Chapter 5: Sewage Treatment Plant: Water Treatment and Disposal
Chapter 5: Sewage Treatment Plant: Water Treatment and Disposal
Chapter 5: Sewage Treatment Plant: Water Treatment and Disposal
To protect water resources and the greater environment, all waste from buildings
and industrial processes must be treated to meet certain standards of quality. Domestic
sewage from dwellings and DWV systems in buildings are permitted to be discharged
into the public sewers system, which provides the necessary treatment prior to tits
discharge into nature.
Raw or untreated sewage is mostly pure water since it comprises about 99.9% water
and only about 0.1% impurities. However, sewage contains biodegradable organic
material, which is very likely to contain pathogenic micro organisms.
• For water to be safe for drinking the E. coli count shall not be more than 1 E. coli
per 100ml (about 0.4 cup) of water.
• For water to be considered safe for swimming the E. coli shall be more than 200
E. coli per 100ml of water.
Biological Oxygen Demand (BOD). The measure of the strength of the sewage in
relation to the total amount of organic material it contains. Untreated domestic sanitary
sewage has an average BOD of about 200mg/ liter. DENR standard is 50 mg/ liter.
Total Suspended Solids (TSS). The measure of the strength of the sewage in
relation to the total amount of suspended solids. Untreated domestic sanitary sewage
has an average TSS of 240 mg/ liter.
Following are the definitions of some commonly used terms related to the subject of
sewage treatment methods and disposal processes:
Drainage Fittings. This are pipe accessories in the drainage system such as a
coupling, bend, wye, etc; used to join two or more pipes together or to change their
directions.
1. Waste pipe
2. Soil pipe
3. Storm pipe
4. Vent pipe
1. Waste pipe. The pipe which carries only liquid waste, free of human excrement
or fecal matter.
2. Soil pipe- the pipe which carries the waste from water closets, urinals or
fixtures of similar function to the building drain. This contains human
excrements.
3. Storm pipe- the pipe which convey rainwater from the roof gutter and down
spout to the building storm drain.
4. Vent pipe- the pipe connected to the drainage system that conveys air to and
from the system and keep the water from being siphoned from the trap.
The selection of piping materials for the drainage system depends on the following:
This type of pipe is made of asbestos fibers combined under pressure with Portland
cement and silica to form a dense and homogeneous material. It is dense cured for
strength.
1. Pressure A.C. Pipe- is used for sewer mains, industrial effluent and process
piping, working pressure ranges at 100, 150, and 200 psi.
2. Non-pressure A.C. Pipe- is used for sewer casings for electric cables and as
storm drains.
Properties:
Diameter: 75mm (3’) to 900 mm (13’)
Length: 3.00m (10’) or 4.00m (13’)
For 75, 100, 150mm.
4.00m (13’) for 200mm. (8”0
Through 900 mm. (36”)
Grades: 1500, 2400, 3000, 4000 and 5000
Lbs/ft.
Joints: rubber gasket joint and cement joint
Note:
Asbestos cement pipe (ACP) is remarkably suited for embedment in concrete
structure since both materials have the same properties.
1. Bends (elbows)- are used to complete change of direction in soil, waste and
drain lines in horizontal, vertical and diagonal directions.
2. Y (wye) branches- are used for change of direction (diagonal) and branch
connections of soil, waste and drain pipes.
3. T (tee) branches- are used to join 3 or 4 pipes at perpendicular directions.
Cast iron soil pipe (CISP) is made from an alloy of iron, carbon and silicon, with the
controlled amounts of manganese, sulfur and phosphorous. This is primarily used for
sanitary drain, waste and storm systems.
1. Single hub- is equipped with one hub and one spigot end and used in the
installation of plumbing in its full length.
2. Double hub- is constructed with a hub on each end so it may be cut into two
pieces when a short piece of pipe is needed.
3. Hubless (no hub)- there is no hub on either ends of the pipe, it is used in lieu of
the single hub calking of the pipe is difficult.
PROPERTIES
• Available diameter (Nom. I.D.) 2”, 3 ”, 4”, 5”, 6”, 8”, 10”, 12”, 15”
• Hydrostatic Test:
50 psi for service weight
100 psi for extra heavy
*Oakum- a hemp treated with pitch to make it moisture proof and resistant to
the elements contained in the waste.
*Calking- plugging an opening with oakum and lead that are pounded into
place.
