PROJECT : Relief Project

MASTER SCHEDULE (REV0.02) Dated 18Jul22


ID Task Name AdditionalTask Duration Start Finish % Plan %
task added Complete
date Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Ap
1 RELIEF PROJECT: PROPOSED MASTER SCHEDULE 364 d 31-05-22 18-06-23 13.83% 11% RELIEF PROJECT: PROPOSED MASTER SCHEDULE 18 Jul, '22
2 Project Keydate 364 d 31-05-22 18-06-23 100.00% 0% Project Keydate
3 General 364 d 31-05-22 18-06-23 100.00% 0% General
4 LOA, Award Main Contractor 0d 31-05-22 31-05-22 100.00% 100% LOA, Award Main Contractor 31 May '22

5 LOA, Award for MEP Package 0d 15-07-22 15-07-22 100.00% 0% LOA, Award for MEP Package 15 Jul '22

6 Commencement Work On Site 0d 15-06-22 15-06-22 100.00% 100% Commencement Work On Site 15 Jun '22

7 Contract Completion (Final handover of All area) 0d 18-06-23 18-06-23 0.00% 0%

8 Key Milestones 132 d 09-01-23 30-05-23 0.00% 0% Key Milestones


9 M1 - Main Factory Roof Completion 0d 09-01-23 09-01-23 0.00% 0% M1 - Main Factory Roof Completion 09 Jan '23
10 M2 - 1st Floor structure completion & 0d 21-01-23 21-01-23 0.00% 0% M2 - 1st Floor structure completion & Underground Utilities 21 Jan '23
Underground Utilities
11 M3 - 2nd Floor Structure Completion 0d 21-02-23 21-02-23 0.00% 0% M3 - 2nd Floor Structure Completion 21 Feb '23
12 M4 - Guardhouse & Custrm office 0d 17-03-23 17-03-23 0.00% 0% M4 - Guardhouse & Custrm office 17 Mar '23
13 M5 - Stormwater Drainage System 0d 30-05-23 30-05-23 0.00% 0%
14 M6 - Road & Pavement, Loading dock, Truck 0d 30-05-23 30-05-23 0.00% 0%
scale
15 M7 - VIP & Visitor Parking (Northside) 0d 30-05-23 30-05-23 0.00% 0%
16 M8 - Car & Motorcycle Parking (Southside) 0d 22-05-23 22-05-23 0.00% 0%
17 M9 - Boundary fence & Main entrance 0d 22-05-23 22-05-23 0.00% 0%
18 M10 - Green area & Landscape 0d 30-05-23 30-05-23 0.00% 0%
19 M11 - MEP hookup and ready for Testing & 0d 26-05-23 26-05-23 0.00% 0%
Commissioning
20 Handover Milestones 184 d 02-12-22 18-06-23 0.00% 0% Handover Milestones
21 H.O. - East Utility Building Completion 0d 02-12-22 02-12-22 0.00% 0% H.O. - East Utility Building Completion 02 Dec '22
22 H.O. - South Utility Building Completion 0d 31-01-23 31-01-23 0.00% 0% H.O. - South Utility Building Completion 31 Jan '23
23 H.O. - Retention pond Completion 0d 21-02-23 21-02-23 0.00% 0% H.O. - Retention pond Completion 21 Feb '23
24 H.O. - Building Completion 0d 08-06-23 08-06-23 0.00% 0%
25 H.O - Final handover all areas 0d 18-06-23 18-06-23 0.00% 0%
26 Application & Permit 32 d 31-05-22 01-07-22 100.00% 100% Application & Permit 01 Jul '22
27 Application & Permit- Construction Permit by 0d 31-05-22 31-05-22 100.00% 100% Application & Permit- Construction Permit by Owner 31 May '22
Owner
28 Application & Permit - Temporary Power 24 d 08-06-22 01-07-22 100.00% 100% Application & Permit - Temporary Power 01 Jul '22
29 Temporary Power Supply - Submission 9d 08-06-22 16-06-22 100.00% 100% Temporary Power Supply - Submission Application by TKC to PEA 16 Jun '22
Application by TKC to PEA
30 Temporary Power Supply - PEA site survey & 14 d 13-06-22 26-06-22 100.00% 100% Temporary Power Supply - PEA site survey & quotation 26 Jun '22
quotation
31 Temporary Power Supply - Issuanace PO to PEA 5d 27-06-22 01-07-22 100.00% 100% Temporary Power Supply - Issuanace PO to PEA 01 Jul '22

32 Application & Permit - Temporary Water Supply 13 d 14-06-22 26-06-22 100.00% 100% Application & Permit - Temporary Water Supply and Drainage Work 26 Jun '22
and Drainage Work
33 Temp. Water & Drainage - Submission 4d 14-06-22 17-06-22 100.00% 100% Temp. Water & Drainage - Submission Application CW to WHA 17 Jun '22
Application CW to WHA
34 Temp. Water & Drainage - Quotation by WHA 5d 18-06-22 22-06-22 100.00% 100% Temp. Water & Drainage - Quotation by WHA 22 Jun '22
35 Temp. Water & Drainage - Issuanace PO to WHA 5d 22-06-22 26-06-22 100.00% 100% Temp. Water & Drainage - Issuanace PO to WHA 26 Jun '22
36 Mobilization & Temporary Work 70 d 31-05-22 11-08-22 68.57% 86% Mobilization & Temporary Work 11 Aug '22
37 Submission and Approval - Temporary Work 37 d 01-06-22 07-07-22 100.00% 100% Submission and Approval - Temporary Work 07 Jul '22
38 Submission & Approval - Temporary Owner & 7d 01-06-22 07-06-22 100.00% 100% Submission & Approval - Temporary Owner & Consult office 07 Jun '22
Consult office
39 Temporary Owner & Consult office - 2d 01-06-22 Temporary
02-06-22 100.00% Owner & Consult office - Preparation & Submission Drawings by TKC
100% 02 Jun '22
Preparation & Submission Drawings by TKC
40 Temporary Owner & Consult office - Review 5d 03-06-22 Temporary
07-06-22 100.00% 100% Owner & Consult office - Review & Approval Drawings by Consultant 07 Jun '22
& Approval Drawings by Consultant
41 Submission & Approval - Temporary Gate 37 d 01-06-22 07-07-22 100.00% 100% Submission & Approval - Temporary Gate No.2 07 Jul '22
No.2
42 Temporary Gate No.2 - Submission 14 d 01-06-22 14-06-22 100.00% 100% Temporary Gate No.2 - Submission Application by TKC 14 Jun '22
Application by TKC
43 Temporary Gate No.2 - Review & Approval 23 d 15-06-22 07-07-22 100.00% 100% Temporary Gate No.2 - Review & Approval by WHA 07 Jul '22
by WHA
44 Temporary Facilities 70 d 31-05-22 11-08-22 68.57% 85% Temporary Facilities 11 Aug '22
45 TKC Office & Toilet 34 d 04-06-22 07-07-22 100.00% 100% TKC Office & Toilet 07 Jul '22
46 TKC Office & Toilets - Installation 9d 04-06-22 12-06-22 100.00% 100% TKC Office & Toilets - Installation 12 Jun '22
47 TKC Office & Toilets - CW, drain pipe , septic 9d 13-06-22 21-06-22 100.00% 100% TKC Office & Toilets - CW, drain pipe , septic tank connect 21 Jun '22
tank connect
48 TKC Office & Toilets - Roof, walkway and 25 d 13-06-22 07-07-22 100.00% 100% TKC Office & Toilets - Roof, walkway and miscellaneous 07 Jul '22
miscellaneous
49 Owner & Consult office Office 37 d 08-06-22 15-07-22 100.00% 100% Owner & Consult office Office 15 Jul '22
50 Owner & Consult office Office - Order 7d 08-06-22 14-06-22 100.00% 100% Owner & Consult office Office - Order temporary contaner office 14 Jun '22
temporary contaner office
51 Owner & Consult office Office - Installation 4d 19-06-22 22-06-22 100.00% 100% Owner & Consult office Office - Installation 22 Jun '22
52 TKC Office & Toilets - CW, drain pipe , septic 8d 23-06-22 30-06-22 100.00% 100% TKC Office & Toilets - CW, drain pipe , septic tank connect 30 Jun '22
tank connect
53 TKC Office & Toilets - CCTV 4d 23-06-22 26-06-22 100.00% 100% TKC Office & Toilets - CCTV 26 Jun '22
54 TKC Office & Toilets - Roof, walkway and 22 d 23-06-22 15-07-22 100.00% 100% TKC Office & Toilets - Roof, walkway and miscellaneous 15 Jul '22
miscellaneous
55 Temporary rest area for worker 27 d 04-06-22 30-06-22 100.00% 100% Temporary rest area for worker 30 Jun '22
56 Temporary Gate (2 Gates) 22 d 08-07-22 01-08-22 38.46% 53% Temporary Gate (2 Gates) 01 Aug '22
57 Temporary Gate No.1 (use existing gate) - 13 d 16-07-22 30-07-22 18.75% 59% Temporary Gate No.1 (use existing gate) - Additional Wheel cleaning at gate 1 30 Jul '22
Additional Wheel cleaning at gate 1
58 Install steel frame inside pit 2d 16-07-22 17-07-22 100.00% 100% Install steel frame inside pit 17 Jul '22
59 Install sump pit for drainage x 2 nos. 4d 17-07-22 20-07-22 100.00% 70% Install sump pit for drainage x 2 nos. 20 Jul '22
60 Concrete ramp 7d 21-07-22 27-07-22 0.00% 50% Concrete ramp 27 Jul '22
61 Complete new wheel washing area 1d 30-07-22 30-07-22 0.00% 0% Complete new wheel washing area 30 Jul '22
62 Temporary Gate No.2 22 d 08-07-22 01-08-22 45.45% 50% Temporary Gate No.2 01 Aug '22
63 Temporary Gate No.2 - Leveling & 10 d 08-07-22 18-07-22 100.00% 100% Temporary Gate No.2 - Leveling & concerete connnect to WHA road 18 Jul '22
concerete connnect to WHA road
64 Temporary Gate No.2 - Foundation for 4d 15-07-22 18-07-22 100.00% 100% Temporary Gate No.2 - Foundation for temporary gate 18 Jul '22
temporary gate
65 Temporary Gate No.2 - Foundation 8d 19-07-22 26-07-22 0.00% 0% Temporary Gate No.2 - Foundation Curring 26 Jul '22
Curring
66 Temporary Gate No.2 - Install Gate frame 1d 26-07-22 26-07-22 0.00% 0% Temporary Gate No.2 - Install Gate frame 26 Jul '22

67 Temporary Gate No.2 - Wheel cleaning at 3d 15-07-22 17-07-22 66.67% 100% Temporary Gate No.2 - Wheel cleaning at gate 2 Wall both side install 17 Jul '22
gate 2 Wall both side install
68 Temporary Gate No.2 - Install steel frame 2d 22-07-22 23-07-22 0.00% 0% Temporary Gate No.2 - Install steel frame inside pit 23 Jul '22
inside pit
69 Temporary Gate No.2 - Install sump pit for 2d 23-07-22 24-07-22 0.00% 0% Temporary Gate No.2 - Install sump pit for drainage x 1 nos. 24 Jul '22
drainage x 1 nos.
70 Temporary Gate No.2 - Spread the Crusher stone work for the wheel
3 d washing
25-07-22
area 27-07-22 0.00% 0% Temporary Gate No.2 - Spread the Crusher stone work for the wheel washing area 27 Jul '22
71 Temporary Gate No.2 - Complete new 1 d 01-08-22 01-08-22 0.00% 0% Temporary Gate No.2 - Complete new wheel washing area 01 Aug '22
wheel washing area
72 Temporary Guardhouse (3 nos) 24 d 07-06-22 30-06-22 100.00% 100% Temporary Guardhouse (3 nos) 30 Jun '22
73 Temporary worker toilet (45 rooms) 47 d 06-06-22 23-07-22 89.36% 100% Temporary worker toilet (45 rooms) 23 Jul '22
74 Temporary worker toilet (30 rooms) - 13 d 06-06-22 18-06-22 100.00% 100% Temporary worker toilet (30 rooms) - Installation 18 Jun '22
Installation
75 Temporary worker toilet (30 rooms) - CW, 22 d 14-06-22 05-07-22 100.00% 100% Temporary worker toilet (30 rooms) - CW, drain pipe , septic tank connect 05 Jul '22
drain pipe , septic tank connect
76 TKC Office & Toilets (30 rooms) - Temporary 14 d 01-07-22 15-07-22 100.00% 100% TKC Office & Toilets (30 rooms) - Temporary fence (blind wall) 15 Jul '22
fence (blind wall)
77 Temporary worker toilet (15 rooms) - 10 d 05-07-22 15-07-22 100.00% 100% Temporary worker toilet (15 rooms) - Installation 15 Jul '22
Installation
78 Temporary worker toilet (15 rooms) - CW, 13 d 10-07-22 23-07-22 61.54% 100% Temporary worker toilet (15 rooms) - CW, drain pipe , septic tank connect 23 Jul '22
drain pipe , septic tank connect
79 TKC Office & Toilets (15 rooms) - Temporary 8d 16-07-22 23-07-22 37.50% 100% TKC Office & Toilets (15 rooms) - Temporary fence (blind wall) 23 Jul '22
fence (blind wall)
80 Temporary moring talk & carpark area 42 d 10-06-22 22-07-22 90.48% 100% Temporary moring talk & carpark area 22 Jul '22
81 Temporary moring talk 11 d 10-06-22 20-06-22 100.00% 100% Temporary moring talk 20 Jun '22
82 Temporary carpark 1 with walkway 33 d 10-06-22 12-07-22 100.00% 100% Temporary carpark 1 with walkway 12 Jul '22
83 Temporary carpark 2 14 d 08-07-22 22-07-22 71.43% 100% Temporary carpark 2 22 Jul '22
84 Temporary TK storage,checemical store 29 d 12-06-22 10-07-22 100.00% 100% Temporary TK storage,checemical store ,garbage house & rebar yard 10 Jul '22
,garbage house & rebar yard
85 Temporary TK storage - Line mark / Soil 7d 12-06-22 18-06-22 100.00% 100% Temporary TK storage - Line mark / Soil Adjustment Level / Compaction 18 Jun '22
Adjustment Level / Compaction
86 Temporary TK storage - Roof wall & door 22 d 19-06-22 10-07-22 100.00% 100% Temporary TK storage - Roof wall & door 10 Jul '22
87 Temporary formwork,scaffolding yard 44 d 14-06-22 30-07-22 77.27% 100% Temporary formwork,scaffolding yard 30 Jul '22
88 Temporary formwork,scaffolding yard - Line mark / Soil Adjustment
5 dLevel14-06-22
/ Compaction
18-06-22 100.00% 100% Temporary formwork,scaffolding yard - Line mark / Soil Adjustment Level / Compaction 18 Jun '22
89 Temporary formwork,scaffolding yard - 18 d 10-07-22 30-07-22 44.44% 100% Temporary formwork,scaffolding yard - Temporary fence 30 Jul '22
Temporary fence
90 Temporary Road (Blue Color) 37 d 08-06-22 15-07-22 100.00% 100% Temporary Road (Blue Color) 15 Jul '22
91 Temporary Road - Line mark 4d 08-06-22 11-06-22 100.00% 100% Temporary Road - Line mark 11 Jun '22
92 Temporary Road - Soil adjustment level 19 d 12-06-22 30-06-22 100.00% 100% Temporary Road - Soil adjustment level 30 Jun '22
93 Temporary Road - Soil cement & compaction 25 d 16-06-22 10-07-22 100.00% 100% Temporary Road - Soil cement & compaction 10 Jul '22
94 Temporary Road - Rain drainage gutter 22 d 23-06-22 15-07-22 100.00% 100% Temporary Road - Rain drainage gutter 15 Jul '22
95 Temporary Internal Road (Orange Color) 49 d 10-06-22 31-07-22 77.55% 83% Temporary Internal Road (Orange Color) 31 Jul '22
96 Temporary Road - Line mark 4d 10-06-22 13-06-22 100.00% 100% Temporary Road - Line mark 13 Jun '22
97 Temporary Road - Pile head cut 30 d 15-06-22 15-07-22 100.00% 95% Temporary Road - Pile head cut 15 Jul '22
98 Temporary Road - Soil adjustment level 30 d 20-06-22 20-07-22 93.33% 94% Temporary Road - Soil adjustment level 20 Jul '22
99 Temporary Road - Soil cement & compaction 31 d 24-06-22 25-07-22 77.42% 78% Temporary Road - Soil cement & compaction 25 Jul '22
100 Temporary Road - Rain drainage gutter 26 d 03-07-22 31-07-22 57.69% 60% Temporary Road - Rain drainage gutter 31 Jul '22
101 Labour Camp 70 d 31-05-22 11-08-22 68.57% 56% Labour Camp 11 Aug '22
102 Labour Camp - Construction 60 d 31-05-22 01-08-22 80.00% 80% Labour Camp - Construction 01 Aug '22
103 Labour Camp - Temporary power supply 40 d 30-06-22 11-08-22 45.00% 45% Labour Camp - Temporary power supply 11 Aug '22
104 Lobour Camp - Temporary water supply 25 d 16-07-22 11-08-22 12.00% 15% Lobour Camp - Temporary water supply 11 Aug '22
105 M&E Temporary Work 45 d 16-06-22 02-08-22 71.11% 81% M&E Temporary Work 02 Aug '22
106 M&E Temporary Work - Power Supply 41 d 20-06-22 02-08-22 68.29% 75% M&E Temporary Work - Power Supply 02 Aug '22
107 M&E Temporary Work - Power Supply - 19 d 20-06-22 08-07-22 100.00% 90% M&E Temporary Work - Power Supply - PEA work 08 Jul '22
PEA work
108 Temp. Power Supply - Transformer 5d 20-06-22 24-06-22 100.00% 100% Temp. Power Supply - Transformer 500KVA installation 24 Jun '22
500KVA installation
109 Temp. Power Supply - MDB 800AT 5d 23-06-22 27-06-22 100.00% 100% Temp. Power Supply - MDB 800AT installation 27 Jun '22
installation

1 OF 16
PROJECT : Relief Project
MASTER SCHEDULE (REV0.02) Dated 18Jul22
ID Task Name AdditionalTask Duration Start Finish % Plan %
task added Complete
date Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Ap
110 Temp. Power Supply - PEA inspection 5d 27-06-22 01-07-22 100.00% 100% Temp. Power Supply - PEA inspection 01 Jul '22 18 Jul, '22

111 Temp.Power Supply - PEA Install 5d 30-06-22 04-07-22 100.00% 100% Temp.Power Supply - PEA Install PT,CT&KWH.meter 04 Jul '22
PT,CT&KWH.meter
112 Temp.Power Supply - Connection 3d 04-07-22 06-07-22 100.00% 80% Temp.Power Supply - Connection 22KV Cable by PEA 06 Jul '22
22KV Cable by PEA
113 Temp. Power Supply - Electric Power 2d 07-07-22 08-07-22 100.00% 0% Temp. Power Supply - Electric Power on 08 Jul '22
on
114 M&E Temporary Work - Outdoor lighting 20 d 11-07-22 02-08-22 35.00% 40% M&E Temporary Work - Outdoor lighting for construciton site area 02 Aug '22
for construciton site area
115 M&E Temporary Work - Power supply to 5d 18-07-22 22-07-22 20.00% 100% M&E Temporary Work - Power supply to Office 22 Jul '22
Office
116 M&E Temporary Work - Power supply to 4d 10-07-22 14-07-22 100.00% 100% M&E Temporary Work - Power supply to fabrication yard 14 Jul '22
fabrication yard
117 M&E Temporary Work - Power supply to 4d 14-07-22 17-07-22 100.00% 100% M&E Temporary Work - Power supply to canteen/toilet 17 Jul '22
canteen/toilet
118 M&E Temporary Work - CCTV & Install wiring 9d 05-07-22 14-07-22 100.00% 40% M&E Temporary Work - CCTV & Install wiring 14 Jul '22
119 M&E Temporary Work - CCTV & Install 6d 05-07-22 10-07-22 100.00% 60% M&E Temporary Work - CCTV & Install wiring - Power Supply to camera 10 Jul '22
wiring - Power Supply to camera
120 M&E Temporary Work - CCTV & Install 3d 11-07-22 14-07-22 100.00% 0% M&E Temporary Work - CCTV & Install wiring - Testing signal 14 Jul '22
wiring - Testing signal
121 M&E Temporary Work - Lightning 20 d 01-07-22 21-07-22 85.00% 100% M&E Temporary Work - Lightning protection work 21 Jul '22
protection work
122 M&E Temporary Work - Internet & Lan 11 d 16-06-22 26-06-22 100.00% 100% M&E Temporary Work - Internet & Lan 26 Jun '22
123 M&E Temporary Work - Water supply and 7d 28-06-22 04-07-22 100.00% 100% M&E Temporary Work - Water supply and Drainage works 04 Jul '22
Drainage works
124 Completion of Temporary Work 0 d 11-08-22 11-08-22 0.00% 0% Completion of Temporary Work 11 Aug '22
125 Project Execution 355 d 08-06-22 18-06-23 11.54% 7% Project Execution
126 Received For Construction Drawing 0 d 08-06-22 08-06-22 100.00% 100% Received For Construction Drawing 08 Jun '22
127 Received For Construction Drawing - Main 0d 08-06-22 08-06-22 100.00% 100% Received For Construction Drawing - Main Factory 08 Jun '22
Factory
128 Received For Construction Drawing - Zone 0d 08-06-22 08-06-22 100.00% 100% Received For Construction Drawing - Zone A 08 Jun '22
A
129 Received For Con. Drawings - Zone A - 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - Zone A - Structural work 08 Jun '22
Structural work
130 Received For Con. Drawings - Zone A - 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - Zone A - Str. Work - Foundation 08 Jun '22
Str. Work - Foundation
131 Received For Con. Drawings - Zone A - 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - Zone A - Str. Work - Under ground pipe 08 Jun '22
Str. Work - Under ground pipe
132 Received For Con. Drawings - Zone A - 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - Zone A - Str. Work - Level 1 PT Slab 08 Jun '22
Str. Work - Level 1 PT Slab
133 Received For Con. Drawings - Zone A - 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - Zone A - Str. Work - Level 2 PT Slab 08 Jun '22
Str. Work - Level 2 PT Slab
134 Received For Con. Drawings - Zone A - 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - Zone A - Str. Work - Roof steel Structure 08 Jun '22
Str. Work - Roof steel Structure
135 Received For Con. Drawings - Zone A - 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - Zone A - Architectural work 08 Jun '22
Architectural work
136 Received For Con. Drawings - Zone A - 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - Zone A - Ar. Work - Level 1 Plan 08 Jun '22
Ar. Work - Level 1 Plan
137 Received For Con. Drawings - Zone A - 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - Zone A - Ar. Work - Level 2 Plan 08 Jun '22
Ar. Work - Level 2 Plan
138 Received For Con. Drawings - Zone A - 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - Zone A - Ar. Work - Roof Metal Sheet 08 Jun '22
Ar. Work - Roof Metal Sheet
139 Received For Construction Drawing - Zone 0d 08-06-22 08-06-22 100.00% 100% Received For Construction Drawing - Zone B 08 Jun '22
B
140 Received For Con. Drawings - Zone B - 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - Zone B - Structural work 08 Jun '22
Structural work
141 Received For Con. Drawings - Zone B - 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - Zone B - Str. Work - Foundation 08 Jun '22
Str. Work - Foundation
142 Received For Con. Drawings - Zone B - 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - Zone B - Str. Work - Level 1 PT Slab 08 Jun '22
Str. Work - Level 1 PT Slab
143 Received For Con. Drawings - Zone B - 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - Zone B - Str. Work - Level 2 PT Slab 08 Jun '22
Str. Work - Level 2 PT Slab
144 Received For Con. Drawings - Zone B - 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - Zone B - Str. Work - Roof 08 Jun '22
Str. Work - Roof
145 Received For Con. Drawings - Zone B - 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - Zone B - Str. Work - Under ground pipe 08 Jun '22
Str. Work - Under ground pipe
146 Received For Con. Drawings - Zone B - 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - Zone B - Architectural work 08 Jun '22
Architectural work
147 Received For Con. Drawings - Zone B - 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - Zone B - Ar. Work - Level 1 Plan 08 Jun '22
Ar. Work - Level 1 Plan
148 Received For Con. Drawings - Zone B - 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - Zone B - Ar. Work - Level 2 Plan 08 Jun '22
Ar. Work - Level 2 Plan
149 Received For Con. Drawings - Zone B - 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - Zone B - Ar. Work - Roof Metal Sheet 08 Jun '22
Ar. Work - Roof Metal Sheet
150 Received For Construction Drawing - Office 0d 08-06-22 08-06-22 100.00% 100% Received For Construction Drawing - Office and Canteen 08 Jun '22
and Canteen
151 Received For Con. Drawings - Office and 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - Office and Canteen - Structural work 08 Jun '22
Canteen - Structural work
152 Received For Con. Drawings - Office and 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - Office and Canteen - Str. Work - Foundation 08 Jun '22
Canteen - Str. Work - Foundation
153 Received For Con. Drawings - Office and 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - Office and Canteen - Str. Work - Level 1 PT Slab 08 Jun '22
Canteen - Str. Work - Level 1 PT Slab
154 Received For Con. Drawings - Office and 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - Office and Canteen - Str. Work - Level M PT Slab 08 Jun '22
Canteen - Str. Work - Level M PT Slab
155 Received For Con. Drawings - Office and 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - Office and Canteen - Str. Work - Level 2 PT Slab 08 Jun '22
Canteen - Str. Work - Level 2 PT Slab
156 Received For Con. Drawings - Office and 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - Office and Canteen - Str. Work - Roof PT Slab 08 Jun '22
Canteen - Str. Work - Roof PT Slab
157 Received For Con. Drawings - Office and 0d 08-06-22 08-06-22 100.00% 100%Received For Con. Drawings - Office and Canteen - Str. Work - Under ground pipe 08 Jun '22
Canteen - Str. Work - Under ground pipe
158 Received For Con. Drawings - Office and 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - Office and Canteen - Architectural work 08 Jun '22
Canteen - Architectural work
159 Received For Con. Drawings - Office and 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - Office and Canteen - Ar. Work - Level 1 Plan 08 Jun '22
Canteen - Ar. Work - Level 1 Plan
160 Received For Con. Drawings - Office and 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - Office and Canteen - Ar. Work - Level M Plan 08 Jun '22
Canteen - Ar. Work - Level M Plan
161 Received For Con. Drawings - Office and 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - Office and Canteen - Ar. Work - Level 2 Plan 08 Jun '22
Canteen - Ar. Work - Level 2 Plan
162 Received For Con. Drawings - Office and 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - Office and Canteen - Ar. Work - Roof Plan 08 Jun '22
Canteen - Ar. Work - Roof Plan
163 Received For Con. Drawings - Office and 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - Office and Canteen - Façade work 08 Jun '22
Canteen - Façade work
164 Received For Construction Drawing - East 0d 08-06-22 08-06-22 100.00% 100% Received For Construction Drawing - East Utility Building 08 Jun '22
Utility Building
165 Received For Con. Drawings - East Utility 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - East Utility Building - Structural work 08 Jun '22
Building - Structural work
166 Received For Con. Drawings - East Utility 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - East Utility Building - Str. Work - Foundation 08 Jun '22
Building - Str. Work - Foundation
167 Received For Con. Drawings - East Utility Building - Str. Work - Level
0 d 1 PT
08-06-22
Slab 08-06-22 100.00% 100% Received For Con. Drawings - East Utility Building - Str. Work - Level 1 PT Slab 08 Jun '22
168 Received For Con. Drawings - East Utility Building - Str. Work - Roof
0 d PT08-06-22
Slab 08-06-22 100.00% 100% Received For Con. Drawings - East Utility Building - Str. Work - Roof PT Slab 08 Jun '22
169 Received For Con. Drawings - East Utility 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - East Utility Building - Architectural work 08 Jun '22
Building - Architectural work
170 Received For Con. Drawings - East Utility 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - East Utility Building - Ar. Work - Level 1 Plan 08 Jun '22
Building - Ar. Work - Level 1 Plan
171 Received For Con. Drawings - East Utility Building - Ar. Work - Roof
0 d (Aluminum
08-06-22trellis)
08-06-22 100.00% Received For Con. Drawings - East Utility Building - Ar. Work - Roof (Aluminum trellis)
100% 08 Jun '22
172 Received For Construction Drawing - South 0d 08-06-22 08-06-22 100.00% 100% Received For Construction Drawing - South Utility Building 08 Jun '22
Utility Building
173 Received For Con. Drawings - South Utility 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - South Utility Building - Structural work 08 Jun '22
Building - Structural work
174 Received For Con. Drawings - South 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - South Utility Building - Str. Work - Foundation 08 Jun '22
Utility Building - Str. Work - Foundation
175 Received For Con. Drawings - South Utility Building - Str. Work -0Level
d 108-06-22
PT Slab 08-06-22 100.00% 100% Received For Con. Drawings - South Utility Building - Str. Work - Level 1 PT Slab 08 Jun '22
176 Received For Con. Drawings - South Utility Building - Str. Work -0Level
d 08-06-22
2 PT Slab 08-06-22 100.00% 100% Received For Con. Drawings - South Utility Building - Str. Work - Level 2 PT Slab 08 Jun '22
177 Received For Con. Drawings - South Utility Building - Str. Work -0Roof
d Steel
08-06-22
Structure
08-06-22 100.00% Received For Con. Drawings - South Utility Building - Str. Work - Roof Steel Structure
100% 08 Jun '22
178 Received For Con. Drawings - South 0 d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - South Utility Building - Str. Work - Water Tank 08 Jun '22
Utility Building - Str. Work - Water Tank
179 Received For Con. Drawings - South Utility Building - Str. - RC.Stair,
0 d Link
08-06-22
Bridge 08-06-22 100.00% 100% Received For Con. Drawings - South Utility Building - Str. - RC.Stair, Link Bridge 08 Jun '22
180 Received For Con. Drawings - South Utility Building - Str. Work -0External
d 08-06-22
Stl. Staircase
08-06-22 100.00% Received For Con. Drawings - South Utility Building - Str. Work - External Stl. Staircase
100% 08 Jun '22
181 Received For Con. Drawings - South Utility 0 d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - South Utility Building - Architectural work 08 Jun '22
Building - Architectural work
182 Received For Con. Drawings - South 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - South Utility Building - Ar. Work - Level 1 Plan 08 Jun '22
Utility Building - Ar. Work - Level 1 Plan
183 Received For Con. Drawings - South 0d 08-06-22 08-06-22 100.00% 100% Received For Con. Drawings - South Utility Building - Ar. Work - Level 2 Plan 08 Jun '22
Utility Building - Ar. Work - Level 2 Plan
184 Received For Con. Drawings - South Utility Building - Ar. Work - Roof
0 d Metal
08-06-22
Sheet 08-06-22 100.00% 100%Received For Con. Drawings - South Utility Building - Ar. Work - Roof Metal Sheet 08 Jun '22
185 Received For Construction Drawing - External 0d 08-06-22 08-06-22 100.00% 100% Received For Construction Drawing - External Work 08 Jun '22
Work
186 Received For Construction Drawing - 0d 08-06-22 08-06-22 100.00% 100% Received For Construction Drawing - External Work - Retention pond 08 Jun '22
External Work - Retention pond
187 Received For Construction Drawing - External Work - Boundary fence
0 d& Main
08-06-22
entrance08-06-22 100.00% Received For Construction Drawing - External Work - Boundary fence & Main entrance
100% 08 Jun '22
188 Received For Construction Drawing - External Work - Stormwater drainage
0 d 08-06-22
system 08-06-22 100.00% 100%Received For Construction Drawing - External Work - Stormwater drainage system 08 Jun '22
189 Received For Construction Drawing - 0 d 08-06-22 08-06-22 100.00% 100%Received For Construction Drawing - External Work - Guardhouse & Custrm office 08 Jun '22
External Work - Guardhouse & Custrm office
190 Received For Construction Drawing - External Work - Road & Pavement,
0 d Loading
08-06-22
dock,08-06-22
Truck scale Received For
100.00% Construction Drawing - External Work - Road & Pavement, Loading dock, Truck scale
100% 08 Jun '22
191 Received For Construction Drawing - External Work - Car & Motorcycle
0 d parking
08-06-22 08-06-22 100.00% Received
(Southside) 100%For Construction Drawing - External Work - Car & Motorcycle parking (Southside) 08 Jun '22
192 Received For Construction Drawing - External Work - VIP & Visitor parking
0 d 08-06-22
(Northside)08-06-22 100.00% 100% Received For Construction Drawing - External Work - VIP & Visitor parking (Northside) 08 Jun '22
193 Received For Construction Drawing - 0d 08-06-22 08-06-22 100.00% 100% Received For Construction Drawing - External Work - Green area & Landscape 08 Jun '22
External Work - Green area & Landscape
194 Received For Construction Drawing - 0d 08-06-22 08-06-22 100.00% 100% Received For Construction Drawing - External Work - Truck Scale 08 Jun '22
External Work - Truck Scale
195 Received For Construction Drawing - 0d 08-06-22 08-06-22 100.00% 100% Received For Construction Drawing - External Work - Link Bridge 08 Jun '22
External Work - Link Bridge
196 Received For Construction Drawing - 0d 08-06-22 08-06-22 100.00% 100% Received For Construction Drawing - External Work - Walk Way 08 Jun '22
External Work - Walk Way

