Professional Documents
Culture Documents
Safe Working Practice
Safe Working Practice
Safe Working Practice
1
Instrumentation Training Course Page: 1
Module 1 Safe Working Practice of: 42
Module 1 Contents
FOREWORD: ZADCO EMERGENCY PROCEDURES................................................ 2
PERSONAL SAFETY:
M1.0 SAFE WORKING PRACTICE ........................................................................... 4
M1.1 ELECTRICAL SAFETY ..................................................................................... 4
M1.2 EARTHING (GROUNDING) .............................................................................. 5
M1.3 WORK PERMITS .............................................................................................. 6
M1.4 NON-SPARKING TOOLS ............................................................................... 18
M1.5 CONFINED SPACES ...................................................................................... 18
M1.6 INERT GAS ..................................................................................................... 18
M1.7 OTHER HEALTH HAZARDS ON SITE ........................................................... 18
M1.8 PRESSURISED LINE & COMPRESSED AIR PRECAUTIONS ..................... 19
PLANT SAFETY:
M1.9 FLAMMABLE FACTS ...................................................................................... 20
M1.10 HAZARDOUS AREA CLASSIFICATION ........................................................ 21
M1.11 ELECTRICAL EQUIPMENT FOR USE IN HAZARDOUS AREAS ................. 23
M1.12 SUITABILITY OF METHODS OF PROTECTION FOR ZONE 0, 1, 2 ............ 24
M1.13 TEMPERATURE CLASSIFICATION OF EQUIPMENT .................................. 25
M1.14 GAS GROUPS ................................................................................................. 25
M1.15 INTRINSIC SAFETY ........................................................................................ 26
M1.16 ZENER BARRIERS ......................................................................................... 28
M1.17 MAINTENANCE WORK IN HAZARDOUS AREAS ........................................ 31
M1.18 PRESSURE RELIEF & SAFETY VALVES ..................................................... 31
M1.19 RUPTURE DISCS ........................................................................................... 35
M1.20 HYDROGEN SULPHIDE .................................................................................. 36
M1.21 INGRESS PROTECTION ................................................................................ 36
M1.22 PRACTICAL .................................................................................................... 37
M1.23 QUESTIONS ................................................................................................... 38
ZADCO COLD WORK PERMIT .................................................................................. 39
ZADCO HOT WORK PERMIT .................................................................................... 40
APPENDIX REFERENCE ........................................................................................... 41
Revisions:
v1 1989 First version
v6.1 Sept 2001 Foreword and Pilot Operated PSV added. Electrical safety revised
April 2002 1.5b page 6 'Health Hazards' added
v6.2 Aug 2002 Reference Section Added, On site exercise added
Nov 2002 PSV terminology added 1.18.1
v7.0 Jan 2003 Zadco work permit procedures updated
v7.1 June 2003
Objectives of Module 1
This section aims to make trainees aware of the potential hazards of:
1. Electricity
2. Confined Spaces
3. Compressed Air
4. Fire and Explosion
5. Hydrogen Sulphide
and to explain how safe working practices and procedures and a permit to work system
allow us to work on a petrochemical plant without risk to ourselves, to other people, to the
plant or to our environment.
FOREWORD
Before starting your instrument training, you should have received;
1. Fire Fighting Training
2. First Aid Training
3. H2S Training
4. Gas Test Training
and you must know the following:
1_safety.p65 (W.Phillips)
Zirku-HRT Revision: 7.1
Instrumentation Training Course Page: 3
Module 1 Safe Working Practice of: 42
Whenever possible, avoid working on or near energised circuits or equipment. This does
not forbid working live but doing so requires justification. (This means you must have a good
reason for working live.)
NOTES:
1. Circuits with capacitors (for example, uninterruptable power supplies) may give severe shock
even after being disconnected from the supply. They can be discharged by shorting with a 5 kohm
resistor. They should not be directly shorted as this can cause damage to the plates of the capacitor
and the device shorting them.