*HUB- that portion of the pipe which, for a short distance, is sufficiently enlarged to
receive the end of another pipe of the same diameter for the purpose of making a
joint. It is also known as Bell.
*SPIGOT- the end of the pipe that fits into a bell or spigot.
FITTINGS FOR CAST IRON SOIL PIPE
CONCRETE PIPE
Concrete pipe is cast in metal molds and compacted by tamping or spinning the molds
(centrifugal casting).
1. Non-reinforced concrete pipe- is used for drainage, sewer lines and for
gravityflow water supply lines if the joints are carefully made. Diameters available
range from 100mm. (4”) to 900mm (36”).
2. Reinforced concrete pipe (RCP)- is made by the addition of steel wire or steel
bars and is primarily used for sewage and storm drainage. Diameters available
range from 300mm (12”) to 3600mm (144”)
Vitrified clay pipe is extruded from a suitable grade of shale or clay and fired in kilns
producing an extremely hard and dense corrosion resistant material. It is generally used
for underground public sewers, house sewers, drainage (sanitary and storm) systems
and for industrial wastes such as acids.
Vitrified clay pipe is suitable for most gravity-flow systems and is not intended for
pressure service. It is brittle and cracks when laid on unstable ground or base.
PROPERTIES
*Diameter- 100mm (4”) to 1050 mm (42”)
*Grades- standard
- extra strength
- perforated
*Joints - cement joint
- pre-fabricated compression seals
PLASTIC PIPES
1. Thermosel Plastic- has the property of being permanently rigid. Epoxy and fiber
glass are example of this.
2. Thermo Plastic- is a material having the property of softening when heated and
hardening when cooled.
Properties
*Diameter- 100mm (4’) to 900mm (36”)
*Color- black
*Joint- Screw-type couplings
*Brand- Atlanta
THE COMMON TOOLS USED IN THE DRAINAGE PIPES AND FIITINGS ARE:
Calking Iron- this is used for
Tin snip. This is used for
caulking oakum and lead for
cutting G.I. sheets for straps to
bed and spigot joints.
anchor pipes.
Plunger. This is used to clear the
trap at floor drains, or minor
obstructions through a pumping
action. This is also known as
Plumber’s friend or Plumber’s
helper.
Soldering Copper. This is
used for soldering lead on Plumb Level. This is used to
flashing of vent pipes on G.I. establish and guide grades on
Roofing. horizontal drain pipe runs.
File. This is used to remove
the burrs of cut pipes.
Generally speaking, potable water is supplied from a local utility through a public water
system.
For buildings without public water system, an alternative source of water must be
considered, such as springs, wells and rain water.
SPRING WATER SOURCE
In most conditions, springs are shallow wells with water supply just a few meters from the
ground surface. If this is the source of domestic water supply, careful attention must be
given to yield and purify. The flow may stop during dry season or surface water may get
contaminated.
The determination of the yield of the spring water source employs a very simple
procedure. They are as follows:
1. Channel the flow of the spring into a collection basin. Make sure that the basin
collects all available flow.
2. Place an overflow pipe through the dam so that the collected water flows freely
through the pipe. There should be no leakage around the pipe.
3. Put a bucket of known volume (for example, a 10-liter bucket) under the
overflow pipe to catch the flow.
4. With a watch, measure the amount of time it takes to fill the bucket. At this
instance, the rate of flow can be determined.
5. Check the rate of flow per day if it is sufficient to supply the daily water demand
of the occupants.
It takes a spring 60 seconds to fill a 10-liter bucket. Determine if its daily yield is sufficient
to the water demand of the community of 200 people. The average daily water
consumption per person is 60 liters.
Solution:
Therefore, the spring with the daily flow of 13,824 liters can sufficiently meet the
demand of the community of 200 people.
WELLS
Wells are holes or shafts sunk into the earth to obtain water from an aquifer. An
aquifer is a water-bearing formation of gravel, permeable rock or sand that is capable
of providing water, in usable quantities, to springs or wells.
The types of wells generally refer to the method of its construction, which are:
1. Dub
2. Bored
3. Driven
4. Drilled
a. Percussion or standard
b. Rotary
c. Reverse-circulation rotary
d. Jetting
4. Drilled Wells- A drilling rig is used to drill the well hole and then a
casing or tubular pipe is forced down the hole to prevent it from caving-in.
when a water-bearing stratum of sufficient capacity is found, a well screen is
set in place to permit the water to flow into the casing and to hold back the
fine material. The depth of this well is limited only by the distance one must
dig to obtain an adequate supply of fresh water, even down to 450 meters.