2 OF 16
PROJECT : Relief Project
MASTER SCHEDULE (REV0.02) Dated 18Jul22
ID Task Name AdditionalTask Duration Start Finish % Plan %
task added Complete
date Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Ap
197 Received For Construction Drawing - 0d 08-06-22 08-06-22 100.00% 100% Received For Construction Drawing - External Work - Pipe Rack 08 Jun '22 18 Jul, '22
External Work - Pipe Rack
198 Received For Construction Drawing - 0d 08-06-22 08-06-22 100.00% 100% Received For Construction Drawing - External Work - Main entrance 08 Jun '22
External Work - Main entrance
199 Submission&Approval - Shop Drawing 210 d 09-06-22 15-01-23 18.57% 22% Submission&Approval - Shop Drawing 15 Jan '23
200 Submission&Approval - Shop Drawing - 115 d 09-06-22 05-10-22 33.91% 39% Submission&Approval - Shop Drawing - Structural work 05 Oct '22
Structural work
201 BIM Structural Model prepare and 59 d 14-07-22 13-09-22 100.00% 25% BIM Structural Model prepare and submission 13 Sep '22
submission
202 Submission&Approval - Shop Drawing Str. 100 d 09-06-22 20-09-22 39.00% 46% Submission&Approval - Shop Drawing Str. - Main Factory 20 Sep '22
- Main Factory
203 Submission&Approval - Shop Drawing 100 d 09-06-22 20-09-22 39.00% 46% Submission&Approval - Shop Drawing Str. - Zone A 20 Sep '22
Str. - Zone A
204 Submission&Approval - Shop 6d 09-06-22 14-06-22 100.00% 100% Submission&Approval - Shop Drawing Str. - Zone A - Pile Cut Off 14 Jun '22
Drawing Str. - Zone A - Pile Cut Off
205 Zone A - Pile Cut Off - Preparation 3d 09-06-22 11-06-22 100.00% 100% Zone A - Pile Cut Off - Preparation & Submission 11 Jun '22
& Submission
206 Zone A - Pile Cut Off - Review & 3d 12-06-22 14-06-22 100.00% 100% Zone A - Pile Cut Off - Review & Approval by Consultant 14 Jun '22
Approval by Consultant
207 Submission&Approval - Shop Drawing Str. - Zone A - Foundation
23 d 16-06-22
& Ground beam
08-07-22 100.00% 100% Submission&Approval - Shop Drawing Str. - Zone A - Foundation & Ground beam 08 Jul '22
208 Zone A - Foundation - 1st 7 d 16-06-22 22-06-22 100.00% 100% Zone A - Foundation - 1st Preparation & Submission 22 Jun '22
Preparation & Submission
209 Zone A - Foundation - 1st Review & 3d 23-06-22 25-06-22 100.00% 100% Zone A - Foundation - 1st Review & Approval by Consultant 25 Jun '22
Approval by Consultant
210 Zone A - Gr. beam - 1st Preparation 10 d 26-06-22 05-07-22 100.00% 100% Zone A - Gr. beam - 1st Preparation & Submission 05 Jul '22
& Submission
211 Zone A - Gr. Beam - 1st Review & 3d 06-07-22 08-07-22 100.00% 100% Zone A - Gr. Beam - 1st Review & Approval by Consultant 08 Jul '22
Approval by Consultant
212 Submission&Approval - Shop Drawing Str. - Zone A - Pca. 15
Column
d 01-07-22 16-07-22 100.00% 83% Submission&Approval - Shop Drawing Str. - Zone A - Pca. Column 16 Jul '22
213 Zone A1 - Pca. Column - 1st 8d 01-07-22 08-07-22 100.00% 100% Zone A1 - Pca. Column - 1st Preparation & Submission 08 Jul '22
Preparation & Submission
214 Zone A1 - Pca. Column - 1st Review 2d 09-07-22 10-07-22 100.00% 75% Zone A1 - Pca. Column - 1st Review & Approval by Consultant 10 Jul '22
& Approval by Consultant
215 Zone A2 - Pca. Column - 1st 7d 04-07-22 10-07-22 100.00% 100% Zone A2 - Pca. Column - 1st Preparation & Submission 10 Jul '22
Preparation & Submission
216 Zone A2 - Pca. Column - 1st Review 2d 11-07-22 12-07-22 100.00% 75% Zone A2 - Pca. Column - 1st Review & Approval by Consultant 12 Jul '22
& Approval by Consultant
217 Zone A3 - Pca. Column - 1st 7d 07-07-22 14-07-22 100.00% 75% Zone A3 - Pca. Column - 1st Preparation & Submission 14 Jul '22
Preparation & Submission
218 Zone A3 - Pca. Column - 1st Review 2d 15-07-22 16-07-22 100.00% 0% Zone A3 - Pca. Column - 1st Review & Approval by Consultant 16 Jul '22
& Approval by Consultant
219 Submission&Approval - Shop Drawing Str. - Zone A - Core10
Wall
d Details
04-07-22 14-07-22 100.00% 95% Submission&Approval - Shop Drawing Str. - Zone A - Core Wall Details 14 Jul '22
220 Zone A - Core Wall Details - 1st 8 d 04-07-22 11-07-22 100.00% 100% Zone A - Core Wall Details - 1st Preparation & Submission 11 Jul '22
Preparation & Submission
221 Zone A - Core Wall Details-1st 2d 12-07-22 14-07-22 100.00% 75% Zone A - Core Wall Details-1st Review & Approval by Consultant 14 Jul '22
Review & Approval by Consultant
222 Submission&Approval - Shop Drawing Str. - Zone A - Roof14
Steel
d Structure
08-07-22 22-07-22 71.43% 93% Submission&Approval - Shop Drawing Str. - Zone A - Roof Steel Structure 22 Jul '22
223 Zone A - Roof - 1st Preparation & 10 d 08-07-22 18-07-22 100.00% 100% Zone A - Roof - 1st Preparation & Submission 18 Jul '22
Submission
224 Zone A - Roof - 1st Review & 4d 19-07-22 22-07-22 0.00% 75% Zone A - Roof - 1st Review & Approval by Consultant 22 Jul '22
Approval by Consultant
225 Submission&Approval - Shop Drawing Str. - Zone A - Under
24ground
d 30-07-22
pipe 23-08-22 0.00% 0% Submission&Approval - Shop Drawing Str. - Zone A - Under ground pipe 23 Aug '22
226 Zone A - Under ground pipe - 1st 6d 30-07-22 04-08-22 0.00% 0% Zone A - Under ground pipe - 1st Preparation & Submission 04 Aug '22
Preparation & Submission
227 Zone A - Under ground pipe - 1st 6d 05-08-22 10-08-22 0.00% 0% Zone A - Under ground pipe - 1st Review & Approval by Consultant 10 Aug '22
Review & Approval by Consultant
228 Zone A - Under ground pipe - 2nd 6d 11-08-22 17-08-22 0.00% 0% Zone A - Under ground pipe - 2nd Preparation & Submission 17 Aug '22
Preparation & Submission
229 Zone A - Under ground pipe - 2nd 6d 18-08-22 23-08-22 0.00% 0% Zone A - Under ground pipe - 2nd Review & Approval by Consultant 23 Aug '22
Review & Approval by Consultant
230 Submission&Approval - Shop Drawing Str. - Zone A - Level281 d
PT Slab
10-08-22 07-09-22 0.00% 0% Submission&Approval - Shop Drawing Str. - Zone A - Level 1 PT Slab 07 Sep '22
231 Zone A - Level 1 - 1st Preparation & 7 d 10-08-22 17-08-22 0.00% 0% Zone A - Level 1 - 1st Preparation & Submission 17 Aug '22
Submission
232 Zone A - Level 1 - 1st Review & 7d 18-08-22 24-08-22 0.00% 0% Zone A - Level 1 - 1st Review & Approval by Consultant 24 Aug '22
Approval by Consultant
233 Zone A - Level 1 - 2nd Preparation & 7d 25-08-22 31-08-22 0.00% 0% Zone A - Level 1 - 2nd Preparation & Submission 31 Aug '22
Submission
234 Zone A - Level 1 - 2nd Review & 7d 01-09-22 07-09-22 0.00% 0% Zone A - Level 1 - 2nd Review & Approval by Consultant 07 Sep '22
Approval by Consultant
235 Submission&Approval - Shop Drawing Str. - Zone A - Level282 d
PT Slab
24-08-22 20-09-22 0.00% 0% Submission&Approval - Shop Drawing Str. - Zone A - Level 2 PT Slab 20 Sep '22
236 Zone A - Level 2 - 1st Preparation & 7 d 24-08-22 30-08-22 0.00% 0% Zone A - Level 2 - 1st Preparation & Submission 30 Aug '22
Submission
237 Zone A - Level 2 - 1st Review & 7d 31-08-22 06-09-22 0.00% 0% Zone A - Level 2 - 1st Review & Approval by Consultant 06 Sep '22
Approval by Consultant
238 Zone A - Level 2 - 2nd Preparation & 7d 07-09-22 13-09-22 0.00% 0% Zone A - Level 2 - 2nd Preparation & Submission 13 Sep '22
Submission
239 Zone A - Level 2 - 2nd Review & 7d 14-09-22 20-09-22 0.00% 0% Zone A - Level 2 - 2nd Review & Approval by Consultant 20 Sep '22
Approval by Consultant
240 Submission&Approval - Shop Drawing 94 d 09-06-22 14-09-22 41.49% 45% Submission&Approval - Shop Drawing Str. - Zone B 14 Sep '22
Str. - Zone B
241 Submission&Approval - Shop 9d 09-06-22 17-06-22 100.00% 100% Submission&Approval - Shop Drawing Str. - Zone B - Pile Cut off 17 Jun '22
Drawing Str. - Zone B - Pile Cut off
242 Zone B - Pile Cut Off - Preparation & 4d 09-06-22 12-06-22 100.00% 100% Zone B - Pile Cut Off - Preparation & Submission 12 Jun '22
Submission
243 Zone B - Pile Cut Off - Review & 5d 13-06-22 17-06-22 100.00% 100% Zone B - Pile Cut Off - Review & Approval by Consultant 17 Jun '22
Approval by Consultant
244 Submission&Approval - Shop Drawing Str. - Zone B - Foundation
23 d 16-06-22
& Ground beam
08-07-22 100.00% 97% Submission&Approval - Shop Drawing Str. - Zone B - Foundation & Ground beam 08 Jul '22
245 Zone B - Foundation - Preparation 7 d 16-06-22 22-06-22 100.00% 100% Zone B - Foundation - Preparation & Submission 22 Jun '22
& Submission
246 Zone B - Foundation - Review & 3d 23-06-22 25-06-22 100.00% 100% Zone B - Foundation - Review & Approval by Consultant 25 Jun '22
Approval by Consultant
247 Zone B - Gr. Beam - Preparation & 10 d 26-06-22 05-07-22 100.00% 100% Zone B - Gr. Beam - Preparation & Submission 05 Jul '22
Submission
248 Zone B - Gr. Beam - Review & 3d 06-07-22 08-07-22 100.00% 75% Zone B - Gr. Beam - Review & Approval by Consultant 08 Jul '22
Approval by Consultant
249 Submission&Approval - Shop Drawing Str. - Zone B - Pca. 18
Column
d 01-07-22 19-07-22 94.44% 72% Submission&Approval - Shop Drawing Str. - Zone B - Pca. Column 19 Jul '22
250 Zone B1 - Pca. Column - 1st 8d 01-07-22 08-07-22 100.00% 100% Zone B1 - Pca. Column - 1st Preparation & Submission 08 Jul '22
Preparation & Submission
251 Zone B1 - Pca. Column - 1st Review 2d 09-07-22 10-07-22 100.00% 75% Zone B1 - Pca. Column - 1st Review & Approval by Consultant 10 Jul '22
& Approval by Consultant
252 Zone B2 - Pca. Column - 1st 7d 04-07-22 10-07-22 100.00% 100% Zone B2 - Pca. Column - 1st Preparation & Submission 10 Jul '22
Preparation & Submission
253 Zone B2 - Pca. Column - 1st Review 2d 11-07-22 12-07-22 100.00% 75% Zone B2 - Pca. Column - 1st Review & Approval by Consultant 12 Jul '22
& Approval by Consultant
254 Zone B3 - Pca. Column - 1st 7d 07-07-22 14-07-22 100.00% 75% Zone B3 - Pca. Column - 1st Preparation & Submission 14 Jul '22
Preparation & Submission
255 Zone B3 - Pca. Column - 1st Review 2d 15-07-22 16-07-22 100.00% 0% Zone B3 - Pca. Column - 1st Review & Approval by Consultant 16 Jul '22
& Approval by Consultant
256 Zone B4 - Pca. Column - 1st 7d 10-07-22 17-07-22 100.00% 50% Zone B4 - Pca. Column - 1st Preparation & Submission 17 Jul '22
Preparation & Submission
257 Zone B4 - Pca. Column - 1st Review 2d 18-07-22 19-07-22 50.00% 0% Zone B4 - Pca. Column - 1st Review & Approval by Consultant 19 Jul '22
& Approval by Consultant
258 Submission&Approval - Shop Drawing Str. - Zone B - Core10
Wall
d Details
04-07-22 14-07-22 100.00% 95% Submission&Approval - Shop Drawing Str. - Zone B - Core Wall Details 14 Jul '22
259 Zone B - Core Wall Details - 1st 8 d 04-07-22 11-07-22 100.00% 100% Zone B - Core Wall Details - 1st Preparation & Submission 11 Jul '22
Preparation & Submission
260 Zone B - Core Wall Details - 1st 2d 12-07-22 14-07-22 100.00% 75% Zone B - Core Wall Details - 1st Review & Approval by Consultant 14 Jul '22
Review & Approval by Consultant
261 Submission&Approval - Shop Drawing Str. - Zone B - Roof14
Steel
d Structure
01-07-22 15-07-22 100.00% 93% Submission&Approval - Shop Drawing Str. - Zone B - Roof Steel Structure 15 Jul '22
262 Zone B - Roof - 1st Preparation & 10 d 01-07-22 10-07-22 100.00% 100% Zone B - Roof - 1st Preparation & Submission 10 Jul '22
Submission
263 Zone B - Roof - 1st Review & 4d 11-07-22 15-07-22 100.00% 75% Zone B - Roof - 1st Review & Approval by Consultant 15 Jul '22
Approval by Consultant
264 Submission&Approval - Shop Drawing Str. - Zone B - Under
28ground
d 24-07-22
pipe 23-08-22 0.00% 0% Submission&Approval - Shop Drawing Str. - Zone B - Under ground pipe 23 Aug '22
265 Zone B - Under ground pipe - 1st 7d 24-07-22 01-08-22 0.00% 0% Zone B - Under ground pipe - 1st Preparation & Submission 01 Aug '22
Preparation & Submission
266 Zone B - Under ground pipe - 1st 7d 02-08-22 08-08-22 0.00% 0% Zone B - Under ground pipe - 1st Review & Approval by Consultant 08 Aug '22
Review & Approval by Consultant
267 Zone B - Under ground pipe - 2nd 7d 09-08-22 16-08-22 0.00% 0% Zone B - Under ground pipe - 2nd Preparation & Submission 16 Aug '22
Preparation & Submission
268 Zone B - Under ground pipe - 2nd 7d 17-08-22 23-08-22 0.00% 0% Zone B - Under ground pipe - 2nd Review & Approval by Consultant 23 Aug '22
Review & Approval by Consultant
269 Submission&Approval - Shop Drawing Str. - Zone B - Level281 PT
d Slab
04-08-22 01-09-22 0.00% 0% Submission&Approval - Shop Drawing Str. - Zone B - Level 1 PT Slab 01 Sep '22
270 Zone B - Level 1 - 1st Preparation & 7d 04-08-22 10-08-22 0.00% 0% Zone B - Level 1 - 1st Preparation & Submission 10 Aug '22
Submission
271 Zone B - Level 1 - 1st Review & 7d 11-08-22 18-08-22 0.00% 0% Zone B - Level 1 - 1st Review & Approval by Consultant 18 Aug '22
Approval by Consultant
272 Zone B - Level 1 - 2nd Preparation & 7d 19-08-22 25-08-22 0.00% 0% Zone B - Level 1 - 2nd Preparation & Submission 25 Aug '22
Submission
273 Zone B - Level 1 - 2nd Review & 7d 26-08-22 01-09-22 0.00% 0% Zone B - Level 1 - 2nd Review & Approval by Consultant 01 Sep '22
Approval by Consultant
274 Submission&Approval - Shop Drawing Str. - Zone B - Level282 PT
d Slab
18-08-22 14-09-22 0.00% 0% Submission&Approval - Shop Drawing Str. - Zone B - Level 2 PT Slab 14 Sep '22
275 Zone B - Level 2 - 1st Preparation & 7 d 18-08-22 24-08-22 0.00% 0% Zone B - Level 2 - 1st Preparation & Submission 24 Aug '22
Submission
276 Zone B - Level 2 - 1st Review & 7d 25-08-22 31-08-22 0.00% 0% Zone B - Level 2 - 1st Review & Approval by Consultant 31 Aug '22
Approval by Consultant
277 Zone B - Level 2 - 2nd Preparation & 7d 01-09-22 07-09-22 0.00% 0% Zone B - Level 2 - 2nd Preparation & Submission 07 Sep '22
Submission
278 Zone B - Level 2 - 2nd Review & 7d 08-09-22 14-09-22 0.00% 0% Zone B - Level 2 - 2nd Review & Approval by Consultant 14 Sep '22
Approval by Consultant
279 Submission&Approval - Shop Drawing Str. 115 d 09-06-22 05-10-22 33.91% 22% Submission&Approval - Shop Drawing Str. - Office and Canteen 05 Oct '22
- Office and Canteen
280 Submission&Approval - Shop Drawing 6d 09-06-22 14-06-22 100.00% 100% Submission&Approval - Shop Drawing Str. - Office and Canteen - Pile Cut Off 14 Jun '22
Str. - Office and Canteen - Pile Cut Off
281 Office and Canteen - Pile Cut Off - 3d 09-06-22 11-06-22 100.00% 100% Office and Canteen - Pile Cut Off - Preparation & Submission 11 Jun '22
Preparation & Submission

3 OF 16
PROJECT : Relief Project
MASTER SCHEDULE (REV0.02) Dated 18Jul22
ID Task Name AdditionalTask Duration Start Finish % Plan %
task added Complete
date Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Ap
282 Office and Canteen - Pile Cut Off - 3d 12-06-22 14-06-22 100.00% 100% Office and Canteen - Pile Cut Off - Review & Approval by Consultant 14 Jun '22 18 Jul, '22
Review & Approval by Consultant
283 Submission&Approval - Shop Drawing Str. - Office and Canteen
23 d- Foundation
16-06-22 & 08-07-22
Ground beam
100.00% 97% Submission&Approval - Shop Drawing Str. - Office and Canteen - Foundation & Ground beam 08 Jul '22
284 Office and Canteen - Foundation - 7 d 16-06-22 22-06-22 100.00% 100% Office and Canteen - Foundation - Preparation & Submission 22 Jun '22
Preparation & Submission
285 Office and Canteen - Foundation - 3d 23-06-22 25-06-22 100.00% 100% Office and Canteen - Foundation - Review & Approval by Consultant 25 Jun '22
Review & Approval by Consultant
286 Office and Canteen - Gr. Beam - 10 d 26-06-22 05-07-22 100.00% 100% Office and Canteen - Gr. Beam - Preparation & Submission 05 Jul '22
Preparation & Submission
287 Office and Canteen - Gr. Beam - 3d 06-07-22 08-07-22 100.00% 75% Office and Canteen - Gr. Beam - Review & Approval by Consultant 08 Jul '22
Review & Approval by Consultant
288 Submission&Approval - Shop Drawing Str. - Office and Canteen
10 d- Pca.
01-07-22
Column 10-07-22 100.00% 72% Submission&Approval - Shop Drawing Str. - Office and Canteen - Pca. Column 10 Jul '22
289 Office and Canteen - Pca. Column - 1st 8d 01-07-22 08-07-22 100.00% 90% Office and Canteen - Pca. Column - 1st Preparation & Submission 08 Jul '22
Preparation & Submission
290 Office and Canteen - Pca. Column - 1st 2d 09-07-22 10-07-22 100.00% 0% Office and Canteen - Pca. Column - 1st Review & Approval by Consultant 10 Jul '22
Review & Approval by Consultant
291 Submission&Approval - Shop Drawing Str. - Office and Canteen
5 d- Core
10-07-22
Wall Details
15-07-22 100.00% 42% Submission&Approval - Shop Drawing Str. - Office and Canteen - Core Wall Details 15 Jul '22
292 Office and Canteen - Core Wall Details 3d 10-07-22 12-07-22 100.00% 70% Office and Canteen - Core Wall Details - 1st Preparation & Submission 12 Jul '22
- 1st Preparation & Submission
293 Office and Canteen - Core Wall Details - 1st Review & Approval
2 dby Consultant
14-07-22 15-07-22 100.00% 0% Office and Canteen - Core Wall Details - 1st Review & Approval by Consultant 15 Jul '22
294 Submission&Approval - Shop Drawing Str. - Office and Canteen 21 d- Under
07-07-22
ground30-07-22
pipe 52.38% 25% Submission&Approval - Shop Drawing Str. - Office and Canteen - Under ground pipe 30 Jul '22
295 Office and Canteen - Under ground 7d 07-07-22 14-07-22 100.00% 75% Office and Canteen - Under ground pipe - 1st Preparation & Submission 14 Jul '22
pipe - 1st Preparation & Submission
296 Office and Canteen - Under ground pipe - 1st Review & Approval
7 d by 15-07-22
Consultant 21-07-22 57.14% 0% Office and Canteen - Under ground pipe - 1st Review & Approval by Consultant 21 Jul '22
297 Office and Canteen - Under ground 4 d 22-07-22 25-07-22 0.00% 0% Office and Canteen - Under ground pipe - 2nd Preparation & Submission 25 Jul '22
pipe - 2nd Preparation & Submission
298 Office and Canteen - Under ground pipe - 2nd Review & Approval
3 d by26-07-22
Consultant 30-07-22 0.00% 0% Office and Canteen - Under ground pipe - 2nd Review & Approval by Consultant 30 Jul '22
299 Submission&Approval - Shop Drawing Str. - Office and Canteen
14 d- Level
22-07-22
1 PT Slab
06-08-22 0.00% 0% Submission&Approval - Shop Drawing Str. - Office and Canteen - Level 1 PT Slab 06 Aug '22
300 Office and Canteen - Level 1 - 1st 7d 22-07-22 30-07-22 0.00% 0% Office and Canteen - Level 1 - 1st Preparation & Submission 30 Jul '22
Preparation & Submission
301 Office and Canteen - Level 1 - 1st 7d 31-07-22 06-08-22 0.00% 0% Office and Canteen - Level 1 - 1st Review & Approval by Consultant 06 Aug '22
Review & Approval by Consultant
302 Submission&Approval - Shop Drawing Str. - Office and Canteen
28 d- Level
21-07-22
M PT Slab
20-08-22 0.00% 0% Submission&Approval - Shop Drawing Str. - Office and Canteen - Level M PT Slab 20 Aug '22
303 Office and Canteen - Level M - 1st 7d 21-07-22 27-07-22 0.00% 0% Office and Canteen - Level M - 1st Preparation & Submission 27 Jul '22
Preparation & Submission
304 Office and Canteen - Level M - 1st 7d 30-07-22 05-08-22 0.00% 0% Office and Canteen - Level M - 1st Review & Approval by Consultant 05 Aug '22
Review & Approval by Consultant
305 Office and Canteen - Level M - 2nd 7d 06-08-22 13-08-22 0.00% 0% Office and Canteen - Level M - 2nd Preparation & Submission 13 Aug '22
Preparation & Submission
306 Office and Canteen - Level M - 2nd 7d 14-08-22 20-08-22 0.00% 0% Office and Canteen - Level M - 2nd Review & Approval by Consultant 20 Aug '22
Review & Approval by Consultant
307 Submission&Approval - Shop Drawing Str. - Office and Canteen
28 d- Level
04-08-22
2 PT Slab01-09-22 0.00% 0% Submission&Approval - Shop Drawing Str. - Office and Canteen - Level 2 PT Slab 01 Sep '22
308 Office and Canteen - Level 2 - 1st 7 d 04-08-22 10-08-22 0.00% 0% Office and Canteen - Level 2 - 1st Preparation & Submission 10 Aug '22
Preparation & Submission
309 Office and Canteen - Level 2 - 1st 7d 11-08-22 18-08-22 0.00% 0% Office and Canteen - Level 2 - 1st Review & Approval by Consultant 18 Aug '22
Review & Approval by Consultant
310 Office and Canteen - Level 2 - 2nd 7d 19-08-22 25-08-22 0.00% 0% Office and Canteen - Level 2 - 2nd Preparation & Submission 25 Aug '22
Preparation & Submission
311 Office and Canteen - Level 2 - 2nd 7d 26-08-22 01-09-22 0.00% 0% Office and Canteen - Level 2 - 2nd Review & Approval by Consultant 01 Sep '22
Review & Approval by Consultant
312 Submission&Approval - Shop Drawing Str. - Office and Canteen
28 d- Roof
18-08-22
PT slab 14-09-22 0.00% 0% Submission&Approval - Shop Drawing Str. - Office and Canteen - Roof PT slab 14 Sep '22
313 Office and Canteen - Roof - 1st 7 d 18-08-22 24-08-22 0.00% 0% Office and Canteen - Roof - 1st Preparation & Submission 24 Aug '22
Preparation & Submission
314 Office and Canteen - Roof - 1st Review 7d 25-08-22 31-08-22 0.00% 0% Office and Canteen - Roof - 1st Review & Approval by Consultant 31 Aug '22
& Approval by Consultant
315 Office and Canteen - Roof - 2nd 7d 01-09-22 07-09-22 0.00% 0% Office and Canteen - Roof - 2nd Preparation & Submission 07 Sep '22
Preparation & Submission
316 Office and Canteen - Roof - 2nd Review 7d 08-09-22 14-09-22 0.00% 0% Office and Canteen - Roof - 2nd Review & Approval by Consultant 14 Sep '22
& Approval by Consultant
317 Submission&Approval - Shop Drawing Str. - Office and Canteen
28 d- Top
08-09-22
Roof PT Slab
05-10-22 0.00% 0% Submission&Approval - Shop Drawing Str. - Office and Canteen - Top Roof PT Slab 05 Oct '22
318 Office and Canteen - Top Roof - 1st 7 d 08-09-22 14-09-22 0.00% 0% Office and Canteen - Top Roof - 1st Preparation & Submission 14 Sep '22
Preparation & Submission
319 Office and Canteen - Top Roof - 1st 7d 15-09-22 21-09-22 0.00% 0% Office and Canteen - Top Roof - 1st Review & Approval by Consultant 21 Sep '22
Review & Approval by Consultant
320 Office and Canteen - Top Roof- 2nd 7d 22-09-22 28-09-22 0.00% 0% Office and Canteen - Top Roof- 2nd Preparation & Submission 28 Sep '22
Preparation & Submission
321 Office and Canteen - Top Roof- 2nd 7d 29-09-22 05-10-22 0.00% 0% Office and Canteen - Top Roof- 2nd Review & Approval by Consultant 05 Oct '22
Review & Approval by Consultant
322 Submission&Approval - Shop Drawing Str. 68 d 09-06-22 19-08-22 57.35% 52% Submission&Approval - Shop Drawing Str. - East Utility Building 19 Aug '22
- East Utility Building
323 Submission&Approval - Shop Drawing Str. - East Utility Building
10 d - Pile
09-06-22
Cut Off 18-06-22 100.00% 100% Submission&Approval - Shop Drawing Str. - East Utility Building - Pile Cut Off 18 Jun '22
324 East Utility Building - Pile Cut Off - 5d 09-06-22 13-06-22 100.00% 100% East Utility Building - Pile Cut Off - Preparation & Submission 13 Jun '22
Preparation & Submission
325 East Utility Building - Pile Cut Off - 5d 14-06-22 18-06-22 100.00% 100% East Utility Building - Pile Cut Off - Review & Approval by Consultant 18 Jun '22
Review & Approval by Consultant
326 Submission&Approval - Shop Drawing Str. - East Utility Building
23 d - Foundation
16-06-22 &08-07-22
Ground beam
100.00% 100% Submission&Approval - Shop Drawing Str. - East Utility Building - Foundation & Ground beam 08 Jul '22
327 East Utility Building - Foundation - 7 d 16-06-22 22-06-22 100.00% 100% East Utility Building - Foundation - Preparation & Submission 22 Jun '22
Preparation & Submission
328 East Utility Building - Foundation - 3d 23-06-22 25-06-22 100.00% 100% East Utility Building - Foundation - Review & Approval by Consultant 25 Jun '22
Review & Approval by Consultant
329 East Utility Building - Gr. Beam - 10 d 26-06-22 05-07-22 100.00% 100% East Utility Building - Gr. Beam - Preparation & Submission 05 Jul '22
Preparation & Submission
330 East Utility Building - Gr. Beam - 3d 06-07-22 08-07-22 100.00% 100% East Utility Building - Gr. Beam - Review & Approval by Consultant 08 Jul '22
Review & Approval by Consultant
331 Submission&Approval - Shop Drawing Str. - East Utility Building
10 d - Pca.
01-07-22
Column 10-07-22 100.00% 95% Submission&Approval - Shop Drawing Str. - East Utility Building - Pca. Column 10 Jul '22
332 East Utility Building - Pca. Column - 1st 8d 01-07-22 08-07-22 100.00% 100% East Utility Building - Pca. Column - 1st Preparation & Submission 08 Jul '22
Preparation & Submission
333 East Utility Building - Pca. Column - 1st 2d 09-07-22 10-07-22 100.00% 75% East Utility Building - Pca. Column - 1st Review & Approval by Consultant 10 Jul '22
Review & Approval by Consultant
334 Submission&Approval - Shop Drawing Str. - East Utility Building
21 d - Level
14-07-22
1 PT Slab
05-08-22 23.81% 25% Submission&Approval - Shop Drawing Str. - East Utility Building - Level 1 PT Slab 05 Aug '22
335 East Utility Building - Level 1 - 1st 7d 14-07-22 20-07-22 71.43% 75% East Utility Building - Level 1 - 1st Preparation & Submission 20 Jul '22
Preparation & Submission
336 East Utility Building - Level 1 - 1st 7d 21-07-22 27-07-22 0.00% 0% East Utility Building - Level 1 - 1st Review & Approval by Consultant 27 Jul '22
Review & Approval by Consultant
337 East Utility Building - Level 1 - 2nd 4d 30-07-22 02-08-22 0.00% 0% East Utility Building - Level 1 - 2nd Preparation & Submission 02 Aug '22
Preparation & Submission
338 East Utility Building - Level 1 - 2nd 3d 03-08-22 05-08-22 0.00% 0% East Utility Building - Level 1 - 2nd Review & Approval by Consultant 05 Aug '22
Review & Approval by Consultant
339 Submission&Approval - Shop Drawing Str. - East Utility Building-
28 d Roof
20-07-22
PT Slab 19-08-22 0.00% 0% Submission&Approval - Shop Drawing Str. - East Utility Building- Roof PT Slab 19 Aug '22
340 East Utility Building - Roof - 1st 7d 20-07-22 26-07-22 0.00% 0% East Utility Building - Roof - 1st Preparation & Submission 26 Jul '22
Preparation & Submission
341 East Utility Building - Roof - 1st Review 7d 27-07-22 04-08-22 0.00% 0% East Utility Building - Roof - 1st Review & Approval by Consultant 04 Aug '22
& Approval by Consultant
342 East Utility Building - Roof - 2nd 7d 05-08-22 11-08-22 0.00% 0% East Utility Building - Roof - 2nd Preparation & Submission 11 Aug '22
Preparation & Submission
343 East Utility Building - Roof - 2nd 7d 13-08-22 19-08-22 0.00% 0% East Utility Building - Roof - 2nd Review & Approval by Consultant 19 Aug '22
Review & Approval by Consultant
344 Submission&Approval - Shop Drawing Str. 101 d 09-06-22 21-09-22 38.61% 40% Submission&Approval - Shop Drawing Str. - South Utility Building 21 Sep '22
- South Utility Building
345 Submission&Approval - Shop Drawing Str. - South Utility Building
10 d - 09-06-22
Pile Cut Off18-06-22 100.00% 100% Submission&Approval - Shop Drawing Str. - South Utility Building - Pile Cut Off 18 Jun '22
346 South Utility Building - Pile Cut Off - 5 d 09-06-22 13-06-22 100.00% 100% South Utility Building - Pile Cut Off - Preparation & Submission 13 Jun '22
Preparation & Submission
347 South Utility Building - Pile Cut Off - 5d 14-06-22 18-06-22 100.00% 100% South Utility Building - Pile Cut Off - Review & Approval by Consultant 18 Jun '22
Review & Approval by Consultant
348 Submission&Approval - Shop Drawing Str. - South Utility Building
24 d - 16-06-22
Foundation09-07-22
& Ground100.00%
beam 100%Submission&Approval - Shop Drawing Str. - South Utility Building - Foundation & Ground beam 09 Jul '22
349 South Utility Building - Foundation - 7 d 16-06-22 22-06-22 100.00% 100% South Utility Building - Foundation - Preparation & Submission 22 Jun '22
Preparation & Submission
350 South Utility Building - Foundation - 3d 23-06-22 25-06-22 100.00% 100% South Utility Building - Foundation - Review & Approval by Consultant 25 Jun '22
Review & Approval by Consultant
351 South Utility Building - Gr. beam - 7d 30-06-22 06-07-22 100.00% 100% South Utility Building - Gr. beam - Preparation & Submission 06 Jul '22
Preparation & Submission
352 South Utility Building - Gr. Beam - 3d 07-07-22 09-07-22 100.00% 100% South Utility Building - Gr. Beam - Review & Approval by Consultant 09 Jul '22
Review & Approval by Consultant
353 Submission&Approval - Shop Drawing Str. - South Utility Building
21 d - 21-06-22
Water Tank11-07-22 100.00% 100% Submission&Approval - Shop Drawing Str. - South Utility Building - Water Tank 11 Jul '22
354 South Utility Building - Water Tank- 1st 18 d 21-06-22 08-07-22 100.00% 100% South Utility Building - Water Tank- 1st Preparation & Submission 08 Jul '22
Preparation & Submission
355 South Utility Building - Water Tank - 3d 09-07-22 11-07-22 100.00% 100% South Utility Building - Water Tank - 1st Review & Approval by Consultant 11 Jul '22
1st Review & Approval by Consultant
356 Submission&Approval - Shop Drawing Str. - South Utility Building
10 d - 01-07-22
Pca. Column10-07-22 100.00% 72% Submission&Approval - Shop Drawing Str. - South Utility Building - Pca. Column 10 Jul '22
357 South Utility Building - Pca. Column - 8d 01-07-22 08-07-22 100.00% 90% South Utility Building - Pca. Column - 1st Preparation & Submission 08 Jul '22
1st Preparation & Submission
358 South Utility Building - Pca. Column - 2d 09-07-22 10-07-22 100.00% 0% South Utility Building - Pca. Column - 1st Review & Approval by Consultant 10 Jul '22
1st Review & Approval by Consultant
359 Submission&Approval - Shop Drawing Str. - South Utility Building
14 d - 01-07-22
Roof Steel Structure
15-07-22 100.00% 93% Submission&Approval - Shop Drawing Str. - South Utility Building - Roof Steel Structure 15 Jul '22
360 South Utility Building - Roof - 1st 10 d 01-07-22 10-07-22 100.00% 100% South Utility Building - Roof - 1st Preparation & Submission 10 Jul '22
Preparation & Submission
361 South Utility Building - Roof - 1st 4d 11-07-22 15-07-22 100.00% 75% South Utility Building - Roof - 1st Review & Approval by Consultant 15 Jul '22
Review & Approval by Consultant
362 Submission&Approval - Shop Drawing Str. - South Utility Building
21 d - 26-07-22
Level 1 PT Slab
18-08-22 0.00% 0% Submission&Approval - Shop Drawing Str. - South Utility Building - Level 1 PT Slab 18 Aug '22
363 South Utility Building - Level 1 - 1st 7d 26-07-22 03-08-22 0.00% 0% South Utility Building - Level 1 - 1st Preparation & Submission 03 Aug '22
Preparation & Submission
364 South Utility Building - Level 1 - 1st 7d 04-08-22 10-08-22 0.00% 0% South Utility Building - Level 1 - 1st Review & Approval by Consultant 10 Aug '22
Review & Approval by Consultant
365 South Utility Building - Level 1 - 2nd 4d 11-08-22 15-08-22 0.00% 0% South Utility Building - Level 1 - 2nd Preparation & Submission 15 Aug '22
Preparation & Submission
366 South Utility Building - Level 1 - 2nd 3d 16-08-22 18-08-22 0.00% 0% South Utility Building - Level 1 - 2nd Review & Approval by Consultant 18 Aug '22
Review & Approval by Consultant
367 Submission&Approval - Shop Drawing Str. -South Utility Building
28 d - Level
10-08-22
2 PT Slab
07-09-22 0.00% 0% Submission&Approval - Shop Drawing Str. -South Utility Building - Level 2 PT Slab 07 Sep '22
368 South Utility Building - Level 2 - 1st 7 d 10-08-22 17-08-22 0.00% 0% South Utility Building - Level 2 - 1st Preparation & Submission 17 Aug '22
Preparation & Submission
369 South Utility Building - Level 2 - 1st 7d 18-08-22 24-08-22 0.00% 0% South Utility Building - Level 2 - 1st Review & Approval by Consultant 24 Aug '22
Review & Approval by Consultant
370 South Utility Building - Level 2 - 2nd 7d 25-08-22 31-08-22 0.00% 0% South Utility Building - Level 2 - 2nd Preparation & Submission 31 Aug '22
Preparation & Submission

