The document is a Gantt chart schedule for the construction of a Mrs.Sarasa G+3 building project from May 2022 to July 2023. It outlines the key activities in the pre-construction, engineering, and construction phases. The pre-construction phase involves design, quantity finalization, and site mobilization activities over 44 days. The 337 day engineering phase includes foundation work, wall construction for each floor, slab work, electrical conduiting, plastering, and external plastering.
The document is a Gantt chart schedule for the construction of a Mrs.Sarasa G+3 building project from May 2022 to July 2023. It outlines the key activities in the pre-construction, engineering, and construction phases. The pre-construction phase involves design, quantity finalization, and site mobilization activities over 44 days. The 337 day engineering phase includes foundation work, wall construction for each floor, slab work, electrical conduiting, plastering, and external plastering.
The document is a Gantt chart schedule for the construction of a Mrs.Sarasa G+3 building project from May 2022 to July 2023. It outlines the key activities in the pre-construction, engineering, and construction phases. The pre-construction phase involves design, quantity finalization, and site mobilization activities over 44 days. The 337 day engineering phase includes foundation work, wall construction for each floor, slab work, electrical conduiting, plastering, and external plastering.
Completion of SF Slab 7.00 02-Nov-22 09:00 AM 09-Nov-22 06:00 PM
A1800 Slab Shuttering at SF 3.00 02-Nov-22 09:00 AM 04-Nov-22 06:00 PM A1810 Slab Reinforcement at SF 2.00 05-Nov-22 09:00 AM 07-Nov-22 06:00 PM A1820 Slab Concreting at SF 1.00 09-Nov-22 09:00 AM 09-Nov-22 06:00 PM Completion of TF Slab 7.00 02-Dec-22 09:00 AM 09-Dec-22 06:00 PM A1610 Slab Shuttering at TF 3.00 02-Dec-22 09:00 AM 05-Dec-22 06:00 PM A1620 Slab Reinforcement at TF 2.00 06-Dec-22 09:00 AM 07-Dec-22 06:00 PM A1630 Slab Concreting at TF 1.00 09-Dec-22 09:00 AM 09-Dec-22 06:00 PM Completion of Electrical Slab Conduiting 79.00 08-Sep-22 09:00 AM 08-Dec-22 06:00 PM A1230 GF Electrical slab Conduiting 1.00 08-Sep-22 09:00 AM 08-Sep-22 06:00 PM A1240 FF Electrical Slab Conduiting 1.00 08-Oct-22 09:00 AM 08-Oct-22 06:00 PM A1650 SF Electrical Slab Conduting 1.00 08-Nov-22 09:00 AM 08-Nov-22 06:00 PM A1830 TF Electrical Slab Conduiting 1.00 08-Dec-22 09:00 AM 08-Dec-22 06:00 PM Completion of Internal Plaster 39.00 16-Jan-23 09:00 AM 01-Mar-23 06:00 PM A1250 Internal Plaster at GF 9.00 16-Jan-23 09:00 AM 25-Jan-23 06:00 PM A1260 Internal Plaster at FF 9.00 27-Jan-23 09:00 AM 