In spite of these conditions, rainwater collection system remains a viable water source
alternative. This system typically employ a cistern or covered reservoir tanks to store
water collected from roofs or other relatively clean, impervious surfaces. The collected
rain can be used for flushing water closets and urinals, as well as for landscape
purposes wherein potable water is not necessary.
The city council of Cebu promulgated City Ordinance No. 1711 otherwise known as
the “water conservation and Flood Prevention ordinance”. This ordinance requires all
projects to provide a permanent rainwater tank or container proportionate to the roof
area. These are stated as follows:
One cubic meter of tank/ container for every fifteen (15) square meters of roof
area and deck, up to a maximum of seven (7) cubic meters.
One cubic meter of tank/ container for every fifteen (15) square meters of roof
area and deck, up to a maximum of three (3) cubic meters.
There are two methods that can be used in determining the size of the storage tank for
rain water:
1. The use of Cebu city Ordinance 1711 which states that for every fifteen (15)
square meter of roof area, one (1) cubic meter of rain water can be collected. This
is the short method of sizing the cistern.
2. The use of the rain fall data of the locality. This is the long method of determining
the size of the cistern.
As part of the design problem, it was required that 5 water closets, 2 urinals
and 2 slop sinks of a school building in Cebu city be provided with an alternative
source of water supply, specifically from rainfall catchment. Your are to determine the
size of the rainwater cistern based on the following givens or assumptions:
Solution
Therefore:
The domestic cold water supply of the plumbing system consists of the piping and
fittings which supply cold water from the building water supply to the fixtures, such as
lavatories, bath, tubs, water closets and kitchen sinks. This is also known as water
distribution system.
1. Galvanized Iron (G.I.) Pipes and fittings, schedule 40- is moderately corrosion
resistant and suitable for mildly acid water. It is connected to its fitting with
threaded connections. It is available in diameters form 12 mm (1/2”) to 300 mm
(12”) at a length of 6 meters (20 feet).
2. Polyvinyl chloride (PVC) Pipes and fittings, schedule 40- is economy and ease of
instruction make it popular, especially on low budget projects.
3. Polybutilyne (PB) pipe
4. Polyethylene (PE) pipe
5. Copper Pipes and Tubing
a. Type K- used primarily for underground water service. It is color-coded in
green.
b. Type L- is most popular for use in water supply system. It is color-coded in
blue.
c. Type M- it has the thinnest wall and is used where water pressure is not
too great. It is color-coded in red.
Fittings
A variety of fittings must be used to install the piping in the project. Fittings are
accessories usually standardized, used for joining two or more pipes together.
Fittings include:
1. Nipple- a short of piece of pipe, threaded on the outside (male threads) at both
ends, used to join couplings or other fittings
a. Short nipple- below 75mm in length. Also known as shoulder nipple.
b. Long nipple- over 75mm in length.
c. Close nipple- where threading meet.
2. Couple- a short internally threaded (female thread) at both ends and used to
connect two pipes in straight line.
3. Elbow- a pipe fitting having a bend and makes an angle (90o or 45o) between
adjacent pipes for a change in direction. It is also known as ell or straight elbow.
a. Reducing elbow- Joins two pipes of different diameters at right angle of each
other. When specifying reducer fittings, the bigger diameter is stated first,
(followed by the smaller diameter. (example: reducing elbow, 25mm x 20mm)
b. Street elbow- an elbow fitting having a 45o or 90o bend with an inside thread
on one end and outside thread on the other. It is also known as service ell or
street ell.
4. Tee- a T-shaped pipe fitting that joins 3 or 4 pipes at perpendicular directions.
a. Straight tee c. reducing tee
b. Straight cross tee d. reducing cross tee
2. WATER METER
4. RISERS
5. FIXTURES BRANCHES
7. STORAGE TANKS
SERVICE TAP CONNECTION DETAIL
CORPORATION COCK- a valve screwed into the street water main to supply the house
service connection.
GOOSE NECK- the part of a pipe curve like the neck of a goose, usually flexible. CURB
STOP- A control valve for the water supply of a building, usually placed in case of
emergency or should the water supply of the building be discontinued.
WATER METER- a mechanical device used to measure the volume of water passing
through a pipe.
METER STOP- A valve placed at the street side of the water meter and serves as a
controlling device for the building installation.
