Download as pdf or txt
Download as pdf or txt
You are on page 1of 28

Best Reliability And Maintenance Practices And Return On Investment

(Implementation)
Rob Probst, Norske Skog Tasman
August 1, 2008

Summary: Empirical data has been gathered during a five The crafts are covered by two different trade unions. There
year implementation of a Maintenance Best Practices are 422 people working at the mill. There are 30 (FTE)
program at Fonterra Dairy Cooperative in New Zealand. full time equivalent contract maintenance craftspersons
The basis of the Fonterra MBP program is the IDCON, Inc. used primarily on shutdown work. Theses craftspersons
CBP audit and handbooks. Performance data collected plus the Norske Skog craftspersons employed “on the
from 2002 – 2007 has been used by MaintainNZ, (an tools” result in a total of 118 (MPP), maintenance
industry-based, non-profit maintenance training & performing personnel,
resource organization in New Zealand), to develop a Return
on Investment (ROI) model that can be used to project An IDCON “Current Best Practices Maintenance” audit
financial benefits for maintenance and reliability best was conducted at the Norske Skog Tasman mill in April,
practices program implementation. It provides an 2007. The purpose of the audit was to establish the current
indicative value for operational and maintenance state of practice and define opportunities to close the “gap”
improvement that is directly attributable to measured to maintenance best practices. As a result of previous
improvement in the delivery of “Best Reliability and experience at the Fonterra Dairy Cooperative, the author
Maintenance” practices. The Return on Investment (ROI) was well aware of the direct connection between improved
model is used to predict the time to implement maintenance operational and financial performance and the improvement
and reliability best practices at Norske Skog Tasman in maintenance best practices.
newsprint mill in Kawerau, New Zealand as well as the
investment cost and financial benefit. The model may be Following the IDCON audit, a steering group consisting of
used to predict financial return on investment at other maintenance and engineering management as well as
manufacturing operations. The elements of “Best operations and engineering union representatives agreed to
Reliability and Maintenance Practices,” are reviewed to focus on three top priorities that would help to close the
illustrate the premise and mechanics behind the empirical “gap” in crucial “execution-based” areas; planning and
model. A technical description of the model follows this scheduling , preventive maintenance and root cause
paper. problem elimination (RCPE).

Initiatives were established during the remainder of 2007


Norkse Skog Tasman ROI Case Study to implement a “daily/weekly” planning and scheduling
discipline as well as an analysis of preventive maintenance
The Norske Skog Tasman newsprint mill consists of one practices. A program was also initiated to establish a
mechanical pulp mill and two newsprint machines which listing of top downtime and cost incidents related to
are capable of manufacturing in excess of 300,000 tonnes equipment failure, and conduct root cause analysis to
of newsprint per annum. eliminate reoccurrences.

The mill has been in operation since 1954 . Both paper Tracking of equipment breakdowns and operational and
machines have recently been rebuilt, (2005-2007), and this financial losses associated with the breakdowns was also
work along with the ample supply of geo-thermally initiated. Automated downtime and cost figures were
generated electricity, virgin fiber supply from pine forest tracked prior to the maintenance best practices program
plantations, and ample water supply provide a firm implementation in 2007, but the numbers were not
foundation for success. The paper machines are currently accumulated into totals. The total R&M expenditure for
running at an average of 83.5% total efficiency with a unplanned downtime, (breakdowns) in 2007 was estimated
target of 88%. Increased time and paper efficiency are a to be $1.25 Million dollars.
necessity.
The associated, “equipment-related loss” or “Cost of
The Equipment Replacement Value (ERV) of the paper Failure” was estimated to be $5.5 Million dollars. The
mill is approximately NZ $1 Billion dollars. Annual equipment downtime was directly related to reduced
maintenance expenditure is NZ $24 Million dollars. There EBITDA (earnings be interest, taxes, depreciation and
are 10 fulltime professional engineers (electrical, amortization), associated with lost sales volumes as well as
mechanical) supporting the maintenance and capital project quality, yield losses and increased energy, raw materials
work at the mill. There are 88 fulltime maintenance staff and labor. These 2007 results confirm the “Iceberg”
which include management staff and crafts. Craft effect of equipment related losses where unnecessary
disciplines are mechanical or electrical/instrumentation. maintenance costs (e.g. breakdowns) are 25% of the
“hidden” equipment related loss (COF) costs.
(See Figure 1)
to occur 48 months after the full initiation of the
maintenance best practices program. (See Figure 2)