4 OF 16
PROJECT : Relief Project
MASTER SCHEDULE (REV0.02) Dated 18Jul22
ID Task Name AdditionalTask Duration Start Finish % Plan %
task added Complete
date Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Ap
371 South Utility Building - Level 2 - 2nd 7d 01-09-22 07-09-22 0.00% 0% 18 Jul, '22 South Utility Building - Level 2 - 2nd Review & Approval by Consultant 07 Sep '22
Review & Approval by Consultant
372 Submission&Approval - Shop Drawing Str. - South Utility Building
28 d - 25-08-22
RC.Stair, Link
21-09-22
Bridge 0.00% 0% Submission&Approval - Shop Drawing Str. - South Utility Building - RC.Stair, Link Bridge 21 Sep '22
373 South Utility Building - RC.Stair, Link 7 d 25-08-22 31-08-22 0.00% 0% South Utility Building - RC.Stair, Link Bridge- 1st Preparation & Submission 31 Aug '22
Bridge- 1st Preparation & Submission
374 South Utility Building - RC.Stair, Link Bridge - 1st Review & Approval
7 d 01-09-22
by Consultant
07-09-22 0.00% 0% South Utility Building - RC.Stair, Link Bridge - 1st Review & Approval by Consultant 07 Sep '22
375 South Utility Building - RC.Stair, Link 7 d 08-09-22 14-09-22 0.00% 0% South Utility Building - RC.Stair, Link Bridge - 2nd Preparation & Submission 14 Sep '22
Bridge - 2nd Preparation & Submission
376 South Utility Building - RC.Stair, Link Bridge- 2nd Review & Approval
7d 15-09-22
by Consultant
21-09-22 0.00% 0% South Utility Building - RC.Stair, Link Bridge- 2nd Review & Approval by Consultant 21 Sep '22
377 Submission&Approval - Shop Drawing Str. - South Utility Building 28 d - 25-08-22
External Stl.21-09-22
Staircase0.00% 0% Submission&Approval - Shop Drawing Str. - South Utility Building - External Stl. Staircase 21 Sep '22
378 South Utility Building - External Stl. Staircase- 1st Preparation7 &
d Submission
25-08-22 31-08-22 0.00% 0% South Utility Building - External Stl. Staircase- 1st Preparation & Submission 31 Aug '22
379 South Utility Building - External Stl. Staircase - 1st Review & Approval
7 d 01-09-22
by Consultant
07-09-22 0.00% 0% South Utility Building - External Stl. Staircase - 1st Review & Approval by Consultant 07 Sep '22
380 South Utility Building - External Stl. Staircase - 2nd Preparation
7 d& Submission
08-09-22 14-09-22 0.00% 0% South Utility Building - External Stl. Staircase - 2nd Preparation & Submission 14 Sep '22
381 South Utility Building - External Stl. Staircase- 2nd Review & Approval
7d 15-09-22
by Consultant
21-09-22 0.00% 0% South Utility Building - External Stl. Staircase- 2nd Review & Approval by Consultant 21 Sep '22
382 Submission&Approval - Shop Drawing - 104 d 11-07-22 28-10-22 6.73% 3% Submission&Approval - Shop Drawing - Architectural work 28 Oct '22
Architectural work
383 BIM Architectural Model prepare and 59 d 14-07-22 13-09-22 100.00% 25% BIM Architectural Model prepare and submission 13 Sep '22
submission
384 Submission&Approval - Shop Drawing Ar. - 82 d 04-08-22 27-10-22 0.00% 0% Submission&Approval - Shop Drawing Ar. - Main Factory 27 Oct '22
Main Factory
385 Submission&Approval - Shop Drawing 76 d 10-08-22 27-10-22 0.00% 0% Submission&Approval - Shop Drawing Ar. - Zone A 27 Oct '22
Ar. - Zone A
386 Submission&Approval - Shop Drawing Ar. - Zone A - Roof 14
Metal
d Sheet
10-08-22 24-08-22 0.00% 0% Submission&Approval - Shop Drawing Ar. - Zone A - Roof Metal Sheet 24 Aug '22
387 Zone A - Roof - 1st Preparation & 7 d 10-08-22 17-08-22 0.00% 0% Zone A - Roof - 1st Preparation & Submission 17 Aug '22
Submission
388 Zone A - Roof - 1st Review & 7d 18-08-22 24-08-22 0.00% 0% Zone A - Roof - 1st Review & Approval by Consultant 24 Aug '22
Approval by Consultant
389 Submission&Approval - Shop Drawing Ar. - Zone A - Aluminium
28 d Door,
01-09-22
Window
28-09-22 0.00% 0% Submission&Approval - Shop Drawing Ar. - Zone A - Aluminium Door, Window 28 Sep '22
390 Zone A - Aluminium Door, Window - 1st Preparation & Submission
7 d 01-09-22 07-09-22 0.00% 0% Zone A - Aluminium Door, Window - 1st Preparation & Submission 07 Sep '22
391 Zone A - Aluminium Door, Window - 1st Review & Approval
7 dby Consultant
08-09-22 14-09-22 0.00% 0% Zone A - Aluminium Door, Window - 1st Review & Approval by Consultant 14 Sep '22
392 Zone A - Aluminium Door, Window - 2nd Preparation & Submission
7d 15-09-22 21-09-22 0.00% 0% Zone A - Aluminium Door, Window - 2nd Preparation & Submission 21 Sep '22
393 Zone A - Aluminium Door, Window - 2nd Review & Approval
7 dby Consultant
22-09-22 28-09-22 0.00% 0% Zone A - Aluminium Door, Window - 2nd Review & Approval by Consultant 28 Sep '22
394 Submission&Approval - Shop 28 d 21-09-22 19-10-22 0.00% 0% Submission&Approval - Shop Drawing Ar. - Zone A - PC. Wall 19 Oct '22
Drawing Ar. - Zone A - PC. Wall
395 Zone A - PC. Wall - 1st Preparation 7d 21-09-22 27-09-22 0.00% 0% Zone A - PC. Wall - 1st Preparation & Submission 27 Sep '22
& Submission
396 Zone A - PC. Wall - 1st Review & 7d 28-09-22 04-10-22 0.00% 0% Zone A - PC. Wall - 1st Review & Approval by Consultant 04 Oct '22
Approval by Consultant
397 Zone A - PC. Wall - 2nd Preparation 7d 05-10-22 11-10-22 0.00% 0% Zone A - PC. Wall - 2nd Preparation & Submission 11 Oct '22
& Submission
398 Zone A - PC. Wall - 2nd Review & 7d 12-10-22 19-10-22 0.00% 0% Zone A - PC. Wall - 2nd Review & Approval by Consultant 19 Oct '22
Approval by Consultant
399 Submission&Approval - Shop 28 d 28-09-22 27-10-22 0.00% 0% Submission&Approval - Shop Drawing Ar. - Zone A - Level 1 Plan 27 Oct '22
Drawing Ar. - Zone A - Level 1 Plan
400 Zone A - Level 1 - 1st Preparation & 7d 28-09-22 04-10-22 0.00% 0% Zone A - Level 1 - 1st Preparation & Submission 04 Oct '22
Submission
401 Zone A - Level 1 - 1st Review & 7d 05-10-22 11-10-22 0.00% 0% Zone A - Level 1 - 1st Review & Approval by Consultant 11 Oct '22
Approval by Consultant
402 Zone A - Level 1 - 2nd Preparation & 7d 12-10-22 19-10-22 0.00% 0% Zone A - Level 1 - 2nd Preparation & Submission 19 Oct '22
Submission
403 Zone A - Level 1 - 2nd Review & 7d 20-10-22 27-10-22 0.00% 0% Zone A - Level 1 - 2nd Review & Approval by Consultant 27 Oct '22
Approval by Consultant
404 Submission&Approval - Shop 28 d 28-09-22 27-10-22 0.00% 0% Submission&Approval - Shop Drawing Ar. - Zone A - Level 2 Plan 27 Oct '22
Drawing Ar. - Zone A - Level 2 Plan
405 Zone A - Level 2 - 1st Preparation & 7d 28-09-22 04-10-22 0.00% 0% Zone A - Level 2 - 1st Preparation & Submission 04 Oct '22
Submission
406 Zone A - Level 2 - 1st Review & 7d 05-10-22 11-10-22 0.00% 0% Zone A - Level 2 - 1st Review & Approval by Consultant 11 Oct '22
Approval by Consultant
407 Zone A - Level 2 - 2nd Preparation & 7d 12-10-22 19-10-22 0.00% 0% Zone A - Level 2 - 2nd Preparation & Submission 19 Oct '22
Submission
408 Zone A - Level 2 - 2nd Review & 7d 20-10-22 27-10-22 0.00% 0% Zone A - Level 2 - 2nd Review & Approval by Consultant 27 Oct '22
Approval by Consultant
409 Submission&Approval - Shop Drawing 76 d 04-08-22 20-10-22 0.00% 0% Submission&Approval - Shop Drawing Ar. - Zone B 20 Oct '22
Ar. - Zone B
410 Submission&Approval - Shop Drawing Ar. - Zone B - Roof 14
Metal
d Sheet
04-08-22 18-08-22 0.00% 0% Submission&Approval - Shop Drawing Ar. - Zone B - Roof Metal Sheet 18 Aug '22
411 Zone B - Roof - 1st Preparation & 7 d 04-08-22 10-08-22 0.00% 0% Zone B - Roof - 1st Preparation & Submission 10 Aug '22
Submission
412 Zone B - Roof - 1st Review & 7d 11-08-22 18-08-22 0.00% 0% Zone B - Roof - 1st Review & Approval by Consultant 18 Aug '22
Approval by Consultant
413 Submission&Approval - Shop Drawing Ar. - Zone B - Aluminium
28 d Door,
01-09-22
Window
28-09-22 0.00% 0% Submission&Approval - Shop Drawing Ar. - Zone B - Aluminium Door, Window 28 Sep '22
414 Zone B - Aluminium Door, Window - 1st Preparation & Submission
7 d 01-09-22 07-09-22 0.00% 0% Zone B - Aluminium Door, Window - 1st Preparation & Submission 07 Sep '22
415 Zone B - Aluminium Door, Window - 1st Review & Approval
7 dby Consultant
08-09-22 14-09-22 0.00% 0% Zone B - Aluminium Door, Window - 1st Review & Approval by Consultant 14 Sep '22
416 Zone B - Aluminium Door, Window - 2nd Preparation & Submission
7d 15-09-22 21-09-22 0.00% 0% Zone B - Aluminium Door, Window - 2nd Preparation & Submission 21 Sep '22
417 Zone B - Aluminium Door, Window - 2nd Review & Approval
7 dby Consultant
22-09-22 28-09-22 0.00% 0% Zone B - Aluminium Door, Window - 2nd Review & Approval by Consultant 28 Sep '22
418 Submission&Approval - Shop 28 d 15-09-22 12-10-22 0.00% 0% Submission&Approval - Shop Drawing Ar. - Zone B - PC. Wall 12 Oct '22
Drawing Ar. - Zone B - PC. Wall
419 Zone B - PC. Wall - 1st Preparation 7d 15-09-22 21-09-22 0.00% 0% Zone B - PC. Wall - 1st Preparation & Submission 21 Sep '22
& Submission
420 Zone B - PC. Wall - 1st Review & 7d 22-09-22 28-09-22 0.00% 0% Zone B - PC. Wall - 1st Review & Approval by Consultant 28 Sep '22
Approval by Consultant
421 Zone B - PC. Wall - 2nd Preparation 7d 29-09-22 05-10-22 0.00% 0% Zone B - PC. Wall - 2nd Preparation & Submission 05 Oct '22
& Submission
422 Zone B - PC. Wall - 2nd Review & 7d 06-10-22 12-10-22 0.00% 0% Zone B - PC. Wall - 2nd Review & Approval by Consultant 12 Oct '22
Approval by Consultant
423 Submission&Approval - Shop 28 d 22-09-22 20-10-22 0.00% 0% Submission&Approval - Shop Drawing Ar. - Zone B - Level 1 Plan 20 Oct '22
Drawing Ar. - Zone B - Level 1 Plan
424 Zone B - Level 1 - 1st Preparation & 7d 22-09-22 28-09-22 0.00% 0% Zone B - Level 1 - 1st Preparation & Submission 28 Sep '22
Submission
425 Zone B - Level 1 - 1st Review & 7d 29-09-22 05-10-22 0.00% 0% Zone B - Level 1 - 1st Review & Approval by Consultant 05 Oct '22
Approval by Consultant
426 Zone B - Level 1 - 2nd Preparation & 7d 06-10-22 12-10-22 0.00% 0% Zone B - Level 1 - 2nd Preparation & Submission 12 Oct '22
Submission
427 Zone B - Level 1 - 2nd Review & 7d 14-10-22 20-10-22 0.00% 0% Zone B - Level 1 - 2nd Review & Approval by Consultant 20 Oct '22
Approval by Consultant
428 Submission&Approval - Shop 28 d 22-09-22 20-10-22 0.00% 0% Submission&Approval - Shop Drawing Ar. - Zone B - Level 2 Plan 20 Oct '22
Drawing Ar. - Zone B - Level 2 Plan
429 Zone B - Level 2 - 1st Preparation & 7d 22-09-22 28-09-22 0.00% 0% Zone B - Level 2 - 1st Preparation & Submission 28 Sep '22
Submission
430 Zone B - Level 2 - 1st Review & 7d 29-09-22 05-10-22 0.00% 0% Zone B - Level 2 - 1st Review & Approval by Consultant 05 Oct '22
Approval by Consultant
431 Zone B - Level 2 - 2nd Preparation & 7d 06-10-22 12-10-22 0.00% 0% Zone B - Level 2 - 2nd Preparation & Submission 12 Oct '22
Submission
432 Zone B - Level 2 - 2nd Review & 7d 14-10-22 20-10-22 0.00% 0% Zone B - Level 2 - 2nd Review & Approval by Consultant 20 Oct '22
Approval by Consultant
433 Submission&Approval - Shop Drawing Ar. - 69 d 19-08-22 28-10-22 0.00% 0% Submission&Approval - Shop Drawing Ar. - Office and Canteen 28 Oct '22
Office and Canteen
434 Submission&Approval - Shop Drawing Ar. - Office and Canteen
14 -dFaçade
19-08-22
work &01-09-22
Curtain wall
0.00% 0% Submission&Approval - Shop Drawing Ar. - Office and Canteen - Façade work & Curtain wall 01 Sep '22
435 Office and Canteen - Façade work - 1st 7 d 19-08-22 25-08-22 0.00% 0% Office and Canteen - Façade work - 1st Preparation & Submission 25 Aug '22
Preparation & Submission
436 Office and Canteen - Façade work - 1st 7d 26-08-22 01-09-22 0.00% 0% Office and Canteen - Façade work - 1st Review & Approval by Consultant 01 Sep '22
Review & Approval by Consultant
437 Submission&Approval - Shop Drawing 28 d 30-08-22 26-09-22 0.00% 0% Submission&Approval - Shop Drawing Ar. - Office and Canteen - Level 1 Plan 26 Sep '22
Ar. - Office and Canteen - Level 1 Plan
438 Office and Canteen - Level 1 - 1st 7d 30-08-22 05-09-22 0.00% 0% Office and Canteen - Level 1 - 1st Preparation & Submission 05 Sep '22
Preparation & Submission
439 Office and Canteen - Level 1 - 1st 7d 06-09-22 12-09-22 0.00% 0% Office and Canteen - Level 1 - 1st Review & Approval by Consultant 12 Sep '22
Review & Approval by Consultant
440 Office and Canteen - Level 1 - 2nd 7d 13-09-22 19-09-22 0.00% 0% Office and Canteen - Level 1 - 2nd Preparation & Submission 19 Sep '22
Preparation & Submission
441 Office and Canteen - Level 1 - 2nd 7d 20-09-22 26-09-22 0.00% 0% Office and Canteen - Level 1 - 2nd Review & Approval by Consultant 26 Sep '22
Review & Approval by Consultant
442 Submission&Approval - Shop Drawing 28 d 15-09-22 12-10-22 0.00% 0% Submission&Approval - Shop Drawing Ar. - Office and Canteen - Level M Plan 12 Oct '22
Ar. - Office and Canteen - Level M Plan
443 Office and Canteen - Level M - 1st 7d 15-09-22 21-09-22 0.00% 0% Office and Canteen - Level M - 1st Preparation & Submission 21 Sep '22
Preparation & Submission
444 Office and Canteen - Level M - 1st 7d 22-09-22 28-09-22 0.00% 0% Office and Canteen - Level M - 1st Review & Approval by Consultant 28 Sep '22
Review & Approval by Consultant
445 Office and Canteen - Level M - 2nd 7d 29-09-22 05-10-22 0.00% 0% Office and Canteen - Level M - 2nd Preparation & Submission 05 Oct '22
Preparation & Submission
446 Office and Canteen - Level M - 2nd 7d 06-10-22 12-10-22 0.00% 0% Office and Canteen - Level M - 2nd Review & Approval by Consultant 12 Oct '22
Review & Approval by Consultant
447 Submission&Approval - Shop Drawing 28 d 22-09-22 20-10-22 0.00% 0% Submission&Approval - Shop Drawing Ar. - Office and Canteen - Level 2 Plan 20 Oct '22
Ar. - Office and Canteen - Level 2 Plan
448 Office and Canteen - Level 2 - 1st 7d 22-09-22 28-09-22 0.00% 0% Office and Canteen - Level 2 - 1st Preparation & Submission 28 Sep '22
Preparation & Submission
449 Office and Canteen - Level 2 - 1st 7d 29-09-22 05-10-22 0.00% 0% Office and Canteen - Level 2 - 1st Review & Approval by Consultant 05 Oct '22
Review & Approval by Consultant
450 Office and Canteen - Level 2 - 2nd 7d 06-10-22 12-10-22 0.00% 0% Office and Canteen - Level 2 - 2nd Preparation & Submission 12 Oct '22
Preparation & Submission
451 Office and Canteen - Level 2 - 2nd 7d 14-10-22 20-10-22 0.00% 0% Office and Canteen - Level 2 - 2nd Review & Approval by Consultant 20 Oct '22
Review & Approval by Consultant
452 Submission&Approval - Shop Drawing 28 d 29-09-22 28-10-22 0.00% 0% Submission&Approval - Shop Drawing Ar. - Office and Canteen - Roof Plan 28 Oct '22
Ar. - Office and Canteen - Roof Plan
453 Office and Canteen - Roof - 1st 7d 29-09-22 05-10-22 0.00% 0% Office and Canteen - Roof - 1st Preparation & Submission 05 Oct '22
Preparation & Submission
454 Office and Canteen - Roof - 1st Review 7d 06-10-22 12-10-22 0.00% 0% Office and Canteen - Roof - 1st Review & Approval by Consultant 12 Oct '22
& Approval by Consultant
455 Office and Canteen - Roof - 2nd 7d 14-10-22 20-10-22 0.00% 0% Office and Canteen - Roof - 2nd Preparation & Submission 20 Oct '22
Preparation & Submission
456 Office and Canteen - Roof - 2nd Review 7d 21-10-22 28-10-22 0.00% 0% Office and Canteen - Roof - 2nd Review & Approval by Consultant 28 Oct '22
& Approval by Consultant
457 Submission&Approval - Shop Drawing Ar. - Office and Canteen
28 -dTop29-09-22
Roof Plan 28-10-22 0.00% 0% Submission&Approval - Shop Drawing Ar. - Office and Canteen - Top Roof Plan 28 Oct '22
458 Office and Canteen - Top Roof - 1st 7 d 29-09-22 05-10-22 0.00% 0% Office and Canteen - Top Roof - 1st Preparation & Submission 05 Oct '22
Preparation & Submission

5 OF 16
PROJECT : Relief Project
MASTER SCHEDULE (REV0.02) Dated 18Jul22
ID Task Name AdditionalTask Duration Start Finish % Plan %
task added Complete
date Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Ap
459 Office and Canteen - Top Roof - 1st 7d 06-10-22 12-10-22 0.00% 0% 18 Jul, '22 Office and Canteen - Top Roof - 1st Review & Approval by Consultant 12 Oct '22
Review & Approval by Consultant
460 Office and Canteen - Top Roof - 2nd 7d 14-10-22 20-10-22 0.00% 0% Office and Canteen - Top Roof - 2nd Preparation & Submission 20 Oct '22
Preparation & Submission
461 Office and Canteen - Top Roof - 2nd 7d 21-10-22 28-10-22 0.00% 0% Office and Canteen - Top Roof - 2nd Review & Approval by Consultant 28 Oct '22
Review & Approval by Consultant
462 Submission&Approval - Shop Drawing Ar. - 68 d 27-07-22 05-10-22 0.00% 0% Submission&Approval - Shop Drawing Ar. - East Utility Building 05 Oct '22
East Utility Building
463 Submission&Approval - Shop Drawing Ar. - East Utility Building-
22 d Roof
27-07-22
(Aluminum
20-08-22
trellis) 0.00% 0% Submission&Approval - Shop Drawing Ar. - East Utility Building- Roof (Aluminum trellis) 20 Aug '22
464 East Utility Building - Roof - 1st 7d 27-07-22 04-08-22 0.00% 0% East Utility Building - Roof - 1st Preparation & Submission 04 Aug '22
Preparation & Submission
465 East Utility Building - Roof - 1st Review 7d 05-08-22 11-08-22 0.00% 0% East Utility Building - Roof - 1st Review & Approval by Consultant 11 Aug '22
& Approval by Consultant
466 East Utility Building - Roof - 2nd 4d 13-08-22 16-08-22 0.00% 0% East Utility Building - Roof - 2nd Preparation & Submission 16 Aug '22
Preparation & Submission
467 East Utility Building - Roof - 2nd 4d 17-08-22 20-08-22 0.00% 0% East Utility Building - Roof - 2nd Review & Approval by Consultant 20 Aug '22
Review & Approval by Consultant
468 Submission&Approval - Shop Drawing 14 d 24-08-22 06-09-22 0.00% 0% Submission&Approval - Shop Drawing Ar. - East Utility Building - Level 1 Plan 06 Sep '22
Ar. - East Utility Building - Level 1 Plan
469 East Utility Building - Level 1 - 1st 7d 24-08-22 30-08-22 0.00% 0% East Utility Building - Level 1 - 1st Preparation & Submission 30 Aug '22
Preparation & Submission
470 East Utility Building - Level 1 - 1st 7d 31-08-22 06-09-22 0.00% 0% East Utility Building - Level 1 - 1st Review & Approval by Consultant 06 Sep '22
Review & Approval by Consultant
471 Submission&Approval - Shop Drawing Ar. - East Utility Building28 d- Aluminium
26-08-22 Door,
22-09-22
Window
0.00% 0% Submission&Approval - Shop Drawing Ar. - East Utility Building - Aluminium Door, Window 22 Sep '22
472 East Utility Building - Aluminium Door, Window - 1st Preparation
7 d & Submission
26-08-22 01-09-22 0.00% 0% East Utility Building - Aluminium Door, Window - 1st Preparation & Submission 01 Sep '22
473 East Utility Building - Aluminium Door, Window - 1st Review &
7 dApproval
02-09-22
by Consultant
08-09-22 0.00% 0% East Utility Building - Aluminium Door, Window - 1st Review & Approval by Consultant 08 Sep '22
474 East Utility Building - Aluminium Door, Window - 2nd Preparation
7 d &09-09-22
Submission 15-09-22 0.00% 0% East Utility Building - Aluminium Door, Window - 2nd Preparation & Submission 15 Sep '22
475 East Utility Building - Aluminium Door, Window - 2nd Review7&dApproval
16-09-22
by Consultant
22-09-22 0.00% 0% East Utility Building - Aluminium Door, Window - 2nd Review & Approval by Consultant 22 Sep '22
476 Submission&Approval - Shop Drawing 21 d 15-09-22 05-10-22 0.00% 0% Submission&Approval - Shop Drawing Ar. - East Utility Building - PC. Wall 05 Oct '22
Ar. - East Utility Building - PC. Wall
477 East Utility Building - PC. Wall - 1st 7d 15-09-22 21-09-22 0.00% 0% East Utility Building - PC. Wall - 1st Preparation & Submission 21 Sep '22
Preparation & Submission
478 East Utility Building - PC. Wall - 1st 7d 22-09-22 28-09-22 0.00% 0% East Utility Building - PC. Wall - 1st Review & Approval by Consultant 28 Sep '22
Review & Approval by Consultant
479 East Utility Building - PC. Wall - 2nd 4d 29-09-22 02-10-22 0.00% 0% East Utility Building - PC. Wall - 2nd Preparation & Submission 02 Oct '22
Preparation & Submission
480 East Utility Building - PC. Wall - 2nd 3d 03-10-22 05-10-22 0.00% 0% East Utility Building - PC. Wall - 2nd Review & Approval by Consultant 05 Oct '22
Review & Approval by Consultant
481 Submission&Approval - Shop Drawing Ar. - 90 d 11-07-22 12-10-22 7.78% 5% Submission&Approval - Shop Drawing Ar. - South Utility Building 12 Oct '22
South Utility Building
482 Submission&Approval - Shop Drawing Ar. - South Utility Building
14 d - Roof
11-07-22
Metal Sheet
25-07-22 50.00% 40% Submission&Approval - Shop Drawing Ar. - South Utility Building - Roof Metal Sheet 25 Jul '22
483 South Utility Building - Roof - 1st 7d 11-07-22 18-07-22 100.00% 80% South Utility Building - Roof - 1st Preparation & Submission 18 Jul '22
Preparation & Submission
484 South Utility Building - Roof - 1st 7d 19-07-22 25-07-22 0.00% 0% South Utility Building - Roof - 1st Review & Approval by Consultant 25 Jul '22
Review & Approval by Consultant
485 Submission&Approval - Shop Drawing Ar. - South Utility Building
28 d - Level
25-08-22
1 Plan 21-09-22 0.00% 0% Submission&Approval - Shop Drawing Ar. - South Utility Building - Level 1 Plan 21 Sep '22
486 South Utility Building - Level 1 - 1st 7d 25-08-22 31-08-22 0.00% 0% South Utility Building - Level 1 - 1st Preparation & Submission 31 Aug '22
Preparation & Submission
487 South Utility Building - Level 1 - 1st 7d 01-09-22 07-09-22 0.00% 0% South Utility Building - Level 1 - 1st Review & Approval by Consultant 07 Sep '22
Review & Approval by Consultant
488 South Utility Building - Level 1 - 2nd 7d 08-09-22 14-09-22 0.00% 0% South Utility Building - Level 1 - 2nd Preparation & Submission 14 Sep '22
Preparation & Submission
489 South Utility Building - Level 1 - 2nd 7d 15-09-22 21-09-22 0.00% 0% South Utility Building - Level 1 - 2nd Review & Approval by Consultant 21 Sep '22
Review & Approval by Consultant
490 Submission&Approval - Shop Drawing Ar. - South Utility Building
28 d - Aluminium
26-08-22 Door,
22-09-22
Window
0.00% 0% Submission&Approval - Shop Drawing Ar. - South Utility Building - Aluminium Door, Window 22 Sep '22
491 South Utility Building - Aluminium Door, Window - 1st Preparation
7 d &26-08-22
Submission01-09-22 0.00% 0% South Utility Building - Aluminium Door, Window - 1st Preparation & Submission 01 Sep '22
492 South Utility Building - Aluminium Door, Window - 1st Review7 &
d Approval
02-09-22
by Consultant
08-09-22 0.00% 0% South Utility Building - Aluminium Door, Window - 1st Review & Approval by Consultant 08 Sep '22
493 South Utility Building - Aluminium Door, Window - 2nd Preparation
7 d 09-09-22
& Submission15-09-22 0.00% 0% South Utility Building - Aluminium Door, Window - 2nd Preparation & Submission 15 Sep '22
494 South Utility Building - Aluminium Door, Window - 2nd Review
7 d& Approval
16-09-22
by Consultant
22-09-22 0.00% 0% South Utility Building - Aluminium Door, Window - 2nd Review & Approval by Consultant 22 Sep '22
495 Submission&Approval - Shop Drawing 28 d 15-09-22 12-10-22 0.00% 0% Submission&Approval - Shop Drawing Ar. - South Utility Building - PC. Wall 12 Oct '22
Ar. - South Utility Building - PC. Wall
496 South Utility Building - PC. Wall - 1st 7d 15-09-22 21-09-22 0.00% 0% South Utility Building - PC. Wall - 1st Preparation & Submission 21 Sep '22
Preparation & Submission
497 South Utility Building - PC. Wall - 1st 7d 22-09-22 28-09-22 0.00% 0% South Utility Building - PC. Wall - 1st Review & Approval by Consultant 28 Sep '22
Review & Approval by Consultant
498 South Utility Building - PC. Wall - 2nd 7d 29-09-22 05-10-22 0.00% 0% South Utility Building - PC. Wall - 2nd Preparation & Submission 05 Oct '22
Preparation & Submission
499 South Utility Building - PC. Wall - 2nd 7d 06-10-22 12-10-22 0.00% 0% South Utility Building - PC. Wall - 2nd Review & Approval by Consultant 12 Oct '22
Review & Approval by Consultant
500 Submission&Approval - Shop Drawing Ar. -South Utility Building
14 d - Level
17-09-22
2 Plan 30-09-22 0.00% 0% Submission&Approval - Shop Drawing Ar. -South Utility Building - Level 2 Plan 30 Sep '22
501 South Utility Building - Level 2 - 1st 4d 17-09-22 20-09-22 0.00% 0% South Utility Building - Level 2 - 1st Preparation & Submission 20 Sep '22
Preparation & Submission
502 South Utility Building - Level 2 - 1st 3d 21-09-22 23-09-22 0.00% 0% South Utility Building - Level 2 - 1st Review & Approval by Consultant 23 Sep '22
Review & Approval by Consultant
503 South Utility Building - Level 2 - 2nd 4d 24-09-22 27-09-22 0.00% 0% South Utility Building - Level 2 - 2nd Preparation & Submission 27 Sep '22
Preparation & Submission
504 South Utility Building - Level 2 - 2nd 3d 28-09-22 30-09-22 0.00% 0% South Utility Building - Level 2 - 2nd Review & Approval by Consultant 30 Sep '22
Review & Approval by Consultant
505 Submission&Approval - Shop Drawing - 196 d 23-06-22 15-01-23 12.76% 17% Submission&Approval - Shop Drawing - External work 15 Jan '23
External work
506 BIM Civil Model prepare and submission 59 d 14-07-22 13-09-22 100.00% 25% BIM Civil Model prepare and submission 13 Sep '22
507 BIM Sanitary Model prepare and 59 d 14-07-22 13-09-22 100.00% 25% BIM Sanitary Model prepare and submission 13 Sep '22
submission
508 Submission&Approval - Shop Drawing - 20 d 23-06-22 12-07-22 100.00% 93% Submission&Approval - Shop Drawing - External work - Retention pond 12 Jul '22
External work - Retention pond
509 Retention pond - 1st Preparation & 14 d 23-06-22 06-07-22 100.00% 100% Retention pond - 1st Preparation & Submission 06 Jul '22
Submission
510 Retention pond - 1st Review & Approval 6d 07-07-22 12-07-22 100.00% 75% Retention pond - 1st Review & Approval by Consultant 12 Jul '22
by Consultant
511 Submission&Approval - Shop Drawing - 16 d 29-06-22 15-07-22 100.00% 95% Submission&Approval - Shop Drawing - External work - Boundary fence 15 Jul '22
External work - Boundary fence
512 Boundary fence - 1st Preparation & 13 d 29-06-22 11-07-22 100.00% 100% Boundary fence - 1st Preparation & Submission 11 Jul '22
Submission
513 Boundary fence - 1st Review & Approval 3d 12-07-22 15-07-22 100.00% 75% Boundary fence - 1st Review & Approval by Consultant 15 Jul '22
by Consultant
514 Submission&Approval - Shop Drawing - External work - Stormwater
15 d drainage
12-07-22
system
27-07-22 40.00% 27% Submission&Approval - Shop Drawing - External work - Stormwater drainage system 27 Jul '22
515 Stormwater drainage system - 1st 8d 12-07-22 20-07-22 75.00% 50% Stormwater drainage system - 1st Preparation & Submission 20 Jul '22
Preparation & Submission
516 Stormwater drainage system - 1st Review 7d 21-07-22 27-07-22 0.00% 0% Stormwater drainage system - 1st Review & Approval by Consultant 27 Jul '22
& Approval by Consultant
517 Submission&Approval - Shop Drawing - External work - Guardhouse
20 d & 04-08-22
Custrm office
24-08-22 0.00% 0% Submission&Approval - Shop Drawing - External work - Guardhouse & Custrm office 24 Aug '22
518 Guardhouse & Custrm office - 1st 5 d 04-08-22 08-08-22 0.00% 0% Guardhouse & Custrm office - 1st Preparation & Submission 08 Aug '22
Preparation & Submission
519 Guardhouse & Custrm office - 1st Review 5d 09-08-22 14-08-22 0.00% 0% Guardhouse & Custrm office - 1st Review & Approval by Consultant 14 Aug '22
& Approval by Consultant
520 Guardhouse & Custrm office - 2nd 5d 15-08-22 19-08-22 0.00% 0% Guardhouse & Custrm office - 2nd Preparation & Submission 19 Aug '22
Preparation & Submission
521 Guardhouse & Custrm office - 2nd Review 5d 20-08-22 24-08-22 0.00% 0% Guardhouse & Custrm office - 2nd Review & Approval by Consultant 24 Aug '22
& Approval by Consultant
522 Submission&Approval - Shop Drawing - External work - Road & 21
Pavement,
d 25-08-22
Loading
14-09-22
dock, Truck
0.00%
scale 0% Submission&Approval - Shop Drawing - External work - Road & Pavement, Loading dock, Truck scale 14 Sep '22
523 Road & Pavement, Loading dock, Truck 7 d 25-08-22 31-08-22 0.00% 0% Road & Pavement, Loading dock, Truck scale - 1st Preparation & Submission 31 Aug '22
scale - 1st Preparation & Submission
524 Road & Pavement, Loading dock, Truck scale - 1st Review & Approval
7 d by01-09-22
Consultant07-09-22 0.00% 0% Road & Pavement, Loading dock, Truck scale - 1st Review & Approval by Consultant 07 Sep '22
525 Road & Pavement, Loading dock, Truck 4d 08-09-22 11-09-22 0.00% 0% Road & Pavement, Loading dock, Truck scale - 2nd Preparation & Submission 11 Sep '22
scale - 2nd Preparation & Submission
526 Road & Pavement, Loading dock, Truck scale - 2nd Review & Approval
3d 12-09-22
by Consultant
14-09-22 0.00% 0% Road & Pavement, Loading dock, Truck scale - 2nd Review & Approval by Consultant 14 Sep '22
527 Submission&Approval - Shop Drawing - External work - Car & Motorcycle
28 d 25-08-22
parking (Southside)
21-09-22 0.00% 0% Submission&Approval - Shop Drawing - External work - Car & Motorcycle parking (Southside) 21 Sep '22
528 Car & Motorcycle parking (Southside) - 1st 7d 25-08-22 31-08-22 0.00% 0% Car & Motorcycle parking (Southside) - 1st Preparation & Submission 31 Aug '22
Preparation & Submission
529 Car & Motorcycle parking (Southside) - 1st 7d 01-09-22 07-09-22 0.00% 0% Car & Motorcycle parking (Southside) - 1st Review & Approval by Consultant 07 Sep '22
Review & Approval by Consultant
530 Car & Motorcycle parking (Southside) - 7d 08-09-22 14-09-22 0.00% 0% Car & Motorcycle parking (Southside) - 2nd Preparation & Submission 14 Sep '22
2nd Preparation & Submission
531 Car & Motorcycle parking (Southside) - 7d 15-09-22 21-09-22 0.00% 0% Car & Motorcycle parking (Southside) - 2nd Review & Approval by Consultant 21 Sep '22
2nd Review & Approval by Consultant
532 Submission&Approval - Shop Drawing - External work - VIP & Visitor
28 d parking
25-08-22
(Northside)
21-09-22 0.00% 0% Submission&Approval - Shop Drawing - External work - VIP & Visitor parking (Northside) 21 Sep '22
533 VIP & Visitor parking (Northside) - 1st 7 d 25-08-22 31-08-22 0.00% 0% VIP & Visitor parking (Northside) - 1st Preparation & Submission 31 Aug '22
Preparation & Submission
534 VIP & Visitor parking (Northside) - 1st 7d 01-09-22 07-09-22 0.00% 0% VIP & Visitor parking (Northside) - 1st Review & Approval by Consultant 07 Sep '22
Review & Approval by Consultant
535 VIP & Visitor parking (Northside) - 2nd 7d 08-09-22 14-09-22 0.00% 0% VIP & Visitor parking (Northside) - 2nd Preparation & Submission 14 Sep '22
Preparation & Submission
536 VIP & Visitor parking (Northside) - 2nd 7d 15-09-22 21-09-22 0.00% 0% VIP & Visitor parking (Northside) - 2nd Review & Approval by Consultant 21 Sep '22
Review & Approval by Consultant
537 Submission&Approval - Shop Drawing - 28 d 15-12-22 15-01-23 0.00% 0% Submission&Approval - Shop Drawing - External work - Green area & Landscape 15 Jan '23
External work - Green area & Landscape
538 Green area & Landscape - 1st Preparation 7d 15-12-22 21-12-22 0.00% 0% Green area & Landscape - 1st Preparation & Submission 21 Dec '22
& Submission
539 Green area & Landscape - 1st Review & 7d 22-12-22 28-12-22 0.00% 0% Green area & Landscape - 1st Review & Approval by Consultant 28 Dec '22
Approval by Consultant
540 Green area & Landscape - 2nd 7d 29-12-22 08-01-23 0.00% 0% Green area & Landscape - 2nd Preparation & Submission 08 Jan '23
Preparation & Submission
541 Green area & Landscape - 2nd Review & 7d 09-01-23 15-01-23 0.00% 0% Green area & Landscape - 2nd Review & Approval by Consultant 15 Jan '23
Approval by Consultant
542 Submission&Approval - Shop Drawing - 28 d 15-12-22 15-01-23 0.00% 0% Submission&Approval - Shop Drawing - External work - Main entrance 15 Jan '23
External work - Main entrance
543 Main entrance - 1st Preparation & 7d 15-12-22 21-12-22 0.00% 0% Main entrance - 1st Preparation & Submission 21 Dec '22
Submission
544 Main entrance - 1st Review & Approval by 7d 22-12-22 28-12-22 0.00% 0% Main entrance - 1st Review & Approval by Consultant 28 Dec '22
Consultant
545 Main entrance - 2nd Preparation & 7d 29-12-22 08-01-23 0.00% 0% Main entrance - 2nd Preparation & Submission 08 Jan '23
Submission
546 Main entrance - 2nd Review & Approval 7d 09-01-23 15-01-23 0.00% 0% Main entrance - 2nd Review & Approval by Consultant 15 Jan '23
by Consultant