GENERAL TYPES OF WATER DISTRIBUTION SYSTEM
1. UPFEED DISTRIBUTION SYSTEM
a. Direct system
b. Pneumatic air-pressure system
2. DOWNFEED DISTRIBUTION SYSTEM
5. Reducer- a pipe coupling with inside threads, having one end with a smaller
diameter than the other and used for connecting pipes of different size. Both
openings have the same center line.
6. Bushing- a pipe fitting which is threaded on both the inside and the outside and
used to reduce the size of the pipe opening to receive a pipe or fitting of a
different size.
10. Flange- a ring shaped plate screwed on the end of a pipe and provided with
holes for bolts, to allow joining the pipe to a similarly equipped adjoining pipe.
The resulting joint is a flanged joint.
VALVES
Valves are used to control the flow of water throughout the supply system. The proper
location of valves simplifies repairs to the system, fixtures, or equipment being served.
There are usually valves at:
a. Risers
b. Branches
c. And pipes to individual fixture or equipment
• Types of valves
1. Gate valve
2. Globe valve
3. Check Valve
4. Angle valve
5. Ball valve/ stop cock
6. Faucet/ Bibb
TEE- a t-shaped pipe fitting that joins 3 or 4 pipes at perpendicular Both openings have the same
directions. center line.
BUSHING- a pipe
fitting which is PLUG- is used to close CAP- is used to close EXTENSION PIECE
threaded on both the an opening in a fitting. the end of a pipe
inside and the outside
and used to reduce
the size of the pipe
opening to receive a
pipe or fitting of a
different size
FLANGE- a ring sharped plate screwed
on the end of a pipe and provided with
UNION- a three piece pipe fitting used to connect the ends of holes for bolts; to allow joining the pipe
two pipes, neither of which can be turned. to a similarly equipped adjoining pipe.
It is also used on pipes that are to be taken down
Occasionally. The resulting joint is a flanged joint.
WATER SUPPLY STORAGE TANKS
Tanks storage capacity required for domestic water supply should be based upon the
peak demand load on the water supply system and should be adequate to satisfy that
demand for at least 30 minutes.
Note: In estimating demand for water closet, use the value for flush value type.
6 5
8 6.5
10 8 10 27
12 9.2 12 28.6
14 10.4 14 30.2
16 11.6 16 31.8
18 12.8 18 33.4
20 14 20 35
25 17 25 38
30 20 30 41
35 22.5 35 43.8
40 24.8 40 46.5
45 27 45 49
50 29 50 51.5
60 32 60 55
70 35 70 58.8
80 38 80 62
90 41 90 64.8
100 43.5 100 67.5
120 48 120 72.5
Determine the capacity of the storage tank of a school building with the following
fixtures:
Solution
2. Estimate the demand in gallons per minute (refer to Table 4) from Table 4. The
estimated demand for 724 WSFU is 175 GPM.
3. Estimate capacity of the storage tank.
Assume 1 hour as the duration that will adequately satisfy demand.
V= 10,500 G
264
This method provides for the design population with the assigned average daily water
consumption for various buildings and other facilities.
Where
Where
Determine the capacity of the storage tank of a school building with an estimated
student population of 1,500 people. Assume 25% of the population as daily users of the
building.
Solution
V= 9,551.25
264
V= 36.18 cu.m.
Say: 37 cu.m.
All piping of the potable water supply system should be proved watertight by the
application of the water pressure test, using potable water, so as to disclose leaks and
defects. It is recommended that all potable water supply piping inside buildings should
be tested, prior to covering or concealment and before fixtures and faucets are installed.
DISINFECTION METHODS
• Procedure
1. All water supply connections should be disconnected, plugged or
effectively shut off to prevent any foreign matter or contamination from
entering the water supply thereto.
2. For disinfection, on of the following methods may be applied:
a. The systems, or part thereof, shall be filled with a water solution
containing 50 parts per million (PPM) of available chlorine and
allowed to stand for 24 hours before flushing and returning to
service.
b. The system, or part thereof, shall be filled with a water solution
containing 200 parts per million (PPM) of available chlorine and
allowed to stand for 3 hours before flushing and returning to
service.
