Professional Documents
Culture Documents
Duplex-Body Flow Meter Commissioning Procedure
Duplex-Body Flow Meter Commissioning Procedure
石油能源有限责任公司
شركة بترو انرجي إي آند بي المحدودة
Duplex-body Flow Meter Commissioning Procedures
1. The Duplex-body Flowmeter Skid can be connected to OGM or single well according to the
actual situation. Check and confirm whether the external pipeline connection is correct and
reliable.
2. Before the commissioning of the duplex-body flowmeter skid, check and confirm whether it is
in good condition, especially use a multimeter to check whether three phases' fuses in the
control box are in good condition.
Particular attention: Power supply: AC 380V/3Phases.
3. Power on the duplex-body flowmeter skid, and turn on the power switch on the control box.
This moment, the PLC will self-check, the screen will light on and there will be information
displayed. The electric three-way valve may or may not perform actions, depending on the
liquid level in tanks A & B.
4. Check the electric three-way valve, touch the two motors to see if there is any heat, if it is hot,
turn off the power immediately, if it is normal, go on the next step.
5. Open the inlet valve of the duplex-body flowmeter skid and other valve between the test line
and the flowmeter skid.
6. Operate the single-well valve, slowly open the valve from the single-well to the test line, and
pay attention to observe the DPTs' digital alternative change on two tanks, and two electric
three-way valves' action.
Particular attention: At present, the selected single-well’s valve the trunk line is still at open-
status.
7. Observe the pressure rise in the tank, when the pressure in the tanks reaches the trunk line
pressure, open the outlet valve of duplex-body flowmeter skid and other valve between the
flowmeter skid and the trunk line.
8. Operate the single-well valve, close the valve from the single-well to the trunk line. This
moment, all the production fluid from the single well passes through the duplex-body
flowmeter skid.
9. Depending on the amount of associated gas in a single well, the liquid level in the duplex-body
flowmeter skid may be different. If there is very little associated gas, there may be a liquid level
Plot No.2, Block No.13, West Indust. Area, Khartoum Sudan, Tel: +249-1-83-460921, Fax: +249-1-83-465823, PO. Box: 13473
Page 1 of 12
Petro-Energy E&P Co., Ltd.
石油能源有限责任公司
شركة بترو انرجي إي آند بي المحدودة
HH alarm, just reset the alarm. Then wait until the electric three-way valve can be switched
normally, and press the "Start" button to start metering.
10. If you want to end the measurement, press the "End" button to end the measurement.
11. Switch to the measurement data group on screen to record the daily production and ACCUM
production during this test. Complete the report with recorded data.
12. Operate the single well valve, open the valve from the single well to the trunk line, and close
the valve from the single well to the test line.
13. Close the inlet and outlet valves and turn off power supply on the duplex-body flowmeter skid.
If the other wells of the same OGM are no longer measured, empty the liquid in the both tanks;
if you want to continue to measure the next well, the liquid in both tanks does not need to be
drained.
Three-way status:
Troubleshooting
Question:How to do if the "LL: Too High" alarm message appears on the screen?
Answer:"LL: Too High" means that the liquid level in both tanks is higher than the normal value,
the PLC system will force the electric three-way valve to switch to one tank to inlet and outlet
liquid at the same time, this moment, you can open the drain valve of the non-working tank to
discharge some liquid in the tank. When the pressures of two differential pressure gauges on the
tank are consistent, you can close the drain valve.
Attachment 1 (From operation manual)
Plot No.2, Block No.13, West Indust. Area, Khartoum Sudan, Tel: +249-1-83-460921, Fax: +249-1-83-465823, PO. Box: 13473
Page 2 of 12
Petro-Energy E&P Co., Ltd.
石油能源有限责任公司
شركة بترو انرجي إي آند بي المحدودة
Part III Control Cabinet Operating Manual
1、Control cabinet operation interface and normal operation method.
1.1 Control cabinet operation interface
The operation interface is as follows:
On top of the five lines is the text display screen. On the second line are the indicator lamps and
the buzzer. On the third and fourth lines are the operating buttons. On the bottom line are the rotary
switches. On the lower right-hand corner of each button is the specific form of the operation.
1.2 Display
Plot No.2, Block No.13, West Indust. Area, Khartoum Sudan, Tel: +249-1-83-460921, Fax: +249-1-83-465823, PO. Box: 13473
Page 3 of 12
Petro-Energy E&P Co., Ltd.