2. Before connecting any instrument to the electrical supply be sure to check that it is of correct
voltage and frequency.
3. When connecting or disconnecting an instrument to its power supply make sure that all switches
are in the OFF position. This prevents arcing when connecting up. After connecting replace all
covers on terminals.
1_safety.p65 (W.Phillips)
Zirku-HRT Revision: 7.1
Instrumentation Training Course Page: 5
Module 1 Safe Working Practice of: 42
Earth connections should be direct to earth and not via another instrument. This prevents any fault
on one instrument being transmitted to another.
You should know how to give artificial respiration BUT DO NOT TOUCH ANYONE SUFFERING
FROM ELECTRIC SHOCK UNTIL YOU ARE SURE THAT THEY ARE DISCONNECTED FROM
THE SUPPLY. Drag someone clear of a live supply by touching only their clothing.
Exercise 1.1
The international colour code for single phase ac mains cable is;
Note:
If the mains cable supplied with an instrument is not to the standard colour code, then
1. EARTH is the core that is connected to the metal case or chassis
2. LIVE is the core that goes to the fuse
SECTION 1. GENERAL
1.1 Definitions
Approved. Accepted by, and endorsed by the authority having jurisdiction.
Area Authority. A Company employee, at a supervisory level or his officially assigned
delegate, who is directly accountable and responsible for the operation of a Company
process plant, site, field or installation.
Authority Having Jurisdiction. The Company Management, Department Manager, Site
Management, or individual responsible for approving equipment, installation or procedures.
Company. When mentioned, it means ZADCO.
Competent. A person, who is Approved by the Company as having the required
qualifications and experience to be accountable and responsible in carrying out pre-defined
tasks.
Contractor. An independent organization or person, hired by the Company, to provide
a service, to act on behalf of the Company in carrying out a pre-defined scope / service, or
for temporary / long term filling of any of the Companys established posts.
Designated. Is the nominated competent person approved by his hierarchy to act in the
capacity of Senior Operator or Senior Technician.
Emergency. Undesirable event which could result in fire, explosion, or hazardous
condition that poses an immediate threat to the safety of life, damage to property, or to the
environment.
Jurisdiction. Any Company location, site or installation that adopted this system of work
and procedures.
Performing Authority. A Company employee, or Contractor acting on behalf of the
Company. He shall be at a Supervisory level or above, of the section which is directly in charge
of performing the work or supervising the work performance of a Contractor.
Performer.A Company employee or a Contracted person, who is required by the Company,
either by himself, or leading a group of persons to carry out specific tasks (e.g. maintenance,
construction, demolishing, checking, etc.), on a specific Company facility.
Shall. Indicates a mandatory requirement.
Should. Indicate a recommendation or that which is advised, but not mandatory.
1_safety.p65 (W.Phillips)
Zirku-HRT Revision: 7.1
Instrumentation Training Course Page: 7
Module 1 Safe Working Practice of: 42
1.2 Introduction
The Permit To Work (PTW) System is a formal written procedure used to control all types of work
that are potentially hazardous. Essential features of a Permit To Work (PTW) System are:
Clear definitions stating who may authorize particular jobs, who is responsible for specifying the
necessary precautions and who may accept the precautions to be undertaken during the work.
Training and instruction in the issue and use of permits.
Effective monitoring to ensure that the system works as intended.
A permit to work is not permission to carry out a dangerous job, but is an essential part of a
procedure that provides instructions on how a job can be carried out safely. The issue of a permit
does not, by itself, make a job safe. This can only be achieved by those preparing and those
carrying out the work. The permit to work is a written document that authorizes certain people to
carry out specific work at a certain time with measures needed to complete the job safely.
1.3. Legislation
The United Arab Emirates Law No. 8 for year 1980 on Conservation of Petroleum Resources
Chapter V, Articles-91 and the Ministerial Order No. 32 for year 1982 Protection of Employees
Against Occupational Hazards Article-1, both state that:
Every employer shall provide adequate protection methods to protect the employees from the
danger of injuries and vocational disease that may occur during work as well as from danger of fire
and from hazards that may occur because of employment of machines and other tools. Moreover,
it shall apply any other preventive methods as approved by the Ministry of Labour & Social Affairs.