1. PIPE VISE
2. PIPE CUTTER
3. PIPE REAMER
4. PIPE STOCK AND DIES
5. PIPE TAP
6. PIPE WRENCH
7. MONKEY WRENCH
8. STRAP WRENCH
9. PIPE TONG/ CHAIN WRENCH
10. BASIN WRENCH
PIPE VISE- This is used to hold 11. OPEN- END WRENCH
pipe to be cut, threaded or 12. ADJUSTABLE WRENCH
assembled. 13. FLARING TOOL
CHAPTER 10: PUMPS FOR WATER SUPPLY
Classification of Pumps
1. Reciprocating Pumps
a. Lift pumps
b. Piston or plunger pumps
c. Deep-well piston pumps
2. Centrifugal Pumps
a. Submersible pump
3. Deep-weel jet pumps
4. Hydraulic Rams
5. Hydropneumatic pressure system
1. RECIPROCATING PUMP- a pump which operates with a to- and –fro motion.
a. Lift Pump- the simplest of the reciprocating pumps and consists of a piston
moving up and down in a cylinder or barrel. A lift pump cannot be used to
raise water above 7.50 to 8.50 meter at a normal atmospheric pressure
(101 kPa) due to:
- Loss of efficiency in the pump
- Friction in the intake pipe
- Impossible to obtain a perfect vacuum
b. Piston or Plunger Pump- is a positive displacement reciprocating pump in
which a plunger is driven backwards and forwards, or up and down by a
mechanical working head.
ILLUSTRATION
c. Deep-well piston pump- when water is more than 7.5m below the ground,
it is visually necessary to place the pump in or near the water in the well
and pump from there. Water is forced up th drop pipe and out into the
delivery pipe.
ILLUSTRATION
Centrifugal Pump- a pump with vanes or impellers that rotate inside a close-fitting case
draw-in liquid at the center and, by virtue of centrifugal force, throw-liquid out through an
opening in the periphery of the case. Unlike the reciprocating pump, a centrifugal pump
will not operate unless the casing is full of water.
1. Submersible Pump- is basically a centrifugal pump complete with electric
motorrs which are positioned under water in a suitable bored hole that
delivers the water to the surface.
DEEP WELL JET PUMP. A pump consisting of a revolving impeller in the pump
housing which forces water down a pressure line to an ejector assembly below water
level.
ILLUSTRATION
HYDRAULIC RAM OR RAM PUMP. A pump in which the power generated from flowing
in an enclosed pipe is used to raise part of the water to a height above that from which
the flow began.
1. The fall (h) must be more than 0.66m, but should not exceed 6m.
2. The drive pipe should be straight and laid to an even grade, and its length should
be 6 to 8 times the available fall. The drive pipe must be long enough to ensure
that when the recoil of water takes place more resistance is offeered by te
moving water in the drive pipe than by the delivery valve and the water
immediately above it.
3. The amount of water available should be at least 10 times the required supply
and there must be a get away for the waste water.
4. The height (H) to which the water is to be delivered should not, in general, be
more than 6 to 8 times the available fall.
5. As a rule, the diameter of the drive pipe should be at least twice the diameter of
the delivery pipe.
• Calculation
In calculating for the quantity of water delivered by a hydraulic ram, use the
formula:
q= Q x h x e
H
Where:
To supply a ram, 200 liters of water per hour are available. The head of the ram is
1.00m and the height to which is raised is 5.00mm if the ram is assumed to have an
efficiency of 60%, what quantity of water will be delivered per hour?
SOLUTION:
q= Q x h x e
H
= 200 x 1 x 0.6
5
ILLUSTRATION
Pressure- is defined as force per unit area, the area being measured at right angles to
directon of the force. The unit of pressure N/m2 is called Pascal (Pa). Kilo Pascal (kPa)
and Mega Pascal (MPa) are commonly used.
Head- is the height or vertical distance from the point of measurement to the free level
of water in the system.
a. Positive Head- occurs when the free water level is higher than the point of
measurement.
b. Negative Head- occurs where the free water level is lower than the point
of measurement. It is also known as suction, partial vacuum or negative
pressure.
*Water with head of 1.00m and a base of 1m2 will exert a pressure of 9810 N/m2, or
9810 Pa, that is 9.81 kPa.
• Classification of Heads
There are different kinds of head according to their effect on pumping operations.
1. Static Discharge Head or Gravity Head- results from the vertical height of a
column of water. It is the weight of water exerted as a result of the force of
gravity. In pumping operatons, it is the vertical distance (in meters) from the
center line of the pump to the point of free discharge.