石油能源有限责任公司
شركة بترو انرجي إي آند بي المحدودة
The text display screen is the operating display interface. There are 7 interface groups:
System Title, One page only.
Real-Time Data Group, 3 pages in total.
Measurement Data Group, 8 pages in total.
Measurement Record Data, Maximum 10 records.
Meter Condition Monitoring Group, 3 pages in total.
Clock Setting.
Parameter Setting
The clock setting and parameter setting interface can be turned out by special method.
1.3 Lamp and Buzzer
Measure: whether the system is in measuring operation.
Shift: whether the multichannel oil well selection device is switching. ①
Auto : whether the current measurement is in automatic performance according to the specified
process. ①
Alarm: The buzzer will give a signal when there is anything wrong with the system.
①:effective only when multichannel oil well selection device is joined up.
Plot No.2, Block No.13, West Indust. Area, Khartoum Sudan, Tel: +249-1-83-460921, Fax: +249-1-83-465823, PO. Box: 13473
Page 4 of 12
Petro-Energy E&P Co., Ltd.
石油能源有限责任公司
شركة بترو انرجي إي آند بي المحدودة
①:effective only when multichannel oil well selection device is joined up.
The system name, the Logo and contact information of the manufacturer are displayed.
Real-Time Data Group
There are 3 pages in total.
The interface is shown as the following table:
Page Display Example
Page 1: It reveals the temperature, pressure, the connecting positions of the inlet three-way
valve and the outlet three-way valve.
Plot No.2, Block No.13, West Indust. Area, Khartoum Sudan, Tel: +249-1-83-460921, Fax: +249-1-83-465823, PO. Box: 13473
Page 5 of 12
Petro-Energy E&P Co., Ltd.
石油能源有限责任公司
شركة بترو انرجي إي آند بي المحدودة
There are the following ways to display the connecting position of the three-way valve:
A:Tank-A has been connected.
B: Tank-B has been connected.
A->B:Tank-B is being connected.
B->A:Tank-A is being connecting.
Measurement Data Group
There are 8 pages in total.
Page Display Example
Plot No.2, Block No.13, West Indust. Area, Khartoum Sudan, Tel: +249-1-83-460921, Fax: +249-1-83-465823, PO. Box: 13473
Page 6 of 12
Petro-Energy E&P Co., Ltd.
石油能源有限责任公司
شركة بترو انرجي إي آند بي المحدودة
Page 1: Timing. Setting time of the measurement. For example, 1 means to stop after measuring
for 1 hour. The setting range is 1-24.
Measurement time: displayed on the right of timing, it reveals the present measuring hours. For
example, 12:34:56 means the present measuring time is 12 hours 34 minutes 56 seconds.
Page 8 is the pressure and temperature interface, which reveals the maximum, minimum and
average value of pressure and temperature during the measurement.
The Historical Record Interface Group
The number of pages is related to the quantity of recording. Use page up and page down button
to scan the historical record.
The data revealed in each record include measurement starting time, hours of measurement,
daily liquid output, daily gas output, density of mixed liquid and moisture content.
Meter Condition Monitoring
There are 3 pages in total.
Plot No.2, Block No.13, West Indust. Area, Khartoum Sudan, Tel: +249-1-83-460921, Fax: +249-1-83-465823, PO. Box: 13473
Page 7 of 12
Petro-Energy E&P Co., Ltd.
石油能源有限责任公司
شركة بترو انرجي إي آند بي المحدودة
When the meter is in normal condition, it reveals OK. Otherwise, Loss or other information
will be displayed.
The headline is defined as
TT: Temperature transmitter
PT: Pressure transmitter
Inlet Value: Inlet three-way valve
Outlet Value: Outlet three-way valve
DPT-A1: Tank-A differential pressure transmitter, used to measure the volume of liquid and
gas.
DPT-A2: Tank-A differential pressure transmitter, used to measure moisture content.
DPT-B1: Tank-B differential pressure transmitter, used to measure the volume of liquid and
gas.
DPT-B2: Tank-B differential pressure transmitter, used to measure moisture content.
LL: Overtopped liquid level
Measurement enabled: the enabled condition of measurement. Being normal, Yes is revealed.