A recognized means of complying with the above is the use of a written Permit to Work System.
1.4 Objectives
The objectives of this system is to establish means for the safe control of work which will:
a) Prescribe the nature and extent of the work.
b) Prescribe the conditions (Isolations, Gas tests, etc.) that have to be observed.
c) Provide for maximum safety of both personnel and plant and for good co-ordination between
Operations and maintenance work.
1.5 Hot Work in Hazardous Areas
Hot work is to be avoided in live hazardous areas whenever practicable. Site Management together
with Engineering Department to minimize the need for hot work and provide cost effective
alternatives by careful consideration during the design/modification and construction phases.
1_safety.p65 (W.Phillips)
Zirku-HRT Revision: 7.1
Instrumentation Training Course Page: 9
Module 1 Safe Working Practice of: 42
The Performing Authority shall be a Company employee, or Contractor acting on behalf of the
Company. He shall be at a Supervisory level or above, of the section which is directly in charge of
performing the work or supervising the work performance of a Contractor.
The Performing Authority shall be fully aware and understand all relevant regulations and
procedures prior to being designated as Performing Authority Representative. It will be his
responsibility to ensure that the Performer (Company or Contractor), who is involved in the work
covered by the permit, is aware of and comply with the permit conditions.
2.5 Performer
Performer is the person carrying out the job, or in charge of a number of workers jointly
carrying out the job. The Performer initiates the Work Permit by filling the necessary details
in the INITIATOR Section as referred to in the maintenance work request or planned
maintenance / inspection. The Company Performing Authority shall countersign on this part
as an approval for the application of a Work Permit. The Performer shall state the following:
The nature and description of the work and tools / equipment to be used.
The requested date and time to start the work and the expected duration.
The exact location with any necessary details, drawing or sketches and procedures to be
attached.
On completion of the work, the Performer shall leave the worksite in a safe and clean
condition.
1_safety.p65 (W.Phillips)
Zirku-HRT Revision: 7.1
Instrumentation Training Course Page: 11
Module 1 Safe Working Practice of: 42
Under certain circumstances, an Area Authority may allow certain works to be carried out in his area
of control without the issue of a Permit, but based on a specific formal procedure. The discretion
to use this facility lies entirely with the Area Authority.
This in no way relieves the Area Authority of the responsibility to control work effectively.
The work must not be hazardous to either the person who carries it out or to anyone else including
equipment & environment, and the Area Authority must be satisfied that all reasonable practicable
steps have been taken to ensure the safety of those involved, and anyone else that the work might
affect.
A list of such jobs shall be produced by the Area Authority for approval by the Site Manager / Head
of Field. Examples of such jobs are listed here under for guidance:
Routine production operations (covered by Operating Manuals).
Production / flow testing operation.
Routine Materials handling.
Routine work in offices.
Routine domestic activities (Catering, Cleaning etc.)
Routine helideck operations (including refueling).
General cold work inside workshops.
Watchkeeping.
Visual inspection of areas (not including confined spaces).
Operating or demonstrating portable fire fighting, safety / lifesaving equipment during drills,
training or testing.
Construction site of new facilities until hydrocarbons are first introduced, except where work comes
within 50m of an operating facility.
Well services operations at locations where only well services personnel are working.
Visual inspection.
Simple lubrication of machinery.
Simple cleaning tasks.
Regular and routine check of instruments.
Changing light bulbs in unclassified areas such as offices and buildings.
Sampling of fluids.
Refueling of helicopters.
For each of the Site approved list of jobs, a specific safety standing instructions should be
developed by the Area Authority in consultation with Site HSE and approved by Site Manager / Head
of Field.