2. Pressure head- the vertical height to to which a given pressure will force water to
a certain level
3. Suction Lift- the term used when the source of supply is below the center line of
the pump.
4. Static Suction Lift- the vertical distance (in meters) from the liquid level to the
center line of the pump.
5. Total Suction Lift- the static suction lift plus friction head in the entire suction pipe
and fittings.
6. Suction head- the term used when the source of supply is above the center lne of
the pump. Also known as flooded suction.
7. Static Suction Head- the vertical distance (in meters) from the center line of the
pump to the level of the liquid being pumped.
8. Total Suction Head- the static suction head minus the friction head in the entire
suction pipe and fittings.
9. Total discharge Head- the static delivery head plus the friction head plus the
friction head in all of the delivery pipe and fittings.
10. Velocity Head- the head required to accelerate the water in the delivery pipe. It
should be included in the total pump head but it so nominal that it is usually
ignored.
11. Total Pump Head- the total suction lift plus the total delivery plus the velocity
head.
The above stated types of fuel can be used to heat the water in the following systems:
1. Localized water heating (single appliances)
a. High Pressure
b. Low Pressure
2. Centralized hot water system
a. High Pressure
b. Low Pressure
3. Storage water heaters
a. High Pressure
b. Low Pressure
4. Instantaneous water heaters
a. High Pressure
b. Low Pressure
INSTANTANEOUS HEATERS
Instantaneous heaters instantly heat cold water as it passes through the heater. These
heaters are compact since storage is not required. They are popularly used at showers
and lavatories and due to this condition; there is a shower model and lavatory model.
1. When the cold water control valve is turned on, water flows and exerts pressure
on a pressure switch which in turn completes the electrical circuit so that the
element can now heat the water as it passes through. The pressure switch is the
safeguard that the heating element is only on when water is flowing.
2. A preset thermal cut-out switch is also incorporated as a safety measure against
overheating the water.
3. The heating element is thermostatically controlled using a rod thermostat or invar
steel which expands very little. This is fixed inside a tube of brass which expands
very little. This is fixed inside a tube of brass which expands approximately 18
times as much as the invar steel. When the brass tube, which is in contact with
the water, expands, it draws out the invar rod with it and breaks the electrical
contact.
4. A magnet ensures a clean snap action, as the magnet will hold the control switch
until the last minute, so preventing excessive arcing and rapid deterioration of the
contact points.
CENTRALIZED HOT WATER SUPPLY
In centralized systems, water is heated and stored centrally and distributed to the
hot water faucets via the hot water piping. In the average home, an electric
heating element is directly immersed into the water to be heated. But, for
commercial and larger projects an independent boiler or furnace is used to heat
the water remotely. The hot water is stored in a range boiler or storage tank that
is located as near the boiler as possible to keep heat losses at a minimum.
To provide an adequate supply of hot water for the average family, a 180 liter
storage cylinder is recommended and is designed to provide the central bulk of
the hot water requirements. The aforementioned value should be increased if
there is an abnormally high usage of hot water or be supplemented with
secondary forms of heating water.
1. The hot water storage vessel holds sufficient water to meet a large draw-off at
peak times.
2. It may be possible to use cheaper, lower grade fuel oil, coal, natural gas or other
solid fuel.
3. The boiler can be housed in its own room, keeping noise and dust out of the main
building.
4. One boiler plant reduces maintenance.
• Heating element- the size of the heating element has a direct bearing on the
heating up time, which is also related to the size of the storage cylinder. A
general guide for adequate supply is: 135 liters 1500 watts
180 liters 2000 watts
Both the 180 liter with a 2000 watt element and the 135 liter with a 1500 watt
element will reach a temperature of 60 degrees centigrade in 5 hours and 15 minutes,
based on cold water entering the cylinder at 10 degrees centigrade.
• Range boiler/ hot water storage tank- the hot water tank serves the domestic
hot water system in a storage capacity. There are two types of tanks used for the
storage of hot water:
1. Range boiler- the small cylindrical hot water tank that varies in size from
300 mm to 600 mm in diameter and is not more than 1800 mm long. The
range boiler is made of galvanized steel sheet of standard and extra
heavy gauge. It can be used in either horizontal or vertical position.
2. Storage tank- the large cylindrical hot water tank with a range of diameter
at 600mm to 1350 mm and not more than 4500 mm long.