6 OF 16
PROJECT : Relief Project
MASTER SCHEDULE (REV0.02) Dated 18Jul22
ID Task Name AdditionalTask Duration Start Finish % Plan %
task added Complete
date Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Ap
547 Submission&Approval - Shop Drawing - 28 d 01-09-22 28-09-22 0.00% 0% 18 Jul, '22 Submission&Approval - Shop Drawing - External work - Truck Scale 28 Sep '22
External work - Truck Scale
548 Truck Scale - 1st Preparation & 7d 01-09-22 07-09-22 0.00% 0% Truck Scale - 1st Preparation & Submission 07 Sep '22
Submission
549 Truck Scale - 1st Review & Approval by 7d 08-09-22 14-09-22 0.00% 0% Truck Scale - 1st Review & Approval by Consultant 14 Sep '22
Consultant
550 Truck Scale - 2nd Preparation & 7d 15-09-22 21-09-22 0.00% 0% Truck Scale - 2nd Preparation & Submission 21 Sep '22
Submission
551 Truck Scale - 2nd Review & Approval by 7d 22-09-22 28-09-22 0.00% 0% Truck Scale - 2nd Review & Approval by Consultant 28 Sep '22
Consultant
552 Submission&Approval - Shop Drawing - 28 d 04-08-22 01-09-22 0.00% 0% Submission&Approval - Shop Drawing - External work - Walk Way 01 Sep '22
External work - Walk Way
553 Walk Way - 1st Preparation & Submission 7d 04-08-22 10-08-22 0.00% 0% Walk Way - 1st Preparation & Submission 10 Aug '22
554 Walk Way - 1st Review & Approval by 7d 11-08-22 18-08-22 0.00% 0% Walk Way - 1st Review & Approval by Consultant 18 Aug '22
Consultant
555 Walk Way - 2nd Preparation & Submission 7d 19-08-22 25-08-22 0.00% 0% Walk Way - 2nd Preparation & Submission 25 Aug '22
556 Walk Way - 2nd Review & Approval by 7d 26-08-22 01-09-22 0.00% 0% Walk Way - 2nd Review & Approval by Consultant 01 Sep '22
Consultant
557 Submission&Approval - Shop Drawing - 14 d 01-08-22 15-08-22 0.00% 0% Submission&Approval - Shop Drawing - External work - Pipe Rack 15 Aug '22
External work - Pipe Rack
558 Pipe Rack - 1st Preparation & Submission 10 d 01-08-22 10-08-22 0.00% 0% Pipe Rack - 1st Preparation & Submission 10 Aug '22
559 Pipe Rack - 1st Review & Approval by 4d 11-08-22 15-08-22 0.00% 0% Pipe Rack - 1st Review & Approval by Consultant 15 Aug '22
Consultant
560 Submission&Approval - Material 85 d 19-06-22 15-09-22 34.12% 34% Submission&Approval - Material 15 Sep '22
561 Submission&Approval - Material - Re-Bar 10 d 19-06-22 28-06-22 100.00% 100% Submission&Approval - Material - Re-Bar 28 Jun '22
562 Re-Bar - 1st Preparation & Submission 7d 19-06-22 25-06-22 100.00% 100% Re-Bar - 1st Preparation & Submission 25 Jun '22
563 Re-Bar - 1st Review & Approval by Consultant 3d 26-06-22 28-06-22 100.00% 100% Re-Bar - 1st Review & Approval by Consultant 28 Jun '22
564 Submission&Approval - Material - Concrete 10 d 19-06-22 28-06-22 100.00% 100% Submission&Approval - Material - Concrete 28 Jun '22
565 Concrete - 1st Preparation & Submission 7d 19-06-22 25-06-22 100.00% 100% Concrete - 1st Preparation & Submission 25 Jun '22
566 Concrete - 1st Review & Approval by 3d 26-06-22 28-06-22 100.00% 100% Concrete - 1st Review & Approval by Consultant 28 Jun '22
Consultant
567 Submission&Approval - Material - Fireproof 21 d 23-06-22 14-07-22 100.00% 100% Submission&Approval - Material - Fireproof paint, OP paint for roof/siding wall str 14 Jul '22
paint, OP paint for roof/siding wall str
568 Fireproof paint - 1st Preparation & 7d 23-06-22 29-06-22 100.00% 100% Fireproof paint - 1st Preparation & Submission 29 Jun '22
Submission
569 Fireproof paint - 1st Review & Approval by 7d 30-06-22 06-07-22 100.00% 100% Fireproof paint - 1st Review & Approval by Consultant 06 Jul '22
Consultant
570 OP paint for roof/siding wall str - 1st 5d 04-07-22 08-07-22 100.00% 100% OP paint for roof/siding wall str - 1st Preparation & Submission 08 Jul '22
Preparation & Submission
571 OP paint for roof/siding wall str - 1st Review 5d 09-07-22 14-07-22 100.00% 100% OP paint for roof/siding wall str - 1st Review & Approval by Consultant 14 Jul '22
& Approval by Consultant
572 Submission&Approval - Material - Metal roof 14 d 23-06-22 06-07-22 100.00% 100% Submission&Approval - Material - Metal roof sheet 06 Jul '22
sheet
573 Metal roof sheet - 1st Preparation & 7d 23-06-22 29-06-22 100.00% 100% Metal roof sheet - 1st Preparation & Submission 29 Jun '22
Submission
574 Metal roof sheet - 1st Review & Approval by 7d 30-06-22 06-07-22 100.00% 100% Metal roof sheet - 1st Review & Approval by Consultant 06 Jul '22
Consultant
575 Submission&Approval - Material - 14 d 23-06-22 06-07-22 100.00% 100% Submission&Approval - Material - Polypropylane for process waste 06 Jul '22
Polypropylane for process waste
576 Polypropylane for process waste - 1st 7d 23-06-22 29-06-22 100.00% 100% Polypropylane for process waste - 1st Preparation & Submission 29 Jun '22
Preparation & Submission
577 Polypropylane for process waste - 1st Review 7d 30-06-22 06-07-22 100.00% 100% Polypropylane for process waste - 1st Review & Approval by Consultant 06 Jul '22
& Approval by Consultant
578 Submission&Approval - Material - PVC & 14 d 30-06-22 14-07-22 100.00% 100% Submission&Approval - Material - PVC & HDPE for sanitary waste, soil, vent 14 Jul '22
HDPE for sanitary waste, soil, vent
579 PVC & HDPE for sanitary waste, soil, vent - 7d 30-06-22 06-07-22 100.00% 100% PVC & HDPE for sanitary waste, soil, vent - 1st Preparation & Submission 06 Jul '22
1st Preparation & Submission
580 PVC & HDPE for sanitary waste, soil, vent - 7d 07-07-22 14-07-22 100.00% 100% PVC & HDPE for sanitary waste, soil, vent - 1st Review & Approval by Consultant 14 Jul '22
1st Review & Approval by Consultant
581 Submission&Approval - Material - Dock leveler 28 d 30-06-22 30-07-22 64.29% 0% Submission&Approval - Material - Dock leveler 30 Jul '22
582 Dock leveler - 1st Preparation & Submission 7d 30-06-22 06-07-22 100.00% 0% Dock leveler - 1st Preparation & Submission 06 Jul '22
583 Dock leveler - 1st Review & Approval by 7d 07-07-22 14-07-22 100.00% 0% Dock leveler - 1st Review & Approval by Consultant 14 Jul '22
Consultant
584 Dock leveler - 2nd Preparation & Submission 7d 15-07-22 21-07-22 57.14% 0% Dock leveler - 2nd Preparation & Submission 21 Jul '22
585 Dock leveler - 2nd Review & Approval by 7d 22-07-22 30-07-22 0.00% 0% Dock leveler - 2nd Review & Approval by Consultant 30 Jul '22
Consultant
586 Submission&Approval - Material - Roof Steel 10 d 01-07-22 10-07-22 100.00% 100% Submission&Approval - Material - Roof Steel Structure 10 Jul '22
Structure
587 Roof Steel Structure - 1st Preparation & 7d 01-07-22 07-07-22 100.00% 100% Roof Steel Structure - 1st Preparation & Submission 07 Jul '22
Submission
588 Roof Steel Structure - 1st Review & 3d 08-07-22 10-07-22 100.00% 100% Roof Steel Structure - 1st Review & Approval by Consultant 10 Jul '22
Approval by Consultant
589 Submission&Approval - Material - Formwork 16 d 04-07-22 20-07-22 87.50% 56% Submission&Approval - Material - Formwork for 1M & 2F, posttension slab 20 Jul '22
for 1M & 2F, posttension slab
590 Formwork for 1M & 2F, posttension slab - 1st 9d 04-07-22 12-07-22 100.00% 100% Formwork for 1M & 2F, posttension slab - 1st Preparation & Submission 12 Jul '22
Preparation & Submission
591 Formwork for 1M & 2F, posttension slab - 1st 7d 14-07-22 20-07-22 71.43% 0% Formwork for 1M & 2F, posttension slab - 1st Review & Approval by Consultant 20 Jul '22
Review & Approval by Consultant
592 Submission&Approval - Material - Posttension 20 d 04-07-22 24-07-22 70.00% 75% Submission&Approval - Material - Posttension slab 24 Jul '22
slab
593 Posttension slab - 1st Preparation & 15 d 04-07-22 19-07-22 93.33% 100% Posttension slab - 1st Preparation & Submission 19 Jul '22
Submission
594 Posttension slab - 1st Review & Approval by 5d 20-07-22 24-07-22 0.00% 0% Posttension slab - 1st Review & Approval by Consultant 24 Jul '22
Consultant
595 Submission&Approval - Material - External 28 d 07-07-22 06-08-22 39.29% 44% Submission&Approval - Material - External CHB wall & Plastering cement 06 Aug '22
CHB wall & Plastering cement
596 External CHB wall & Plastering cement - 1st 7d 07-07-22 14-07-22 100.00% 100% External CHB wall & Plastering cement - 1st Preparation & Submission 14 Jul '22
Preparation & Submission
597 External CHB wall & Plastering cement - 1st 7d 15-07-22 21-07-22 57.14% 75% External CHB wall & Plastering cement - 1st Review & Approval by Consultant 21 Jul '22
Review & Approval by Consultant
598 External CHB wall & Plastering cement - 2nd 7d 22-07-22 30-07-22 0.00% 0% External CHB wall & Plastering cement - 2nd Preparation & Submission 30 Jul '22
Preparation & Submission
599 External CHB wall & Plastering cement - 2nd 7d 31-07-22 06-08-22 0.00% 0% External CHB wall & Plastering cement - 2nd Review & Approval by Consultant 06 Aug '22
Review & Approval by Consultant
600 Submission&Approval - Material - Exterior & 28 d 07-07-22 06-08-22 39.29% 25% Submission&Approval - Material - Exterior & Interior paint 06 Aug '22
Interior paint
601 Exterior & Interior paint - 1st Preparation & 7d 07-07-22 14-07-22 100.00% 100% Exterior & Interior paint - 1st Preparation & Submission 14 Jul '22
Submission
602 Exterior & Interior paint - 1st Review & 7d 15-07-22 21-07-22 57.14% 0% Exterior & Interior paint - 1st Review & Approval by Consultant 21 Jul '22
Approval by Consultant
603 Exterior & Interior paint - 2nd Preparation & 7d 22-07-22 30-07-22 0.00% 0% Exterior & Interior paint - 2nd Preparation & Submission 30 Jul '22
Submission
604 Exterior & Interior paint - 2nd Review & 7d 31-07-22 06-08-22 0.00% 0% Exterior & Interior paint - 2nd Review & Approval by Consultant 06 Aug '22
Approval by Consultant
605 Submission&Approval - Material - Wall sand 24 d 10-07-22 05-08-22 33.33% 34% Submission&Approval - Material - Wall sand wich panel 05 Aug '22
wich panel
606 Wall sand wich panel - 1st Preparation & 15 d 10-07-22 25-07-22 53.33% 55% Wall sand wich panel - 1st Preparation & Submission 25 Jul '22
Submission
607 Wall sand wich panel - 1st Review & Approval 9d 26-07-22 05-08-22 0.00% 0% Wall sand wich panel - 1st Review & Approval by Consultant 05 Aug '22
by Consultant
608 Submission&Approval - Material - Sheet 28 d 15-07-22 14-08-22 14.29% 15% Submission&Approval - Material - Sheet shutter (high speed shutter) 14 Aug '22
shutter (high speed shutter)
609 Sheet shutter (high speed shutter) - 1st 7d 15-07-22 21-07-22 57.14% 60% Sheet shutter (high speed shutter) - 1st Preparation & Submission 21 Jul '22
Preparation & Submission
610 Sheet shutter (high speed shutter) - 1st 7d 22-07-22 30-07-22 0.00% 0% Sheet shutter (high speed shutter) - 1st Review & Approval by Consultant 30 Jul '22
Review & Approval by Consultant
611 Sheet shutter (high speed shutter) - 2nd 7d 31-07-22 06-08-22 0.00% 0% Sheet shutter (high speed shutter) - 2nd Preparation & Submission 06 Aug '22
Preparation & Submission
612 Sheet shutter (high speed shutter) - 2nd 7d 07-08-22 14-08-22 0.00% 0% Sheet shutter (high speed shutter) - 2nd Review & Approval by Consultant 14 Aug '22
Review & Approval by Consultant
613 Submission&Approval - Material - 28 d 15-07-22 14-08-22 14.29% 15% Submission&Approval - Material - Shutter,Steel & Aluminum door 14 Aug '22
Shutter,Steel & Aluminum door
614 Shutter,Steel & Aluminum door - 1st 7d 15-07-22 21-07-22 57.14% 60% Shutter,Steel & Aluminum door - 1st Preparation & Submission 21 Jul '22
Preparation & Submission
615 Shutter,Steel & Aluminum door - 1st Review 7d 22-07-22 30-07-22 0.00% 0% Shutter,Steel & Aluminum door - 1st Review & Approval by Consultant 30 Jul '22
& Approval by Consultant
616 Shutter,Steel & Aluminum door - 2nd 7d 31-07-22 06-08-22 0.00% 0% Shutter,Steel & Aluminum door - 2nd Preparation & Submission 06 Aug '22
Preparation & Submission
617 Shutter,Steel & Aluminum door - 2nd Review 7d 07-08-22 14-08-22 0.00% 0% Shutter,Steel & Aluminum door - 2nd Review & Approval by Consultant 14 Aug '22
& Approval by Consultant
618 Submission&Approval - Material - Roof 13 d 15-07-22 27-07-22 30.77% 31% Submission&Approval - Material - Roof Insulation & gal.mesh (Rock Wool) 27 Jul '22
Insulation & gal.mesh (Rock Wool)
619 Roof Insulation & gal.mesh (Rock Wool) - 1st 8d 15-07-22 22-07-22 50.00% 50% Roof Insulation & gal.mesh (Rock Wool) - 1st Preparation & Submission 22 Jul '22
Preparation & Submission
620 Roof Insulation & gal.mesh (Rock Wool) - 1st 5d 23-07-22 27-07-22 0.00% 0% Roof Insulation & gal.mesh (Rock Wool) - 1st Review & Approval by Consultant 27 Jul '22
Review & Approval by Consultant
621 Submission&Approval - Material - Siding wall 15 d 20-07-22 05-08-22 0.00% 0% Submission&Approval - Material - Siding wall sheet 05 Aug '22
sheet
622 Siding wall sheet - 1st Preparation & 8d 20-07-22 27-07-22 0.00% 0% Siding wall sheet - 1st Preparation & Submission 27 Jul '22
Submission
623 Siding wall sheet - 1st Review & Approval by 7d 30-07-22 05-08-22 0.00% 0% Siding wall sheet - 1st Review & Approval by Consultant 05 Aug '22
Consultant
624 Submission&Approval - Material - Interior wall & floor finishing,ceramic28 d tile,OA
22-07-22
floor,21-08-22
epoxy,pcv0.00%
vinyl sheet0% Submission&Approval - Material - Interior wall & floor finishing,ceramic tile,OA floor, epoxy,pcv vinyl sheet 21 Aug '22
625 Interior wall & floor finishing,ceramic tile,OA floor, epoxy,pcv vinyl sheet
7 d -22-07-22
1st Preparation
30-07-22
& Submission
0.00% 0% Interior wall & floor finishing,ceramic tile,OA floor, epoxy,pcv vinyl sheet - 1st Preparation & Submission 30 Jul '22
626 Interior wall & floor finishing,ceramic tile,OA floor, epoxy,pcv vinyl sheet
7 d - 31-07-22
1st Review &06-08-22
Approval 0.00%
by Consultant
0% Interior wall & floor finishing,ceramic tile,OA floor, epoxy,pcv vinyl sheet - 1st Review & Approval by Consultant 06 Aug '22
627 Interior wall & floor finishing,ceramic tile,OA floor, epoxy,pcv vinyl sheet
7 d -07-08-22
2nd Preparation
14-08-22
& Submission
0.00% 0% Interior wall & floor finishing,ceramic tile,OA floor, epoxy,pcv vinyl sheet - 2nd Preparation & Submission 14 Aug '22
628 Interior wall & floor finishing,ceramic tile,OA floor, epoxy,pcv vinyl sheet
7 d -15-08-22
2nd Review 21-08-22
& Approval0.00%
by Consultant
0% Interior wall & floor finishing,ceramic tile,OA floor, epoxy,pcv vinyl sheet - 2nd Review & Approval by Consultant 21 Aug '22
629 Submission&Approval - Material - Water proof 28 d 22-07-22 21-08-22 0.00% 0% Submission&Approval - Material - Water proof for water tank,toilet,kitchen,roof slab 21 Aug '22
for water tank,toilet,kitchen,roof slab
630 Water proof for water tank,toilet,kitchen,roof slab - 1st Preparation7&dSubmission
22-07-22 30-07-22 0.00% 0% Water proof for water tank,toilet,kitchen,roof slab - 1st Preparation & Submission 30 Jul '22
631 Water proof for water tank,toilet,kitchen,roof slab - 1st Review & Approval
7d 31-07-22
by Consultant
06-08-22 0.00% 0% Water proof for water tank,toilet,kitchen,roof slab - 1st Review & Approval by Consultant 06 Aug '22
632 Water proof for water tank,toilet,kitchen,roof slab - 2nd Preparation7 d& Submission
07-08-22 14-08-22 0.00% 0% Water proof for water tank,toilet,kitchen,roof slab - 2nd Preparation & Submission 14 Aug '22
633 Water proof for water tank,toilet,kitchen,roof slab - 2nd Review & Approval
7d 15-08-22
by Consultant
21-08-22 0.00% 0% Water proof for water tank,toilet,kitchen,roof slab - 2nd Review & Approval by Consultant 21 Aug '22
634 Submission&Approval - Material - Aluminum window,composite cladding 10 d 22-07-22
& Insulated02-08-22
glass system
0.00% 0% Submission&Approval - Material - Aluminum window,composite cladding & Insulated glass system 02 Aug '22
635 Aluminum window,composite cladding & Insulated glass system - 1st 5 dPreparation
22-07-22& Submission
26-07-22 0.00% 0% Aluminum window,composite cladding & Insulated glass system - 1st Preparation & Submission 26 Jul '22

7 OF 16
PROJECT : Relief Project
MASTER SCHEDULE (REV0.02) Dated 18Jul22
ID Task Name AdditionalTask Duration Start Finish % Plan %
task added Complete
date Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Ap
636 Aluminum window,composite cladding & Insulated glass system - 1st
5 dReview
27-07-22
& Approval
02-08-22
by Consultant
0.00% 0% Aluminum window,composite cladding & Insulated glass system - 1st Review & Approval
18 Jul,by
'22Consultant 02 Aug '22
637 Submission&Approval - Material - Toilet 28 d 31-07-22 28-08-22 0.00% 25% Submission&Approval - Material - Toilet partition 28 Aug '22
partition
638 Toilet partition - 1st Preparation & 7d 31-07-22 06-08-22 0.00% 100% Toilet partition - 1st Preparation & Submission 06 Aug '22
Submission
639 Toilet partition - 1st Review & Approval by 7d 07-08-22 14-08-22 0.00% 0% Toilet partition - 1st Review & Approval by Consultant 14 Aug '22
Consultant
640 Toilet partition - 2nd Preparation & 7d 15-08-22 21-08-22 0.00% 0% Toilet partition - 2nd Preparation & Submission 21 Aug '22
Submission
641 Toilet partition - 2nd Review & Approval by 7d 22-08-22 28-08-22 0.00% 0% Toilet partition - 2nd Review & Approval by Consultant 28 Aug '22
Consultant
642 Submission&Approval - Material - Key & lock 19 d 01-08-22 20-08-22 0.00% 0% Submission&Approval - Material - Key & lock set 20 Aug '22
set
643 Key & lock set - 1st Preparation & Submission 7d 01-08-22 07-08-22 0.00% 0% Key & lock set - 1st Preparation & Submission 07 Aug '22
644 Key & lock set - 1st Review & Approval by 12 d 08-08-22 20-08-22 0.00% 0% Key & lock set - 1st Review & Approval by Consultant 20 Aug '22
Consultant
645 Submission&Approval - Material - Dry wall & 28 d 07-08-22 04-09-22 0.00% 0% Submission&Approval - Material - Dry wall & Ceiling 04 Sep '22
Ceiling
646 Dry wall & Ceiling - 1st Preparation & 7d 07-08-22 14-08-22 0.00% 0% Dry wall & Ceiling - 1st Preparation & Submission 14 Aug '22
Submission
647 Dry wall & Ceiling - 1st Review & Approval by 7d 15-08-22 21-08-22 0.00% 0% Dry wall & Ceiling - 1st Review & Approval by Consultant 21 Aug '22
Consultant
648 Dry wall & Ceiling - 2nd Preparation & 7d 22-08-22 28-08-22 0.00% 0% Dry wall & Ceiling - 2nd Preparation & Submission 28 Aug '22
Submission
649 Dry wall & Ceiling - 2nd Review & Approval 7d 29-08-22 04-09-22 0.00% 0% Dry wall & Ceiling - 2nd Review & Approval by Consultant 04 Sep '22
by Consultant
650 Submission&Approval - Material - Floor 28 d 19-08-22 15-09-22 0.00% 0% Submission&Approval - Material - Floor hardener 15 Sep '22
hardener
651 Floor hardener - 1st Preparation & Submission 7d 19-08-22 25-08-22 0.00% 0% Floor hardener - 1st Preparation & Submission 25 Aug '22
652 Floor hardener - 1st Review & Approval by 7d 26-08-22 01-09-22 0.00% 0% Floor hardener - 1st Review & Approval by Consultant 01 Sep '22
Consultant
653 Floor hardener - 2nd Preparation & 7d 02-09-22 08-09-22 0.00% 0% Floor hardener - 2nd Preparation & Submission 08 Sep '22
Submission
654 Floor hardener - 2nd Review & Approval by 7d 09-09-22 15-09-22 0.00% 0% Floor hardener - 2nd Review & Approval by Consultant 15 Sep '22
Consultant
655 Procurement 211 d 07-07-22 13-02-23 5.21% 5% Procurement 13 Feb '23
656 Procurement - Material - Fireproof paint, OP 40 d 07-07-22 19-08-22 27.50% 29% Procurement - Material - Fireproof paint, OP paint for roof/siding wall structure 19 Aug '22
paint for roof/siding wall structure
657 Procurement - Fireproof paint, OP paint for roof/siding wall structure
10 -dSelect
07-07-22
Vendor &17-07-22
Issued P.O.
100.00% 100% Procurement - Fireproof paint, OP paint for roof/siding wall structure - Select Vendor & Issued P.O. 17 Jul '22
658 Procurement - Fireproof paint, OP paint for 30 d 18-07-22 19-08-22 3.33% 5% Procurement - Fireproof paint, OP paint for roof/siding wall structure - Lead time 19 Aug '22
roof/siding wall structure - Lead time
659 Procurement - Fireproof paint, OP paint for 0d 19-08-22 19-08-22 0.00% 0% Procurement - Fireproof paint, OP paint for roof/siding wall structure - Mat on site 19 Aug '22
roof/siding wall structure - Mat on site
660 Procurement - Material - Polypropylane for 30 d 07-07-22 08-08-22 36.67% 40% Procurement - Material - Polypropylane for process waste 08 Aug '22
process waste
661 Procurement - Polypropylane for process 10 d 07-07-22 17-07-22 100.00% 100% Procurement - Polypropylane for process waste - Select Vendor & Issued P.O. 17 Jul '22
waste - Select Vendor & Issued P.O.
662 Procurement - Polypropylane for process 20 d 18-07-22 08-08-22 5.00% 10% Procurement - Polypropylane for process waste - Lead time 08 Aug '22
waste - Lead time
663 Procurement - Polypropylane for process 0d 08-08-22 08-08-22 0.00% 0% Procurement - Polypropylane for process waste - Mat on site 08 Aug '22
waste - Mat on site
664 Procurement - Material - Metal roof sheet 57 d 08-07-22 06-09-22 17.54% 18% Procurement - Material - Metal roof sheet 06 Sep '22
665 Procurement - Metal roof sheet - Select 1d 08-07-22 08-07-22 100.00% 100% Procurement - Metal roof sheet - Select Vendor & Issued P.O. 08 Jul '22
Vendor & Issued P.O.
666 Procurement - Metal roof sheet - Lead time 56 d 09-07-22 06-09-22 16.07% 17% Procurement - Metal roof sheet - Lead time 06 Sep '22
667 Procurement - Metal roof sheet - Mat on site 0d 06-09-22 06-09-22 0.00% 0% Procurement - Metal roof sheet - Mat on site 06 Sep '22
668 Procurement - Material - Roof Steel Structure 36 d 11-07-22 19-08-22 19.44% 21% Procurement - Material - Roof Steel Structure 19 Aug '22

