Soal :
1. SPT : (6 → 10→ 3 →7 → 9 →1 → 8→ 2 →5 → 4 ¿
Makespan
Days
ID Task Name Duration
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
1 J6 on M1 2
2 J7 on M1 3
3 J8 on M1 5
4 J4 on M1 8
5 J10 on M2 2
6 J9 on M2 4
7 J2 on M2 6
8 J3 on M3 3
9 J1 on M3 5
10 J5 on M3 7
Maksimum Tardienss = 33
33+26+21+14+ 11+ 2
Mean of Tardiness = =10.7
10
Number of Tardy = 6
2. LPT : ( 4 →5 → 2→ 1→ 8 → 9→ 3 →7 → 6 →10 )
303
=30.3
10
Dimas Adi Wijaya
20200201024
Makespan
Days
ID Task Name Duration
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1 J4 on M1 8
2 J9 on M1 4
3 J7 on M1 3
4 J5 on M2 7
5 J8 on M2 5
6 J6 on M2 2
7 J10 on M2 2
8 J2 on M3 6
9 J1 on M3 5
10 J3 on M3 3
Maksimum Tardiness = 38
Mean of Tardiness =
Total nilai tardiness 4+12+18+21+20+ 24+33+38+38 208
= = =20.8
n 10 10
Number of Tardy = 9