4.1 Initiation
4.1.1 The Performing Authority shall initiate the Work Permit by filling the necessary details in the
INITIATOR Section as referred to in the maintenance work request or planned maintenance /
inspection. The Company Performing Authority to sign on this part as an approval for the application
of a Work Permit. The Permit should state:
(i) The nature and description of the work and tools/equipment to be used.
(ii) The date and time to start the work and the expected duration.
(iii) The exact location with any necessary details, drawing or sketches and procedures to be
attached.
4.1.2 An application for a Work Permit is normally made at least a day in advance of the start of
the work. This is to give adequate time for the correct arrangements to be made.
Exceptions will be made at the discretion of Area Authority in order to deal with urgent / emergency
works, but the full Permit to Work System must be applied.
4.1.3 Under no circumstances shall a Contractor be authorized to issue a work permit.
4.1.4 In no case will the same person be allowed to sign the permit as both Area and Performing
Authorities.
4.1.5 In certain cases where the Area Authority is the work Performer, then the Senior Supervisor
/ Supervisor will issue the permit as Area Authority and his subordinate Supervisor/Sr. Operator will
sign as Performing Authority. (see 4.1.4 above).
The Area Authority Supervisor may at his discretion delegate the most competent and trained Snr.
Operator or designated Operator to authorize a work to start after checking that all listed conditions/
precautionary measures are met and the intended work will be carried out safely.
A designated operator will sign on the work permit in the capacity of Snr. Operator.
The performing Authority Supervisor may at his discretion delegate the most competent and
trained Snr. Technician or designated Technician (ZADCO or Contractor) to receive the work
permit at location as Performer after checking that all conditions and precautionary measures are
met.
A formal list of all competent and trained Operators and Technicians designated as work permit
signatories will be kept and updated as required by site.
The designated competent operators and technicians are proposed by their direct Supervisors,
trained in the PTW by site HSE and approved by the Site Manager/Site Team Leader who will be
responsible and accountable for the delegation under items 4.1.6 and 4.1.7 above.
4.2 Permit Distribution
4.2.1 Original Copy (white):
Will be issued to the Performer and will be retained and clearly displayed on site by the person
responsible for the work and will be kept on the job site until the work is complete.
4.2.2 Yellow Copy:
Will remain in the possession of the Area Authority until completion of work.
4.2.3 Pink Copy:
Should be collected by HSE Engineer for random daily auditing of work permits.
4.2.4 Green Copy:
Will be posted in a permanent place in the control room at a convenient location.
1_safety.p65 (W.Phillips)
Zirku-HRT Revision: 7.1
Instrumentation Training Course Page: 13
Module 1 Safe Working Practice of: 42
5.1 Only trained persons, approved by the Area Authority and Site Senior HSE Engineer, will
carry out and certify gas tests. A list of such approved persons, will be held and updated by the
respective Site Manager / Head of Field and copied to all site concerned Authorities.
5.2 A person authorized to carry out gas tests will be responsible for ensuring that the gas
detector is tested and functioning properly.
5.3 In case of hot work the gas test must be carried out prior to immediate commencement of
work.
5.4 Gas Test must show the absence of hydrocarbon vapor / gas.
5.5 Should repetitive gas tests be required then the Authorized Gas Tester may indicate the
result on the Performers copy of work permit. If the risk of gas release may exist at any time
then a continuous gas monitor should be considered.
5.6 In certain Cold/Hot works the Area Authority Supervisor may indicate in the GAS TEST
Section that the area is safe from gases i.e. gas test is not required and sign accordingly.
5.7 Whenever work stops for any reason (e.g. tea, lunch, etc.) then prior to resumption of work,
further gas tests shall be taken. Should the gas test readings section become full, the gas
tester shall continue to record the readings and sign on the reverse side of the permit.
5.8 Training of Site Personnel, to be Approved Gas Testers, shall be conducted by Site HSE.
1_safety.p65 (W.Phillips)
Zirku-HRT Revision: 7.1
Instrumentation Training Course Page: 15
Module 1 Safe Working Practice of: 42
7.1 Withdrawal:
7.1.1 If the site or working conditions change, or are likely to change, after the issuance of the
permit, the Area Authority Supervisor must inform the Performing Authority Supervisor to stop the
work. Similarly if the Performing Authority feels that conditions have changed then he must
withdraw the permit and consult with the Area Authority Supervisor.