Being abnormal, No is revealed.
The abnormal conditions are as follows:
Display(At “XXXX”)
Title
Display Explanation
未检测到温度变送器 Temperature
Loss
transmitter is not detected.
TT
温度超上限报警 Temperature exceeds the
Too High
stated maximum limit.
未检测到压力变送器 Pressure transmitter is
Loss
not detected.
PT
压力超上限报警 Pressure exceeds the stated
Too High
maximum limit.
Inlet Valve Overload 进口电动三通阀负载过重 The inlet electric
Plot No.2, Block No.13, West Indust. Area, Khartoum Sudan, Tel: +249-1-83-460921, Fax: +249-1-83-465823, PO. Box: 13473
Page 8 of 12
Petro-Energy E&P Co., Ltd.
石油能源有限责任公司
شركة بترو انرجي إي آند بي المحدودة
three-way valve is overloaded.
故障,无法运行 Error. Incapable of
Error
operation
出口电动三通阀负载过重 The outlet
Overload
electric three-way valve is overloaded.
Outlet Valve
故障,无法运行 Error. Incapable of
Error
operation
DPT-A1
DPT-A2 未检测到差压变送器 Differential pressure
Loss
DPT-B1 transmitter is not detected.
DPT-B2
两个罐内的液位过高。Overtopped liquid
LL Too High
level in both Tanks.
因仪表故障而导致计量无法进行。
Measurement
No ! Incapable of measurement because of meter
Enabled
breakdown
3. System Setting
系统设置包括系统校时和参数设置。进入系统设置模式后,系统常规的按钮操作失效。
System setting includes timing and parameter setting. After the system setting mode starts, the
conventional button operation of the system loses efficacy.
先按一下“Query”按钮将当前显示界面切换到系统标题界面,然后按住“Page UP”按钮约
5~8 秒直至进入校时模式,或者按住“Page Down”按钮约 5~8 秒直至进入参数设置模式。
Press Query button first to switch from the present interface to the system title interface. Then
press the Page Up button for about 5~8 seconds to enter the timing mode or the Page Down button
for about 5~8 seconds to enter the parameter setting mode.
进入校时界面后的按钮操作方法:Button operation method after entering timing interface:
Query:保存修改后的时钟,并退出校时模式。Save the revised time, then exit timing mode.
Plot No.2, Block No.13, West Indust. Area, Khartoum Sudan, Tel: +249-1-83-460921, Fax: +249-1-83-465823, PO. Box: 13473
Page 9 of 12
Petro-Energy E&P Co., Ltd.
石油能源有限责任公司
شركة بترو انرجي إي آند بي المحدودة
Page Up, Page Down:移动要修改的位置。Move the position to be revised.
Start, End:修改数据 Revise the data.
说明:Note:
PLC 的时钟默认在掉电的情况下可以保持 7 天,当掉电时间过长,系统时钟回复到 2000 年 1
月 1 日,测试需要进行校时。
The PLC clock can keep timing for as long as 7 days in the power failure condition. When the
time of power failure is too long, the clock returns to Jan. 1, 2000 and time calibration is required.
参数设置可设置的参数如下:Parameters available in parameter setting:
Modbus Slave ID
Modbus RS485 Baud rate
Modbus RS485 Parity
Density Of crude oil
Density of Water in crude mixture
压力上限 Upper pressure limit
温度上限 Upper temperature limit
Plot No.2, Block No.13, West Indust. Area, Khartoum Sudan, Tel: +249-1-83-460921, Fax: +249-1-83-465823, PO. Box: 13473
Page 10 of 12
Petro-Energy E&P Co., Ltd.
石油能源有限责任公司
شركة بترو انرجي إي آند بي المحدودة
Main Material
Plot No.2, Block No.13, West Indust. Area, Khartoum Sudan, Tel: +249-1-83-460921, Fax: +249-1-83-465823, PO. Box: 13473
Page 11 of 12
Petro-Energy E&P Co., Ltd.
石油能源有限责任公司
شركة بترو انرجي إي آند بي المحدودة
Duplex-body continuous 316L
Metering ■ Nut (Inside)
metering
Plot No.2, Block No.13, West Indust. Area, Khartoum Sudan, Tel: +249-1-83-460921, Fax: +249-1-83-465823, PO. Box: 13473
Page 12 of 12