Structure Rates with shuttering -Ganga Expessway Phase-II

Box MNB/MJBR/R
Box
Structures / OB/FO
Sl No. Description of items Unit Culvert Remarks
Underpasses (Girder Type /
/ HPC
/ MNB Circular shaft)

Pouring of concrete, vibrating, and final finishing by means of manually/


mechanically as per the instruction of Engineer in charge (Items including
1 shuttering materials, Moulds, curing, site lighting, shuttering &
Deshuttering,shifting, staging etc) for below activities of Major Bridges, Minor
Bridge, Vaiduct,Culvert, Under passes & ROB & etc.
For M-15 Grade for PCC at the excavated bed of the structure at the desired level
i Cum 400 400 400
and alignment.

For all grade of Concrete for execution of Foundation, Raft, Pile cap &
ii Cum 900 900 900
Foundation for Retaining Structure as per technical drawings & specifications.

For all grade of Concrete for execution of Abutment wall/Shaft & Pier Wall/Shaft
iii (a) Cum 1400 1400 1400
Substructure as per technical drawings & specifications.

For all grade of Concrete for execution of Abutment wall/Shaft & Pier Wall/Shaft
iii (b) Cum 1800
Substructure as per technical drawings & specifications. (For Circular type)

For all grade of Concrete for execution of Abutment Cap, Pier and Column, Dirt
iv(a) Cum 1400
Wall and Bracket as per technical drawings & specifications. (For MJB / MNB)

For all grade of Concrete for execution of Abutment Cap, Pier and Column, Dirt
iv(b) 2100
Wall and Bracket as per technical drawings & specifications. (For GS / VUP/ ROB)

For all grade of Concrete for execution of Pier Cap & Pedestal as per technical
v Cum 2100
drawings & specifications.
For all grade of Concrete for execution of Wall's of Box type Structure as per
vi Cum 1400 1400
technical drawings & specifications.
For all grade of Concrete for execution of Slab in Box structure as per technical
vii Cum 2100 2100
drawings & specifications.
For all grade of Concrete for execution of Superstructure for Pre Cast PSC Girder
as per technical drawings & specifications. Girder Shutter shall be provided by
viii Cum 2000
HGIEL.
Note:Rates are inclusive of bed PCC
For all grade of Concrete for execution of Superstructure for Pre Cast RCC Girder
as per technical drawings & specifications. Girder Shutter shall be provided by
ix Cum 2000
HGIEL
Note:Rates are inclusive of bed PCC
For all grade of Concrete for execution of Superstructure for Deck Slab (with
x Cum 2500
Staging) as per technical drawings & specifications.

For all grade of Concrete for execution of Superstructure for Deck Slab (with
xi Deck plank) as per technical drawings & specifications. Cum 1700
Not:- In case of Deck plank
For all grade of Concrete for execution of Approach Slab as per technical
xii Cum 900 900 900
drawings & specifications.
For all grade of Concrete for execution of Retaining/Return Wall as per technical
xiii Cum 1400 1400 1400
drawings & specifications.

Laying & Pouring of PCC/RCC concrete for Curtain wall, Toe wall, Cut off wall etc..
The rates are including The rates are including cost of Shuttering/Staging material,
xiv Cum 900 900 900
cost of fixing of shuttering material with proper supports & removal of shuttering
material & proper curing arrangements.

For all grade of Concrete for execution of Crash Barrier as per technical drawings
xiv (a) Rm 1100 1100 1100
& specifications.
Box MNB/MJBR/R
Box
Structures / OB/FO
Sl No. Description of items Unit Culvert Remarks
Underpasses (Girder Type /
/ HPC
/ MNB Circular shaft)

Labour charges for Cutting, Bending , shifting & Fixing of Reinforcement as per
the drawing and instruction of Engineer in charge including all consumable like
2 MT
binding wire, cover block, electricity, cutting & bending machine etc complete for
above activities.

2a Steel cutting / bending (Central Cut & Bend yard) MT 1600 1600 1600
Steel placing in position and binding as per technical specification including cost of
2b MT 3750 3750 3750
binding wire
Laying & Pouring of PCC/RCC concrete for Headwall. The rates are including cost
3 of Providing and fixing of shuttering material with proper supports & removal of Cum 1150
shuttering material & proper curing arrangements.

4 Laying & Pouring of Cradle concrete for Pipe Culvert. The rates are including cost Cum 800
of fixing of Providing and shuttering material with proper supports & removal of
shuttering material & proper curing arrangements

Laying & Pouring of Encasing slab for pipe culvert. The rates are including cost of
5 Providing and fixing of shuttering material with proper supports & removal of Cum 800
shuttering material & proper curing arrangements
Pipe Laying/fixing with bed preparation-600 mm dia 1200 dia.JCB & Hydra shall be
6 in Contractor's scope. Pipe shall be supplied by HGIEL at site. Rmt. 250

Providing and fixing weep holes with 100 mm dia PVC pipe, extended through the
7 Rm 145 145 145
full width as per drawing and direction of Engg. Including cost of PVC Pipe.

Labour Charges for fixing of Expansion Joints as per drawing and direction of
8 Rm 1500 1500
Engg.
Labour Charges for fixing of All types of Bearings as per drawing and direction of
9
Engg.
i Elastomeric Bearing Nos 500 500

ii POT PTEF Bearing Nos 1500 1500


Special Terms and Conditions
1 Structural rates included with shuttering.
2 Terms and conditions are as per attached scope matrix.
Scope Matrix
Structure Rates Works
Sr. No. Description of item with shuttering -Ganga HGIEL
Expessway Phase-II

1 Labour for construction activity-Skilled/Unskilled Y

2 Labour Accommodation and Fooding arrangement of Labours Y


Water for Labour Camp & construction activity
3 Y
(PRW Contractor may carry the water from HGIEL Camp by his own vehicle)
4 Lighting arrangement for Labour Camp Y

5 Land for labour camp(Construction Site Location) Y

6 Transportation of labour upto site and site to site both Y

7 Labour for Loading/Unloading of Material Y

8 Shuttering/staging/Scoffolding Material Y

9 Safety/HSE/ PPE’s Y

10 Safety and security of construction material/machine Y

11 Steel Cutting & Binding Machine Y

12 First aid / Medical facility Y

13 Lighting arrangement or DG Set for construction activities & Lighting arrangements Y


Consumbles ( Nut,Bolt,Shuttering Oil,Thermocol Sheet,Welding Rod,Binding Wire ,Hassion
14 Y
clothe,etc.)
15 Tools & Tackles Y

16 Transportation of Shuttering/Staging Material Y

17 Transportation of Steel ( Stock Yard to Site ) Y

18 Watch & Ward of Construction material at site Y

19 Statutory Compliance (PF ,ESIC,Insurance etc. for Contractor's Labours) Y

20 Staging material like Pipes, H-Frame, Cup lock, plywood sheets etc. Y

21 HSD Y
Concrete Pump/Boom Placer with its deisel and operator (without labour)
22 Y
(Boom Placer will be provided for major structure only)
23 Labour for concrete pump/boom placer Y

24 Tanker and Storage of Water for Curing Y

RMC & Steel within permissible limit of wastage i.e 1% for RMC and 2% for Steel
25 Y
(1.5% scrap and 0.5% invisible wastage)