7.1.2 All work permits shall be considered withdrawn when the emergency alarm is
sounded. The Performing Authority is not required to hand over the work permit copy to the Area
Authority under emergency condition. The permit may later be re-issued when the Area Authority
is satisfied that the original conditions, under which the permit was issued remain or restored as
originally approved. Re-endorsement to this effect must be indicated by the Area Authority.
7.2 Cancellation:
7.2.1 A work permit is immediately cancelled as soon as the stipulated conditions are not
maintained.
7.2.2 When a work permit has been cancelled work cannot be resumed unless a new permit has
been raised.
Work on Wellhead Platforms Involving the Opening of Cabinets Enclosing Wellhead Safety
Control Systems
Prior to such work commencing on a wellhead platform, a hydrocarbon gas test has to be carried
out by an Authorized Gas Tester. The procedure to be adhered to is as follows:
On arrival at the site, an Authorized Gas Tester is required to conduct a general survey of the area.
Positive readings on gas detection equipment at this stage must be reported by radio to the Area
Authority.
Wellhead control systems cabinets shall be opened and time to be allowed for any accumulated
gas to disperse. All personnel involved to stay up wind of open cabinets.
On completion of work all electrical enclosures and other control cabinets to be closed.
1_safety.p65 (W.Phillips)
Zirku-HRT Revision: 7.1
Instrumentation Training Course Page: 17
Module 1 Safe Working Practice of: 42
A confined space may be dangerous because H2S or inert gas can build-up if we have not ensured
adequate ventillation.
Note that the same combustion process happens in a motor car engine and if you stay in a closed
garage with a car engine running, then you may die from carbon monoxide poisoning.
1_safety.p65 (W.Phillips)
Zirku-HRT Revision: 7.1
Instrumentation Training Course Page: 19
Module 1 Safe Working Practice of: 42
BEFORE UNCOUPLING
1. Obtain a work permit.
2. Find out contents of pipe and get necessary protective clothing and equipment.
3. Inform process operator, he may need to change from automatic control to manual.
4. Ensure process isolator is closed.
UNCOUPLING
1. Open drain/vent valve to depressurise instrument system, ensure process fluid is correctly
disposed of.
2. Close instrument isolators.
3. Remove instrument and fit blanking plugs to the open ends of impulse lines.
4. Close drain/vent valves.
5. On refitting the instrument, again ensure that the system is depressurised before removing
blanking plugs.
PLANT SAFETY
M1.9 FLAMMABLE FACTS
= FIRE OR EXPLOSION
Inflammable (or combustible) gases or vapours mixed with air will form an explosive atmosphere
if the mixture is between certain limits. These limits are expressed as a percentage of the gas by
volume in air. Below the Lower Explosive Limit (LEL) the mixture of gas in air does not contain
enough gas to ignite and cause an explosion. Above the Upper Explosive Limit (UEL) the mixture
does not contain enough air to ignite.
Examples of explosive limits;
A Combustible Gas Monitor (Explosimeter) is used to measure the concentration of gas in the
air and to give an alarm if the concentration of gas goes above 25% of the LEL.
These monitors are installed all over the plant to give an alarm in case of leaks or spillages.
Hand-held versions are used during HOT WORK to make sure that when the work invloves a source
of ignition, then there is no explosive mixture present.
NOTE: Certain mixtures are particularly hazardous since they will ignite without a spark
(spontaneously) e.g.
1) grease or oil plus oxygen - gauges for oxygen cylinders must not get oil inside when calibrated
2) pyrophoric scale (formed inside pipes and vessels that have contained oil or gas mixed with H2S)
ignites when pipes (and instruments) used for "sour service" are opened to the air.
