Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 12

Dense Bituminous Macadam(DBM)

Dense Bituminous Macadam(DBM) is a binder course used for roads and


highway works with a greater number of heavy commercial vehicles and a close-
graded premix material vehicle and a close-graded premix material having a
voids content of 5-10 percent.

Function
 This material has increased in popularity due to durable surface which
performs almost well as in all situations.
 Suitable for all pavement layers and for all traffic conditions.
 DBM provides a good quality smooth surface and improved skid resistance.
 Should be able to withstand the higher shear stress that occur below the
bearing course.

Material Requirement for Dense Bituminous


Macadam (DBM)
Bitumen (Binder):

 Viscosity grade bitumen-VG10, VG20, VG30, VG40 etc.


 Modified Bitumen- Polymer Modified Bitumen (PMB), Crumbled Rubber
Method Bitumen (CRMB) etc.

Coarse Aggregate:

 Coarse aggregate shall consist of crushed rock or crushed gravel.


 Separate stock pile for DBM purpose to be maintained for each size of
aggregate.

Fine Aggregate:

 Fine aggregate shall consist of crushed or naturally occurring material or a


combination of two.
Filler:

 Filler shall be consisting of finally divided mineral matter such as rock dust,
hydrated lime of cement.

Anti-Stripping Agent:

 Anti-stripping available either in liquid form or powder form (hydrated lime,


cement, rock filler). It will improve the moisture sensitivity of aggregates.
 Anti-striping agent is the special item and the codes requirement to be satisfied
before use.
 10 min test to be performed as per ASTM D3625 to evaluate the stripping of
aggregate.
Grading Requirement for Dense Bituminous Macadam (DBM)

Grading I II

Nominal Aggregate Size 37.5 26.5

Layer Thickness 75-100 50-75

OBC Min 4.0% Min 4.5%

Cumulative % by weight Cumulative % by weight


IS Sieve (mm)
of total aggregate passing of total aggregate passing

45 100 –

37.5 95-100 100

26.5 63-93 90-100

19 – 71-95

13.2 55-75 56-80

4.75 38-54 38-54

2.36 28-42 28-42


0.3 7-21 7-21

0.075 2-8 2-8


 In case aggregate have specific gravity more than 2.7, minimum bitumen
content can be reduced proportionally.

Grading Requirement for DBM


Requirements of Fines in DBM (MORTH V):

Layer Fines Requirements


Remarks
Thickness (75 mic passing)

Grading 1
75-100 mm 2-8 %
(MORTH V Table 500-10)

Grading 2
50-75 mm 2-8 %
(MORTH V Table 500-10)

Plasticity Index≤ 4%                                      Sand Equivalent Value < 50%

Layer Requirement (300mic
Remarks
Thickness passing)

75-100 mm                 7-21 % Grading 1 (MORTH V Table 500-10

50-75 mm                 7-21 % Grading 2 (MORTH V Table 500-10

Plant & Machinery Required

 Hot mix plant


 Asphalt Paver
 Tandem Roller
 Pneumatic Tired Roller
 Prime/Tack Spray Tanker
 Survey Instrument

Tests and Frequency of testing for Bitumen


Test Specification Ref. Code Frequency

Absolute Viscosity 2400-3600 IS 1206 Part 2 1 test per lot

Kinematic
Min 350 IS 1206 Part 3 1 test per lot
Viscosity

Softening Point Min 47 IS 1205 1 test per lot

Penetration Test Min 45 IS 1203 1 test per lot

IS 1448 Part
Flash Point Min 220 1 test per lot
69

Ductility Min 40 IS 1208 1 test per lot

Viscosity Ratio at
Max 4 IS 1206 Part 2 1 test per lot
60°
Acceptance Criteria & Frequency

Test Specification Ref. Code Frequency

Mix Grading Within JMF IS 2386 Part 1 1 Test/400 MT

Combined EI & FI Max 35% IS 2386 Part 1 1 Test/350m³

Los Angles Value Max 35% IS 2386 Part 4 1 Test/350m³

Aggregate Impact
Max 27% IS 2386 Part 4 1 Test/350m³
Value

Max 12%
1 Test for Each
Soundness Test Na2SO4 Max IS 2386 Part 5
Source/Source change
18% Mg2SO4

Sp. Gravity & WA- Max 1 Test for Each


IS 2386 Part 3
Water Absorption 2% Source/Source change

1 Test for Each


Stripping Value Min 95% IS 6241
Source/Source change

Sand Equivalent IS 2720 Part 1 Test for Each


Min 50%
Test 37 Source/Source change

1 Test for Each


Plasticity Index Max 4% IS 2720 Part 5
Source/Source change
Acceptance Criteria for DBM & Frequency

Specificat
Test Ref. Code Frequency
ion

Marshal Stability Min 9.0 Is 2386 part 1 1 test/400 MT

Marshal Flow 2-4 Is 2386 part 1 1 test/400 MT

Marshal Quotient 2-5 Is 2386 part 4 1 test/400 MT

% Air Voids 3-5 Is 2386 part 4 1 test/400 MT

% Void filled with


65-75 Is 2386 part 5 1 test/400 MT
Bitumen

Tensile Strength
Min 80% IS 6241 One test per mix
Ratio

% Voids in mineral Table 500- AASTHO


1 test/400 MT
Aggregate 13 T283

Fines to Bitumen MORTH V


0.6-1.2 1 test/400 MT
Ratio & MS2

Optimum Bitumen OBC±0.3


MORTH V 1 test/400 MT
Content %
Rate of spread of mix – MORTH V After every 5th truck load

Density of 92% of
MORTH V 1/700 sqm
Compaction GMM

Construction of DBM Layer


Construction of Dense Bituminous Macadam (DBM) layer is to be carried out by
following activities-

Preparation of WMM surface to receive Prime Coat:


Approved WMM surface shall be swept clean by power brooms or mechanical
sweepers. All the loose particles to be removed.