669 Procurement - Roof Steel Structure - Select 10 d 11-07-22 21-07-22 70.00% 75% Procurement - Roof Steel Structure - Select Vendor & Issued P.O. 21 Jul '22
Vendor & Issued P.O.
670 Procurement - Roof Steel Structure - Lead 26 d 22-07-22 19-08-22 0.00% 0% Procurement - Roof Steel Structure - Lead time 19 Aug '22
time
671 Procurement - Roof Steel Structure - Mat on 0d 19-08-22 19-08-22 0.00% 0% Procurement - Roof Steel Structure - Mat on site 19 Aug '22
site
672 Procurement - Material - PVC & HDPE for 20 d 15-07-22 05-08-22 20.00% 25% Procurement - Material - PVC & HDPE for sanitary waste, soil, vent 05 Aug '22
sanitary waste, soil, vent
673 Procurement - PVC & HDPE for sanitary waste, soil, vent - Select Vendor
10 d &15-07-22
Issued P.O.24-07-22 40.00% 50% Procurement - PVC & HDPE for sanitary waste, soil, vent - Select Vendor & Issued P.O. 24 Jul '22
674 Procurement - PVC & HDPE for sanitary 10 d 25-07-22 05-08-22 0.00% 0% Procurement - PVC & HDPE for sanitary waste, soil, vent - Lead time 05 Aug '22
waste, soil, vent - Lead time
675 Procurement - PVC & HDPE for sanitary 0d 05-08-22 05-08-22 0.00% 0% Procurement - PVC & HDPE for sanitary waste, soil, vent - Mat on site 05 Aug '22
waste, soil, vent - Mat on site
676 Procurement - Material - Formwork for 1M & 27 d 21-07-22 19-08-22 0.00% 0% Procurement - Material - Formwork for 1M & 2F, posttension slab 19 Aug '22
2F, posttension slab
677 Procurement - Formwork for 1M & 2F, 10 d 21-07-22 01-08-22 0.00% 0% Procurement - Formwork for 1M & 2F, posttension slab - Select Vendor & Issued P.O. 01 Aug '22
posttension slab - Select Vendor & Issued
678 P.O.
Procurement - Formwork for 1M & 2F, 17 d 02-08-22 19-08-22 0.00% 0% Procurement - Formwork for 1M & 2F, posttension slab - Lead time 19 Aug '22
posttension slab - Lead time
679 Procurement - Formwork for 1M & 2F, 0d 19-08-22 19-08-22 0.00% 0% Procurement - Formwork for 1M & 2F, posttension slab - Mat on site 19 Aug '22
posttension slab - Mat on site
680 Procurement - Material - Posttension slab 20 d 25-07-22 16-08-22 0.00% 0% Procurement - Material - Posttension slab 16 Aug '22
681 Procurement - Posttension slab - Select 10 d 25-07-22 05-08-22 0.00% 0% Procurement - Posttension slab - Select Vendor & Issued P.O. 05 Aug '22
Vendor & Issued P.O.
682 Procurement - Posttension slab - Lead time 10 d 06-08-22 16-08-22 0.00% 0% Procurement - Posttension slab - Lead time 16 Aug '22
683 Procurement - Posttension slab - Mat on site 0d 16-08-22 16-08-22 0.00% 0% Procurement - Posttension slab - Mat on site 16 Aug '22
684 Procurement - Material - Roof Insulation & 38 d 30-07-22 06-09-22 0.00% 20% Procurement - Material - Roof Insulation & gal.mesh (rock wool) 06 Sep '22
gal.mesh (rock wool)
685 Procurement - Roof Insulation & gal.mesh 10 d 30-07-22 08-08-22 0.00% 75% Procurement - Roof Insulation & gal.mesh (rock wool) - Select Vendor & Issued P.O. 08 Aug '22
(rock wool) - Select Vendor & Issued P.O.
686 Procurement - Roof Insulation & gal.mesh 28 d 09-08-22 06-09-22 0.00% 0% Procurement - Roof Insulation & gal.mesh (rock wool) - Lead time 06 Sep '22
(rock wool) - Lead time
687 Procurement - Roof Insulation & gal.mesh 0d 06-09-22 06-09-22 0.00% 0% Procurement - Roof Insulation & gal.mesh (rock wool) - Mat on site 06 Sep '22
(rock wool) - Mat on site
688 Procurement - Material - Dock leveler 190 d 31-07-22 13-02-23 0.00% 0% Procurement - Material - Dock leveler 13 Feb '23
689 Procurement - Dock leveler - Select Vendor & 10 d 31-07-22 09-08-22 0.00% 0% Procurement - Dock leveler - Select Vendor & Issued P.O. 09 Aug '22
Issued P.O.
690 Procurement - Dock leveler - Lead time 180 d 10-08-22 13-02-23 0.00% 0% Procurement - Dock leveler - Lead time 13 Feb '23
691 Procurement - Dock leveler - Mat on site 0d 13-02-23 13-02-23 0.00% 0% Procurement - Dock leveler - Mat on site 13 Feb '23
692 Procurement - Material - Aluminum window,composite cladding &106Insulated
d 03-08-22
glass system
19-11-22 0.00% 1% Procurement - Material - Aluminum window,composite cladding & Insulated glass system 19 Nov '22
693 Procurement - Aluminum window,composite cladding & Insulated glass
5 d system
03-08-22
- Select
07-08-22
Vendor &0.00%
Issued P.O.25% Procurement - Aluminum window,composite cladding & Insulated glass system - Select Vendor & Issued P.O. 07 Aug '22
694 Procurement - Aluminum window,composite cladding & Insulated101
glass
d system
08-08-22
- Lead19-11-22
time 0.00% 0% Procurement - Aluminum window,composite cladding & Insulated glass system - Lead time 19 Nov '22
695 Procurement - Aluminum window,composite cladding & Insulated glass
0 d system
19-11-22
- Mat on
19-11-22
site 0.00% 0% Procurement - Aluminum window,composite cladding & Insulated glass system - Mat on site 19 Nov '22
696 Procurement - Material - Siding wall sheet 57 d 06-08-22 02-10-22 0.00% 0% Procurement - Material - Siding wall sheet 02 Oct '22
697 Procurement - Siding wall sheet - Select 10 d 06-08-22 16-08-22 0.00% 0% Procurement - Siding wall sheet - Select Vendor & Issued P.O. 16 Aug '22
Vendor & Issued P.O.
698 Procurement - Siding wall sheet - Lead time 47 d 17-08-22 02-10-22 0.00% 0% Procurement - Siding wall sheet - Lead time 02 Oct '22
699 Procurement - Siding wall sheet - Mat on site 0d 02-10-22 02-10-22 0.00% 0% Procurement - Siding wall sheet - Mat on site 02 Oct '22

700 Procurement - Material - Wall sand wich panel 82 d 06-08-22 29-10-22 0.00% 0% Procurement - Material - Wall sand wich panel 29 Oct '22

701 Procurement - Wall sand wich panel - Select 10 d 06-08-22 16-08-22 0.00% 0% Procurement - Wall sand wich panel - Select Vendor & Issued P.O. 16 Aug '22
Vendor & Issued P.O.
702 Procurement - Wall sand wich panel - Lead 72 d 17-08-22 29-10-22 0.00% 0% Procurement - Wall sand wich panel - Lead time 29 Oct '22
time
703 Procurement - Wall sand wich panel - Mat on 0d 29-10-22 29-10-22 0.00% 0% Procurement - Wall sand wich panel - Mat on site 29 Oct '22
site
704 Procurement - Material - External CHB wall & 55 d 07-08-22 01-10-22 0.00% 0% Procurement - Material - External CHB wall & plastering cement 01 Oct '22
plastering cement
705 Procurement - External CHB wall & plastering 10 d 07-08-22 17-08-22 0.00% 0% Procurement - External CHB wall & plastering cement - Select Vendor & Issued P.O. 17 Aug '22
cement - Select Vendor & Issued P.O.
706 Procurement - External CHB wall & plastering 45 d 18-08-22 01-10-22 0.00% 0% Procurement - External CHB wall & plastering cement - Lead time 01 Oct '22
cement - Lead time
707 Procurement - External CHB wall & plastering 0d 01-10-22 01-10-22 0.00% 0% Procurement - External CHB wall & plastering cement - Mat on site 01 Oct '22
cement - Mat on site
708 Procurement - Material - Exterior & Interior 55 d 07-08-22 01-10-22 0.00% 0% Procurement - Material - Exterior & Interior paint - Select Vendor & Issued P.O. 01 Oct '22
paint - Select Vendor & Issued P.O.
709 Procurement - Exterior & Interior paint - 10 d 07-08-22 17-08-22 0.00% 0% Procurement - Exterior & Interior paint - Select Vendor & Issued P.O. 17 Aug '22
Select Vendor & Issued P.O.
710 Procurement - Exterior & Interior paint - Lead 45 d 18-08-22 01-10-22 0.00% 0% Procurement - Exterior & Interior paint - Lead time 01 Oct '22
time
711 Procurement - Exterior & Interior paint - Mat 0d 01-10-22 01-10-22 0.00% 0% Procurement - Exterior & Interior paint - Mat on site 01 Oct '22
on site
712 Procurement - Material - Sheet shutter (high 130 d 15-08-22 25-12-22 0.00% 0% Procurement - Material - Sheet shutter (high speed shutter) 25 Dec '22
speed shutter)
713 Procurement - Sheet shutter (high speed 10 d 15-08-22 24-08-22 0.00% 0% Procurement - Sheet shutter (high speed shutter) - Select Vendor & Issued P.O. 24 Aug '22
shutter) - Select Vendor & Issued P.O.
714 Procurement - Sheet shutter (high speed 120 d 25-08-22 25-12-22 0.00% 0% Procurement - Sheet shutter (high speed shutter) - Lead time 25 Dec '22
shutter) - Lead time
715 Procurement - Sheet shutter (high speed 0d 25-12-22 25-12-22 0.00% 0% Procurement - Sheet shutter (high speed shutter) - Mat on site 25 Dec '22
shutter) - Mat on site
716 Procurement - Material - Shutter,Steel & 60 d 15-08-22 14-10-22 0.00% 0% Procurement - Material - Shutter,Steel & Aluminum door 14 Oct '22
Aluminum door
717 Procurement - Shutter,Steel & Aluminum 10 d 15-08-22 24-08-22 0.00% 0% Procurement - Shutter,Steel & Aluminum door - Select Vendor & Issued P.O. 24 Aug '22
door - Select Vendor & Issued P.O.
718 Procurement - Shutter,Steel & Aluminum 50 d 25-08-22 14-10-22 0.00% 0% Procurement - Shutter,Steel & Aluminum door - Lead time 14 Oct '22
door - Lead time
719 Procurement - Shutter,Steel & Aluminum 0d 14-10-22 14-10-22 0.00% 0% Procurement - Shutter,Steel & Aluminum door - Mat on site 14 Oct '22
door - Mat on site
720 Procurement - Material - Key & lock set 59 d 21-08-22 19-10-22 0.00% 0% Procurement - Material - Key & lock set 19 Oct '22
721 Procurement - Key & lock set - Select Vendor 10 d 21-08-22 30-08-22 0.00% 0% Procurement - Key & lock set - Select Vendor & Issued P.O. 30 Aug '22
& Issued P.O.
722 Procurement - Key & lock set - Lead time 49 d 31-08-22 19-10-22 0.00% 0% Procurement - Key & lock set - Lead time 19 Oct '22
723 Procurement - Key & lock set - Mat on site 0d 19-10-22 19-10-22 0.00% 0% Procurement - Key & lock set - Mat on site 19 Oct '22
724 Procurement - Material - Interior wall & floor finishing ceramic tile,OA70 dfloor,
22-08-22
epoxy,pcv 01-11-22
vinyl sheet
0.00% 0% Procurement - Material - Interior wall & floor finishing ceramic tile,OA floor, epoxy,pcv vinyl sheet 01 Nov '22
725 Procurement - Interior wall & floor finishing ceramic tile,OA floor, epoxy,pcv
10 d 22-08-22
vinyl sheet
31-08-22
- Select Vendor
0.00% & Issued
0% P.O. Procurement - Interior wall & floor finishing ceramic tile,OA floor, epoxy,pcv vinyl sheet - Select Vendor & Issued P.O. 31 Aug '22
726 Procurement - Interior wall & floor finishing ceramic tile,OA floor, epoxy,pcv
60 d 01-09-22
vinyl sheet
01-11-22
- Lead time
0.00% 0% Procurement - Interior wall & floor finishing ceramic tile,OA floor, epoxy,pcv vinyl sheet - Lead time 01 Nov '22

8 OF 16
PROJECT : Relief Project
MASTER SCHEDULE (REV0.02) Dated 18Jul22
ID Task Name AdditionalTask Duration Start Finish % Plan %
task added Complete
date Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Ap
727 Procurement - Interior wall & floor finishing ceramic tile,OA floor, epoxy,pcv
0d 01-11-22
vinyl sheet
01-11-22
- Mat on site
0.00% 0% 18 Jul, '22 Procurement - Interior wall & floor finishing ceramic tile,OA floor, epoxy,pcv vinyl sheet - Mat on site 01 Nov '22
728 Procurement - Material - Water proof for 40 d 22-08-22 30-09-22 0.00% 13% Procurement - Material - Water proof for water tank,toilet,kitchen,roof slab 30 Sep '22
water tank,toilet,kitchen,roof slab
729 Procurement - Water proof for water tank,toilet,kitchen,roof slab -10
Select
d 22-08-22
Vendor & Issued
31-08-22
P.O. 0.00% 50% Procurement - Water proof for water tank,toilet,kitchen,roof slab - Select Vendor & Issued P.O. 31 Aug '22
730 Procurement - Water proof for water 30 d 01-09-22 30-09-22 0.00% 0% Procurement - Water proof for water tank,toilet,kitchen,roof slab - Lead time 30 Sep '22
tank,toilet,kitchen,roof slab - Lead time
731 Procurement - Water proof for water 0d 30-09-22 30-09-22 0.00% 0% Procurement - Water proof for water tank,toilet,kitchen,roof slab - Mat on site 30 Sep '22
tank,toilet,kitchen,roof slab - Mat on site
732 Procurement - Material - Toilet partition 70 d 29-08-22 08-11-22 0.00% 0% Procurement - Material - Toilet partition 08 Nov '22
733 Procurement - Toilet partition - Select 10 d 29-08-22 07-09-22 0.00% 0% Procurement - Toilet partition - Select Vendor & Issued P.O. 07 Sep '22
Vendor & Issued P.O.
734 Procurement - Toilet partition - Lead time 60 d 08-09-22 08-11-22 0.00% 0% Procurement - Toilet partition - Lead time 08 Nov '22
735 Procurement - Toilet partition - Mat on site 0d 08-11-22 08-11-22 0.00% 0% Procurement - Toilet partition - Mat on site 08 Nov '22
736 Procurement - Material - Dry wall & Ceiling 50 d 05-09-22 26-10-22 0.00% 0% Procurement - Material - Dry wall & Ceiling 26 Oct '22
737 Procurement - Dry wall & Ceiling - Select 10 d 05-09-22 14-09-22 0.00% 0% Procurement - Dry wall & Ceiling - Select Vendor & Issued P.O. 14 Sep '22
Vendor & Issued P.O.
738 Procurement - Dry wall & Ceiling - Lead time 40 d 15-09-22 26-10-22 0.00% 0% Procurement - Dry wall & Ceiling - Lead time 26 Oct '22
739 Procurement - Dry wall & Ceiling - Mat on 0d 26-10-22 26-10-22 0.00% 0% Procurement - Dry wall & Ceiling - Mat on site 26 Oct '22
site
740 Procurement - Material - Floor hardener 20 d 16-09-22 05-10-22 0.00% 0% Procurement - Material - Floor hardener 05 Oct '22
741 Procurement - Floor hardener - Select 10 d 16-09-22 25-09-22 0.00% 0% Procurement - Floor hardener - Select Vendor & Issued P.O. 25 Sep '22
Vendor & Issued P.O.
742 Procurement - Floor hardener - Lead time 10 d 26-09-22 05-10-22 0.00% 0% Procurement - Floor hardener - Lead time 05 Oct '22
743 Procurement - Floor hardener - Mat on site 0d 05-10-22 05-10-22 0.00% 0% Procurement - Floor hardener - Mat on site 05 Oct '22
744 Construction 339 d 15-06-22 08-06-23 10.25% 3% Construction
745 Main Factory 326 d 15-06-22 26-05-23 10.25% 4% Main Factory
746 Main Factory - Structural Work 241 d 15-06-22 21-02-23 13.69% 6% Main Factory - Structural Work 21 Feb '23
747 Main Factory - Structural Work - Zone A 225 d 15-06-22 05-02-23 14.67% 7% Main Factory - Structural Work - Zone A 05 Feb '23

748 Main Factory - Structural Work - 198 d 15-06-22 09-01-23 17.37% 10% Main Factory - Structural Work - Zone A1 09 Jan '23
Zone A1
749 Main Factory - Substructure- Zone 90 d 15-06-22 16-09-22 40.24% 34% Main Factory - Substructure- Zone A1 16 Sep '22
A1
750 Zone A1 - Pile Cut-off Level 21 d 15-06-22 05-07-22 100.00% 100% Zone A1 - Pile Cut-off Level 05 Jul '22
751 Zone A1.2 - Pile Cut-off Level 7d 15-06-22 21-06-22 100.00% 100% Zone A1.2 - Pile Cut-off Level 21 Jun '22

752 Zone A1.1 - Pile Cut-off Level 7d 22-06-22 28-06-22 100.00% 100% Zone A1.1 - Pile Cut-off Level 28 Jun '22

753 Zone A1.3 - Pile Cut-off Level 7d 29-06-22 05-07-22 100.00% 100% Zone A1.3 - Pile Cut-off Level 05 Jul '22

754 Zone A1 - Soil backfill under 27 d 22-06-22 19-07-22 96.30% 97% Zone A1 - Soil backfill under slab 19 Jul '22
slab
755 Zone A1.2 - Soil backfill under 9d 22-06-22 30-06-22 100.00% 100% Zone A1.2 - Soil backfill under slab 30 Jun '22
slab
756 Zone A1.1 - Soil backfill under 9d 01-07-22 09-07-22 100.00% 100% Zone A1.1 - Soil backfill under slab 09 Jul '22
slab
757 Zone A1.3 - Soil backfill under 9d 10-07-22 19-07-22 88.89% 90% Zone A1.3 - Soil backfill under slab 19 Jul '22
slab
758 Zone A1 - Foundation and Pier 41 d 09-07-22 22-08-22 27.27% 0% Zone A1 - Foundation and Pier 22 Aug '22

759 Zone A1.2 - Foundation and 19 d 09-07-22 30-07-22 81.82% 0% Zone A1.2 - Foundation and Pier 30 Jul '22
Pier
760 Excavation 7d 09-07-22 16-07-22 #ERROR 0% Excavation 16 Jul '22
761 Check Pile deviation pile 27-07-22 7d 11-07-22 18-07-22 #ERROR 0% Check Pile deviation 18 Jul '22
deviation
issue
762 Waiting Information for pile 27-07-22 4d 11-07-22 15-07-22 #ERROR 0% Waiting Information for Reinforcement 15 Jul '22
Reinforcement deviation
issue
763 Make Shop Drawing pile 27-07-22 2d 16-07-22 17-07-22 #ERROR 0% Make Shop Drawing 17 Jul '22
deviation
issue
764 Approve Shop Drawing pile 27-07-22 1d 18-07-22 18-07-22 #ERROR 0% Approve Shop Drawing 18 Jul '22
deviation
issue
765 Rebar,Form,Concrete 10 d 19-07-22 30-07-22 #ERROR 0% Rebar,Form,Concrete 30 Jul '22
766 Zone A1.1 - Foundation and 11 d 31-07-22 10-08-22 0.00% 0% Zone A1.1 - Foundation and Pier 10 Aug '22
Pier
767 Zone A1.3 - Foundation and 11 d 11-08-22 22-08-22 0.00% 0% Zone A1.3 - Foundation and Pier 22 Aug '22
Pier
768 Zone A1 - Pca.Column, Core 36 d 11-08-22 16-09-22 0.00% 0% Zone A1 - Pca.Column, Core wall, Gr.Beam 16 Sep '22
wall, Gr.Beam
769 Zone A1.2 - Pca.Column, Core 12 d 11-08-22 23-08-22 0.00% 0% Zone A1.2 - Pca.Column, Core wall, Gr.Beam 23 Aug '22
wall, Gr.Beam
770 Zone A1.1 - Pca.Column, Core 12 d 24-08-22 04-09-22 0.00% 0% Zone A1.1 - Pca.Column, Core wall, Gr.Beam 04 Sep '22
wall, Gr.Beam
771 Zone A1.3 - Pca.Column, Core 12 d 05-09-22 16-09-22 0.00% 0% Zone A1.3 - Pca.Column, Core wall, Gr.Beam 16 Sep '22
wall, Gr.Beam
772 Main Factory - Underground 32 d 26-08-22 26-09-22 0.00% 0% Main Factory - Underground Piping Work - Zone A1 26 Sep '22
Piping Work - Zone A1
773 Zone A1 - U/G Toilet x 3 Rm. 32 d 26-08-22 26-09-22 0.00% 0% Zone A1 - U/G Toilet x 3 Rm. 26 Sep '22
774 Zone A1 - U/G Toilet x 3 Rm. - 6d 26-08-22 31-08-22 0.00% 0% Zone A1 - U/G Toilet x 3 Rm. - Excavation 31 Aug '22
Excavation
775 Zone A1 - U/G Toilet x 3 Rm. - 6d 28-08-22 02-09-22 0.00% 0% Zone A1 - U/G Toilet x 3 Rm. - Sand Compacted 02 Sep '22
Sand Compacted
776 Zone A1 - U/G Toilet x 3 Rm. - 20 d 30-08-22 18-09-22 0.00% 0% Zone A1 - U/G Toilet x 3 Rm. - Install Pipes 18 Sep '22
Install Pipes
777 Zone A1 - U/G Toilet x 3 Rm. - 6d 19-09-22 24-09-22 0.00% 0% Zone A1 - U/G Toilet x 3 Rm. - Pressure Test 24 Sep '22
Pressure Test
778 Zone A1 - U/G Toilet x 3 Rm. - 2d 25-09-22 26-09-22 0.00% 0% Zone A1 - U/G Toilet x 3 Rm. - Inspection (Kajima & CM) 26 Sep '22
Inspection (Kajima & CM)
779 Zone A1 - U/G Pipe 16 d 01-09-22 16-09-22 0.00% 0% Zone A1 - U/G Pipe 16 Sep '22
780 Zone A1 - U/G Pipe - 7d 01-09-22 07-09-22 0.00% 0% Zone A1 - U/G Pipe - Excavation 07 Sep '22
Excavation
781 Zone A1 - U/G Pipe - Sand 7d 02-09-22 08-09-22 0.00% 0% Zone A1 - U/G Pipe - Sand Compacted 08 Sep '22
Compacted
782 Zone A1 - U/G Pipe - Install 10 d 03-09-22 12-09-22 0.00% 0% Zone A1 - U/G Pipe - Install Pipes 12 Sep '22
Pipes
783 Zone A1 - U/G Pipe - Pressure 10 d 05-09-22 14-09-22 0.00% 0% Zone A1 - U/G Pipe - Pressure Test 14 Sep '22
Test
784 Zone A1 - U/G Pipe - 2d 15-09-22 16-09-22 0.00% 0% Zone A1 - U/G Pipe - Inspection (Kajima & CM) 16 Sep '22
Inspection (Kajima & CM)
785 Main Factory - Roof Work - Zone 88 d 28-08-22 25-11-22 0.00% 0% Main Factory - Roof Work - Zone A1 25 Nov '22
A1
786 Zone A1 - Roof Steel Structure 34 d 28-08-22 30-09-22 0.00% 0% Zone A1 - Roof Steel Structure 30 Sep '22

787 Zone A1.1&1.2 - Roof Steel 17 d 28-08-22 13-09-22 0.00% 0% Zone A1.1&1.2 - Roof Steel Structure 13 Sep '22
Structure
788 Zone A1.2&1.3 - Roof Steel 17 d 14-09-22 30-09-22 0.00% 0% Zone A1.2&1.3 - Roof Steel Structure 30 Sep '22
Structure
789 Zone A1 - Roof Matel Sheet 70 d 15-09-22 25-11-22 0.00% 0% Zone A1 - Roof Matel Sheet 25 Nov '22
790 Zone A1.1&1.2 - Roof Matel 35 d 15-09-22 20-10-22 0.00% 0% Zone A1.1&1.2 - Roof Matel Sheet 20 Oct '22
Sheet
791 Zone A1.2&1.3 - Roof Matel 35 d 21-10-22 25-11-22 0.00% 0% Zone A1.2&1.3 - Roof Matel Sheet 25 Nov '22
Sheet
792 Main Factory - Post Tension Slab - 92 d 03-10-22 09-01-23 0.00% 0% Main Factory - Post Tension Slab - Zone A1 09 Jan '23
Zone A1
793 Zone A1 - PT Slab Floor 1 69 d 03-10-22 13-12-22 0.00% 0% Zone A1 - PT Slab Floor 1 13 Dec '22
794 Zone A1.2 - PT Slab Floor 1 23 d 03-10-22 27-10-22 0.00% 0% Zone A1.2 - PT Slab Floor 1 27 Oct '22
795 Zone A1.1 - PT Slab Floor 1 23 d 28-10-22 19-11-22 0.00% 0% Zone A1.1 - PT Slab Floor 1 19 Nov '22
796 Zone A1.3 - PT Slab Floor 1 23 d 20-11-22 13-12-22 0.00% 0% Zone A1.3 - PT Slab Floor 1 13 Dec '22
797 Zone A1 - PT Slab Floor 2 69 d 28-10-22 09-01-23 0.00% 0% Zone A1 - PT Slab Floor 2 09 Jan '23
798 Zone A1.2 - PT Slab Floor 2 23 d 28-10-22 19-11-22 0.00% 0% Zone A1.2 - PT Slab Floor 2 19 Nov '22
799 Zone A1.1 - PT Slab Floor 2 23 d 20-11-22 13-12-22 0.00% 0% Zone A1.1 - PT Slab Floor 2 13 Dec '22
800 Zone A1.3 - PT Slab Floor 2 23 d 14-12-22 09-01-23 0.00% 0% Zone A1.3 - PT Slab Floor 2 09 Jan '23
801 Main Factory - Structural Work - 187 d 29-06-22 12-01-23 10.16% 8% Main Factory - Structural Work - Zone A2 12 Jan '23
Zone A2
802 Main Factory - Substructure- Zone 82 d 29-06-22 22-09-22 23.17% 24% Main Factory - Substructure- Zone A2 22 Sep '22
A2
803 Zone A2 - Pile Cut-off Level 21 d 29-06-22 20-07-22 90.48% 91% Zone A2 - Pile Cut-off Level 20 Jul '22
804 Zone A2.2 - Pile Cut-off Level 7d 29-06-22 05-07-22 100.00% 100% Zone A2.2 - Pile Cut-off Level 05 Jul '22

805 Zone A2.1 - Pile Cut-off Level 7d 06-07-22 12-07-22 100.00% 100% Zone A2.1 - Pile Cut-off Level 12 Jul '22

806 Zone A2.3 - Pile Cut-off Level 7d 14-07-22 20-07-22 71.43% 72% Zone A2.3 - Pile Cut-off Level 20 Jul '22

807 Zone A2 - Soil backfill under 27 d 06-07-22 04-08-22 44.44% 45% Zone A2 - Soil backfill under slab 04 Aug '22
slab
808 Zone A2.2 - Soil backfill under 9d 06-07-22 15-07-22 100.00% 100% Zone A2.2 - Soil backfill under slab 15 Jul '22
slab
809 Zone A2.1 - Soil backfill under 9d 16-07-22 24-07-22 33.33% 35% Zone A2.1 - Soil backfill under slab 24 Jul '22
slab
810 Zone A2.3 - Soil backfill under 9d 25-07-22 04-08-22 0.00% 0% Zone A2.3 - Soil backfill under slab 04 Aug '22
slab
811 Zone A2 - Foundation and Pier 45 d 16-07-22 01-09-22 6.67% 0% Zone A2 - Foundation and Pier 01 Sep '22

812 Zone A2.2 - Foundation and 15 d 16-07-22 01-08-22 20.00% 0% Zone A2.2 - Foundation and Pier 01 Aug '22
Pier
813 Zone A2.1 - Foundation and 15 d 02-08-22 17-08-22 0.00% 0% Zone A2.1 - Foundation and Pier 17 Aug '22
Pier
814 Zone A2.3 - Foundation and 15 d 18-08-22 01-09-22 0.00% 0% Zone A2.3 - Foundation and Pier 01 Sep '22
Pier
815 Zone A2 - PCa.Column, Core 36 d 18-08-22 22-09-22 0.00% 0% Zone A2 - PCa.Column, Core wall, Gr.Beam 22 Sep '22
wall, Gr.Beam

9 OF 16
PROJECT : Relief Project
MASTER SCHEDULE (REV0.02) Dated 18Jul22
ID Task Name AdditionalTask Duration Start Finish % Plan %
task added Complete
date Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Ap
816 Zone A2.2 - Pca.Column, Core 12 d 18-08-22 29-08-22 0.00% 0% 18 Jul, '22 Zone A2.2 - Pca.Column, Core wall, Gr.Beam 29 Aug '22
wall, Gr.Beam
817 Zone A2.1 - Pca.Column, Core 12 d 30-08-22 10-09-22 0.00% 0% Zone A2.1 - Pca.Column, Core wall, Gr.Beam 10 Sep '22
wall, Gr.Beam
818 Zone A2.3 - Pca.Column, Core 12 d 11-09-22 22-09-22 0.00% 0% Zone A2.3 - Pca.Column, Core wall, Gr.Beam 22 Sep '22
wall, Gr.Beam
819 Main Factory - Underground 16 d 22-09-22 07-10-22 0.00% 0% Main Factory - Underground Piping Work - Zone A2 07 Oct '22
Piping Work - Zone A2
820 Zone A2 - U/G Pipe 16 d 22-09-22 07-10-22 0.00% 0% Zone A2 - U/G Pipe 07 Oct '22
821 Zone A2 - U/G Pipe - 7d 22-09-22 28-09-22 0.00% 0% Zone A2 - U/G Pipe - Excavation 28 Sep '22
Excavation
822 Zone A2 - U/G Pipe - Sand 7d 23-09-22 29-09-22 0.00% 0% Zone A2 - U/G Pipe - Sand Compacted 29 Sep '22
Compacted
823 Zone A2 - U/G Pipe - Install 10 d 24-09-22 03-10-22 0.00% 0% Zone A2 - U/G Pipe - Install Pipes 03 Oct '22
Pipes
824 Zone A2 - U/G Pipe - Pressure 10 d 26-09-22 05-10-22 0.00% 0% Zone A2 - U/G Pipe - Pressure Test 05 Oct '22
Test
825 Zone A2 - U/G Pipe - 2d 06-10-22 07-10-22 0.00% 0% Zone A2 - U/G Pipe - Inspection (Kajima & CM) 07 Oct '22
Inspection (Kajima & CM)
826 Main Factory - Roof Work - Zone 87 d 02-09-22 29-11-22 0.00% 0% Main Factory - Roof Work - Zone A2 29 Nov '22
A2
827 Zone A2 - Roof Steel Structure 34 d 02-09-22 05-10-22 0.00% 0% Zone A2 - Roof Steel Structure 05 Oct '22

828 Zone A2.1&2.2 - Roof Steel 17 d 02-09-22 18-09-22 0.00% 0% Zone A2.1&2.2 - Roof Steel Structure 18 Sep '22
Structure
829 Zone A2.2&2.3 - Roof Steel 17 d 19-09-22 05-10-22 0.00% 0% Zone A2.2&2.3 - Roof Steel Structure 05 Oct '22
Structure
830 Zone A2 - Roof Matel Sheet 70 d 19-09-22 29-11-22 0.00% 0% Zone A2 - Roof Matel Sheet 29 Nov '22
831 Zone A2.1&2.2 - Roof Matel 35 d 19-09-22 25-10-22 0.00% 0% Zone A2.1&2.2 - Roof Matel Sheet 25 Oct '22
Sheet
832 Zone A2.2&2.3 - Roof Matel 35 d 26-10-22 29-11-22 0.00% 0% Zone A2.2&2.3 - Roof Matel Sheet 29 Nov '22
Sheet
833 Main Factory - Post Tension Slab - 90 d 08-10-22 12-01-23 0.00% 0% Main Factory - Post Tension Slab - Zone A2 12 Jan '23
Zone A2
834 Zone A2 - PT Slab Floor 1 69 d 08-10-22 18-12-22 0.00% 0% Zone A2 - PT Slab Floor 1 18 Dec '22
835 Zone A2.2 - PT Slab Floor 1 23 d 08-10-22 01-11-22 0.00% 0% Zone A2.2 - PT Slab Floor 1 01 Nov '22
836 Zone A2.1 - PT Slab Floor 1 23 d 02-11-22 24-11-22 0.00% 0% Zone A2.1 - PT Slab Floor 1 24 Nov '22
837 Zone A2.3 - PT Slab Floor 1 23 d 25-11-22 18-12-22 0.00% 0% Zone A2.3 - PT Slab Floor 1 18 Dec '22
838 Zone A2 - PT Slab Floor 2 69 d 31-10-22 12-01-23 0.00% 0% Zone A2 - PT Slab Floor 2 12 Jan '23
839 Zone A2.2 - PT Slab Floor 2 23 d 31-10-22 22-11-22 0.00% 0% Zone A2.2 - PT Slab Floor 2 22 Nov '22
840 Zone A2.1 - PT Slab Floor 2 23 d 23-11-22 16-12-22 0.00% 0% Zone A2.1 - PT Slab Floor 2 16 Dec '22
841 Zone A2.3 - PT Slab Floor 2 23 d 17-12-22 12-01-23 0.00% 0% Zone A2.3 - PT Slab Floor 2 12 Jan '23
842 Main Factory - Structural Work - 197 d 14-07-22 05-02-23 2.54% 3% Main Factory - Structural Work - Zone A3 05 Feb '23
Zone A3
843 Main Factory - Substructure- Zone 81 d 14-07-22 05-10-22 6.17% 12% Main Factory - Substructure- Zone A3 05 Oct '22
A3
844 Zone A3 - Pile Cut-off Level 21 d 14-07-22 05-08-22 23.81% 75% Zone A3 - Pile Cut-off Level 05 Aug '22
845 Zone A3.2 - Pile Cut-off Level 7d 14-07-22 20-07-22 71.43% 75% Zone A3.2 - Pile Cut-off Level 20 Jul '22

846 Zone A3.1 - Pile Cut-off Level 7d 21-07-22 27-07-22 0.00% 75% Zone A3.1 - Pile Cut-off Level 27 Jul '22

847 Zone A3.3 - Pile Cut-off Level 7d 30-07-22 05-08-22 0.00% 75% Zone A3.3 - Pile Cut-off Level 05 Aug '22

848 Zone A3 - Soil backfill under 27 d 21-07-22 19-08-22 0.00% 0% Zone A3 - Soil backfill under slab 19 Aug '22
slab
849 Zone A3.2 - Soil backfill under 9d 21-07-22 31-07-22 0.00% 0% Zone A3.2 - Soil backfill under slab 31 Jul '22
slab
850 Zone A3.1 - Soil backfill under 9d 01-08-22 09-08-22 0.00% 0% Zone A3.1 - Soil backfill under slab 09 Aug '22
slab
851 Zone A3.3 - Soil backfill under 9d 10-08-22 19-08-22 0.00% 0% Zone A3.3 - Soil backfill under slab 19 Aug '22
slab
852 Zone A3 - Foundation and Pier 45 d 01-08-22 15-09-22 0.00% 0% Zone A3 - Foundation and Pier 15 Sep '22