1_safety.p65 (W.Phillips)
Zirku-HRT Revision: 7.1
Instrumentation Training Course Page: 21
Module 1 Safe Working Practice of: 42
Zone 1: An area in which an explosive gas/air mixture is likely to occur under normal oper
ating conditions (10 to 1000 hours per year).
TABLE 1.10.1
SUITABLE Ex ia Ex Increased
INSTRUMENTS only certified safety 'e' if
See Table 1.3 capable of
sparking or
good industrial
standard if
incapable of
sparking.
Ex marked on an instrument means that it has been tested and approved for use in a
HAZARDOUS AREA
EEx means that the equipment has been tested at a European (CENELEC) approved testing
laboratory.
FM Ex or CSA Ex are N. American equivalents
1_safety.p65 (W.Phillips)
Zirku-HRT Revision: 7.1
Instrumentation Training Course Page: 23
Module 1 Safe Working Practice of: 42
A conformity certificate proves that the equipment meets (or conforms to) the requirements of
the standard for electrical equipment used in hazardous areas. In Europe the equipment must now
be marked EEx followed by one or more of the following letters indicating the method of protection
which has been used.
INTRINSIC SAFETY "i" - protection is based on non-ignition of the gas. Energy is limited to a level
too low to ignite an explosive atmosphere by spark or hot spot even if the equipment fails. Since
this equipment is part of a circuit, it is necessary to be sure that the whole circuit (certified apparatus
and wiring) maintains a level of safety suitable for the explosive atmosphere in which it is to be used.
Design and calculations are included in a "system document". Increasingly this is the method
preferred for zone 1. Intrinsic safety is the only method approved for zone 0.
INCREASED SAFETY "e" - protection is based on the non-ignition of the gas. The equipment is
so designed as to produce neither arc, spark nor hot point. Often specified for lighting.
NON-SPARKING "n" - as for "e", protection is based on special design
SPECIAL METHODS "s" as for "e", protection is based on special design
POWDER FILLING "q" - protection is based on the non-propagation of flame. The equipment is
inside an enclosure filled with inert powder or beads. Ignition inside the enclosure by spark or hot
point cannot ignite the surrounding atmosphere. Not much used at present.
OIL IMMERSION "o" - protection is based on the exclusion of the explosive atmosphere.
The electrical equipment is immersed in oil and the hazardous atmosphere cannot be in contact
with the equipment. Mainly used for heavy duty electrical equipment.
A Zadco list of which methods of protection are acceptable in each zone is shown in table 1.11.1
1_safety.p65 (W.Phillips)
Zirku-HRT Revision: 7.1
Instrumentation Training Course Page: 25
Module 1 Safe Working Practice of: 42
TABLE 1.13.2
E Ex d IIc T4
European approved for method(s) safe for max temp.
hazardous used for these of this equipment
test centre area protection gases with fault
Exercise
You should copy the hazardous area certification from the following instruments and explain what
the symbols mean and whether we can use the instrument on Zirku in Zone 1.
1. Honywell I to P
2. Camflex Electropneumatic Positioner
3. Hydrocarbon Gas sensor.
ia - Incapable of causing ignition in normal operation with a single fault and with any combination
of two faults, with the following safety factors:
1.5 in normal operation and with 1 fault
1.0 with 2 faults.
ib - Incapable of causing ignition in normal operation and with a single fault applied, with the
following safety factors:
1.5 in normal operation and with 1 fault
1.0 with 1 fault if the apparatus contains no unprotected switch contacts in parts likely to be exposed
to a potentially explosive atmosphere and the fault is self revealing.
Equipment which is certified to ib standards is suitable for all applications in all zones with the
exception of Zone 0. ia equipment is suitable for installation in all zones.
1_safety.p65 (W.Phillips)
Zirku-HRT Revision: 7.1
Instrumentation Training Course Page: 27
Module 1 Safe Working Practice of: 42
This page is for reference and is not required as part of the basic training course
M1.15.1 INTRINSIC SAFETY AND ENERGY STORAGE
When energy storing devices are included in an intrinsically safe circuit, a spark caused by a short
circuit or a circuit breaking condition will be enhanced by the discharge of the stored energy. Hence,
circuits containing capacitance and/or inductance are subject to additional limitations.