06-Feb-23 06:00 PM A1740 Internal Plaster at SF 9.00 08-Feb-23 09:00 AM 17-Feb-23 06:00 PM A1840 Internal Plaster at TF 9.00 20-Feb-23 09:00 AM 01-Mar-23 06:00 PM Completion of External Plaster 39.00 03-Mar-23 09:00 AM 17-Apr-23 06:00 PM A1270 North Face 9.00 03-Mar-23 09:00 AM 13-Mar-23 06:00 PM A1280 East Face 9.00 15-Mar-23 09:00 AM 24-Mar-23 06:00 PM A1290 South Face 9.00 27-Mar-23 09:00 AM 05-Apr-23 06:00 PM A1300 West Face 9.00 07-Apr-23 09:00 AM 17-Apr-23 06:00 PM Flooring 29.00 20-Feb-23 09:00 AM 24-Mar-23 06:00 PM A1310 GF to FF Flooring works 9.00 20-Feb-23 09:00 AM 01-Mar-23 06:00 PM A1660 FF to SF Flooring works 9.00 03-Mar-23 09:00 AM 13-Mar-23 06:00 PM A1860 SF to TF Flooring works 9.00 15-Mar-23 09:00 AM 24-Mar-23 06:00 PM Dadoing 15.00 27-Mar-23 09:00 AM 12-Apr-23 06:00 PM A1320 GF to FF Dadoing works 5.00 27-Mar-23 09:00 AM 31-Mar-23 06:00 PM A1670 FF to SF Dadoing works 5.00 01-Apr-23 09:00 AM 06-Apr-23 06:00 PM A1850 SF to TF Dadoing works 5.00 07-Apr-23 09:00 AM 12-Apr-23 06:00 PM Staircase 15.00 13-Apr-23 09:00 AM 29-Apr-23 06:00 PM A1330 GF to FF works 5.00 13-Apr-23 09:00 AM 18-Apr-23 06:00 PM A1510 FF to SF works 5.00 19-Apr-23 09:00 AM 24-Apr-23 06:00 PM A1870 SF to TF works 5.00 25-Apr-23 09:00 AM 29-Apr-23 06:00 PM Completion 2 coats putty 12.00 01-May-23 09:00 AM 13-May-23 06:00 PM A1340 GF to FF 4.00 01-May-23 09:00 AM 04-May-23 06:00 PM A1680 FF to SF 4.00 05-May-23 09:00 AM 09-May-23 06:00 PM A1880 SF to TF 4.00 10-May-23 09:00 AM 13-May-23 06:00 PM Completion of Primer 9.00 15-May-23 09:00 AM 24-May-23 06:00 PM A1350 GF to FF 3.00 15-May-23 09:00 AM 17-May-23 06:00 PM A1690 FF to SF 3.00 18-May-23 09:00 AM 20-May-23 06:00 PM A1890 SF to TF 3.00 22-May-23 09:00 AM 24-May-23 06:00 PM Completion of Internal Paint 43.00 25-May-23 09:00 AM 13-Jul-23 06:00 PM A1360 1st coat from GF to FF 3.00 25-May-23 09:00 AM 27-May-23 06:00 PM A1530 2nd coat from GF to FF 3.00 04-Jul-23 09:00 AM 06-Jul-23 06:00 PM A1700 1st coat from FF to SF 3.00 29-May-23 09:00 AM 31-May-23 06:00 PM
A1710 2nd coat from FF to SF 3.00 07-Jul-23 09:00 AM 10-Jul-23 06:00 PM
A1900 1st coat from SF to TF 3.00 01-Jun-23 09:00 AM 03-Jun-23 06:00 PM A1910 2nd coat from SF to TF 3.00 11-Jul-23 09:00 AM 13-Jul-23 06:00 PM Completion of External Paint 40.00 05-Jun-23 09:00 AM 20-Jul-23 06:00 PM A1370 North, East, South, West - 1st coat 6.00 05-Jun-23 09:00 AM 10-Jun-23 06:00 PM A1540 North, East, South, West - 2st coat 6.00 14-Jul-23 09:00 AM 20-Jul-23 06:00 PM Completion of Wall Conduit 9.00 19-Dec-22 09:00 AM 28-Dec-22 06:00 PM A1380 GF to FF 3.00 19-Dec-22 09:00 AM 21-Dec-22 06:00 PM A1720 FF to SF 3.00 