853 Zone A3.2 - Foundation and 15 d 01-08-22 16-08-22 0.00% 0% Zone A3.2 - Foundation and Pier 16 Aug '22
Pier
854 Zone A3.1 - Foundation and 15 d 17-08-22 31-08-22 0.00% 0% Zone A3.1 - Foundation and Pier 31 Aug '22
Pier
855 Zone A3.3 - Foundation and 15 d 01-09-22 15-09-22 0.00% 0% Zone A3.3 - Foundation and Pier 15 Sep '22
Pier
856 Zone A3 - PCa.Column, Core 36 d 31-08-22 05-10-22 0.00% 0% Zone A3 - PCa.Column, Core wall, Gr.Beam 05 Oct '22
wall, Gr.Beam
857 Zone A3.2 - Pca.Column, Core 12 d 31-08-22 11-09-22 0.00% 0% Zone A3.2 - Pca.Column, Core wall, Gr.Beam 11 Sep '22
wall, Gr.Beam
858 Zone A3.1 - Pca.Column, Core 12 d 12-09-22 23-09-22 0.00% 0% Zone A3.1 - Pca.Column, Core wall, Gr.Beam 23 Sep '22
wall, Gr.Beam
859 Zone A3.3 - Pca.Column, Core 12 d 24-09-22 05-10-22 0.00% 0% Zone A3.3 - Pca.Column, Core wall, Gr.Beam 05 Oct '22
wall, Gr.Beam
860 Main Factory - Underground 32 d 18-09-22 20-10-22 0.00% 0% Main Factory - Underground Piping Work - Zone A3 20 Oct '22
Piping Work - Zone A3
861 Zone A3 - U/G Toilet x 3 Rm. 32 d 18-09-22 20-10-22 0.00% 0% Zone A3 - U/G Toilet x 3 Rm. 20 Oct '22
862 Zone A3 - U/G Toilet x 3 Rm. - 6d 18-09-22 23-09-22 0.00% 0% Zone A3 - U/G Toilet x 3 Rm. - Excavation 23 Sep '22
Excavation
863 Zone A3 - U/G Toilet x 3 Rm. - 6d 20-09-22 25-09-22 0.00% 0% Zone A3 - U/G Toilet x 3 Rm. - Sand Compacted 25 Sep '22
Sand Compacted
864 Zone A3 - U/G Toilet x 3 Rm. - 20 d 22-09-22 11-10-22 0.00% 0% Zone A3 - U/G Toilet x 3 Rm. - Install Pipes 11 Oct '22
Install Pipes
865 Zone A3 - U/G Toilet x 3 Rm. - 6d 12-10-22 18-10-22 0.00% 0% Zone A3 - U/G Toilet x 3 Rm. - Pressure Test 18 Oct '22
Pressure Test
866 Zone A3 - U/G Toilet x 3 Rm. - 2d 19-10-22 20-10-22 0.00% 0% Zone A3 - U/G Toilet x 3 Rm. - Inspection (Kajima & CM) 20 Oct '22
Inspection (Kajima & CM)
867 Zone A3 - U/G Pipe 16 d 24-09-22 09-10-22 0.00% 0% Zone A3 - U/G Pipe 09 Oct '22
868 Zone A3 - U/G Pipe - 7d 24-09-22 30-09-22 0.00% 0% Zone A3 - U/G Pipe - Excavation 30 Sep '22
Excavation
869 Zone A3 - U/G Pipe - Sand 7d 25-09-22 01-10-22 0.00% 0% Zone A3 - U/G Pipe - Sand Compacted 01 Oct '22
Compacted
870 Zone A3 - U/G Pipe - Install 10 d 26-09-22 05-10-22 0.00% 0% Zone A3 - U/G Pipe - Install Pipes 05 Oct '22
Pipes
871 Zone A3 - U/G Pipe - Pressure 10 d 28-09-22 07-10-22 0.00% 0% Zone A3 - U/G Pipe - Pressure Test 07 Oct '22
Test
872 Zone A3 - U/G Pipe - 2d 08-10-22 09-10-22 0.00% 0% Zone A3 - U/G Pipe - Inspection (Kajima & CM) 09 Oct '22
Inspection (Kajima & CM)
873 Main Factory - Roof Work - Zone 87 d 26-09-22 24-12-22 0.00% 0% Main Factory - Roof Work - Zone A3 24 Dec '22
A3
874 Zone A3 - Roof Steel Structure 36 d 26-09-22 02-11-22 0.00% 0% Zone A3 - Roof Steel Structure 02 Nov '22

875 Zone A3.1&3.2 - Roof Steel 17 d 26-09-22 12-10-22 0.00% 0% Zone A3.1&3.2 - Roof Steel Structure 12 Oct '22
Structure
876 Zone A3.2&3.3 - Roof Steel 17 d 16-10-22 02-11-22 0.00% 0% Zone A3.2&3.3 - Roof Steel Structure 02 Nov '22
Structure
877 Zone A3 - Roof Matel Sheet 70 d 14-10-22 24-12-22 0.00% 0% Zone A3 - Roof Matel Sheet 24 Dec '22
878 Zone A3.1&3.2 - Roof Matel 35 d 14-10-22 18-11-22 0.00% 0% Zone A3.1&3.2 - Roof Matel Sheet 18 Nov '22
Sheet
879 Zone A3.2&3.3 - Roof Matel 35 d 19-11-22 24-12-22 0.00% 0% Zone A3.2&3.3 - Roof Matel Sheet 24 Dec '22
Sheet
880 Main Factory - Post Tension Slab - 102 d 21-10-22 05-02-23 0.00% 0% Main Factory - Post Tension Slab - Zone A3 05 Feb '23
Zone A3
881 Zone A3 - PT Slab Floor 1 69 d 21-10-22 03-01-23 0.00% 0% Zone A3 - PT Slab Floor 1 03 Jan '23
882 Zone A3.2 - PT Slab Floor 1 23 d 21-10-22 13-11-22 0.00% 0% Zone A3.2 - PT Slab Floor 1 13 Nov '22
883 Zone A3.1 - PT Slab Floor 1 23 d 14-11-22 07-12-22 0.00% 0% Zone A3.1 - PT Slab Floor 1 07 Dec '22
884 Zone A3.3 - PT Slab Floor 1 23 d 08-12-22 03-01-23 0.00% 0% Zone A3.3 - PT Slab Floor 1 03 Jan '23
885 Zone A3 - PT Slab Floor 2 79 d 14-11-22 05-02-23 0.00% 0% Zone A3 - PT Slab Floor 2 05 Feb '23
886 Zone A3.2 - PT Slab Floor 2 23 d 14-11-22 07-12-22 0.00% 0% Zone A3.2 - PT Slab Floor 2 07 Dec '22
887 Zone A3.1 - PT Slab Floor 2 23 d 08-12-22 03-01-23 0.00% 0% Zone A3.1 - PT Slab Floor 2 03 Jan '23
888 Zone A3.3 - PT Slab Floor 2 33 d 04-01-23 05-02-23 0.00% 0% Zone A3.3 - PT Slab Floor 2 05 Feb '23
889 Main Factory - Structural Work - Zone B 238 d 18-06-22 21-02-23 12.61% 6% Main Factory - Structural Work - Zone B 21 Feb '23

890 Main Factory - Structural Work - 200 d 18-06-22 14-01-23 15.38% 10% Main Factory - Structural Work - Zone B1 14 Jan '23
Zone B1
891 Main Factory - Substructure- Zone 94 d 18-06-22 23-09-22 36.59% 30% Main Factory - Substructure- Zone B1 23 Sep '22
B1
892 Zone B1 - Pile Cut-off Level 21 d 18-06-22 08-07-22 100.00% 100% Zone B1 - Pile Cut-off Level 08 Jul '22
893 Zone B1.1 - Pile Cut-off Level 7d 18-06-22 24-06-22 100.00% 100% Zone B1.1 - Pile Cut-off Level 24 Jun '22

894 Zone B1.2 - Pile Cut-off Level 7d 25-06-22 01-07-22 100.00% 100% Zone B1.2 - Pile Cut-off Level 01 Jul '22

895 Zone B1.3 - Pile Cut-off Level 7d 02-07-22 08-07-22 100.00% 100% Zone B1.3 - Pile Cut-off Level 08 Jul '22

896 Zone B1 - Soil backfill under 27 d 25-06-22 22-07-22 85.19% 85% Zone B1 - Soil backfill under slab 22 Jul '22
slab
897 Zone B1.1 - Soil backfill under 9d 25-06-22 03-07-22 100.00% 100% Zone B1.1 - Soil backfill under slab 03 Jul '22
slab
898 Zone B1.2 - Soil backfill under 9d 04-07-22 12-07-22 100.00% 100% Zone B1.2 - Soil backfill under slab 12 Jul '22
slab
899 Zone B1.3 - Soil backfill under 9d 14-07-22 22-07-22 55.56% 56% Zone B1.3 - Soil backfill under slab 22 Jul '22
slab
900 Zone B1 - Foundation and Pier 57 d 04-07-22 02-09-22 31.11% 0% Zone B1 - Foundation and Pier 02 Sep '22

901 Zone B1.1 - Foundation and 27 d 04-07-22 02-08-22 93.33% 0% Zone B1.1 - Foundation and Pier 02 Aug '22
Pier
902 Excavation 7d 04-07-22 10-07-22 #ERROR 0% Excavation 10 Jul '22
903 Check Pile deviation pile 27-07-22 7d 11-07-22 18-07-22 #ERROR 0% Check Pile deviation 18 Jul '22
deviation
issue

10 OF 16
PROJECT : Relief Project
MASTER SCHEDULE (REV0.02) Dated 18Jul22
ID Task Name AdditionalTask Duration Start Finish % Plan %
task added Complete
date Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Ap
904 Waiting Information for pile 27-07-22 4d 11-07-22 15-07-22 #ERROR 0% Waiting Information for Reinforcement 15
15 Jul,
18 Jul
Jul '22
'22
'22
Reinforcement deviation
issue
905 Make Shop Drawing pile 27-07-22 2d 16-07-22 17-07-22 #ERROR 0% Make Shop Drawing 17 Jul '22
deviation
issue
906 Approve Shop Drawing pile 27-07-22 1d 18-07-22 18-07-22 #ERROR 0% Approve Shop Drawing 18 Jul '22
deviation
issue
907 Rebar,Form,Concrete 13 d 19-07-22 02-08-22 #ERROR 0% Rebar,Form,Concrete 02 Aug '22
908 Zone B1.2 - Foundation and 15 d 03-08-22 18-08-22 0.00% 0% Zone B1.2 - Foundation and Pier 18 Aug '22
Pier
909 Zone B1.3 - Foundation and 15 d 19-08-22 02-09-22 0.00% 0% Zone B1.3 - Foundation and Pier 02 Sep '22
Pier
910 Zone B1 - PCa.Column, Core 36 d 19-08-22 23-09-22 0.00% 0% Zone B1 - PCa.Column, Core wall, Gr.Beam 23 Sep '22
wall, Gr.Beam
911 Zone B1.1 - Pca.Column, Core 12 d 19-08-22 30-08-22 0.00% 0% Zone B1.1 - Pca.Column, Core wall, Gr.Beam 30 Aug '22
wall, Gr.Beam
912 Zone B1.2 - Pca.Column, Core 12 d 31-08-22 11-09-22 0.00% 0% Zone B1.2 - Pca.Column, Core wall, Gr.Beam 11 Sep '22
wall, Gr.Beam
913 Zone B1.3 - Pca.Column, Core 12 d 12-09-22 23-09-22 0.00% 0% Zone B1.3 - Pca.Column, Core wall, Gr.Beam 23 Sep '22
wall, Gr.Beam
914 Main Factory - Underground 22 d 16-09-22 07-10-22 0.00% 0% Main Factory - Underground Piping Work - Zone B1 07 Oct '22
Piping Work - Zone B1
915 Zone B1 - U/G Toilet x 1 Rm. 22 d 16-09-22 07-10-22 0.00% 0% Zone B1 - U/G Toilet x 1 Rm. 07 Oct '22
916 Zone B1 - U/G Toilet x 1 Rm. - 4d 16-09-22 19-09-22 0.00% 0% Zone B1 - U/G Toilet x 1 Rm. - Excavation 19 Sep '22
Excavation
917 Zone B1 - U/G Toilet x 1 Rm. - 4d 18-09-22 21-09-22 0.00% 0% Zone B1 - U/G Toilet x 1 Rm. - Sand Compacted 21 Sep '22
Sand Compacted
918 Zone B1 - U/G Toilet x 1 Rm. - 13 d 20-09-22 02-10-22 0.00% 0% Zone B1 - U/G Toilet x 1 Rm. - Install Pipes 02 Oct '22
Install Pipes
919 Zone B1 - U/G Toilet x 1 Rm. - 3d 03-10-22 05-10-22 0.00% 0% Zone B1 - U/G Toilet x 1 Rm. - Pressure Test 05 Oct '22
Pressure Test
920 Zone B1 - U/G Toilet x 1 Rm. - 2d 06-10-22 07-10-22 0.00% 0% Zone B1 - U/G Toilet x 1 Rm. - Inspection (Kajima & CM) 07 Oct '22
Inspection (Kajima & CM)
921 Zone B1 - U/G Pipe 16 d 20-09-22 05-10-22 0.00% 0% Zone B1 - U/G Pipe 05 Oct '22
922 Zone B1 - U/G Pipe - 7d 20-09-22 26-09-22 0.00% 0% Zone B1 - U/G Pipe - Excavation 26 Sep '22
Excavation
923 Zone B1 - U/G Pipe - Sand 7d 21-09-22 27-09-22 0.00% 0% Zone B1 - U/G Pipe - Sand Compacted 27 Sep '22
Compacted
924 Zone B1 - U/G Pipe - Install 10 d 22-09-22 01-10-22 0.00% 0% Zone B1 - U/G Pipe - Install Pipes 01 Oct '22
Pipes
925 Zone B1 - U/G Pipe - Pressure 10 d 24-09-22 03-10-22 0.00% 0% Zone B1 - U/G Pipe - Pressure Test 03 Oct '22
Test
926 Zone B1 - U/G Pipe - 2d 04-10-22 05-10-22 0.00% 0% Zone B1 - U/G Pipe - Inspection (Kajima & CM) 05 Oct '22
Inspection (Kajima & CM)
927 Main Factory - Roof Work - Zone 87 d 31-08-22 27-11-22 0.00% 0% Main Factory - Roof Work - Zone B1 27 Nov '22
B1
928 Zone B1 - Roof Steel Structure 35 d 31-08-22 04-10-22 0.00% 0% Zone B1 - Roof Steel Structure 04 Oct '22

929 Zone B1.1&1.2 - Roof Steel 17 d 31-08-22 16-09-22 0.00% 0% Zone B1.1&1.2 - Roof Steel Structure 16 Sep '22
Structure
930 Zone B1.2&1.3 - Roof Steel 17 d 18-09-22 04-10-22 0.00% 0% Zone B1.2&1.3 - Roof Steel Structure 04 Oct '22
Structure
931 Zone B1 - Roof Matel Sheet 70 d 17-09-22 27-11-22 0.00% 0% Zone B1 - Roof Matel Sheet 27 Nov '22
932 Zone B1.1&1.2 - Roof Matel 35 d 17-09-22 22-10-22 0.00% 0% Zone B1.1&1.2 - Roof Matel Sheet 22 Oct '22
Sheet
933 Zone B1.2&1.3 - Roof Matel 35 d 23-10-22 27-11-22 0.00% 0% Zone B1.2&1.3 - Roof Matel Sheet 27 Nov '22
Sheet
934 Main Factory - Post Tension Slab - 92 d 08-10-22 14-01-23 0.00% 0% Main Factory - Post Tension Slab - Zone B1 14 Jan '23
Zone B1
935 Zone B1 - PT Slab Floor 1 69 d 08-10-22 18-12-22 0.00% 0% Zone B1 - PT Slab Floor 1 18 Dec '22
936 Zone B1.1 - PT Slab Floor 1 23 d 08-10-22 01-11-22 0.00% 0% Zone B1.1 - PT Slab Floor 1 01 Nov '22
937 Zone B1.2 - PT Slab Floor 1 23 d 02-11-22 24-11-22 0.00% 0% Zone B1.2 - PT Slab Floor 1 24 Nov '22
938 Zone B1.3 - PT Slab Floor 1 23 d 25-11-22 18-12-22 0.00% 0% Zone B1.3 - PT Slab Floor 1 18 Dec '22
939 Zone B1 - PT Slab Floor 2 69 d 02-11-22 14-01-23 0.00% 0% Zone B1 - PT Slab Floor 2 14 Jan '23
940 Zone B1.1 - PT Slab Floor 2 23 d 02-11-22 24-11-22 0.00% 0% Zone B1.1 - PT Slab Floor 2 24 Nov '22
941 Zone B1.2 - PT Slab Floor 2 23 d 25-11-22 18-12-22 0.00% 0% Zone B1.2 - PT Slab Floor 2 18 Dec '22
942 Zone B1.3 - PT Slab Floor 2 23 d 19-12-22 14-01-23 0.00% 0% Zone B1.3 - PT Slab Floor 2 14 Jan '23
943 Main Factory - Structural Work - 189 d 02-07-22 17-01-23 8.47% 6% Main Factory - Structural Work - Zone B2 17 Jan '23
Zone B2
944 Main Factory - Substructure- Zone 82 d 02-07-22 25-09-22 19.51% 21% Main Factory - Substructure- Zone B2 25 Sep '22
B2
945 Zone B2 - Pile Cut-off Level 21 d 02-07-22 23-07-22 76.19% 85% Zone B2 - Pile Cut-off Level 23 Jul '22
946 Zone B2.1 - Pile Cut-off Level 7d 02-07-22 08-07-22 100.00% 100% Zone B2.1 - Pile Cut-off Level 08 Jul '22

947 Zone B2.2 - Pile Cut-off Level 7d 09-07-22 16-07-22 100.00% 100% Zone B2.2 - Pile Cut-off Level 16 Jul '22

948 Zone B2.3 - Pile Cut-off Level 7d 17-07-22 23-07-22 28.57% 55% Zone B2.3 - Pile Cut-off Level 23 Jul '22

949 Zone B2 - Soil backfill under 27 d 09-07-22 07-08-22 33.33% 33% Zone B2 - Soil backfill under slab 07 Aug '22
slab
950 Zone B2.1 - Soil backfill under 9d 09-07-22 18-07-22 100.00% 100% Zone B2.1 - Soil backfill under slab 18 Jul '22
slab
951 Zone B2.2 - Soil backfill under 9d 19-07-22 27-07-22 0.00% 0% Zone B2.2 - Soil backfill under slab 27 Jul '22
slab
952 Zone B2.3 - Soil backfill under 9d 30-07-22 07-08-22 0.00% 0% Zone B2.3 - Soil backfill under slab 07 Aug '22
slab
953 Zone B2 - Foundation and Pier 45 d 19-07-22 04-09-22 0.00% 0% Zone B2 - Foundation and Pier 04 Sep '22

954 Zone B2.1 - Foundation and 15 d 19-07-22 04-08-22 0.00% 0% Zone B2.1 - Foundation and Pier 04 Aug '22
Pier
955 Zone B2.2 - Foundation and 15 d 05-08-22 20-08-22 0.00% 0% Zone B2.2 - Foundation and Pier 20 Aug '22
Pier
956 Zone B2.3 - Foundation and 15 d 21-08-22 04-09-22 0.00% 0% Zone B2.3 - Foundation and Pier 04 Sep '22
Pier
957 Zone B2 - PCa.Column, Core 36 d 21-08-22 25-09-22 0.00% 0% Zone B2 - PCa.Column, Core wall, Gr.Beam 25 Sep '22
wall, Gr.Beam
958 Zone B2.1 - Pca.Column, Core 12 d 21-08-22 01-09-22 0.00% 0% Zone B2.1 - Pca.Column, Core wall, Gr.Beam 01 Sep '22
wall, Gr.Beam
959 Zone B2.2 - Pca.Column, Core 12 d 02-09-22 13-09-22 0.00% 0% Zone B2.2 - Pca.Column, Core wall, Gr.Beam 13 Sep '22
wall, Gr.Beam
960 Zone B2.3 - Pca.Column, Core 12 d 14-09-22 25-09-22 0.00% 0% Zone B2.3 - Pca.Column, Core wall, Gr.Beam 25 Sep '22
wall, Gr.Beam
961 Main Factory - Underground 22 d 17-09-22 08-10-22 0.00% 0% Main Factory - Underground Piping Work - Zone B2 08 Oct '22
Piping Work - Zone B2
962 Zone B2 - U/G Toilet x 1 Rm. 22 d 17-09-22 08-10-22 0.00% 0% Zone B2 - U/G Toilet x 1 Rm. 08 Oct '22
963 Zone B2 - U/G Toilet x 1 Rm. - 4d 17-09-22 20-09-22 0.00% 0% Zone B2 - U/G Toilet x 1 Rm. - Excavation 20 Sep '22
Excavation
964 Zone B2 - U/G Toilet x 1 Rm. - 4d 19-09-22 22-09-22 0.00% 0% Zone B2 - U/G Toilet x 1 Rm. - Sand Compacted 22 Sep '22
Sand Compacted
965 Zone B2 - U/G Toilet x 1 Rm. - 13 d 21-09-22 03-10-22 0.00% 0% Zone B2 - U/G Toilet x 1 Rm. - Install Pipes 03 Oct '22
Install Pipes
966 Zone B2 - U/G Toilet x 1 Rm. - 3d 04-10-22 06-10-22 0.00% 0% Zone B2 - U/G Toilet x 1 Rm. - Pressure Test 06 Oct '22
Pressure Test
967 Zone B2 - U/G Toilet x 1 Rm. - 2d 07-10-22 08-10-22 0.00% 0% Zone B2 - U/G Toilet x 1 Rm. - Inspection (Kajima & CM) 08 Oct '22
Inspection (Kajima & CM)
968 Zone B2 - U/G Pipe 16 d 21-09-22 06-10-22 0.00% 0% Zone B2 - U/G Pipe 06 Oct '22
969 Zone B2 - U/G Pipe - 7d 21-09-22 27-09-22 0.00% 0% Zone B2 - U/G Pipe - Excavation 27 Sep '22
Excavation
970 Zone B2 - U/G Pipe - Sand 7d 22-09-22 28-09-22 0.00% 0% Zone B2 - U/G Pipe - Sand Compacted 28 Sep '22
Compacted
971 Zone B2 - U/G Pipe - Install 10 d 23-09-22 02-10-22 0.00% 0% Zone B2 - U/G Pipe - Install Pipes 02 Oct '22
Pipes
972 Zone B2 - U/G Pipe - Pressure 10 d 25-09-22 04-10-22 0.00% 0% Zone B2 - U/G Pipe - Pressure Test 04 Oct '22
Test
973 Zone B2 - U/G Pipe - 2d 05-10-22 06-10-22 0.00% 0% Zone B2 - U/G Pipe - Inspection (Kajima & CM) 06 Oct '22
Inspection (Kajima & CM)
974 Main Factory - Roof Work - Zone 94 d 02-09-22 07-12-22 0.00% 0% Main Factory - Roof Work - Zone B2 07 Dec '22
B2
975 Zone B2 - Roof Steel Structure 34 d 02-09-22 05-10-22 0.00% 0% Zone B2 - Roof Steel Structure 05 Oct '22

976 Zone B2.1&2.2 - Roof Steel 17 d 02-09-22 18-09-22 0.00% 0% Zone B2.1&2.2 - Roof Steel Structure 18 Sep '22
Structure
977 Zone B2.2&2.3 - Roof Steel 17 d 19-09-22 05-10-22 0.00% 0% Zone B2.2&2.3 - Roof Steel Structure 05 Oct '22
Structure
978 Zone B2 - Roof Matel Sheet 77 d 19-09-22 07-12-22 0.00% 0% Zone B2 - Roof Matel Sheet 07 Dec '22
979 Zone B2.1&2.2 - Roof Matel 35 d 19-09-22 25-10-22 0.00% 0% Zone B2.1&2.2 - Roof Matel Sheet 25 Oct '22
Sheet
980 Zone B2.2&2.3 - Roof Matel 42 d 26-10-22 07-12-22 0.00% 0% Zone B2.2&2.3 - Roof Matel Sheet 07 Dec '22
Sheet
981 Main Factory - Post Tension Slab - 94 d 09-10-22 17-01-23 0.00% 0% Main Factory - Post Tension Slab - Zone B2 17 Jan '23
Zone B2
982 Zone B2 - PT Slab Floor 1 69 d 09-10-22 19-12-22 0.00% 0% Zone B2 - PT Slab Floor 1 19 Dec '22
983 Zone B2.1 - PT Slab Floor 1 23 d 09-10-22 02-11-22 0.00% 0% Zone B2.1 - PT Slab Floor 1 02 Nov '22
984 Zone B2.2 - PT Slab Floor 1 23 d 03-11-22 25-11-22 0.00% 0% Zone B2.2 - PT Slab Floor 1 25 Nov '22
985 Zone B2.3 - PT Slab Floor 1 23 d 26-11-22 19-12-22 0.00% 0% Zone B2.3 - PT Slab Floor 1 19 Dec '22
986 Zone B2 - PT Slab Floor 2 73 d 01-11-22 17-01-23 0.00% 0% Zone B2 - PT Slab Floor 2 17 Jan '23
987 Zone B2.1 - PT Slab Floor 2 23 d 01-11-22 23-11-22 0.00% 0% Zone B2.1 - PT Slab Floor 2 23 Nov '22
988 Zone B2.2 - PT Slab Floor 2 23 d 24-11-22 17-12-22 0.00% 0% Zone B2.2 - PT Slab Floor 2 17 Dec '22
989 Zone B2.3 - PT Slab Floor 2 27 d 18-12-22 17-01-23 0.00% 0% Zone B2.3 - PT Slab Floor 2 17 Jan '23
990 Main Factory - Structural Work - 192 d 17-07-22 03-02-23 1.04% 5% Main Factory - Structural Work - Zone B3 03 Feb '23
Zone B3
991 Main Factory - Substructure- Zone 82 d 17-07-22 09-10-22 2.44% 16% Main Factory - Substructure- Zone B3 09 Oct '22
B3

11 OF 16
PROJECT : Relief Project
MASTER SCHEDULE (REV0.02) Dated 18Jul22
ID Task Name AdditionalTask Duration Start Finish % Plan %
task added Complete
date Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Ap
992 Zone B3 - Pile Cut-off Level 21 d 17-07-22 08-08-22 9.52% 100% Zone B3 - Pile Cut-off Level 18 Jul, '22 08 Aug '22
993 Zone B3.1 - Pile Cut-off Level 7d 17-07-22 23-07-22 28.57% 100% Zone B3.1 - Pile Cut-off Level 23 Jul '22

994 Zone B3.2 - Pile Cut-off Level 7d 24-07-22 01-08-22 0.00% 100% Zone B3.2 - Pile Cut-off Level 01 Aug '22

995 Zone B3.3 - Pile Cut-off Level 7d 02-08-22 08-08-22 0.00% 100% Zone B3.3 - Pile Cut-off Level 08 Aug '22

996 Zone B3 - Soil backfill under 27 d 24-07-22 22-08-22 0.00% 0% Zone B3 - Soil backfill under slab 22 Aug '22
slab
997 Zone B3.1 - Soil backfill under 9d 24-07-22 03-08-22 0.00% 0% Zone B3.1 - Soil backfill under slab 03 Aug '22
slab
998 Zone B3.2 - Soil backfill under 9d 04-08-22 13-08-22 0.00% 0% Zone B3.2 - Soil backfill under slab 13 Aug '22
slab
999 Zone B3.3 - Soil backfill under 9d 14-08-22 22-08-22 0.00% 0% Zone B3.3 - Soil backfill under slab 22 Aug '22
slab
1000 Zone B3 - Foundation and Pier 45 d 04-08-22 18-09-22 0.00% 0% Zone B3 - Foundation and Pier 18 Sep '22

1001 Zone B3.1 - Foundation and 15 d 04-08-22 19-08-22 0.00% 0% Zone B3.1 - Foundation and Pier 19 Aug '22
Pier
1002 Zone B3.2 - Foundation and 15 d 20-08-22 03-09-22 0.00% 0% Zone B3.2 - Foundation and Pier 03 Sep '22
Pier
1003 Zone B3.3 - Foundation and 15 d 04-09-22 18-09-22 0.00% 0% Zone B3.3 - Foundation and Pier 18 Sep '22
Pier
1004 Zone B3 - PCa.Column, Core 36 d 04-09-22 09-10-22 0.00% 0% Zone B3 - PCa.Column, Core wall, Gr.Beam 09 Oct '22
wall, Gr.Beam
1005 Zone B3.1 - Pca.Column, Core 12 d 04-09-22 15-09-22 0.00% 0% Zone B3.1 - Pca.Column, Core wall, Gr.Beam 15 Sep '22
wall, Gr.Beam
1006 Zone B3.2 - Pca.Column, Core 12 d 16-09-22 27-09-22 0.00% 0% Zone B3.2 - Pca.Column, Core wall, Gr.Beam 27 Sep '22
wall, Gr.Beam
1007 Zone B3.3 - Pca.Column, Core 12 d 28-09-22 09-10-22 0.00% 0% Zone B3.3 - Pca.Column, Core wall, Gr.Beam 09 Oct '22
wall, Gr.Beam
1008 Main Factory - Underground 16 d 07-10-22 23-10-22 0.00% 0% Main Factory - Underground Piping Work - Zone B3 23 Oct '22
Piping Work - Zone B3
1009 Zone B3 - U/G Pipe 16 d 07-10-22 23-10-22 0.00% 0% Zone B3 - U/G Pipe 23 Oct '22
1010 Zone B3 - U/G Pipe - 7d 07-10-22 14-10-22 0.00% 0% Zone B3 - U/G Pipe - Excavation 14 Oct '22
Excavation
1011 Zone B3 - U/G Pipe - Sand 7d 08-10-22 15-10-22 0.00% 0% Zone B3 - U/G Pipe - Sand Compacted 15 Oct '22
Compacted
1012 Zone B3 - U/G Pipe - Install 10 d 09-10-22 19-10-22 0.00% 0% Zone B3 - U/G Pipe - Install Pipes 19 Oct '22
Pipes
1013 Zone B3 - U/G Pipe - Pressure 10 d 11-10-22 21-10-22 0.00% 0% Zone B3 - U/G Pipe - Pressure Test 21 Oct '22
Test
1014 Zone B3 - U/G Pipe - 2d 22-10-22 23-10-22 0.00% 0% Zone B3 - U/G Pipe - Inspection (Kajima & CM) 23 Oct '22
Inspection (Kajima & CM)
1015 Main Factory - Roof Work - Zone 87 d 16-09-22 14-12-22 0.00% 0% Main Factory - Roof Work - Zone B3 14 Dec '22
B3
1016 Zone B3 - Roof Steel Structure 34 d 16-09-22 20-10-22 0.00% 0% Zone B3 - Roof Steel Structure 20 Oct '22

1017 Zone B3.1&3.2 - Roof Steel 17 d 16-09-22 02-10-22 0.00% 0% Zone B3.1&3.2 - Roof Steel Structure 02 Oct '22
Structure
1018 Zone B3.2&3.3 - Roof Steel 17 d 03-10-22 20-10-22 0.00% 0% Zone B3.2&3.3 - Roof Steel Structure 20 Oct '22
Structure
1019 Zone B3 - Roof Matel Sheet 70 d 03-10-22 14-12-22 0.00% 0% Zone B3 - Roof Matel Sheet 14 Dec '22
1020 Zone B3.1&3.2 - Roof Matel 35 d 03-10-22 08-11-22 0.00% 0% Zone B3.1&3.2 - Roof Matel Sheet 08 Nov '22
Sheet
1021 Zone B3.2&3.3 - Roof Matel 35 d 09-11-22 14-12-22 0.00% 0% Zone B3.2&3.3 - Roof Matel Sheet 14 Dec '22
Sheet
1022 Main Factory - Post Tension Slab - 97 d 25-10-22 03-02-23 0.00% 0% Main Factory - Post Tension Slab - Zone B3 03 Feb '23
Zone B3
1023 Zone B3 - PT Slab Floor 1 69 d 25-10-22 06-01-23 0.00% 0% Zone B3 - PT Slab Floor 1 06 Jan '23
1024 Zone B3.1 - PT Slab Floor 1 23 d 25-10-22 16-11-22 0.00% 0% Zone B3.1 - PT Slab Floor 1 16 Nov '22
1025 Zone B3.2 - PT Slab Floor 1 23 d 17-11-22 10-12-22 0.00% 0% Zone B3.2 - PT Slab Floor 1 10 Dec '22
1026 Zone B3.3 - PT Slab Floor 1 23 d 11-12-22 06-01-23 0.00% 0% Zone B3.3 - PT Slab Floor 1 06 Jan '23
1027 Zone B3 - PT Slab Floor 2 74 d 17-11-22 03-02-23 0.00% 0% Zone B3 - PT Slab Floor 2 03 Feb '23
1028 Zone B3.1 - PT Slab Floor 2 23 d 17-11-22 10-12-22 0.00% 0% Zone B3.1 - PT Slab Floor 2 10 Dec '22
1029 Zone B3.2 - PT Slab Floor 2 23 d 11-12-22 06-01-23 0.00% 0% Zone B3.2 - PT Slab Floor 2 06 Jan '23
1030 Zone B3.3 - PT Slab Floor 2 28 d 07-01-23 03-02-23 0.00% 0% Zone B3.3 - PT Slab Floor 2 03 Feb '23
1031 Main Factory - Structural Work - 196 d 02-08-22 21-02-23 0.00% 2% Main Factory - Structural Work - Zone B4 21 Feb '23
Zone B4
1032 Main Factory - Substructure- Zone 82 d 02-08-22 25-10-22 0.00% 6% Main Factory - Substructure- Zone B4 25 Oct '22
B4
1033 Zone B4 - Pile Cut-off Level 21 d 02-08-22 23-08-22 0.00% 35% Zone B4 - Pile Cut-off Level 23 Aug '22
1034 Zone B4.1 - Pile Cut-off Level 7d 02-08-22 08-08-22 0.00% 35% Zone B4.1 - Pile Cut-off Level 08 Aug '22

1035 Zone B4.2 - Pile Cut-off Level 7d 09-08-22 16-08-22 0.00% 35% Zone B4.2 - Pile Cut-off Level 16 Aug '22

1036 Zone B4.3 - Pile Cut-off Level 7d 17-08-22 23-08-22 0.00% 35% Zone B4.3 - Pile Cut-off Level 23 Aug '22

1037 Zone B4 - Soil backfill under 27 d 09-08-22 05-09-22 0.00% 0% Zone B4 - Soil backfill under slab 05 Sep '22
slab
1038 Zone B4.1 - Soil backfill under 9d 09-08-22 18-08-22 0.00% 0% Zone B4.1 - Soil backfill under slab 18 Aug '22
slab
1039 Zone B4.2 - Soil backfill under 9d 19-08-22 27-08-22 0.00% 0% Zone B4.2 - Soil backfill under slab 27 Aug '22
slab
1040 Zone B4.3 - Soil backfill under 9d 28-08-22 05-09-22 0.00% 0% Zone B4.3 - Soil backfill under slab 05 Sep '22
slab
1041 Zone B4 - Foundation and Pier 45 d 19-08-22 02-10-22 0.00% 0% Zone B4 - Foundation and Pier 02 Oct '22