Ignition curves for both capacitive and inductive circuits are published in the European Standard
EN50 020. The energy E stored in a capacitance C charged to a voltage V is calculated from the
expression:
E = CV2 Joules
For a given safe level of energy, the maximum permissible capacitance is therefore dependent
upon the open circuit voltage available to charge the capacitance. When determining the value of
capacitance from the ignition curves, a factor of 1.5 is applied to the maximum working voltage of
the circuit and the value of capacitance is then read off from the curve.
In circuits containing inductance it is the circuit breaking condition which is critical and therefore the
maximum permissible inductance depends on the maximum possible short circuit current. The
energy E stored in an inductance L carrying a current I is given by the expression:
E = LI2 Joules
When using the ignition curves to determine the maximum permissible inductance, a factor of 1.5
is applied to the maximum short circuit current and the permissible inductance value is then read
off from the ignition curve.
1_safety.p65 (W.Phillips)
Zirku-HRT Revision: 7.1
Instrumentation Training Course Page: 29
Module 1 Safe Working Practice of: 42
Details on this page are for reference. They are not required as part of the basic training
course.
M1.16.1 DETERMINING SUITABILITY OF BARRIER FOR AN APPLICATION
FIGURE 1.16.3
When connecting a barrier to intrinsically safe equipment it is necessary to ensure that the
maximum voltage and current delivered by the barrier are smaller or equal to the voltage and current
levels which can be safely received by the apparatus.
In addition, the maximum unprotected capacitance and inductance of the load are subtracted from
the maximum values allowed by the barrier. The remaining inductance and capacitance define the
maximum cable parameters.
The apparatus in figure 1.16.3 may be connected to the barrier providing that:
Vb does not exceed Va
Ib does not exceed Ia
Ca does not exceed Cb
La does not exceed Lb
Cable capacitance does not exceed Cb - Ca
Cable inductance does not exceed Lb -La
where;
Va = maximum voltage the apparatus can receive and remain intrinsically safe
Vb = maximum open circuit voltage of the barrier
Ia = maximum current the apparatus can receive and remain intrinsically safe
Ib = maximum short circuit current of barrier
Ca = maximum unprotected capacitance of apparatus
Cb = maximum capacitance permitted to be connected to barrier
La = maximum unprotected inductance of apparatus
Lb = maximum inductance permitted to be connected to barrier
For more information, see "Intrinsically Safe Instrumentation: A Guide" by Robin Garside, 2nd
edition 1988,Hexagon Technology, ISBN 0 9508 188 0 1
1_safety.p65 (W.Phillips)
Zirku-HRT Revision: 7.1
Instrumentation Training Course Page: 31
Module 1 Safe Working Practice of: 42
Note:
The name Pressure Relief Valve usually means that the valve is for use on liquids and opens
progressively with over pressure.
The name Pressure Safety Valve usually means that the valve is for use on gases or steam and
is designed to provide a wide opening immediately and to close below the set (or 'popping')
pressure.
1_safety.p65 (W.Phillips)
Zirku-HRT Revision: 7.1
Instrumentation Training Course Page: 33
Module 1 Safe Working Practice of: 42
1 -SET PRESSURE
The effective pressure at which the disc of a safety relief valve starts to open under working
conditions. It is this effective pressure which, under these conditions, exerts the force under
the disc which balances out the pressure keeping the disc on its seat
2 - COLD DIFFERENTIAL TEST PRESSURE
The effective pressure at which a safety relief valve starts to open on a test bench.
The cold differential set pressure can be different from the set pressure because of the
corrections which have to be made in order to compensate for certain conditions such as
temperature and the possible effect of back pressure.
3 - OVERPRESSURE
The increase in pressure over set pressure, generally expressed as a percentage of the set
pressure.