• Equipment Failure
It’s important to note that an additional time period needs
Labour,
Labour, Material, Repair Cost to be added to the “Total Months to Reach Target” value in
Overheads
the ROI model. This additional time value is dependent on
Equipment Downtime the readiness and commitment of the organization to
(Availability)
• Hidden Equipment
Reliability (Stop/Start) initiate the program. The larger the organization and the
Quality Failure-Related Losses more “cultural inertia” that exists, the longer the period
Impact on larger
inventories prior to full initiation of the program. There may also be
Longer
Safety
Lost Profit
Customer other mitigating factors present that enable or delay
Lead times
implementation, (e.g. collective employment negotiations).
Waste
Increased
The “lead in” period at Norske Skog Tasman has been 12
Cost of
repairs 126 months. In spite of the length of the “lead in” or “bow
wave” period, there are still likely to be positive behavior
Figure # 1: The Iceberg Effect and financial results simply as a result of increased
discretionary effort and higher standards in “pockets” of the
The R&M costs and equipment-related losses, and other organization that are more rapidly embracing the change
information mentioned, form part of the basis for predicting initiative.
the ROI for implementation of a maintenance and
reliability improvement program. Additional information
required is the current equipment availability, total yield Return on Investment for MBP at Norske Skog
loss, energy consumption, engineering stores value, Improved Practices = Reduced Cost of Failure (COF)
additional sales potential and sales margin (EBITDA), Projected 66% breakdown reduction
number of employees and earnings per employee. $1.25M on the top in 2007

Projection 2012
All of these values can be favorably affected by the
introduction of improved maintenance practices. In Labour,
Labour, Material,
• Equipment Failure
Repair Cost
$ 412K
addition, estimates can be made for additional costs
Overheads

Equipment Downtime
(Availability) • Equipment Failure
• Hidden Equipment
required to educate employees about maintenance best Reliability (Stop/Start) Labour,
Labour, Material, Repair Cost
Overheads

Quality Failure-Related Losses Equipment Downtime


(Availability)
• Hidden Equipment
Reliability (Stop/Start)

