FOR : CLN/EQS/RRR

FROM : BUSINESS DEVELOPMENT GROUP

SUBJECT : INITIAL ASSESMENT TO SITE 3 SAN MATEO

DATE : July 4, 2022

I. BACKGROUND INFORMATION

The proposed category __ Sanitary Landfill site is seated on the following geographic
coordinates: 14.832167 North Latitude and 121.139301 East Longitude covering an area of
28.38 hectares and is accessible via Commonwealth Ave/Don Mariano Marcos Ave and Manila
Gravel Pit Rd/Payatas Rd and the Commonwealth Ave/Don Mariano Marcos Ave to CSJDM
or Mindanao Avenue and Quirino Hwy to Welcome Rd in CSJDM.

the proposed SLF will cater the waste from municipalities of Bulacan, nearby cities and
other municipalities within the close vicinity, and will have an estimated waste handling
capacity of ______ tons per day (TPD).

This site assessment is in accordance with the site identification criteria stipulated in the
Republic Act 9003, and the National Solid Waste Management Commission Resolution No.64,
series of 2013 which mandates this Office to provide technical assistance in conducting
environmental site assessment, identification and selection for proposed waste management
facilities.

II. FINDINGS AND OBSERVATION

1. The area generally lies FLAT/SLOPPING terrain and is surrounded by various vegetation
such as _____, __________________.
2. In terms of the compatibility of the proposed project with the existing land use plan, the
area is currently zoned as __________ land. Favorable clearances from the Department
of Agriculture (DA) and Department of Agrarian Reform (DAR) as well as Municipal
Resolution regarding the use of the said land shall be secured;
3. Based on the rain-induced landslide and flood susceptibility maps, and the results and
findings, the area has low and medium landslide and flood susceptibility rating. However,
according to our INITIAL findings “Majority of the area of the identified proposed site
is not susceptible to flooding except those areas near active river channels which be
inundated duringoccurrences of heavy rains thus experiences moderate to high”
4. Aerial and Table survey shows that the proposed project site is partly part from the
NIPAS and 525.500 away from the CRITICAL WATERSHED.
5. According to the result of HazardHunterPH, the nearest Active Fault is a segment of
West Valley Fault situated about 857 meter and 1 km from the proposed site
Observation based on Site Identification Criteria stipulated in the Republic Act 9003, and the
National Solid Waste Management Commission Resolution No.64, series of 2013 are
summarized on the table below:

Table 1: Site identification Criteria and Suitability Assessment for Waste Management Facilities
under RA 9003 and NSWMC Resolution No. 64, series of 2013

FOR INTERNAL
AND INITIAL
ASSESSSMENT
Site Selection Exclusion (Absolute) ONLY
Findings and Observations
Parameters Criteria
Concerned
Government
Agency/ Entity
Shall not be located on
Shallow unconfined
1. Proximity to
aquifers. Areas within
groundwater MGB/ Proponent’s 3.81km form the existing angat
500 m upgradient.
consultant river
Water used for drinking,
resources
irrigation or livestock
shall be excluded
Shall not be located
within 300 m of
2. Proximity to
watershed areas or
Perennial
upgradient of any EMB Need to have site inspection
surface waters used for
Surface Waters
drinking, irrigation or
livestock
The site shall not be
3. Local
located on areas with
Geological
underlying rocks Cannot Comment from BDG
characterized as jointed, MGB as it must be tested by MGB
Conditions
fractured or fissured Laboratory
(underlying rock
formation)
4. Seismic
No facility shall be
Conditions Note: Nearest Active Fault is
constructed at a site
MGB/ PHIVOLCS about 857 meter (Based on
within 75 meters from a
(Proximity too Hazardhunter of Phivolcs)
Holocene fault
faults)
5. Soil Properties Shall not be located in MGB Litho Spilitic and basic
and availability of unstable, very soft and flows
cover material settling soils Lithodesc Essentially spilitic
and basic flows;
usually intercalated
with graywackes.
Transgressive on
basement rocks
Note: Geohazard map
6. Topography Shall not be located on a
MGB Low to medium on landslide
(Terrain and Slope) landslide-prone area
Note: Geohazard map
not susceptible to flooding
except those areas near active
The site shall not be
7. Vulnerability to river channels which be
located in areas prone to MGB
Flooding inundated duringoccurrences
seasonal flooding
of heavy rains thus experiences
moderate to high

The site shall not be


located in or within 250
m of existing or
8. Proximity to
proposed residential,
residential
commercial or urban
EMB/MGB Need site inspection
development areas, and
areas and other
areas of historical,
sensitive land users
archaeological, cultural,
geological, or scientific
interest
The site shall not be
9. Proximity to located within 500 m of Note: Geohazard map
Ecologically the boundaries of
Sensitive or ecologically sensitive EMB partly part from the NIPAS and
Environmentally areas proclaimed as 525.500 away from the
Critical Areas protected areas under CRITICAL WATERSHED
NIPAS Act
The location of the
facility shall be
10. Consistency
consistent with the The area is currently zoned as
with current or
existing or proposed Host LGU __________land. Need to
proposed land use
land use classification check tax declaration
classification
of CLUP of the host
LGU
located within 3km
11. Proximity to The site shall not be of an airport
No nearby airport
Airport EMB Airport

The site shall be large


12. Area and enough to accommodate
Host LGU Engineering intervention
Lifespan waste for a period of 5
years
accessible via Commonwealth
Ave/Don Mariano Marcos
Ave and Manila Gravel Pit
Rd/Payatas Rd and the
Commonwealth Ave/Don
Mariano Marcos
13. Haul distance, Ave to CSJDM
The site shall be
accessibility or Mindanao
accessible from major
EMB Avenue and Quirino
roadways and
and Road Hwy to Welcome
thoroughfares
Conditions Rd in CSJDM.