The proper size of the hot water storage tank depends on the following:
1. The design of the building
2. The number of occupants and
3. The heating capacity of the supply device
• Hot water pipes- should be as short as possible in order to avoid the use of
“dead legs”. A “dead leg” is a long pipe run whereby it takes a long time to push
out the cold water for the sake of a small amount of hot water. The smallest size
of piping that will provide a satisfactory flow should be used. Short, small sized
pipes are less expensive and they waste less heat and less water.
The storage tank and heating device of a hot water distribution system are so
assembled as to create a circulation of water within them. The movement of the water is
the result of molecular activity. The application of heat to a body of water caused it to
expand and become less dense, which give it a natural tendency to rise. The inequality
of weights between the hot and the cold water contained in the tank results a circulation
of the liquid. The operation and efficiency of the hot water distribution system is
dependent upon the following:
a. Vertical position
b. Horizontal position
c. Pipes, valves and fittings
In this system the water that is being heated by the boiler is actually used out of the hot
water faucets.
Each type should have a temperature and pressure relief valve and sediment drain at
the lowest part of the tank. Relief valves are set to allow water to blow into a drain line
when the temperature exceeds 100 degrees centigrade or when the pressure exceeds
860 kPa.
• Range Boiler and furnace coil- the range boiler is usually mounted upright on a
stand. A drain is placed at the bottom to remove sediment; a temperature and
pressure relief valve is placed at the top for safety. The furnace coil is located in
the furnace box.
• Range boiler and Heater- the range boiler is usually installed horizontally on a
stand. The heater maybe fired by coal, gas or oil.
• Side-Arm Gas Heater- is used mostly during summer months in temperate
countries to support furnace oil heaters.
• Gas water heater- a galvanized iron, copper, or porcelain- lined steel tank
enclosed in an insulating jacket. A gas (LPG) burner provides the heat. The
thermostat controls the temperature of the water in the insulated tank. Its
operation is automatic and will keep water at any temperature from 45 to 75
degree centigrade, according to the setting of the thermostat. Gas water heaters
provide an efficient and inexpensive way to supply hot water at all times.
• Oil-Fired water heaters- are similar to the gas water heater, except that a
vaporizing or pressure oil burner supplies the heat.
• Electric Water Heater- normally has two immersion type heating elements. The
upper heater usually has higher wattage than the lower. Thermostats control
these elements to ensure that the operation is automatic. The heater does not
need a flue or smoke stack since there are no burning products. The electric
water heater may be located in a closet.
INDIRECT HEATING SYSTEM
In this system the water that is heated by the boiler is never used out of the hot water
faucets, but circulates through a heat exchanger. This takes the form of a coil pipe
within the hot water storage tank. The heated water circulates through the system and
in turn heats the water held within the storage tank, then results to the boiler to be
reheated. The advantages of this system are:
1. Since the water in the boiler does not mix with the water in the storage tank, the
risk of rusty water being drawn off through the faucets is eliminated.
2. It keeps the carbonate deposits to a minimum level because once the temporary
hardness of the water has been released it will not recur as the same water is
reheated over and over again.
3. It can use steam as the heating medium instead of water.
There are 3 types of indirect heating system currently used in buildings, these are:
1. Primatic Cylinder
2. Calorifiers
3. Annular Cylinder
NOTE: Where water is being used for heating , the “rule of thumb” to determine the
heating surface is approximately 1000 cubic centimeter of heating surface per 10 liters
of water in the storage tank. For 180 liters of stored water, this works out to
approximately 21 meters of a 15 mm diameter pipe or 16 meters of a 20mm diameter
pipe.
a. Cold water supply- delivered into the tank via a boiler tube that extends to within
150mm of the tank bottom. The purpose for this is to avoid the possibility of
cooling the hot water which accumulates at the top of the tank. This cold water
line must have a small hole within 150mm from the top of the tank. This hole
serves as a vacuum breaker and prevents siphonage. The supply line into the
tank must be equipped with a control valve located as close to the hot water tank
as possible.
b. Flow connection- is connected to an opening on the tank somewhere above its
center point. This line is called the flow connection because the heated water
flows from the heater in the tank.
c. Return connection- is connected to a tapping on the bottom of the tank. This
line is called the return connection because it returns the colder water from the
bottom of the tank of the heater.
d. Drain valve- is located at the lowest point of the storage tank.
e. Hot water distribution pipe- is connected to a tapping on the top of the tank at
the point near the flow inlet.
f. Blow-off valve- is installed to the storage tank to control the temperature and