Quality Failure-Related Losses


Impact on larger Impact on larger
inventories
inventories

practices and create/improve maintenance and reliability


Longer
Safety Customer
Lost Profit
Longer
Lead times

Safety Customer Waste


Increased
Lost Profit Lead times
Cost of
repairs 126

systems and practices. For instance, it may be necessary to Waste


Increased
Cost of
repairs 126

create and train employees in a root cause analysis program $ 1.82M

to eliminate recurring operations and maintenance


$5.5M on the bottom (COF)
problems or to implement a new FMECA-based preventive
4
maintenance program where only a “reactive” breakdown
response existed before.
Figure # 2: Shrinking Iceberg
Once these “input” values have been estimated they can be
loaded into the (ROI) model and a prediction can be made The second scenario for projecting the benefit is using the
for the time for maintenance best practices implementation ROI model. The ROI model , or calculator, projects a net
and the potential ROI , NPV financial benefit. This value benefit of $4.3 Million dollars over a 48 month
can then be substantiated by defining potential savings and implementation period with an implementation cost of
a business case can be developed to support the expenditure $941K. This is roughly equivalent to the simplified
for MBP program implementation. “Iceberg” benefit projection described before. The total
NPV for the project is $3.88Million dollars with an IRR of
There are several ways to look at the potential for 399%. This is the projected financial benefit from an
improvement. The first scenario is simply looking at the improvement from 38% to 70% in maintenance practices
projected reduction in breakdowns and associated cost of measured with the IDCON, Inc audit.
failure (COF) reduction. This does not take into account
the costs for the program implementation or some of the The “front end” of the ROI Calculator, (See Figure 3)
additional savings that may not be captured as a direct shows the inputs for the ROI calculation at Norske Skog
result of unplanned downtime reduction incidents (e.g. Tasman. CBP audit score figure was entered following
energy savings, inventory reduction, headcount reduction conduct of the audit in 2007. The Input CBP score is 38%.
opportunities). That scenario will be explored later in the This is a crucial value in the modeling process as the
paper. increase in CBP score is used to project the increase in
plant availability and reduction in percentage of
In Norske Skog Tasman’s case, the predicted reduction of Breakdown Work Orders. The rate of increase is the
breakdowns is 66% (from 6% to 2% of total workders). foundation for projected financial benefits, time to reach
This means that the submerged portion of the “Iceberg” is target availability as well as costs associated with the MBP
also reduced 66%. Total annual reduction in costs and program implementation.
expenditure is from $6.72M to $2.32M. This is projected
MAINTENANCE BEST PRACTICES ROI CALCULATOR
MBP KEY PERFORMANCE INDICATORS

MBP AUDIT SCORE


20 25 30 35 40 45 50 55 60 65 70
75
COMMITMENT INDUSTRY TYPE Pulp & Paper
Excellent Average Poor
Good Low

ANNUAL R&M SPEND $ 24,000,000 ANNUAL BREAKDOWN W.O.% 6.0

MAINTENANCE PERSONNEL (MPP) 118 ANNUAL EARNINGS / MPP $ 85,000

EQUIPMENT REPLACEMENT VALUR (ERV) $ 1,000,000,000 ENGINEERING STORES VALUE $ 10,000,000

PLANT KEY PERFORMANCE INDICATORS

ANNUAL GRADE LOSS $ 2,000,000 ANNUAL TONNES OF PRODUCT 300000

ANNUAL YIELD LOSS $ 2,000,000 MARGIN PER TONNE $ 200

ANNUAL ENERGY COST $ 34,000,000 ANNUAL EARNING OPERATOR $ 85,000

AVAILABILITY % 94.0 TOTAL OPERATORS 150

Figure #3: ROI Calculator (Input)


The “Commitment” factor shown in the input table is method can be created to estimate the Commitment Factor.
derived from a simple table that estimates the The Commitment Factor does not account for other issues
organization’s willingness to support the MBP program. that can delay or shorten the MBP program
The Commitment score changes the slope of the CBP implementation, (e.g. re-organizations, leadership changes,
score, Availability and Breakdown Work Order curves used industrial action, recessions).
by the model to predict the rate of improvement. The five
elements that comprise the Commitment Factor estimate
are shown in Figure 4. It is highly likely that a more robust
Calculate the Commitment Factor

1- Does CEO/GM support the MBP initiative wholeheartedly……………….... ? No


0
Do Management have MBP KPI’s as part of their Performance agreements (e.g.
2- Plan/Scheduled work completion %, RCPE completion %, Preventive Maintenance No
% Completion)…………………………………………………..... ?
0
Are Maintenance and Operations jointly responsible for the R&M budget
3- No
expenditure……………………………………………………………………....….?
0
Is the Maintenance improvement program part of the company strategy with
4- Yes
money and additional staff to support the development and implementation ?
1
Is the MBP improvement program viewed as a medium term (5 to 7 year)
5- Yes
program…………………………………………………………………………….. ?
1
Back to ROI ENGINE TOTAL COMMITMENT : Low