Application of Prime Coat:

 Primer shall be Slow setting emulsion SS1 and it shall be sprayed uniformly at
the rate of 0.7-1.0 kg/sqm.
 Primer shall not be sprayed during heavy wind, rainy, foggy or when the
ambient temperature is less than 10°c.
 Primed surface shall be cured for at least 24 hrs.

Application of Tack Coat: 

 Tack coat shall be Rapid setting RS1.


 Surface to receive tack coat shall be clean and free from dust.
 Tack coat shall not be sprayed during heavy wind, rainy, foggy or when the
ambient temperature is less than 10°C.
 Tack coat spraying temperature shall be 20°-70° C.
 Rate of spray shall be 0.25-0.3 Kg/sqm.
 Tack coat shall be cured until all the volatiles have evaporated.
Weather limitations for DBM laying:
 Rain, fog or dust.
 When the surface is wet.
 Air temperature on the surface is less than 10°C.
 Wind speed exceeds 40 kmph at 2m height.

Cleaning of Surface:

 Surface shall be cleaned of all loose particles by air jet.

Mixing and Transporting:

 Bituminous mix shall be prepared In hot mix plant of adequate capacity and
appropriate temperature to be maintained for Aggregates, bitumen, mix
temperature.
 Normally, batch mixing time of plant begins with 30 sec mix cycle.
 Bituminous material shall be transported in cleaned and Tarpaulin covered
vehicle.

Mixing, Laying and Rolling Temperature for Bituminous Mixes 

Mixed
Bitumen Bitume Aggregate Laying Rolling
Material
Viscosity n Temp. Temp. Temp. Temp.
Temp.
Grade (°C) (°C) (°C) (°C)
(°C)

VG-40 160-170 160-175 160-170 150 min 100 min

VG-30 150-165 150-170 150-165 140 min 90 min

VG-20 145-165 145-170 145-165 135 min 85 min

VG-10 140-160 140-160 140-160 130 min 80 min


Precautions to be taken at Hot Mix Plant:

 Calibrated Dial thermometer shall be installed at bitumen storage.


 Insulation shall be provided for bitumen storage tank.
 Frequency chart as per client requirement shall be at plant:

Aggregate ±1.5%    Bitumen  ±0.1%   Mineral Filler  ±0.5%

 HMP shall not run more than rated speed.


 Batch mixing time shall be 30 seconds.
 Temperature of aggregates, bitumen and mix displaying at control panel shall
be maintain as per (MORTH V Table 500-2).

Laying of DBM:

 Metallic strings supported on pegs and arms to be used as level reference for
paver. Interval between pegs shall be 10m.
 Before commencing paving operations, paver parts to be completely checked.
Like screed heater, auger, sensor etc.
 Tire pressure of Pneumatic tired roller shall be maintained 0.56kg/cm².
 Water Sprayer to be checked for adequate holes before spraying.
 Temperature of the mix shall be checked before laying into the paver.
 A thumb rule for determining the thickness of the loose mat is multiply the
desired compacted thickness by 1.25 (Ref MS4 pg 265).

Compaction:

 Once the material is spread by paver, compaction to start immediately and


shall be completed within the specified rolling temperature.
 Rolling of longitudinal joints shall be done immediately behind the paving
operations.
 After this, rolling shall start at the edges and progress towards the centre.
 Tyre pressure of PTR shall be at least 0.56 Mpa.
 Three types of rolling is used to achieve the required compaction

            
1.Initial or breakdown rolling 2. Intermediate rolling 3. Finish rolling

 Sample rolling pattern for DBM layer (1 plain pass + 2 Heavy vibration+ 1 Low
vibration+ 3PTR+ 1Plain Pass)
 Initial rolling shall be done with 8-10 T static wheel rollers.
 Intermediate rolling shall be done with 8-10T static or 12-15T PTR.
 Finish rolling shall be done with 6-8T smooth wheel tandem rollers.

 Joints:

 There are two types of joints involved in DBM construction


 Longitudinal       2) Transverse Joints
 All joints shall be cut vertical to the full thickness of previously laid mix.
 Vertical face to be coated with suitable viscosity grade bitumen.
 While spreading the material along the joint, the material shall overlap 25-
50mm on the previously laid mix beyond the vertical face of the joint.
 Transverse joint begins at the end of the day’s paving operation.
 At the end of day, the layer end has to be shape in the form of ramp. The end
portion of layer shall be sawed on the next day before paving operation begin.

Surface Finish:

 The surface of DBM layer shall not vary from ±6mm.


 The longitudinal profile shall be checked with 3m long straight edge at the
middle of each traffic lane along a line parallel to the centre line of the road.
 Density of DBM layer shall be checked by taking cores after 24 hrs laying.
 Min. load density equal to or more than 92% of the theoretical maximum sp.
Gravity (Gmm).

Productivity
 DBM Productivity             :            21000-25000 MT/Month/Team/Day
 Paver Productivity            :            50 m³/hr
 Roller Productivity            :            40 m³/hr

You might also like