22-Dec-22 09:00 AM 24-Dec-22 06:00 PM A1920 SF to TF 3.00 26-Dec-22 09:00 AM 28-Dec-22 06:00 PM Completion of Wiring 6.00 27-Jun-23 09:00 AM 03-Jul-23 06:00 PM A1390 GF to FF 2.00 27-Jun-23 09:00 AM 28-Jun-23 06:00 PM A1730 FF to SF 2.00 29-Jun-23 09:00 AM 30-Jun-23 06:00 PM A1930 SF to TF 2.00 01-Jul-23 09:00 AM 03-Jul-23 06:00 PM Completion of Switches and Plate Fixing 6.00 04-Jul-23 09:00 AM 10-Jul-23 06:00 PM A1400 GF to FF 2.00 04-Jul-23 09:00 AM 05-Jul-23 06:00 PM A1770 FF to SF 2.00 06-Jul-23 09:00 AM 07-Jul-23 06:00 PM A1940 SF to TF 2.00 08-Jul-23 09:00 AM 10-Jul-23 06:00 PM Completion of Internal Plumbing 6.00 27-Jan-23 09:00 AM 02-Feb-23 06:00 PM A1410 GF to FF Internal Plumbing 2.00 27-Jan-23 09:00 AM 28-Jan-23 06:00 PM A1780 FF to SF Internal Plumbing 2.00 30-Jan-23 09:00 AM 31-Jan-23 06:00 PM A1950 SF to TF Internal Plumbing 2.00 01-Feb-23 09:00 AM 02-Feb-23 06:00 PM Completion of External Plumbing 5.00 19-Apr-23 09:00 AM 24-Apr-23 06:00 PM A1420 External plumbing works 5.00 19-Apr-23 09:00 AM 24-Apr-23 06:00 PM Completion of Sanitary Fixing 4.00 11-Jul-23 09:00 AM 14-Jul-23 06:00 PM A1430 Sanitary works 4.00 11-Jul-23 09:00 AM 14-Jul-23 06:00 PM Completion of Door Frame & Window Grills 14.00 29-Dec-22 09:00 AM 13-Jan-23 06:00 PM A1440 GF to FF 4.00 29-Dec-22 09:00 AM 02-Jan-23 06:00 PM A1750 FF to SF 4.00 04-Jan-23 09:00 AM 07-Jan-23 06:00 PM A1960 SF to TF 4.00 10-Jan-23 09:00 AM 13-Jan-23 06:00 PM Completion of Door Shutters 12.00 13-Jun-23 09:00 AM 26-Jun-23 06:00 PM A1450 GF to FF 4.00 13-Jun-23 09:00 AM 16-Jun-23 06:00 PM A1760 FF to SF 4.00 17-Jun-23 09:00 AM 21-Jun-23 06:00 PM A1970 SF to TF 4.00 22-Jun-23 09:00 AM 26-Jun-23 06:00 PM Material Selection 175.00 18-Nov-22 09:00 AM 09-Jun-23 06:00 PM A1550 Wood Frame Material Selection with Client 5.00 18-Nov-22 09:00 AM 23-Nov-22 06:00 PM A1560 Tile / Granite Selectio n with Clie nt 5.00 04-Jan-23 09:00 AM 09-Jan-23 06:00 PM A1570 Electrical Fixtures Selection with Client 5.00 24-May-23 09:00 AM 29-May-23 06:00 PM A1580 Sanitary Fixtures Selection with Client 5.00 05-Jun-23 09:00 AM 09-Jun-23 06:00 PM A1590 Door Shutter Selection with Client 5.00 12-May-23 09:00 AM 17-May-23 06:00 PM Final Handover 13.00 12-Jul-23 09:00 AM 26-Jul-23 06:00 PM Pre House Warming 8.00 12-Jul-23 09:00 AM 20-Jul-23 06:00 PM A1460 Compound wall and MS works 8.00 12-Jul-23 09:00 AM 20-Jul-23 06:00 PM Post House Warming 3.00 24-Jul-23 09:00 AM 26-Jul-23 06:00 PM A1470 Cleaning Interiors 1.00 24-Jul-23 09:00 AM 24-Jul-23 06:00 PM A1480 Cleaning Exteriors 1.00 25-Jul-23 09:00 AM 25-Jul-23 06:00 PM A1490 Final Handover 1.00 26-Jul-23 09:00 AM 26-Jul-23 06:00 PM