Figure #4: Commitment Factor


Headcount figures and earnings for MPP (maintenance organization, the costs can be reduced
performing personnel) and Operators are also inputted to accordingly.
the ROI calculator (See Figure 5), to estimate a number of • Calculation of potential savings in inventory
costs and several benefits: carrying costs
• Need for increase in MPP to support plant and
subsequent salary increase Annual Grade Loss is required to calculate the loss when
• Total cost for training of both MPP and Operators product is downgraded to lower levels from “Prime” or A-
in root cause problem elimination, maintenance Grade. This invariably results in a loss of profit to the
best practices approach company. The model takes just 10% of this loss into
• Potential savings from headcount decrease for consideration when calculating potential savings in this
MPP and Operators. category, as empirical evidence indicates that 10% of the
grade loss is associated with equipment malfunction or
Equipment Replacement Value is used in several breakdown.
calculations:
• ERV/MPP yields a p.a. value (usually in Millions Yield Loss, (e.g. fiber loss to drain in the case of newsprint
of dollars) that each MPP can maintain. If the manufacturing), must be entered. The model takes just
value is greater than a threshold value for the 10% of the total yield loss figure to calculate potential
industry (e.g. $15Million/MPP) then a calculation yield-related savings as a result of the MPB program. The
is made to increase the headcount for MPP. assumption is made , (based on empirical evidence), that
• ERV is also used to estimate the potential the balance of the yield and grade loss recoveries and
reduction in R&M expenditure (as a % of ERV). savings will be made through process engineering, capital ,
This is also based on benchmark threshold values lean operations projects or other means that are not related
for industry. to equipment-related loss reduction.
• The ERV is used to calculate the cost for
implementation of new maintenance processes; Annual Energy Cost figure is entered next. When
preventive maintenance program, root cause unplanned downtime occurs, energy is consumed in order
problem solving sessions, and purchase of to keep process equipment and raw materials circulating,
condition monitoring tools like vibration pens, heated, cooled , moist or dry until equipment is repaired
alignment equipment etc. The assumption is and processing is resumed. As unplanned downtime is
made in calculating these costs that consultants reduced, the energy consumption per unit of product is also
will be utilized and crafts-persons will be reduced. The opportunity for energy savings is based on
“backfilled” to develop the new systems. If the gap between current plant availability and 98.5% which
these items and systems already exist within an is assumed to be maximum plant availability attainable. A
conservative approach is taken when calculating the
opportunity for MBP-related improvements by limiting the
total energy cost reduction to 5% of the potential calculated
using the availability “gap.” Engineering Stores Value is required to estimate the
potential inventory carrying cost savings associated with
Availability is the overall plant availability figure at the MBP improvements. The assumption is made that
time of the CBP audit. The availability is the % of time inventory values will be reduced to a minimum of 0.25%
that the equipment is ready to run. It is one of the three of the ERV. The model calculates the difference between
elements required for calculation of OEE (Overall the current value of the Inventory/ERV ratio and estimates
Equipment Effectiveness), so there is no consideration for the potential carrying cost savings over the established life
speed and quality when calculating the value. The of the MBP program.
availability value and the gap to 98.5%, which is the
benchmark best practice maximum figure, are crucial Annual Tonnes of Product is one of the most leveraging
values in the calculation of outputs with the ROI elements of the model. If the manufacturing output of the
Calculator. The increase in the CBP score is directly organization is limited by raw materials or demand, (e.g.
proportional to the projected availability improvement the Fonterra Dairy Coop is limited by the number of dairy
which drives the calculation of financial benefits for the cows in the country, and the international newsprint
model. market is limited by demand), then it is necessary to decide
whether or not to enter a value other than zero in this
Annual Breakdown Work Order % is entered directly from category. If there is truly an opportunity to increase
CMMS work order history at the time of the CBP audit. production to the value that would be produced at 98.5%
The definition for breakdown, is any event that stops or plant availability, then the current production value must
requires a change in the process. This is another key value be entered here. In the case of Norske Skog Tasman,
that is used directly in benefit calculations. The which is currently “fully sold,” no adjustment has been
assumption is made that an organization will never get to made and current production tonnage is listed. The margin
zero breakdown percentage. per ton may then be entered ($200 is picked as a “sample”
value here as the intention is not to divulge Norske Skog’s
Annual Earnings / MPP (Maintenance Performing Person) sales margin). These two values are then used to calculate
is required to calculate: the increase in EBITDA (earnings before interest, taxes,
• additional headcount cost of maintenance crafts- depreciation and amortization) that can be realized as plant
persons if the ERV/MPP ratio is above the availability is increased to the target value at the end of the
threshold. MBP program. EBITDA has the potential to outweigh
• Cost for backfilling MPP staff to develop any other financial output, so it’s important to be
maintenance systems and participate in RCPE conservative and realistic when entering the production
sessions value,(e.g.Annual Tonnes). If there is any doubt about
• Savings associated with headcount reduction as achievement, then entering a Zero for either or both will
maintenance efficiency improves. This savings negate the contribution and provide a more conservative
is limited to 2% of the total MPP annual cost, estimate of benefit.
which is very conservative.

