Download as pdf or txt
Download as pdf or txt
You are on page 1of 11

ESTIMATION & COSTING

TYPES OF ESTIMATES

AJITHA .
119011001763
TYPES OF ESTIMATES

(I) APPROXIMATE ESTIMATES,


(II) DETAILED ESTIMATES

❑ BEFORE A DETAILED ESTIMATE OF THE PROPOSED WORK IS TO BE TAKEN UP, IT IS NECESSARY TO PREPARE
ITS APPROXIMATE ESTIMATE.
❑ AN APPROXIMATE ESTIMATE GIVES THE APPROXIMATE COST OF THE WORK AND IS PREPARED ON THE
BASIS OF COST OF THE SIMILAR WORKS CARRIED OUT IN THE PAST.
❑ SUCH AN ESTIMATE IS REQUIRED TO OBTAIN ADMINISTRATIVE APPROVAL IN CASE OF GOVERNMENT
WORKS.
❑ ONCE THE WORK IS ADMINISTRATIVELY APPROVED BY THE GOVERNMENT, A DETAILED ESTIMATE IS
WORKED OUT.
❑ A DETAILED ESTIMATE IS PREPARED AFTER ITS COMPLETE SET OF DRAWINGS ARE READY.

❑ THE QUANTITIES OF VARIOUS ITEMS OF WORK ARE WORKED OUT FROM SUCH DRAWINGS AND ARE
MULTIPLIED BY THE PRESENT RATES OF ITEMS OF WORKS TO ARRIVE AT THE ESTIMATED COST OF THE
WORK.
TYPES OF ESTIMATES

THUS THE VARIOUS TYPES OF ESTIMATES PREPARED ACCORDING TO THEIR REQUIREMENTS


MAY BE CLASSIFIED AS FOLLOWS:

❑ PRELIMINARY OR APPROXIMATE OR ROUGH COST ESTIMATE

❑ PLINTH AREA ESTIMATE.

❑ CUBIC CONTENTS METHOD

❑ APPROXIMATE QUANTITY METHOD

❑ DETAILED ESTIMATE (OR ITEM RATE ESTIMATE)

❑ REVISED ESTIMATE

❑ SUPPLEMENTARY ESTIMATE

❑ SUPPLEMENTARY AND REVISED ESTIMATE

❑ ANNUAL REPAIR (A.R) OR ANNUAL MAINTENANCE


TYPES OF ESTIMATES

(i) Preliminary or Approximate or Rough cost estimate:

❑ THIS APPROXIMATE ESTIMATE IS PREPARED FOR PRELIMINARY STUDIES OF THE VARIOUS ASPECTS OF THE WORK
AND ALSO TO DECIDE THE FINANCIAL POSITION AND POLICY FOR ADMINISTRATIVE APPROVAL BY COMPETENT
SANCTIONING AUTHORITY.
❑ IN CASE OF COMMERCIAL PROJECTS SUCH AS RESIDENTIAL BUILDINGS, IRRIGATION AND POWER PROJECTS THAT
EARN REVENUE, THE PROBABLE INCOME IS ALSO MENTIONED AND THE INVESTMENT IN THE PROJECT IS
JUSTIFIED.
❑ IF THE PROJECT IS NON-COMMERCIAL, HAVING NO DIRECT RETURN, ITS NECESSITY, UTILITY, PROSPECTS IN
FUTURE AND AVAILABILITY OF FINANCE ETC. ARE CONSIDERED BEFORE FINAL DECISION IS TAKEN.
❑ THIS ESTIMATE IS PREPARED ON THE BASIS OF PRACTICAL EXPERIENCE OF CARRYING OUT SIMILAR WORKS IN THE
PAST AND THEIR RATES.
❑ IN THIS ESTIMATE, THE APPROXIMATE COST OF ALL IMPORTANT WORKS SUCH AS COST OF LAND, ROADS,
BUILDINGS, WATER SUPPLY, SANITARY WORKS, ELECTRIFICATION ETC. ARE MENTIONED SEPARATELY.
❑ A BRIEF REPORT OF THE PROJECT INDICATING ITS NECESSITY, UTILITY AND METHOD OF ARRIVING AT THE COST OF
EACH ITEM AND THE SITE OR LAYOUT PLAN IS ALSO ENCLOSED WITH THE ESTIMATE.
TYPES OF ESTIMATES

(II) PLINTH AREA ESTIMATE:


❑ AS THE NAME IMPLIES, THIS ESTIMATE IS PREPARED BY MULTIPLYING THE PLINTH AREA OF THE PROPOSED
BUILDING BY THE PLINTH AREA RATE OF SIMILAR BUILDING HAVING SAME SPECIFICATIONS AND HEIGHT THAT IS
CONSTRUCTED VERY RECENTLY IN THE SAME LOCALITY.
❑ THE PLINTH AREA OF THE PROPOSED BUILDING IS CALCULATED FOR THE COVERED I.E. ROOFED PORTION BY
MEASURING THE OUTER DIMENSIONS AT THE PLINTH LEVEL.
❑ THE AREA OF COURTYARDS, AND OTHER OPEN AREAS ARE NOT TO BE INCLUDED WHILE CALCULATING THE PLINTH
AREA.
❑ THE PLINTH-AREA METHOD OF PREPARING ESTIMATE GIVES THE APPROXIMATE COST OF THE BUILDING TO BE
CONSTRUCTED.
❑ EVEN IF THE PLAN OF THE PROPOSED BUILDING IS NOT READY, THE FLOOR AREAS OF DIFFERENT UNITS (I.E.
ROOMS) ARE WORKED OUT FROM THE USERS REQUIREMENTS AND ABOUT 35% OF IT IS ADDED FOR THICKNESS
OF WALLS, CIRCULATION AND WASTE TO OBTAIN THE APPROXIMATE TOTAL PLINTH AREA.
❑ THIS PLINTH AREA IS THEN MULTIPLIED BY THE CURRENT PLINTH AREA RATE IN THE LOCALITY TO OBTAIN THE
APPROXIMATE COST OF THE PROPOSED BUILDING.
❑ THE METHOD IS SIMPLE AND IS USUALLY ADOPTED IN PRACTICE.
TYPES OF ESTIMATES
(III) CUBIC CONTENT METHOD:
❑ THE CUBIC CONTENT METHOD IS AN APPROXIMATE METHOD OF PREPARING AN ESTIMATE OF A PROPOSED
BUILDING AND DIFFERS FROM THE METHOD (II) DESCRIBED ABOVE IN THAT, IN ADDITION TO THE TOTAL PLINTH
AREA OF THE PROPOSED BUILDING, IT ALSO TAKES INTO CONSIDERATION ITS HEIGHT.
❑ THE TOTAL CUBIC CONTENTS OF THE BUILDING ARE OBTAINED BY MULTIPLYING ITS TOTAL PLINTH AREA BY THE
HEIGHT.
❑ KNOWING THE CUBIC CONTENT RATE OF RECENTLY CONSTRUCTED BUILDING HAVING SIMILAR SPECIFICATIONS IN
THE LOCALITY, THE APPROXIMATE COST OF THE PROPOSED BUILDING IS WORKED OUT BY MULTIPLYING THE
TOTAL CUBIC CONTENTS BY ITS CUBIC CONTENT RATE.
❑ IN ORDER TO CALCULATE THE CUBIC CONTENTS OF THE BUILDING, THE LENGTH AND BREADTH ARE MEASURED
AS THE EXTERNAL DIMENSIONS AT THE FLOOR LEVEL AND THE HEIGHT OF THE BUILDING IS MEASURED FROM
THE FLOOR LEVEL TO THE TOP OF THE FLAT ROOF OR UPTO HALF WAY OF THE SLOPED ROOF.
❑ FOR MULTI STOREYED BUILDING, THE HEIGHT IS MEASURED BETWEEN FLOOR LEVEL OF ONE STOREY TO THE TOP
OF NEXT FLOOR ABOVE IT.
❑ AS PER I.S. 3861, THE FOUNDATION AND PLINTH AND THE PARAPET ABOVE THE ROOF ARE NOT TAKEN INTO
CONSIDERATION IN CALCULATING THE CUBIC CONTENTS.
❑ THE CUBIC CONTENT METHOD IS MORE ACCURATE AS COMPARED TO PLINTH AREA METHOD AS IT ACCOUNTS
FOR THE HEIGHT OF THE BUILDING.
❑ IN PRACTICE, HOWEVER, THIS METHOD IS NOT USED.
TYPES OF ESTIMATES

(IV) APPROXIMATE QUANTITY METHOD:


IN THIS METHOD THE STRUCTURE IS DIVIDED INTO:
(A) FOUNDATION INCLUSIVE OF PLINTH
(B) THE SUPER STRUCTURE.
❑ THE COST PER RUNNING METER OF FOUNDATION INCLUSIVE OF PLINTH IS WORKED OUT AND IS MULTIPLIED BY
THE TOTAL LENGTH OF FOUNDATION TO DETERMINE THE TOTAL COST OF FOUNDATION INCLUSIVE OF PLINTH.
❑ SIMILARLY THE COST PER RUNNING METER OF THE SUPERSTRUCTURE IS FOUND OUT AND IS MULTIPLIED BY THE
TOTAL LENGTH OF ALL THE WALLS OF SUPERSTRUCTURE TO GET THE TOTAL COST OF SUPERSTRUCTURE.
❑ THE TOTAL COST OF THE STRUCTURE IS THEN OBTAINED BY THE ADDITION OF TOTAL COST OF FOUNDATION
INCLUSIVE OF PLINTH TO THE TOTAL COST OF THE SUPERSTRUCTURE.
❑ A LINE PLAN OF THE PROPOSED STRUCTURE IS REQUIRED FOR THE ABOVE COMPUTATIONS.
TYPES OF ESTIMATES
(V) DETAILED ESTIMATE (OR ITEM RATE ESTIMATE):
❑ THIS IS THE ACCURATE METHOD OF ESTIMATING IN WHICH THE ENTIRE BUILDING WORK IS SUBDIVIDED INTO
INDIVIDUAL ITEMS OF WORK
❑ THE QUANTITIES OF EACH ITEM OF WORKS ARE CALCULATED FROM THE COMPLETE SET OF DRAWINGS (I.E. PLAN,
ELEVATION, SECTIONS ETC.)
❑ THE ABSTRACT OF THE ESTIMATED COST IS PREPARED BY MULTIPLYING THE QUANTITIES OF EACH OF THE ABOVE
ITEMS BY THE RATE OF THE COMPLETION OF THAT ITEM.
❑ THE RATES OF VARIOUS ITEMS OF WORK CAN BE OBTAINED FROM THE ‘SCHEDULE OF RATE’ PREPARED BY THE
GOVERNMENT ORGANISATION OR FROM ANALYSED RATES OF ITEM.
❑ IN ORDER TO MAKE PROVISION FOR UNFORESEEN EXPENDITURE FOR MISCELLANEOUS PETTY ITEMS (FOR WHICH
NO PROVISION IS MADE IN THE ESTIMATE) AND CONTINGENCIES A 3 TO 5% OF THE ESTIMATED COST IS ADDED TO
IT.
❑ AN ADDITIONAL 1 TO 2% IS ALSO PROVIDED FOR THE WORK-CHARGED ESTABLISHMENT I.E. FOR THE SALARIES TO
BE PAID TO THE CHAWKIDARS, TECHNICAL ASSISTANTS, SUPERVISORS ETC. APPOINTED BY THE GOVERNMENT (OR
OWNER) TO LOOK AFTER THE WORK.
❑ THE GRAND TOTAL OF ALL THE ABOVE COST IS KNOWN AS THE TOTAL ESTIMATED COST OF THE PROPOSED WORK.

❑ AFTER THE ADMINISTRATIVE APPROVAL FOR THE WORK IS OBTAINED, ITS DETAILED ESTIMATE IS PREPARED AND
SENT FOR OBTAINING TECHNICAL SANCTION FROM THE APPROPRIATE COMPETENT GOVERNMENT AUTHORITIES.
❑ THE ACTUAL EXECUTION OF THE WORK COMMENCES ONLY AFTER OBTAINING TECHNICAL SANCTION (FROM THE
GOVERNMENT) AND NECESSARY ALLOCATION OF FUNDS ARE MADE AVAILABLE IN THE BUDGET GRANTS FOR
TYPES OF ESTIMATES

DETAILED ESTIMATE IS GENERALLY PREPARED IN THE FOLLOWING TWO STEPS:


(A) TAKING OUT DIMENSIONS
❑ AND SQUARING THEM I.E. THE DIMENSIONS OF THE VARIOUS ITEMS OF WORK ARE TAKEN FROM THE RELEVANT
DRAWINGS AND ARE MULTIPLIED (I.E. SQUARED) TO OBTAIN ITS QUANTITIES AND ARE ENTERED IN THE
‘MEASUREMENT SHEET FORM’.

