 M$
Internal rate of return (IRR) 32% 29% Power plant alternative system. The hydrogen quantity,
Dynamic payback period (DPBPPdb ) 4.17 years 2.28 years
which would be supplied to Shanghai from Qinghai, is
33858 i n t e r n a t i o n a l j o u r n a l o f h y d r o g e n e n e r g y 4 5 ( 2 0 2 0 ) 3 3 8 4 6 e3 3 8 5 9