MAINTENANCE BEST PRACTICES ROI CALCULATOR


COST : BENEFIT OUTPUT PROJECTION

MBP AUDIT TARGET SCORE


20 25 30 35 40 45 50 55 60 65 70
75
CUMULATED YIELD & GRADE SAVINGS $ 200,681 TOTAL MONTHS TO REACH TARGET 48

CUMULATED ENERGY SAVINGS $ 833,933 AVAILABILITY % 97.5

CUMULATED R&M EXP. SAVINGS $ 2,522,890 BREAKDOWNS % 2.0

CUMULATED ENG. INVENTORY SAVINGS $ 157,681 PROGRAM CUMULATED COSTS $ 941,579

CUMULATED EBITDA INCREASE $ 634,320 PROGRAM CUMULATED SAVINGS $ 5,254,698

MPP STAFFING REDUCTION SAVINGS $ 600,073 TOTAL PROGRAM BENEFIT $ 4,313,120

OP. STAFFING REDUCTION SAVINGS $ 305,122 IRR 399% NPV $ 3,881,988

Figure #5: ROI Calculator (Output)


MBP Audit Target Score is the first and ONLY entry on ROI Model Development
the ROI Calculator Output “front end.” This value
determines the time, financial benefit and costs of the
project. The author recommends a target of at least 65% The ROI Model was developed from empirical data
for the MBP Audit Target Score. An organization truly collected across 20 manufacturing sites at the Fonterra
begins reaping benefits once a score of 50%+ is achieved, Dairy Cooperative in New Zealand. The Fonterra Dairy
but it is not until a value of 65% is reached that the benefits Cooperative was formed in 2002 after the two major dairy
begin to become truly sustainable, and at this point there is companies in New Zealand amalgamated.
still the potential of “backsliding.” Once the thresh-hold to
CBP is reached at 75% there is a fairly strong implicit The new general manager of the organization was aware
guarantee that an organization will maintain its MBP that the estimated 94% plant availability was not “World
program. Class” and initiated a joint project involving Fonterra
maintenance management and the Engineering Printing and
The Cumulative Savings projected for Norske Skog Manufacturing Union (EPMU), which represented crafts-
Tasman over the 48 month period is $ 5.25 Million dollars. persons at the 22 sites. The MBP Project kicked off in
Costs are estimated at $941K leading to a net benefit of February of 2003. The “gap” between the estimated 94%
$4.313 Million dollars. plant availability and best practices target of 98.5% was
equivalent to an entire average-sized dairy plant broken
Once again, it is important to note that the 48 month period down all day , every day. A $350 Million capital
would be achieved only if Norske Skog Tasman was “ready investment that was idle.
to roll,” fully committed on the MBP program on the day
of the first CBP audit in 2007. In reality it has taken six Fonterra Dairy Cooperative is a world leader in the
months to begin implementing aspects of the “Top Three manufacture of dairy products, particularly powdered
Priorities” (Preventive Maintenance, Planning & wholemilk, powdered milk protein, infant formula and a
Scheduling, Root Cause Problem Elimination). The likely host of other valuable products. 95% of Fonterra’s dairy
time period for implementation is closer to 60 months. products are exported worldwide. In 2002, Fonterra
This means that Norske Skog Tasman will achieve a CBP operated 22 manufacturing sites with a capital value of over
audit score of 70% in April of 2012 if there are no $5 Billion and R&M expenditure of $73 Million. R&M
unexpected distractions such as reorganizations, industrial expenditure was immediately increased during the first year
action , natural disasters or market / funding disruptions. of the MBP project to compensate for a previously under-
I’d bet that at least one of these will occur during the five budgeted maintenance program. Crafts-person, planning,
year period that will add an additional six to twelve months management and support staff were increased. Current
to the MBP program. Nevertheless, benefits and positive expenditures are approximately $100M for R&M with over
financial results will be realized along the way that will $6 Billion of installed capital plant at 20 sites.
lead to further support of initiatives.