1042 Zone B4.1 - Foundation and 15 d 19-08-22 02-09-22 0.00% 0% Zone B4.1 - Foundation and Pier 02 Sep '22
Pier
1043 Zone B4.2 - Foundation and 15 d 03-09-22 17-09-22 0.00% 0% Zone B4.2 - Foundation and Pier 17 Sep '22
Pier
1044 Zone B4.3 - Foundation and 15 d 18-09-22 02-10-22 0.00% 0% Zone B4.3 - Foundation and Pier 02 Oct '22
Pier
1045 Zone B4 - PCa.Column, Core 36 d 18-09-22 25-10-22 0.00% 0% Zone B4 - PCa.Column, Core wall, Gr.Beam 25 Oct '22
wall, Gr.Beam
1046 Zone B4.1 - Pca.Column, Core 12 d 18-09-22 29-09-22 0.00% 0% Zone B4.1 - Pca.Column, Core wall, Gr.Beam 29 Sep '22
wall, Gr.Beam
1047 Zone B4.2 - Pca.Column, Core 12 d 30-09-22 11-10-22 0.00% 0% Zone B4.2 - Pca.Column, Core wall, Gr.Beam 11 Oct '22
wall, Gr.Beam
1048 Zone B4.3 - Pca.Column, Core 12 d 12-10-22 25-10-22 0.00% 0% Zone B4.3 - Pca.Column, Core wall, Gr.Beam 25 Oct '22
wall, Gr.Beam
1049 Main Factory - Underground 22 d 16-10-22 07-11-22 0.00% 0% Main Factory - Underground Piping Work - Zone B4 07 Nov '22
Piping Work - Zone B4
1050 Zone B4 - U/G Toilet x 1 Rm. 22 d 16-10-22 07-11-22 0.00% 0% Zone B4 - U/G Toilet x 1 Rm. 07 Nov '22
1051 Zone B4 - U/G Toilet x 1 Rm. - 4d 16-10-22 19-10-22 0.00% 0% Zone B4 - U/G Toilet x 1 Rm. - Excavation 19 Oct '22
Excavation
1052 Zone B4 - U/G Toilet x 1 Rm. - 4d 18-10-22 21-10-22 0.00% 0% Zone B4 - U/G Toilet x 1 Rm. - Sand Compacted 21 Oct '22
Sand Compacted
1053 Zone B4 - U/G Toilet x 1 Rm. - 13 d 20-10-22 02-11-22 0.00% 0% Zone B4 - U/G Toilet x 1 Rm. - Install Pipes 02 Nov '22
Install Pipes
1054 Zone B4 - U/G Toilet x 1 Rm. - 3d 03-11-22 05-11-22 0.00% 0% Zone B4 - U/G Toilet x 1 Rm. - Pressure Test 05 Nov '22
Pressure Test
1055 Zone B4 - U/G Toilet x 1 Rm. - 2d 06-11-22 07-11-22 0.00% 0% Zone B4 - U/G Toilet x 1 Rm. - Inspection (Kajima & CM) 07 Nov '22
Inspection (Kajima & CM)
1056 Zone B4 - U/G Pipe 16 d 20-10-22 05-11-22 0.00% 0% Zone B4 - U/G Pipe 05 Nov '22
1057 Zone B4 - U/G Pipe - 7d 20-10-22 27-10-22 0.00% 0% Zone B4 - U/G Pipe - Excavation 27 Oct '22
Excavation
1058 Zone B4 - U/G Pipe - Sand 7d 21-10-22 28-10-22 0.00% 0% Zone B4 - U/G Pipe - Sand Compacted 28 Oct '22
Compacted
1059 Zone B4 - U/G Pipe - Install 10 d 22-10-22 01-11-22 0.00% 0% Zone B4 - U/G Pipe - Install Pipes 01 Nov '22
Pipes
1060 Zone B4 - U/G Pipe - Pressure 10 d 25-10-22 03-11-22 0.00% 0% Zone B4 - U/G Pipe - Pressure Test 03 Nov '22
Test
1061 Zone B4 - U/G Pipe - 2d 04-11-22 05-11-22 0.00% 0% Zone B4 - U/G Pipe - Inspection (Kajima & CM) 05 Nov '22
Inspection (Kajima & CM)
1062 Main Factory - Roof Work - Zone 95 d 30-09-22 09-01-23 0.00% 0% Main Factory - Roof Work - Zone B4 09 Jan '23
B4
1063 Zone B4 - Roof Steel Structure 34 d 30-09-22 04-11-22 0.00% 0% Zone B4 - Roof Steel Structure 04 Nov '22

1064 Zone B4.1&4.2 - Roof Steel 17 d 30-09-22 17-10-22 0.00% 0% Zone B4.1&4.2 - Roof Steel Structure 17 Oct '22
Structure
1065 Zone B4.2&4.3 - Roof Steel 17 d 18-10-22 04-11-22 0.00% 0% Zone B4.2&4.3 - Roof Steel Structure 04 Nov '22
Structure
1066 Zone B4 - Roof Matel Sheet 78 d 18-10-22 09-01-23 0.00% 0% Zone B4 - Roof Matel Sheet 09 Jan '23
1067 Zone B4.1&4.2 - Roof Matel 39 d 18-10-22 26-11-22 0.00% 0% Zone B4.1&4.2 - Roof Matel Sheet 26 Nov '22
Sheet
1068 Zone B4.2&4.3 - Roof Matel 39 d 27-11-22 09-01-23 0.00% 0% Zone B4.2&4.3 - Roof Matel Sheet 09 Jan '23
Sheet
1069 Main Factory - Post Tension Slab - 101 d 08-11-22 21-02-23 0.00% 0% Main Factory - Post Tension Slab - Zone B4 21 Feb '23
Zone B4
1070 Zone B4 - PT Slab Floor 1 70 d 08-11-22 21-01-23 0.00% 0% Zone B4 - PT Slab Floor 1 21 Jan '23
1071 Zone B4.1 - PT Slab Floor 1 23 d 08-11-22 30-11-22 0.00% 0% Zone B4.1 - PT Slab Floor 1 30 Nov '22
1072 Zone B4.2 - PT Slab Floor 1 23 d 01-12-22 24-12-22 0.00% 0% Zone B4.2 - PT Slab Floor 1 24 Dec '22
1073 Zone B4.3 - PT Slab Floor 1 24 d 25-12-22 21-01-23 0.00% 0% Zone B4.3 - PT Slab Floor 1 21 Jan '23
1074 Zone B4 - PT Slab Floor 2 78 d 01-12-22 21-02-23 0.00% 0% Zone B4 - PT Slab Floor 2 21 Feb '23
1075 Zone B4.1 - PT Slab Floor 2 26 d 01-12-22 27-12-22 0.00% 0% Zone B4.1 - PT Slab Floor 2 27 Dec '22
1076 Zone B4.2 - PT Slab Floor 2 26 d 28-12-22 26-01-23 0.00% 0% Zone B4.2 - PT Slab Floor 2 26 Jan '23
1077 Zone B4.3 - PT Slab Floor 2 26 d 27-01-23 21-02-23 0.00% 0% Zone B4.3 - PT Slab Floor 2 21 Feb '23
1078 Main Factory - Architectural Work 183 d 01-11-22 16-05-23 0.00% 0% Main Factory - Architectural Work
1079 Main Factory - Architectural Work - 180 d 04-11-22 16-05-23 0.00% 0% Main Factory - Architectural Work - Zone A
Zone A
1080 Zone A - 1F.&2F. Interior block wall & 121 d 04-11-22 10-03-23 0.00% 0% Zone A - 1F.&2F. Interior block wall & Dry wall 10 Mar '23
Dry wall
1081 Zone A - Pca.Wall installation 84 d 18-11-22 14-02-23 0.00% 0% Zone A - Pca.Wall installation 14 Feb '23

12 OF 16
PROJECT : Relief Project
MASTER SCHEDULE (REV0.02) Dated 18Jul22
ID Task Name AdditionalTask Duration Start Finish % Plan %
task added Complete
date Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Ap
1082 Zone A - 1F&2F. Toilet wall & floor 98 d 10-12-22 22-03-23 0.00% 0% 18 Jul, '22 Zone A - 1F&2F. Toilet wall
wall & floor
floor ceramic tile / RC.Stair 22 Mar '23
ceramic tile / RC.Stair
1083 Zone A - 1F&2F. Shutter, Door & Window 98 d 06-01-23 20-04-23 0.00% 0% Zone A - 1F&2F. Shutter, Door & Window
1084 Zone A - 1F.&2F. Ceiling finishes 70 d 20-01-23 31-03-23 0.00% 0% Zone A - 1F.&2F. Ceiling finishes 31 Mar '23
1085 Zone A - 1F.&2F. Floor finishes 70 d 20-02-23 09-05-23 0.00% 0% Zone A - 1F.&2F. Floor finishes
1086 Zone A - Dock leveler installation 42 d 14-03-23 30-04-23 0.00% 0% Zone A - Dock leveler installation
1087 Zone A - 1F.&2F. Miscellaneous 28 d 12-04-23 16-05-23 0.00% 0% Zone A - 1F.&2F. Miscellaneous finishing
finishing
1088 Main Factory - Architectural Work - 179 d 01-11-22 12-05-23 0.00% 0% Main Factory - Architectural Work - Zone B
Zone B
1089 Zone B - 1F.&2F. Interior block wall & 112 d 01-11-22 25-02-23 0.00% 0% Zone B - 1F.&2F. Interior block wall & Dry wall 25 Feb '23
Dry wall
1090 Zone B - Pca.Wall installation 84 d 15-11-22 11-02-23 0.00% 0% Zone B - Pca.Wall installation 11 Feb '23
1091 Zone B - 1F&2F. Toilet wall & floor 98 d 07-12-22 19-03-23 0.00% 0% Zone B - 1F&2F. Toilet wall & floor ceramic tile / RC.Stair 19 Mar '23
ceramic tile / RC.Stair
1092 Zone B - 1F&2F. Shutter, Door & Window 98 d 28-12-22 10-04-23 0.00% 0% Zone B - 1F&2F. Shutter, Door & Window 10 Apr '23
1093 Zone B - 1F.&2F. Ceiling finishes 70 d 15-01-23 26-03-23 0.00% 0% Zone B - 1F.&2F. Ceiling finishes 26 Mar '23
1094 Zone B - 1F.&2F. Floor finishes 70 d 16-02-23 05-05-23 0.00% 0% Zone B - 1F.&2F. Floor finishes
1095 Zone B - Dock leveler installation 42 d 10-03-23 26-04-23 0.00% 0% Zone B - Dock leveler installation
1096 Zone B - 1F.&2F. Miscellaneous 28 d 08-04-23 12-05-23 0.00% 0% Zone B - 1F.&2F. Miscellaneous finishing
finishing
1097 Main Factory - MEP work by other (Not 144 d 19-08-22 17-01-23 0.00% 0% Main Factory - MEP work by other (Not TKC Scope of Work, TKC is not responsible) 17 Jan '23
TKC Scope of Work, TKC is not responsible)

1098 Main Factory - MEP Work - Roof Truss 41 d 19-08-22 29-09-22 0.00% 0% Main Factory - MEP Work - Roof Truss (Installation Fire fighting pipe) 29 Sep '22
(Installation Fire fighting pipe)
1099 Zone A1 - Roof Truss - Completed MEP 0d 19-08-22 19-08-22 0.00% 0% Zone A1 - Roof Truss - Completed MEP Installation Fire Fighting pipe at Roof Truss 19 Aug '22
Installation Fire Fighting pipe at Roof
Truss
1100 Zone A2 - Roof Truss - Completed MEP 0d 01-09-22 01-09-22 0.00% 0% Zone A2 - Roof Truss - Completed MEP Installation Fire Fighting pipe at Roof Truss 01 Sep '22
Installation Fire Fighting pipe at Roof
Truss
1101 Zone A3 - Roof Truss - Completed MEP 0d 25-09-22 25-09-22 0.00% 0% Zone A3 - Roof Truss - Completed MEP Installation Fire Fighting pipe at Roof Truss 25 Sep '22
Installation Fire Fighting pipe at Roof
Truss
1102 Zone B1 - Roof Truss - Completed MEP 0d 19-08-22 19-08-22 0.00% 0% Zone B1 - Roof Truss - Completed MEP Installation Fire Fighting pipe at Roof Truss 19 Aug '22
Installation Fire Fighting pipe at Roof
Truss
1103 Zone B2 - Roof Truss - Completed MEP 0d 01-09-22 01-09-22 0.00% 0% Zone B2 - Roof Truss - Completed MEP Installation Fire Fighting pipe at Roof Truss 01 Sep '22
Installation Fire Fighting pipe at Roof
Truss
1104 Zone B3 - Roof Truss - Completed MEP 0d 15-09-22 15-09-22 0.00% 0% Zone B3 - Roof Truss - Completed MEP Installation Fire Fighting pipe at Roof Truss 15 Sep '22
Installation Fire Fighting pipe at Roof
Truss
1105 Zone B4 - Roof Truss - Completed MEP 0d 29-09-22 29-09-22 0.00% 0% Zone B4 - Roof Truss - Completed MEP Installation Fire Fighting pipe at Roof Truss 29 Sep '22
Installation Fire Fighting pipe at Roof
Truss
1106 Main Factory - MEP Installation 59 d 14-11-22 17-01-23 0.00% 0% Main Factory - MEP Installation 17 Jan '23
1107 Main Factory - MEP Installation Fixed 56 d 17-11-22 17-01-23 0.00% 0% Main Factory - MEP Installation Fixed - Zone A 17 Jan '23
- Zone A
1108 Main Factory - MEP Installation 0d 17-11-22 17-11-22 0.00% 0% Main Factory - MEP Installation Fixed Zone A - Start 17 Nov '22
Fixed Zone A - Start
1109 Main Factory - MEP Installation 0d 17-01-23 17-01-23 0.00% 0% Main Factory - MEP Installation Fixed Zone A - Completed 17 Jan '23
Fixed Zone A - Completed
1110 Main Factory - MEP Installation Fixed 56 d 14-11-22 14-01-23 0.00% 0% Main Factory - MEP Installation Fixed - Zone B 14 Jan '23
- Zone B
1111 Main Factory - MEP Installation 0d 14-11-22 14-11-22 0.00% 0% Main Factory - MEP Installation Fixed Zone B - Start 14 Nov '22
Fixed Zone B - Start
1112 Main Factory - MEP Installation 0d 14-01-23 14-01-23 0.00% 0% Main Factory - MEP Installation Fixed Zone B - Completed 14 Jan '23
Fixed Zone B - Completed
1113 Main Factory - Inspection 21 d 06-05-23 26-05-23 0.00% 0%
1114 Main Factory - Inspection - Zone A 17 d 10-05-23 26-05-23 0.00% 0%
1115 Zone A - TKC Inspection 12 d 10-05-23 21-05-23 0.00% 0%
1116 Zone A - Consultant & Owner 10 d 17-05-23 26-05-23 0.00% 0%
Inspection
1117 Main Factory - Inspection - Zone B 21 d 06-05-23 26-05-23 0.00% 0%
1118 Zone B - TKC Inspection 12 d 06-05-23 17-05-23 0.00% 0%
1119 Zone B - Consultant & Owner 10 d 17-05-23 26-05-23 0.00% 0%
Inspection
1120 Office and Canteen 339 d 15-06-22 08-06-23 10.25% 3% Office and Canteen
1121 Office and Canteen - Structural Work 217 d 15-06-22 28-01-23 16.50% 11% Office and Canteen - Structural Work 28 Jan '23
1122 Office and Canteen - Substructure 99 d 15-06-22 25-09-22 40.24% 25% Office and Canteen - Substructure 25 Sep '22
1123 Office and Canteen - Pile Cut-off 21 d 15-06-22 05-07-22 100.00% 100% Office and Canteen - Pile Cut-off Level 05 Jul '22
Level
1124 Office and Canteen (O2) - Pile 7d 15-06-22 21-06-22 100.00% 100% Office and Canteen (O2) - Pile Cut-off Level 21 Jun '22
Cut-off Level
1125 Office and Canteen (O1) - Pile 7d 22-06-22 28-06-22 100.00% 100% Office and Canteen (O1) - Pile Cut-off Level 28 Jun '22
Cut-off Level
1126 Office and Canteen (O3) - Pile 7d 29-06-22 05-07-22 100.00% 100% Office and Canteen (O3) - Pile Cut-off Level 05 Jul '22
Cut-off Level
1127 Office and Canteen - Soil backfill 27 d 22-06-22 19-07-22 96.30% 100% Office and Canteen - Soil backfill under slab 19 Jul '22
under slab
1128 Office and Canteen (O2) - Soil 9d 22-06-22 30-06-22 100.00% 100% Office and Canteen (O2) - Soil backfill under slab 30 Jun '22
backfill under slab
1129 Office and Canteen (O1) - Soil 9d 01-07-22 09-07-22 100.00% 100% Office and Canteen (O1) - Soil backfill under slab 09 Jul '22
backfill under slab
1130 Office and Canteen (O3) - Soil 9d 10-07-22 19-07-22 88.89% 100% Office and Canteen (O3) - Soil backfill under slab 19 Jul '22
backfill under slab
1131 Office and Canteen - Foundation and 62 d 01-07-22 04-09-22 37.78% 1% Office and Canteen - Foundation and Pier 04 Sep '22
Pier
1132 Office and Canteen (O2) - 32 d 01-07-22 04-08-22 100.00% 0% Office and Canteen (O2) - Foundation and Pier 04 Aug '22
Foundation and Pier
1133 Excavation 12 d 01-07-22 12-07-22 #ERROR 0% Excavation 12 Jul '22
1134 Check Pile deviation pile 27-07-22 12 d 03-07-22 15-07-22 #ERROR 0% Check Pile deviation 15 Jul '22
deviation
issue
1135 Waiting Information for pile 27-07-22 4d 11-07-22 15-07-22 #ERROR 0% Waiting Information for Reinforcement 15 Jul '22
Reinforcement deviation
issue
1136 Make Shop Drawing pile 27-07-22 2d 16-07-22 17-07-22 #ERROR 0% Make Shop Drawing 17 Jul '22
deviation
issue
1137 Approve Shop Drawing pile 27-07-22 1d 18-07-22 18-07-22 #ERROR 0% Approve Shop Drawing 18 Jul '22
deviation
issue
1138 Rebar,Form,Concrete 15 d 19-07-22 04-08-22 #ERROR 0% Rebar,Form,Concrete 04 Aug '22
1139 Office and Canteen (O1) - 32 d 17-07-22 20-08-22 13.33% 1% Office and Canteen (O1) - Foundation and Pier 20 Aug '22
Foundation and Pier
1140 Office and Canteen (O3) - 32 d 03-08-22 04-09-22 0.00% 1% Office and Canteen (O3) - Foundation and Pier 04 Sep '22
Foundation and Pier
1141 Office and Canteen - PCa.Column, 36 d 21-08-22 25-09-22 0.00% 0% Office and Canteen - PCa.Column, Core wall, Gr.Beam 25 Sep '22
Core wall, Gr.Beam
1142 Office and Canteen (O2) - 12 d 21-08-22 01-09-22 0.00% 0% Office and Canteen (O2) - Pca.Column, Core wall, Gr.Beam 01 Sep '22
Pca.Column, Core wall, Gr.Beam
1143 Office and Canteen (O1) - 12 d 02-09-22 13-09-22 0.00% 0% Office and Canteen (O1) - Pca.Column, Core wall, Gr.Beam 13 Sep '22
Pca.Column, Core wall, Gr.Beam
1144 Office and Canteen (O3) - 12 d 14-09-22 25-09-22 0.00% 0% Office and Canteen (O3) - Pca.Column, Core wall, Gr.Beam 25 Sep '22
Pca.Column, Core wall, Gr.Beam
1145 Office and Canteen - Underground 26 d 21-08-22 15-09-22 0.00% 0% Office and Canteen - Underground Piping Work 15 Sep '22
Piping Work
1146 Office and Canteen - U/G Toilet x 3 26 d 21-08-22 15-09-22 0.00% 0% Office and Canteen - U/G Toilet x 3 Rm. 15 Sep '22
Rm.
1147 Office and Canteen - U/G Toilet x 3 4d 21-08-22 24-08-22 0.00% 0% Office and Canteen - U/G Toilet x 3 Rm. - Excavation 24 Aug '22
Rm. - Excavation
1148 Office and Canteen - U/G Toilet x 3 4d 23-08-22 26-08-22 0.00% 0% Office and Canteen - U/G Toilet x 3 Rm. - Sand Compacted 26 Aug '22
Rm. - Sand Compacted
1149 Office and Canteen - U/G Toilet x 3 14 d 25-08-22 07-09-22 0.00% 0% Office and Canteen - U/G Toilet x 3 Rm. - Install Pipes 07 Sep '22
Rm. - Install Pipes
1150 Office and Canteen - U/G Toilet x 3 6d 08-09-22 13-09-22 0.00% 0% Office and Canteen - U/G Toilet x 3 Rm. - Pressure Test 13 Sep '22
Rm. - Pressure Test
1151 Office and Canteen - U/G Toilet x 3 2d 14-09-22 15-09-22 0.00% 0% Office and Canteen - U/G Toilet x 3 Rm. - Inspection (Kajima & CM) 15 Sep '22
Rm. - Inspection (Kajima & CM)
1152 Office and Canteen - U/G Pipe 16 d 21-08-22 05-09-22 0.00% 0% Office and Canteen - U/G Pipe 05 Sep '22
1153 Office and Canteen - U/G Pipe - 7d 21-08-22 27-08-22 0.00% 0% Office and Canteen - U/G Pipe - Excavation 27 Aug '22
Excavation
1154 Office and Canteen - U/G Pipe - 7d 22-08-22 28-08-22 0.00% 0% Office and Canteen - U/G Pipe - Sand Compacted 28 Aug '22
Sand Compacted
1155 Office and Canteen - U/G Pipe - 10 d 23-08-22 01-09-22 0.00% 0% Office and Canteen - U/G Pipe - Install Pipes 01 Sep '22
Install Pipes
1156 Office and Canteen - U/G Pipe - 10 d 25-08-22 03-09-22 0.00% 0% Office and Canteen - U/G Pipe - Pressure Test 03 Sep '22
Pressure Test
1157 Office and Canteen - U/G Pipe - 2d 04-09-22 05-09-22 0.00% 0% Office and Canteen - U/G Pipe - Inspection (Kajima & CM) 05 Sep '22
Inspection (Kajima & CM)
1158 Office and Canteen - Post Tension Slab 86 d 10-09-22 07-12-22 0.00% 0% Office and Canteen - Post Tension Slab 07 Dec '22

1159 Office and Canteen - PT Slab, RC Slab 32 d 10-09-22 11-10-22 0.00% 0% Office and Canteen - PT Slab, RC Slab - Floor 1 11 Oct '22
- Floor 1
1160 Office and Canteen (O2) - PT Slab, 9d 10-09-22 18-09-22 0.00% 0% Office and Canteen (O2) - PT Slab, RC Slab - Floor 1 18 Sep '22
RC Slab - Floor 1
1161 Office and Canteen (O1) - PT Slab, 9d 19-09-22 27-09-22 0.00% 0% Office and Canteen (O1) - PT Slab, RC Slab - Floor 1 27 Sep '22
RC Slab - Floor 1
1162 Office and Canteen (O3) - PT Slab, 14 d 28-09-22 11-10-22 0.00% 0% Office and Canteen (O3) - PT Slab, RC Slab - Floor 1 11 Oct '22
RC Slab - Floor 1
1163 Office and Canteen - PT Slab, RC Slab 36 d 24-09-22 31-10-22 0.00% 0% Office and Canteen - PT Slab, RC Slab - Floor M 31 Oct '22
- Floor M

13 OF 16
PROJECT : Relief Project
MASTER SCHEDULE (REV0.02) Dated 18Jul22
ID Task Name AdditionalTask Duration Start Finish % Plan %
task added Complete
date Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Ap
1164 Office and Canteen (O2) - PT Slab, 12 d 24-09-22 05-10-22 0.00% 0% 18 Jul, '22 Office and Canteen (O2) - PT Slab, RC Slab - Floor M 05 Oct '22
RC Slab - Floor M
1165 Office and Canteen (O1) - PT Slab, 12 d 06-10-22 18-10-22 0.00% 0% Office and Canteen (O1) - PT Slab, RC Slab - Floor M 18 Oct '22
RC Slab - Floor M
1166 Office and Canteen (O3) - PT Slab, 12 d 19-10-22 31-10-22 0.00% 0% Office and Canteen (O3) - PT Slab, RC Slab - Floor M 31 Oct '22
RC Slab - Floor M
1167 Office and Canteen - PT Slab - Floor 2 36 d 12-10-22 18-11-22 0.00% 0% Office and Canteen - PT Slab - Floor 2 18 Nov '22

1168 Office and Canteen (O2) - PT Slab - 12 d 12-10-22 25-10-22 0.00% 0% Office and Canteen (O2) - PT Slab - Floor 2 25 Oct '22
Floor 2
1169 Office and Canteen (O1) - PT Slab - 12 d 26-10-22 06-11-22 0.00% 0% Office and Canteen (O1) - PT Slab - Floor 2 06 Nov '22
Floor 2
1170 Office and Canteen (O3) - PT Slab - 12 d 07-11-22 18-11-22 0.00% 0% Office and Canteen (O3) - PT Slab - Floor 2 18 Nov '22
Floor 2
1171 Office and Canteen - PT Slab - PT 36 d 01-11-22 07-12-22 0.00% 0% Office and Canteen - PT Slab - PT Slab Roof 07 Dec '22
Slab Roof
1172 Office and Canteen (O2) - PT Slab - 12 d 01-11-22 12-11-22 0.00% 0% Office and Canteen (O2) - PT Slab - Shade 12 Nov '22
Shade
1173 Office and Canteen (O1) - PT Slab - 12 d 13-11-22 24-11-22 0.00% 0% Office and Canteen (O1) - PT Slab - Shade 24 Nov '22
Shade
1174 Office and Canteen (O3) - PT Slab - 12 d 25-11-22 07-12-22 0.00% 0% Office and Canteen (O3) - PT Slab - Shade 07 Dec '22
Shade
1175 Office and Canteen - Roof Work 63 d 22-11-22 28-01-23 0.00% 0% Office and Canteen - Roof Work 28 Jan '23
1176 Office and Canteen - Top Roof Part 35 d 22-11-22 27-12-22 0.00% 0% Office and Canteen - Top Roof Part 27 Dec '22
1177 Office and Canteen - Waterprofing 28 d 28-12-22 28-01-23 0.00% 0% Office and Canteen - Waterprofing 28 Jan '23
1178 Office and Canteen - Landscape Area 102 d 29-01-23 19-05-23 0.00% 0% Office and Canteen - Landscape Area
1179 Office and Canteen - Architectural Work 196 d 21-10-22 19-05-23 0.00% 0% Office and Canteen - Architectural Work
1180 Office and Canteen - Interior wall 112 d 21-10-22 15-02-23 0.00% 0% Office and Canteen - Interior wall 15 Feb '23
1181 Office and Canteen - Interior wall - 70 d 21-10-22 04-01-23 0.00% 0% Office and Canteen - Interior wall - Floor 1 04 Jan '23
Floor 1
1182 Office and Canteen - Interior wall - 70 d 12-11-22 25-01-23 0.00% 0% Office and Canteen - Interior wall - Floor M 25 Jan '23
Floor M
1183 Office and Canteen - Interior wall - 70 d 03-12-22 15-02-23 0.00% 0% Office and Canteen - Interior wall - Floor 2 15 Feb '23
Floor 2
1184 Office and Canteen - RC.Stair & 126 d 19-11-22 30-03-23 0.00% 0% Office and Canteen - RC.Stair & Finishing 30 Mar '23
Finishing
1185 Office and Canteen - Toilet wall tile 98 d 03-12-22 16-03-23 0.00% 0% Office and Canteen - Toilet wall tile 16 Mar '23
1186 Office and Canteen - Toilet wall tile - 42 d 03-12-22 18-01-23 0.00% 0% Office and Canteen - Toilet wall tile - Floor 1 18 Jan '23
Floor 1
1187 Office and Canteen - Toilet wall tile - 42 d 05-01-23 15-02-23 0.00% 0% Office and Canteen - Toilet wall tile - Floor M 15 Feb '23
Floor M
1188 Office and Canteen - Toilet wall tile - 42 d 02-02-23 16-03-23 0.00% 0% Office and Canteen - Toilet wall tile - Floor 2 16 Mar '23
Floor 2
1189 Office and Canteen - Toilet floor tile 84 d 19-01-23 19-04-23 0.00% 0% Office and Canteen - Toilet floor tile
1190 Office and Canteen - Toilet floor tile - 28 d 19-01-23 15-02-23 0.00% 0% Office and Canteen - Toilet floor tile - Floor 1 15 Feb '23
Floor 1
1191 Office and Canteen - Toilet floor tile - 28 d 16-02-23 16-03-23 0.00% 0% Office and Canteen - Toilet floor tile - Floor M 16 Mar '23
Floor M
1192 Office and Canteen - Toilet floor tile - 28 d 17-03-23 19-04-23 0.00% 0% Office and Canteen - Toilet floor tile - Floor 2
Floor 2
1193 Office and Canteen - Ceiling finishes 98 d 03-12-22 16-03-23 0.00% 0% Office and Canteen - Ceiling finishes 16 Mar '23
1194 Office and Canteen - Ceiling finishes - 56 d 03-12-22 01-02-23 0.00% 0% Office and Canteen - Ceiling finishes - Floor 1 01 Feb '23
Floor 1
1195 Office and Canteen - Ceiling finishes - 56 d 25-12-22 22-02-23 0.00% 0% Office and Canteen - Ceiling finishes - Floor M 22 Feb '23
Floor M
1196 Office and Canteen - Ceiling finishes - 56 d 19-01-23 16-03-23 0.00% 0% Office and Canteen - Ceiling finishes - Floor 2 16 Mar '23
Floor 2
1197 Office and Canteen - Foor finishes 98 d 19-01-23 05-05-23 0.00% 0% Office and Canteen - Foor finishes
1198 Office and Canteen - Foor finishes - 56 d 19-01-23 16-03-23 0.00% 0% Office and Canteen - Foor finishes - Floor 1 16 Mar '23
Floor 1
1199 Office and Canteen - Foor finishes - 56 d 09-02-23 07-04-23 0.00% 0% Office and Canteen - Foor finishes - Floor M 07 Apr '23
Floor M
1200 Office and Canteen - Foor finishes - 56 d 02-03-23 05-05-23 0.00% 0% Office and Canteen - Foor finishes - Floor 2
Floor 2
1201 Office and Canteen - 1F.~2F. 56 d 17-03-23 19-05-23 0.00% 0% Office and Canteen - 1F.~2F. Miscellaneous finishing
Miscellaneous finishing
1202 Office and Canteen - Façade, Curtain wall, 114 d 03-12-22 01-04-23 0.00% 0% Office and Canteen - Façade, Curtain wall, Door & Window 01 Apr '23
Door & Window
1203 Office and Canteen - Façade, Curtain 57 d 03-12-22 02-02-23 0.00% 0% Office and Canteen - Façade, Curtain wall, Door & Window - Floor 1 02 Feb '23
wall, Door & Window - Floor 1
1204 Office and Canteen (O2) - Façade, 19 d 03-12-22 22-12-22 0.00% 0% Office and Canteen (O2) - Façade, Curtain wall, Door & Window - Floor 1 22 Dec '22
Curtain wall, Door & Window - Floor 1
1205 Office and Canteen (O1) - Façade, 19 d 23-12-22 14-01-23 0.00% 0% Office and Canteen (O1) - Façade, Curtain wall, Door & Window - Floor 1 14 Jan '23
Curtain wall, Door & Window - Floor 1
1206 Office and Canteen (O3) - Façade, 19 d 15-01-23 02-02-23 0.00% 0% Office and Canteen (O3) - Façade, Curtain wall, Door & Window - Floor 1 02 Feb '23
Curtain wall, Door & Window - Floor 1
1207 Office and Canteen - Façade, Curtain 57 d 03-02-23 01-04-23 0.00% 0% Office and Canteen - Façade, Curtain wall, Door & Window - Floor 2 01 Apr '23
wall, Door & Window - Floor 2
1208 Office and Canteen (O2) - Façade, 19 d 03-02-23 21-02-23 0.00% 0% Office and Canteen (O2) - Façade, Curtain wall, Door & Window - Floor 2 21 Feb '23
Curtain wall, Door & Window - Floor 2
1209 Office and Canteen (O1) - Façade, 19 d 22-02-23 13-03-23 0.00% 0% Office and Canteen (O1) - Façade, Curtain wall, Door & Window - Floor 2 13 Mar '23
Curtain wall, Door & Window - Floor 2
1210 Office and Canteen (O3) - Façade, 19 d 14-03-23 01-04-23 0.00% 0% Office and Canteen (O3) - Façade, Curtain wall, Door & Window - Floor 2 01 Apr '23
Curtain wall, Door & Window - Floor 2
1211 Office and Canteen - MEP Installation by 70 d 04-11-22 18-01-23 0.00% 0% Office and Canteen - MEP Installation by other (Not TKC Scope of Work, TKC is not responsible) 18 Jan '23
other (Not TKC Scope of Work, TKC is not
responsible)

1212 Office and Canteen - MEP Installation 28 d 04-11-22 02-12-22 0.00% 0% Office and Canteen - MEP Installation Fixed Floor 1 02 Dec '22
Fixed Floor 1

1213 Office and Canteen - MEP Installation 0d 04-11-22 04-11-22 0.00% 0% Office and Canteen - MEP Installation Fixed Floor 1- Start 04 Nov '22
Fixed Floor 1- Start

1214 Office and Canteen - MEP Installation 0d 02-12-22 02-12-22 0.00% 0% Office and Canteen - MEP Installation Fixed Floor 1- Completed 02 Dec '22
Fixed Floor 1- Completed

