Cover Page Final Report
Cover Page Final Report
ON
SOLAR INVERTER
AND
LOAD SURVEY
SUBMITTED BY
PREPARED BY SIGNATURE
MUKUSH KUMAR ROY (SIP/19/EL/020)
i
DEPARTMENT OF ELECTRICAL ENGINEERING
SILCHAR POLYTECHNIC
SILCHAR-788015
ASSAM, INDIA
2022
CERTIFICATE
This is to certify that the work contained in the thesis entitled LOAD SURVEY OF NEW
ACADEMIC BUILDING AND SOLAR INVERTER which is being submitted to
electrical engineering department, SILCHAR POLYTECHNIC, by
MUKUSH KUMAR ROY (SIP/19/EL/020)
ii
DEPARTMENT OF ELECTRICAL ENGINEERING
SILCHAR POLYTECHNIC
SILCHAR-788015
ASSAM, INDIA
2022
CERTIFICATE
This is to certify that the work contained in the thesis entitled "LOAD SURVEY OF
NEW ACADEMIC BUILDING AND SOLAR INVERTER" which is being
submitted to electrical engineering department, SILCHAR POLYTECHNIC, by
MUKUSH KUMAR ROY (SIP/19/EL/020)
Date: 21/07/202
iii
ACKNOWLEDGEMENT
Doing a project in not a one man approach. In course of making this project we have accepted
suggestion and helps from various people without who help the success of this project would
merely be a dream we the undersigned take this opportunity of thank our guide and Lecturer
Mr. Partha Pratim Paul who has helped us in doing our project last but not the least we would
like to thank the persons who have helped us directly in the successful completion of our project
and we are sorry for failing to recall their at this junction.
PREPARED BY SIGNATURE
MUKUSH KUMAR ROY (SIP/19/EL/020)
iv
ABSTRACT
The sudden change in voltage is huge issue in enterprises and in home machines and it
causes misfortunes in electrical circuits. The on-time postpone circuit shields the heap from
exchanging floods as well as from speedy changeover [off and on] impact. Here is an
economical auto cut-off circuit, which is manufactured utilizing transistor and other
discrete parts. It very well may be utilized to secure loads, for example, T.V, Refrigerator
and so forth., from unwanted over and under line voltages. This circuit might be embedded
between a current programmed/manual stabilizer and the heap. The over/under voltage cut-
off with ON-Time delay gives different sorts of security: Over voltage/under voltage
assurance, insurance against homeless people and so on.
v
ENGINEERING
A person skilled in the science of putting scientific knowledge to practical use, specifically in
the design, planning, construction or maintenance manufactured things.
All engineers must learn a number of concept and skills such as:
• System.
• How to access and minimize the ecology foot print of human economic activity.
• Technical, design, scientific and institutional strategies and techniques that foster
sustainable development, promote energy and natural resources and preserve
biological diversity.
• The educational process includes experimental education to practice the skill on the
campus and in the larger community, including industry and government.
vi
MEANING OF PROJECT REPORT
The project report describes the purpose of the project and how it will be organised and
managed. A project report should be produced, and signed up to by all project members. The
project report should include the following sections:
Project Completion
This essential final stage is to ensure efficient closure of the project, and should include:
vii
PREFACE
SECTION 1:
Load survey of “New Academic Building” of the Silchar Polytechnic. The rating and alternator
design with prediction of near future demand in our “New Academic Building” of the Silchar
Polytechnic.
1st"we have tried to highlight from the practice point that how load varies on above mentioned
buildings throughout the year. Then we can design the size of the alternator which will meet
the required load.
The annual load curve has been made of the “New Academic Building” of the Silchar
Polytechnic is divided in two seasons. Summer consisting of 210 days and winter of 155 days.
The load survey is made after calculating all connected loads and demand factor and
accordingly the maximum demand of the above mentioned building has been calculated. From
the data, we can calculate the rating of AC generator set required to be installed.
SECTION 2:
ELECTRICAL PROJECT
SECTION 3:
viii