The “Joint” Fonterra Management & EPMU Maintenance
Cumulative benefits are described for each of the subsets as Best Practices Improvement Project selected the IDCON,
noted on the input and output figures. A portion of these Inc. model for maintenance best practices and adopted the
benefits will continue to be realized on a per annum basis IDCON CBP (Current Best Practices) audit as a benchmark
once the target is reached. The IRR is calculated only for and tool to improve the maintenance program at each of the
the period shown. Detailed graphs and charts display the manufacturing sites. This decision was made in May of
monthly cumulative and non-cumulative costs and benefits. 2003, and a definition of MBP was completed for review in
(See Technical Paper at the end of this paper) October 2003 along with an action plan for
implementation. The delay of nearly six months from
It is also interesting to note that the ROI Calculator can be conception to initiation of project actions was typical for a
worked in reverse to show the negative impact associated large organization
with reducing funding for maintenance and engineering. It
is assumed that users can estimate the reduction of plant A business case was developed to support expenditure on
availability and/or the increase in Breakdown Work Orders MBP improvement initiatives. Project cost and benefit
if funding is removed to support preventive maintenance, over the five year period required to increase the plant
planning and scheduling once better or best practices have availability to 98.5% was estimated to be:
been reached. The MBP Audit Score can be entered at its Benefit:
best practice value on the Input Calculator and the lower • $11 Million for deferred capital cost (getting the
MBP Target Score (as a result of funding and resource $350 Million plant back on line)
reduction) can be entered on the ROI Calculator Output. • $6.4 Million reduction in Yield & Grade loss
The Total Program benefit will then turn to a negative • $7.7 Million reduction in R&M expenditure
value and will accumulate the negative values over a (assuming that current expenditure was adequate,
predicted time period. This can be used to demonstrate the which was disproved early in the project)
potential impact for removal of support for a MBP program Costs:
by naïve accounts or leadership. • $2.5 Million increase in R&M operating costs
(hiring of additional craftspeople and planners)
• $10 Million capital expenditure (not required)
• $ 8 Million expenditure to: Year 3 of the MBP Project was the year of the
o Develop preventive maintenance pgm “breakthrough” where the curve shape for CBP scores as
o Develop planning & scheduling well as the Plant Availability and Breakdown Work Orders
o Root Cause Problem Elimination made dramatic changes in slope. MBP Project team
o Training in MBP, RCPE, etc. members and R&M staff at the sites became aware of the
o Purchase of vibration pens, alignment “breakthrough” and realized that there was a correlation
equipment etc. with the Hedge Hog affect noted by Jim Collins in his
o Consultant fees book, “Good to Great.” See Figure #6.
o Backfill for program development
o Salaries for national MBP Project BREAKTHROUGH - Current Best Practise .......IDCON Site Audits
Past Reactive to Stabilisation (20-40%) & Preventive Zones (40-60%)
Team
o Expenses for networking forums within
60 Te Rapa
Fonterra Maintenance & Engineering 57
Whareroa
50
Edgecumbe
The MBP program posted a 1.7% improvement in plant 46
41 Hautapu
40
availability after the first year’s implementation. 38
36 Te Awamutu
Presumably a result of the increased manning levels, 33
32 Edendale
30 31
30
26 Clandeboye
system implementation at several of the 20 sites and an 25
Waitoa
increase in discretionary effort at most sites. The following 20 19
16 17 Stirling
year was disappointing as the MBP program bogged down 10 Maungaturoto
for a number of reasons: Kauri
o Collective Agreement negotiation complications 0 Reporoa