1215 Office and Canteen - MEP Installation 28 d 25-11-22 24-12-22 0.00% 0% Office and Canteen - MEP Installation Fixed Floor M 24 Dec '22
Fixed Floor M

1216 Office and Canteen - MEP Installation 0d 25-11-22 25-11-22 0.00% 0% Office and Canteen - MEP Installation Fixed Floor M - Start 25 Nov '22
Fixed Floor M - Start

1217 Office and Canteen - MEP Installation 0d 24-12-22 24-12-22 0.00% 0% Office and Canteen - MEP Installation Fixed Floor M - Completed 24 Dec '22
Fixed Floor M - Completed

1218 Office and Canteen - MEP Installation 28 d 17-12-22 18-01-23 0.00% 0% Office and Canteen - MEP Installation Fixed Floor 2 18 Jan '23
Fixed Floor 2

1219 Office and Canteen - MEP Installation 0d 17-12-22 17-12-22 0.00% 0% Office and Canteen - MEP Installation Fixed Floor 2 - Start 17 Dec '22
Fixed Floor 2 - Start

1220 Office and Canteen - MEP Installation 0d 18-01-23 18-01-23 0.00% 0% Office and Canteen - MEP Installation Fixed Floor 2 - Completed 18 Jan '23
Fixed Floor 2 - Completed

1221 Office and Canteen - Inspection 20 d 20-05-23 08-06-23 0.00% 0%


1222 Office and Canteen - TKC Inspection 14 d 20-05-23 02-06-23 0.00% 0%
1223 Office and Canteen - Consultant & Owner 13 d 27-05-23 08-06-23 0.00% 0%
Inspection
1224 East Utility Building 161 d 19-06-22 02-12-22 19.33% 13% East Utility Building 02 Dec '22
1225 East Utility Building - Structural Work 139 d 19-06-22 10-11-22 22.66% 17% East Utility Building - Structural Work 10 Nov '22
1226 East Utility Building - Substructure 80 d 19-06-22 10-09-22 42.03% 26% East Utility Building - Substructure 10 Sep '22
1227 East Utility Building - Pile Cut-off 21 d 19-06-22 09-07-22 100.00% 100% East Utility Building - Pile Cut-off Level 09 Jul '22
Level
1228 East Utility Building (E1) - Pile 7d 19-06-22 25-06-22 100.00% 100% East Utility Building (E1) - Pile Cut-off Level 25 Jun '22
Cut-off Level
1229 East Utility Building (E2) - Pile 7d 26-06-22 02-07-22 100.00% 100% East Utility Building (E2) - Pile Cut-off Level 02 Jul '22
Cut-off Level
1230 East Utility Building (E3) - Pile 7d 03-07-22 09-07-22 100.00% 100% East Utility Building (E3) - Pile Cut-off Level 09 Jul '22
Cut-off Level
1231 East Utility Building - Soil backfill 27 d 26-06-22 23-07-22 81.48% 82% East Utility Building - Soil backfill under slab 23 Jul '22
under slab
1232 East Utility Building (E1) - Soil 9d 26-06-22 04-07-22 100.00% 100% East Utility Building (E1) - Soil backfill under slab 04 Jul '22
backfill under slab
1233 East Utility Building (E2) - Soil 9d 05-07-22 14-07-22 100.00% 100% East Utility Building (E2) - Soil backfill under slab 14 Jul '22
backfill under slab
1234 East Utility Building (E3) - Soil 9d 15-07-22 23-07-22 44.44% 45% East Utility Building (E3) - Soil backfill under slab 23 Jul '22
backfill under slab
1235 East Utility Building - Foundation 38 d 05-07-22 15-08-22 48.15% 0% East Utility Building - Foundation and Pier 15 Aug '22
and Pier
1236 East Utility Building (E1) - 20 d 05-07-22 25-07-22 100.00% 0% East Utility Building (E1) - Foundation and Pier 25 Jul '22
Foundation and Pier
1237 Excavation 7d 05-07-22 11-07-22 #ERROR 0% Excavation 11 Jul '22
1238 Check Pile deviation pile 27-07-22 7d 11-07-22 18-07-22 #ERROR 0% Check Pile deviation 18 Jul '22
deviation
issue
1239 Waiting Information for pile 27-07-22 4d 11-07-22 15-07-22 #ERROR 0% Waiting Information for Reinforcement 15 Jul '22
Reinforcement deviation
issue
1240 Make Shop Drawing pile 27-07-22 2d 16-07-22 17-07-22 #ERROR 0% Make Shop Drawing 17 Jul '22
deviation
issue
1241 Approve Shop Drawing pile 27-07-22 1d 18-07-22 18-07-22 #ERROR 0% Approve Shop Drawing 18 Jul '22
deviation
issue
1242 Rebar,Form,Concrete 7d 19-07-22 25-07-22 #ERROR 0% Rebar,Form,Concrete 25 Jul '22
1243 East Utility Building (E2) - 9d 26-07-22 05-08-22 44.44% 0% East Utility Building (E2) - Foundation and Pier 05 Aug '22
Foundation and Pier
1244 East Utility Building (E3) - 9d 06-08-22 15-08-22 0.00% 0% East Utility Building (E3) - Foundation and Pier 15 Aug '22
Foundation and Pier

14 OF 16
PROJECT : Relief Project
MASTER SCHEDULE (REV0.02) Dated 18Jul22
ID Task Name AdditionalTask Duration Start Finish % Plan %
task added Complete
date Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Ap
1245 East Utility Building - Gr.Beam 42 d 22-07-22 04-09-22 19.05% 0% East Utility Building -18
Gr.Beam
Jul, '22 04 Sep '22
1246 East Utility Building (E1) - Gr.Beam 14 d 22-07-22 06-08-22 57.14% 0% East Utility Building (E1) - Gr.Beam 06 Aug '22

1247 East Utility Building (E2) - Gr.Beam 14 d 07-08-22 21-08-22 0.00% 0% East Utility Building (E2) - Gr.Beam 21 Aug '22

1248 East Utility Building (E3) - Gr.Beam 14 d 22-08-22 04-09-22 0.00% 0% East Utility Building (E3) - Gr.Beam 04 Sep '22

1249 East Utility Building - Pca.Column 27 d 15-08-22 10-09-22 0.00% 0% East Utility Building - Pca.Column 10 Sep '22
1250 East Utility Building (E1) - 9d 15-08-22 23-08-22 0.00% 0% East Utility Building (E1) - Pca.Column 23 Aug '22
Pca.Column
1251 East Utility Building (E2) - 9d 24-08-22 01-09-22 0.00% 0% East Utility Building (E2) - Pca.Column 01 Sep '22
Pca.Column
1252 East Utility Building (E3) - 9d 02-09-22 10-09-22 0.00% 0% East Utility Building (E3) - Pca.Column 10 Sep '22
Pca.Column
1253 East Utility Building - Post Tension Slab 38 d 31-08-22 07-10-22 0.00% 0% East Utility Building - Post Tension Slab 07 Oct '22

1254 East Utility Building - PT Slab Floor 1 24 d 31-08-22 23-09-22 0.00% 0% East Utility Building - PT Slab Floor 1 23 Sep '22

1255 East Utility Building (E1) - PT Slab 8d 31-08-22 07-09-22 0.00% 0% East Utility Building (E1) - PT Slab Floor 1 07 Sep '22
Floor 1
1256 East Utility Building (E2) - PT Slab 8d 08-09-22 15-09-22 0.00% 0% East Utility Building (E2) - PT Slab Floor 1 15 Sep '22
Floor 1
1257 East Utility Building (E3) - PT Slab 8d 16-09-22 23-09-22 0.00% 0% East Utility Building (E3) - PT Slab Floor 1 23 Sep '22
Floor 1
1258 East Utility Building - PT Slab Roof 24 d 14-09-22 07-10-22 0.00% 0% East Utility Building - PT Slab Roof Floor 07 Oct '22
Floor
1259 East Utility Building (E1) - PT Slab 8d 14-09-22 21-09-22 0.00% 0% East Utility Building (E1) - PT Slab Roof Floor 21 Sep '22
Roof Floor
1260 East Utility Building (E2) - PT Slab 8d 22-09-22 29-09-22 0.00% 0% East Utility Building (E2) - PT Slab Roof Floor 29 Sep '22
Roof Floor
1261 East Utility Building (E3) - PT Slab 8d 30-09-22 07-10-22 0.00% 0% East Utility Building (E3) - PT Slab Roof Floor 07 Oct '22
Roof Floor
1262 East Utility Building - Roof Work 42 d 28-09-22 10-11-22 0.00% 0% East Utility Building - Roof Work 10 Nov '22
1263 East Utility Building - Aluminum trellis, 21 d 28-09-22 19-10-22 0.00% 0% East Utility Building - Aluminum trellis, Equip, FDN 19 Oct '22
Equip, FDN
1264 East Utility Building - Waterproofing 28 d 12-10-22 10-11-22 0.00% 0% East Utility Building - Waterproofing 10 Nov '22
1265 East Utility Building - Architectural Work 35 d 20-10-22 24-11-22 0.00% 0% East Utility Building - Architectural Work 24 Nov '22
1266 East Utility Building - Installation PC.wall 25 d 20-10-22 14-11-22 0.00% 0% East Utility Building - Installation PC.wall & Interior block wall & Plastering 14 Nov '22
& Interior block wall & Plastering
1267 East Utility Building - Shutter, Door & 18 d 04-11-22 21-11-22 0.00% 0% East Utility Building - Shutter, Door & Window 21 Nov '22
Window
1268 East Utility Building - Miscellaneous 14 d 11-11-22 24-11-22 0.00% 0% East Utility Building - Miscellaneous finishing 24 Nov '22
finishing
1269 East Utility Building - Inspection 14 d 18-11-22 01-12-22 0.00% 0% East Utility Building - Inspection 01 Dec '22
1270 East Utility Building - TKC Inspection 11 d 18-11-22 28-11-22 0.00% 0% East Utility Building - TKC Inspection 28 Nov '22
1271 East Utility Building - Consultant & Owner 3d 29-11-22 01-12-22 0.00% 0% East Utility Building - Consultant & Owner Inspection 01 Dec '22
Inspection
1272 Handover to MEP Contractor for 0d 02-12-22 02-12-22 0.00% 0% Handover to MEP Contractor for Installation Main Equipment 02 Dec '22
Installation Main Equipment
1273 South Utility Building 216 d 19-06-22 31-01-23 14.08% 7% South Utility Building 31 Jan '23
1274 South Utility Building - Structural Work 174 d 19-06-22 16-12-22 17.68% 13% South Utility Building - Structural Work 16 Dec '22
1275 South Utility Building - Substructure 89 d 19-06-22 19-09-22 36.71% 20% South Utility Building - Substructure 19 Sep '22
1276 South Utility Building - Pile Cut-off 21 d 19-06-22 09-07-22 100.00% 100% South Utility Building - Pile Cut-off Level 09 Jul '22
Level
1277 South Utility Building - Zone A - Pile 21 d 19-06-22 09-07-22 100.00% 100% South Utility Building - Zone A - Pile Cut-off Level 09 Jul '22
Cut-off Level
1278 South Utility Building - Zone B - Pile 21 d 19-06-22 09-07-22 100.00% 100% South Utility Building - Zone B - Pile Cut-off Level 09 Jul '22
Cut-off Level
1279 South Utility Building - Soil backfill 28 d 26-06-22 24-07-22 78.57% 80% South Utility Building - Soil backfill under slab 24 Jul '22
under slab
1280 South Utility Building - Foundation 55 d 03-07-22 30-08-22 33.33% 1% South Utility Building - Foundation and Pier 30 Aug '22
and Pier
1281 South Utility Building - Zone A - 55 d 03-07-22 30-08-22 33.33% 0% South Utility Building - Zone A - Foundation and Pier (GL.11-29) 30 Aug '22
Foundation and Pier (GL.11-29)
1282 Excavation 40 d 03-07-22 15-08-22 #ERROR 0% Excavation 15 Aug '22
1283 Check Pile deviation pile 27-07-22 40 d 05-07-22 17-08-22 #ERROR 0% Check Pile deviation 17 Aug '22
deviation
issue
1284 Waiting Information for pile 27-07-22 4d 11-07-22 15-07-22 #ERROR 0% Waiting Information for Reinforcement 15 Jul '22
Reinforcement deviation
issue
1285 Make Shop Drawing pile 27-07-22 2d 16-07-22 17-07-22 #ERROR 0% Make Shop Drawing 17 Jul '22
deviation
issue
1286 Approve Shop Drawing pile 27-07-22 1d 18-07-22 18-07-22 #ERROR 0% Approve Shop Drawing 18 Jul '22
deviation
issue
1287 Rebar,Form,Concrete 40 d 19-07-22 30-08-22 #ERROR 0% Rebar,Form,Concrete 30 Aug '22
1288 South Utility Building - Zone B - 39 d 09-07-22 20-08-22 23.08% 5% South Utility Building - Zone B - Foundation and Pier (GL.1.3-11) 20 Aug '22
Foundation and Pier (GL.1.3-11)
1289 South Utility Building - Gr.Beam 21 d 10-08-22 31-08-22 0.00% 0% South Utility Building - Gr.Beam 31 Aug '22
1290 South Utility Building - Zone A - 21 d 10-08-22 31-08-22 0.00% 0% South Utility Building - Zone A - Gr.Beam 31 Aug '22
Gr.Beam
1291 South Utility Building - Zone B - 18 d 13-08-22 30-08-22 0.00% 0% South Utility Building - Zone B - Gr.Beam 30 Aug '22
Gr.Beam
1292 South Utility Building - Pca.Column 38 d 13-08-22 19-09-22 0.00% 0% South Utility Building - Pca.Column 19 Sep '22

1293 South Utility Building - Zone A - 28 d 23-08-22 19-09-22 0.00% 0% South Utility Building - Zone A - Pca.Column 19 Sep '22
Pca.Column
1294 South Utility Building - Zone B - 28 d 13-08-22 09-09-22 0.00% 0% South Utility Building - Zone B - Pca.Column 09 Sep '22
Pca.Column
1295 South Utility Building - Roof Work 42 d 06-09-22 18-10-22 0.00% 0% South Utility Building - Roof Work 18 Oct '22
1296 South Utility Building - Roof Steel 28 d 06-09-22 03-10-22 0.00% 0% South Utility Building - Roof Steel Structure / RB2 03 Oct '22
Structure / RB2
1297 South Utility Building - Roof Matel 28 d 20-09-22 18-10-22 0.00% 0% South Utility Building - Roof Matel Sheet, Cladding 18 Oct '22
Sheet, Cladding
1298 South Utility Building - Post Tension 42 d 04-10-22 16-11-22 0.00% 0% South Utility Building - Post Tension Slab 16 Nov '22
Slab
1299 South Utility Building - PT Slab Floor 28 d 04-10-22 02-11-22 0.00% 0% South Utility Building - PT Slab Floor 1 02 Nov '22
1
1300 South Utility Building - PT Slab 21 d 04-10-22 26-10-22 0.00% 0% South Utility Building - PT Slab Floor 1 (GL.1.3-4) 26 Oct '22
Floor 1 (GL.1.3-4)
1301 South Utility Building - PT Slab 14 d 19-10-22 02-11-22 0.00% 0% South Utility Building - PT Slab Floor 1 (GL.4-11) 02 Nov '22
Floor 1 (GL.4-11)
1302 South Utility Building - PT Slab Floor 28 d 19-10-22 16-11-22 0.00% 0% South Utility Building - PT Slab Floor 2 16 Nov '22
2
1303 South Utility Building - PT Slab 21 d 19-10-22 09-11-22 0.00% 0% South Utility Building - PT Slab Floor 2 (GL.19-27) 09 Nov '22
Floor 2 (GL.19-27)
1304 South Utility Building - PT Slab 21 d 27-10-22 16-11-22 0.00% 0% South Utility Building - PT Slab Floor 2 (GL.1.3-4) 16 Nov '22
Floor 2 (GL.1.3-4)
1305 South Utility Building - PT Slab 14 d 03-11-22 16-11-22 0.00% 0% South Utility Building - PT Slab Floor 2 (GL.4-11) 16 Nov '22
Floor 2 (GL.4-11)
1306 South Utility Building - Stair Work 36 d 10-11-22 16-12-22 0.00% 0% South Utility Building - Stair Work 16 Dec '22
1307 South Utility Building - RC.Stair, Link 28 d 10-11-22 08-12-22 0.00% 0% South Utility Building - RC.Stair, Link Bridge 08 Dec '22
Bridge
1308 South Utility Building - External Stl. 18 d 28-11-22 16-12-22 0.00% 0% South Utility Building - External Stl. Staircase 16 Dec '22
Staircase
1309 South Utility Building - Water Tank 137 d 20-07-22 09-12-22 0.00% 0% South Utility Building - Water Tank 09 Dec '22
1310 South Utility Building - WT.Base slab, 35 d 20-07-22 26-08-22 0.00% 0% South Utility Building - WT.Base slab, RC. Slab 26 Aug '22
RC. Slab
1311 South Utility Building - WT.Base slab, 10 d 20-07-22 31-07-22 0.00% 0% South Utility Building - WT.Base slab, RC. Slab (GL.27-Y) 31 Jul '22
RC. Slab (GL.27-Y)
1312 South Utility Building - WT.Base slab, 10 d 23-07-22 03-08-22 0.00% 0% South Utility Building - WT.Base slab, RC. Slab (GL.22-27) 03 Aug '22
RC. Slab (GL.22-27)
1313 South Utility Building - WT.Base slab, 10 d 31-07-22 09-08-22 0.00% 0% South Utility Building - WT.Base slab, RC. Slab (GL.19-22) 09 Aug '22
RC. Slab (GL.19-22)
1314 South Utility Building - WT.Base slab, 10 d 09-08-22 19-08-22 0.00% 0% South Utility Building - WT.Base slab, RC. Slab (GL.15-19) 19 Aug '22
RC. Slab (GL.15-19)
1315 South Utility Building - WT.Base slab, 10 d 17-08-22 26-08-22 0.00% 0% South Utility Building - WT.Base slab, RC. Slab (GL.11-1) 26 Aug '22
RC. Slab (GL.11-1)
1316 South Utility Building - WT.RC.Wall 41 d 27-08-22 06-10-22 0.00% 0% South Utility Building - WT.RC.Wall 06 Oct '22
1317 South Utility Building - WT.RC.Wall 13 d 27-08-22 08-09-22 0.00% 0% South Utility Building - WT.RC.Wall (GL.23-27) 08 Sep '22
(GL.23-27)
1318 South Utility Building - WT.RC.Wall 13 d 06-09-22 18-09-22 0.00% 0% South Utility Building - WT.RC.Wall (GL.22-24) 18 Sep '22
(GL.22-24)
1319 South Utility Building - WT.RC.Wall 13 d 17-09-22 29-09-22 0.00% 0% South Utility Building - WT.RC.Wall (GL.19-22) 29 Sep '22
(GL.19-22)
1320 South Utility Building - Pca.column at 7d 09-09-22 15-09-22 0.00% 0% South Utility Building - Pca.column at WT.area (GL.23-27) 15 Sep '22
WT.area (GL.23-27)
1321 South Utility Building - Pca.column at 7d 19-09-22 25-09-22 0.00% 0% South Utility Building - Pca.column at WT.area (GL.22-24) 25 Sep '22
WT.area (GL.22-24)
1322 South Utility Building - Pca.column at 7d 30-09-22 06-10-22 0.00% 0% South Utility Building - Pca.column at WT.area (GL.19-22) 06 Oct '22
WT.area (GL.19-22)
1323 South Utility Building - WT.Top slab 28 d 01-10-22 30-10-22 0.00% 0% South Utility Building - WT.Top slab 30 Oct '22
1324 South Utility Building - WT.Top slab 14 d 01-10-22 15-10-22 0.00% 0% South Utility Building - WT.Top slab (GL.22-27) 15 Oct '22
(GL.22-27)
1325 South Utility Building - WT.Top slab 14 d 16-10-22 30-10-22 0.00% 0% South Utility Building - WT.Top slab (GL.19-22) 30 Oct '22
(GL.19-22)
1326 South Utility Building - Rf.steel 21 d 31-10-22 20-11-22 0.00% 0% South Utility Building - Rf.steel structure / RB2 20 Nov '22
structure / RB2
1327 South Utility Building - Roof metal sht, 25 d 14-11-22 09-12-22 0.00% 0% South Utility Building - Roof metal sht, Cladding 09 Dec '22
Cladding
1328 South Utility Building - Architect Work 77 d 03-11-22 23-01-23 0.00% 0% South Utility Building - Architect Work 23 Jan '23
1329 South Utility Building - 1F.&2F. 49 d 03-11-22 22-12-22 0.00% 0% South Utility Building - 1F.&2F. Installation PC.wall /Painting work 22 Dec '22
Installation PC.wall /Painting work

15 OF 16
PROJECT : Relief Project
MASTER SCHEDULE (REV0.02) Dated 18Jul22
ID Task Name AdditionalTask Duration Start Finish % Plan %
task added Complete
date Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Ap
1330 South Utility Building - 1F&2F. Interior 35 d 17-11-22 22-12-22 0.00% 0% 18 Jul, '22 South Utility Building - 1F&2F. Interior wall 22 Dec '22
wall
1331 South Utility Building - 1F&2F. Wall tile & 35 d 24-11-22 29-12-22 0.00% 0% South Utility Building - 1F&2F. Wall tile & Celing finishes 29 Dec '22
Celing finishes
1332 South Utility Building - 1F&2F. Shutter, 35 d 01-12-22 09-01-23 0.00% 0% South Utility Building - 1F&2F. Shutter, Door & Window 09 Jan '23
Door & Window
1333 South Utility Building - 1F.&2F. Floor 35 d 09-12-22 16-01-23 0.00% 0% South Utility Building - 1F.&2F. Floor finishes 16 Jan '23
finishes
1334 South Utility Building - 1F.&2F. 28 d 23-12-22 23-01-23 0.00% 0% South Utility Building - 1F.&2F. Miscellaneous finishing 23 Jan '23
Miscellaneous finishing
1335 South Utility Building - MEP Work by other 87 d 26-08-22 23-11-22 0.00% 0% South Utility Building - MEP Work by other (Not TKC Scope of Work, TKC is not responsible) 23 Nov '22
(Not TKC Scope of Work, TKC is not
responsible)
1336 South Utility Building - MEP Work - Roof 0d 26-08-22 26-08-22 0.00% 0% South Utility Building - MEP Work - Roof Truss (Installation Fire fighting pipe) 26 Aug '22
Truss (Installation Fire fighting pipe)

1337 South Utility Building - Roof Truss - 0d 26-08-22 26-08-22 0.00% 0% South Utility Building - Roof Truss - Completed MEP Installation Fire Fighting pipe at Roof Truss 26 Aug '22
Completed MEP Installation Fire
Fighting pipe at Roof Truss
1338 South Utility Building - MEP Installation 14 d 09-11-22 23-11-22 0.00% 0% South Utility Building - MEP Installation Fixed 23 Nov '22
Fixed
1339 South Utility Building - MEP 0d 09-11-22 09-11-22 0.00% 0% South Utility Building - MEP Installation Fixed - MEP Start 09 Nov '22
Installation Fixed - MEP Start
1340 South Utility Building - MEP 0d 23-11-22 23-11-22 0.00% 0% South Utility Building - MEP Installation Fixed - MEP Completed 23 Nov '22
Installation Fixed - MEP Completed
1341 South Utility Building - Inspection 15 d 16-01-23 30-01-23 0.00% 0% South Utility Building - Inspection 30 Jan '23
1342 South Utility Building - TKC Inspection 8d 16-01-23 23-01-23 0.00% 0% South Utility Building - TKC Inspection 23 Jan '23
1343 South Utility Building - Consultant & 7d 24-01-23 30-01-23 0.00% 0% South Utility Building - Consultant & Owner Inspection 30 Jan '23
Owner Inspection
1344 South Utility Building - Handover to Owner 1d 31-01-23 31-01-23 0.00% 0% South Utility Building - Handover to Owner 31 Jan '23

1345 External Work 302 d 14-07-22 30-05-23 1.70% 0% External Work


1346 External Work - Retention pond 213 d 14-07-22 21-02-23 2.35% 0% External Work - Retention pond 21 Feb '23
1347 Retention Pond - Soil Excavation 63 d 14-07-22 17-09-22 7.94% 0% Retention Pond - Soil Excavation 17 Sep '22
1348 Retention Pond - Finishing work 30 d 23-01-23 21-02-23 0.00% 0% Retention Pond - Finishing work 21 Feb '23
1349 External Work - Boundary fence & Main 292 d 16-07-22 22-05-23 1.03% 0% External Work - Boundary fence & Main entrance
entrance
1350 External Work - Boundary fence 292 d 16-07-22 22-05-23 1.03% 0% External Work - Boundary fence
1351 Mock up Boundary fence type 2 (West 14 d 16-07-22 31-07-22 21.43% 0% Mock up Boundary fence type 2 (West Side) 31 Jul '22
Side)
1352 Boundary fence Team 1 - At Future 114 d 01-08-22 25-11-22 0.00% 0% Boundary fence Team 1 - At Future Expansion (West Side) 25 Nov '22
Expansion (West Side)
1353 Mock up Boundary fence type 3 (North 24 d 20-07-22 15-08-22 0.00% 0% Mock up Boundary fence type 3 (North Side to East Side) 15 Aug '22
Side to East Side)
1354 Mock up Boundary fence type 1 (North 22 d 01-08-22 23-08-22 0.00% 0% Mock up Boundary fence type 1 (North Side to East Side) 23 Aug '22
Side to East Side)
1355 Boundary fence Team 2 - At Main 160 d 28-08-22 10-02-23 0.00% 0% Boundary fence Team 2 - At Main Factory (North Side to East Side) 10 Feb '23
Factory (North Side to East Side)
1356 Boundary fence Team 3 - At Parking 130 d 25-10-22 09-03-23 0.00% 0% Boundary fence Team 3 - At Parking Area (South Side) 09 Mar '23
Area (South Side)
1357 Boundary fence Team 4 - At Retention 140 d 21-12-22 22-05-23 0.00% 0% Boundary fence Team 4 - At Retention Pond (South Side)
Pond (South Side)
1358 External Work - Main entrance 60 d 16-03-23 22-05-23 0.00% 0% External Work - Main entrance
1359 External Work - Stormwater drainage 286 d 01-08-22 30-05-23 0.00% 0% External Work - Stormwater drainage system
system
1360 Stormwater drainage system Zone 1 - At 132 d 01-08-22 14-12-22 0.00% 0% Stormwater drainage system Zone 1 - At Retention Pond 14 Dec '22
Retention Pond
1361 Stormwater drainage system Zone 2 - At 168 d 23-08-22 13-02-23 0.00% 0% Stormwater drainage system Zone 2 - At Parking Area (South side) 13 Feb '23
Parking Area (South side)
1362 Stormwater drainage system Zone 3 - At 182 d 30-09-22 08-04-23 0.00% 0% Stormwater drainage system Zone 3 - At Future Expansion 08 Apr '23
Future Expansion
1363 Stormwater drainage system Zone 4 - At 213 d 15-10-22 30-05-23 0.00% 0% Stormwater drainage system Zone 4 - At Main Factory
Main Factory
1364 External Work - Guardhouse & Custrm 180 d 11-09-22 17-03-23 0.00% 0% External Work - Guardhouse & Custrm office 17 Mar '23
office
1365 External Work - Road & Pavement, 223 d 04-10-22 30-05-23 0.00% 0% External Work - Road & Pavement, Loading dock, Truck scale
Loading dock, Truck scale
1366 Road & Pavement Zone 1 - At Retention 104 d 04-10-22 22-01-23 0.00% 0% Road & Pavement Zone 1 - At Retention Pond 22 Jan '23
Pond
1367 Road & Pavement Zone 2 - At Parking 133 d 27-10-22 14-03-23 0.00% 0% Road & Pavement Zone 2 - At Parking Area (South side) 14 Mar '23
Area (South side)
1368 Road & Pavement Zone 3 - At Future 154 d 27-11-22 13-05-23 0.00% 0% Road & Pavement Zone 3 - At Future Expansion
Expansion
1369 Road & Pavement Zone 4 - At Main 157 d 12-12-22 30-05-23 0.00% 0% Road & Pavement Zone 4 - At Main Factory
Factory
1370 External Work - Car & Motorcycle parking 194 d 27-10-22 22-05-23 0.00% 0% External Work - Car & Motorcycle parking (Southside)
(Southside)
1371 External Work - VIP & Visitor parking 168 d 30-11-22 30-05-23 0.00% 0% External Work - VIP & Visitor parking (Northside)
(Northside)
1372 External Work - Green area & Landscape 98 d 13-02-23 30-05-23 0.00% 0% External Work - Green area & Landscape
1373 External Work - Truck Scale 215 d 04-10-22 22-05-23 0.00% 0% External Work - Truck Scale
1374 External Work - Walk Way 238 d 11-09-22 22-05-23 0.00% 0% External Work - Walk Way
1375 External Work - Pipe Rack 81 d 22-02-23 22-05-23 0.00% 0% External Work - Pipe Rack
1376 MEP Work by Other Contractor (Not TKC 242 d 15-08-22 27-04-23 0.00% 0% MEP Work by Other Contractor (Not TKC Scope of Work, TKC is not responsible)
Scope of Work, TKC is not responsible)
1377 MEP Work - Main Factory 242 d 15-08-22 27-04-23 0.00% 0% MEP Work - Main Factory
1378 MEP Work - Main Factory Zone A 242 d 15-08-22 27-04-23 0.00% 0% MEP Work - Main Factory Zone A
1379 Zone A1 - MEP Work at Roof Truss 5d 15-08-22 19-08-22 0.00% 0% Zone A1 - MEP Work at Roof Truss (Installation Fire fighting pipe) 19 Aug '22
(Installation Fire fighting pipe)
1380 Zone A2 - MEP Work at Roof Truss 5d 28-08-22 01-09-22 0.00% 0% Zone A2 - MEP Work at Roof Truss (Installation Fire fighting pipe) 01 Sep '22
(Installation Fire fighting pipe)
1381 Zone A3 - MEP Work at Roof Truss 5d 21-09-22 25-09-22 0.00% 0% Zone A3 - MEP Work at Roof Truss (Installation Fire fighting pipe) 25 Sep '22
(Installation Fire fighting pipe)
1382 Zone A - MEP Installation Work (EE, 56 d 18-11-22 17-01-23 0.00% 0% Zone A - MEP Installation Work (EE, AC and SN) 17 Jan '23
AC and SN)
1383 Zone A - Testing & Commissioning 14 d 09-04-23 27-04-23 0.00% 0% Zone A - Testing & Commissioning
1384 MEP Work - Main Factory Zone B 242 d 15-08-22 27-04-23 0.00% 0% MEP Work - Main Factory Zone B
1385 Zone B1 - MEP Work at Roof Truss 5d 15-08-22 19-08-22 0.00% 0% Zone B1 - MEP Work at Roof Truss (Installation Fire fighting pipe) 19 Aug '22
(Installation Fire fighting pipe)
1386 Zone B2 - MEP Work at Roof Truss 5d 28-08-22 01-09-22 0.00% 0% Zone B2 - MEP Work at Roof Truss (Installation Fire fighting pipe) 01 Sep '22
(Installation Fire fighting pipe)
1387 Zone B3 - MEP Work at Roof Truss 5d 11-09-22 15-09-22 0.00% 0% Zone B3 - MEP Work at Roof Truss (Installation Fire fighting pipe) 15 Sep '22
(Installation Fire fighting pipe)
1388 Zone B4 - MEP Work at Roof Truss 5d 25-09-22 29-09-22 0.00% 0% Zone B4 - MEP Work at Roof Truss (Installation Fire fighting pipe) 29 Sep '22
(Installation Fire fighting pipe)
1389 Zone B - MEP Installation Work (EE, AC 56 d 15-11-22 14-01-23 0.00% 0% Zone B - MEP Installation Work (EE, AC and SN) 14 Jan '23
and SN)
1390 Zone B - Testing & Commissioning 14 d 09-04-23 27-04-23 0.00% 0% Zone B - Testing & Commissioning
1391 MEP Work - Office and Canteen 162 d 05-11-22 27-04-23 0.00% 0% MEP Work - Office and Canteen
1392 Office and Canteen - MEP Installation 28 d 05-11-22 02-12-22 0.00% 0% Office and Canteen - MEP Installation Work (EE, AC and SN) - Floor 1 02 Dec '22
Work (EE, AC and SN) - Floor 1
1393 Office and Canteen - MEP Installation 28 d 26-11-22 24-12-22 0.00% 0% Office and Canteen - MEP Installation Work (EE, AC and SN) - Floor M 24 Dec '22
Work (EE, AC and SN) - Floor M
1394 Office and Canteen - MEP Installation 28 d 18-12-22 18-01-23 0.00% 0% Office and Canteen - MEP Installation Work (EE, AC and SN) - Floor 2 18 Jan '23
Work (EE, AC and SN) - Floor 2
1395 Office and Canteen - Testing & 14 d 09-04-23 27-04-23 0.00% 0% Office and Canteen - Testing & Commissioning
Commissioning
1396 MEP Work - East Building 120 d 03-12-22 08-04-23 0.00% 0% MEP Work - East Building 08 Apr '23
1397 East Building - Installation Main 120 d 03-12-22 08-04-23 0.00% 0% East Building - Installation Main Equipment 08 Apr '23
Equipment
1398 MEP Work - South Building 92 d 22-08-22 23-11-22 0.00% 0% MEP Work - South Building 23 Nov '22
1399 South Building - MEP Work at Roof Truss 5d 22-08-22 26-08-22 0.00% 0% South Building - MEP Work at Roof Truss (Installation Fire fighting pipe) 26 Aug '22
(Installation Fire fighting pipe)
1400 South Building - MEP Installation Work 14 d 10-11-22 23-11-22 0.00% 0% South Building - MEP Installation Work (EE, AC and SN) 23 Nov '22
(EE, AC and SN)
1401 Handover & Practical Completion 90 d 13-03-23 18-06-23 0.00% 0% Handover & Practical Completion

1402 Handover & Practical Completion - As Built 90 d 13-03-23 18-06-23 0.00% 0% Handover & Practical Completion - As Built Drawing
Drawing
1403 Handover & Practical Completion - Completed 90 d 13-03-23 18-06-23 0.00% 0% Handover & Practical Completion - Completed Document
Document
1404 Practical Completion 0d 18-06-23 18-06-23 0.00% 0%