4 - CLOSING PRESSURE
The value of the effective pressure measured in the installation protected by the safety relief
valve once the disc re-establishes contact with the seat.
5 - BLOWDOWN
The difference between the set pressure and the closing pressure. This is generally expressed
as a percentage of the set pressure.
6 - LEAK TEST PRESSURE
The pressure at which a safety relief valve is leak-free. This is generally different from the
closing pressure. It is at this pressure that tightness is checked. Leak test pressure is equal to
90% of cold differential test pressure.
7 - INITIAL BACKPRESSURE
The pressure existing downstream from the safety relief valve at the moment it starts to
function.
PRINCIPLE OF OPERATION
The key to relief valve operation is the pilot ball (figure 1.18.2) which is anchored between the ball
adjuster and ball seat. Inlet pressure registers on the main valve disc and enters the pilot through
the control line. As long as inlet pressure remains below set pressure, the pilot control spring holds
the pilot exhaust ball seat ring against the pilot ball. Inlet pressure loads the piston through the pilot
restriction and keeps the main valve closed. An inlet pressure rise above the set pressure
overcomes the pilot control spring and strokes the pilot exhaust ball seat ring away from the ball.
Piston loading pressure bleeds downstream through the pilot exhaust ball seat ring faster than it
can build up through the pilot restriction. This permits inlet pressure to unbalance the main valve
disc and open the main valve. As inlet pressure drops back to set pressure, the pilot control spring
pushes the pilot diaphragms and pilot exhaust ball seat ring back against the ball. Inlet pressure
again loads the piston and closes the main valve.
1_safety.p65 (W.Phillips)
Zirku-HRT Revision: 7.1
Instrumentation Training Course Page: 35
Module 1 Safe Working Practice of: 42
P & ID SYMBOL
1_safety.p65 (W.Phillips)
Zirku-HRT Revision: 7.1
Instrumentation Training Course Page: 37
Module 1 Safe Working Practice of: 42
TAG
TYPE OF EQUIPMENT MANUFACTURER CERTIFICATION NOTES
NUMBER
Junction Box
Tra ns m i tte r o ld e r
Rosemount
model
I to P ABB
Position Switch
Other
By inspection on site, you should fill-in the blanks in the table above.
1.21 QUESTIONS
1. What do we call a mixture containing the least amount of an inflammable substance in air which
will ignite (or explode)?
2. What principle of protection is used for an intrinsically safe loop?
3.What does the IP specification of an instrument tell you?
4. Is an instrument marked EEx ib IIA T2 suitable for use on an ethylene plant in zone 1?
5. What is the difference between a pressure relief valve for liquids and a pressure safety valve for
gasses?
6. What I.P. specification is usually required for a field instrument?
7. For what purpose is an earth connection provided on the metal case of a mains powered
instrument?
8. What precautions must be taken before using a multimeter in zone 1?
9. What is the temperature classification and gas group of crude oil?
10. How do you report an emergency?
11. What voltage is safe to use in zone 1 without special precautions?
12. When can you work on a live circuit in zone 1?
13. What are non-sparking tools?
14. Why do we need a permit to work system?
15. What is hot work?
16. What is a confined space?
17. What is meant by an area of plant classified as zone 1?
18. What is an explosion proof enclosure?
19. What is a rupture disc?
20. Where on unit 401 will you find a pressurized/purged enclosure?
21. How would you know that that there was a leak of H2S on the plant?
22. Why do we need 434-PSV-006 in the drawing below?
1_safety.p65 (W.Phillips)
Zirku-HRT Revision: 7.1
Instrumentation Training Course Page: 39
Module 1 Safe Working Practice of: 42
ZADCO WORK PERMIT PROCEDURES
1.31.0
1.31.1
1_safety.p65 (W.Phillips)
Zirku-HRT Revision: 7.1
Instrumentation Training Course Page: 41
Module 1 Safe Working Practice of: 42
1.31.3
1.31.4
1_safety.p65 (W.Phillips)