(B) ABSTRACTING
❑ I.E. THE QUANTITIES OF THE VARIOUS ITEMS OF WORK CALCULATED AS ABOVE ARE MULTIPLIED BY THE RATES OF
THOSE ITEMS OBTAINED EITHER FROM THE SCHEDULE OF RATE OR WORKED OUT BY RATE ANALYSIS AND ARE
ENTERED IN THE ‘ABSTRACT SHEET FORM’. IF ‘RATE’ AND ‘AMOUNT’ COLUMNS IN THE ABSTRACT SHEET FORM
ARE LEFT BLANK (TO BE ENTERED BY THE CONTRACTOR) THEN IT IS TERMED AS THE ‘BILL OF QUANTITY’.
TYPES OF ESTIMATES

(VI) REVISED ESTIMATE:


IT IS ALSO A DETAILED ESTIMATE AND IS TO BE PREPARED WHEN:
❑ THE ORIGINAL SANCTIONED AMOUNT OF ESTIMATE EXCEEDS BY MORE THAN 5%.

❑ AMOUNT SPENT ON THE WORK EXCEEDS ADMINISTRATIVELY SANCTIONED AMOUNT MORE THAN 10%.

❑ WHEN THERE ARE DRASTIC CHANGES IN ORIGINAL PROPOSAL I.E. THE ORIGINAL LOAD BEARING STRUCTURE IS
NOW PROPOSED TO BE CONVERTED INTO A FRAMED STRUCTURE, EVEN IF THE COST OF THE WORK DOES NOT
EXCEED THE SANCTIONED AMOUNT.
❑ THE REVISED ESTIMATE IS ACCOMPANIED BY A COMPARATIVE STATEMENT IN THE PRESCRIBED FORMAT
INDICATING THE CHANGES IN EACH ITEM OF WORKS, ITS RATE AND AMOUNT AS PER ORIGINAL AND REVISED
WITH FULL JUSTIFICATION FOR SUCH VARIATIONS AND EXCESS ETC.
❑ (VII) SUPPLEMENTARY ESTIMATE:

❑ IT IS A FRESH DETAILED ESTIMATE WHICH IS TO BE PREPARED WHEN ADDITIONAL WORKS ARE REQUIRED TO
SUPPLEMENT THE ORIGINAL PROPOSED WORK OR WHEN FURTHER DEVELOPMENT OR EXTENSION OF THE WORK
IS REQUIRED TO BE CARRIED DURING PROGRESS OF THE WORK.
❑ THE ABSTRACT MUST INDICATE THE ORIGINAL AMOUNT OF THE ESTIMATE AND THE TOTAL AMOUNT INCLUDING
SUPPLEMENTARY AMOUNT FOR WHICH FRESH SANCTION IS TO BE OBTAINED.
TYPES OF ESTIMATES
(VIII) SUPPLEMENTARY AND REVISED ESTIMATE:
•THIS ESTIMATE IS PREPARED WHEN A PARTICULAR WORK IS ABANDONED AND THE COST OF THE WORK REMAINING
IS LESS THAN 95% OF THE ORIGINAL SANCTIONED AMOUNT OF THE WORK
•OR WHERE THERE ARE MATERIAL DEVIATIONS FROM THE ORIGINAL PROPOSED WORK WHICH MAY RESULT IN
SUBSTANTIAL SAVING IN THE ESTIMATE.
•IN SUCH CASES A FRESH SUPPLEMENTARY AND REVISED ESTIMATE IS TO BE PREPARED AND SENT FOR REVISED
TECHNICAL SANCTION.
(IX) ANNUAL REPAIRS (A.R.) OR ANNUAL MAINTENANCE (A.M.) ESTIMATE:
•ANNUAL REPAIR (A.R.) OR ANNUAL MAINTENANCE (A.M.) IS A DETAILED ESTIMATE PREPARED TO KEEP OR MAINTAIN
THE BUILDING OR ROADS IN PROPER WORKING AND SAFE CONDITION.
•IN CASE OF BUILDINGS, THIS INCLUDES ITEMS SUCH AS WHITE WASHING, PAINTING OF DOORS AND WINDOWS,
INSIDE AND OUTSIDE PLASTERING AND MINOR REPAIRS ETC.
•THE AMOUNT OF SUCH ESTIMATE SHOULD BE WITHIN 1.5 TO 2% OF THE ORIGINAL COST OF THE BUILDING.

•IN CASE OF ROADS, IT INCLUDES ITEMS SUCH AS FILLING PATCHES, MINOR REPAIRS TO BRIDGES AND CULVERTS,
REPAIRS TO BERMS ETC.
•IN CASE OF DAMAGES CAUSED TO THE WORKS DURING MONSOON, WHICH CANNOT BE REPAIRED WITHIN THE
ANNUAL REPAIR GRANTS A ‘SPECIAL REPAIR ESTIMATE’ IS TO BE PREPARED.

You might also like