F02 F04 F06 Average
and resistance at a number of sites with historic
Industrial Relations “baggage”
o Too many initiatives at once within the MBP Figure# 6: Breakthrough
project
o A lack of MBP Project team resources (which In 2007 , members of Fonterra’s maintenance organization
were increased from 2 to 6 staff for year 3) and representatives from MaintainNZ, a non-profit,
o A general challenge getting the “flywheel” of stakeholder-based maintenance training and improvement
improvement into acceleration. centre in New Zealand decided to document the
o Lack of commitment by a number of Operations improvements in CBP scores across Fonterra sites and
leaders investigate the correlation between the CBP scores and
o Estimates of the 1.7% availability improvement improvements in key performance indicators to see if there
were over-stated due to manual data entry errors was a basis for a predictive ROI model.
in Baseline and Year 1, which were curtailed in
year 2 of the program. Data was available from all of the 20 sites for the following
key performance indicators:
Midway through year 3 of the project a substantial o ERV ratio
increase was observed that carried into years 4 and 5. The o Breakdown Workorder %
author believes that one of the primary reasons for o Plant Availability %
increased “traction” was the willing incorporation of the o IDCON CBP Score %
CBP Score targets into the performance agreements for Site o R&M Expenditure
Operations Managers in addition to maintenance staff. o Engineering Stores Value
Operations managers voluntarily incorporated the o Annual Earnings for crafts and operations
improvement requirement for maintenance practices as they o Expenditure for MBP Project activities including
had begun to see the positive affects on the site o PM program development costs
performance. o Training in MBP concepts
o Planning & Scheduling development
Year 3 was also the year that a review of preventive o Consulting and backfill costs
maintenance practices during the “off-season” took positive o Condition Monitoring equipment
affect. Historically, many site maintenance programs had purchases
over-hauled equipment whether or not it was broken, with o Alignment and other MBP tool
the mistaken belief that over-hauls would increase purchases
equipment life and prevent failures. With the incorporation o MBP Project Team support
of FMECA and reliability centered maintenance philosophy
from IDCON, Inc. into preventive maintenance programs Data was available at only three of the 20 sites for
and average of 15% or Winter Shut PM tasks were reduction in equipment-related Cost of Failure, directly
eliminated along with the infant mortality failures, contract attributed to MBP actions :
craftsperson costs and parts. Plant availability was o Annual Grade and Yield Loss improvement
positively affected. o Energy reduction improvement
o R&M expenditure reduction
o Production Tonnes increases
The 17 remaining sites had registered improvements in the at several different sites within Fonterra Dairy and at four
same categories but were unable or unwilling to estimate locations outside the Dairy industry in NZ for validity. A
what portion of the improvement was attributable to the review of the results was conducted with representatives of
MBP program. There were competing improvement the Fonterra Dairy accounting department who were non-
initiatives such as an energy reduction program, capital committal. Site management and accountants at the three
project initiatives and the Dairy Worker Union sponsored sites with data were supportive of conclusions.
“Manufacturing Excellence program.” The author had
encouraged maintenance managers at all sites to track the It is interesting to note that the model curve shape for the
specific equipment-related losses on a yearly basis to prove CBP improvement (which includes real data from all 20
the impact of the MBP program by correlating a reduction sites over the five year period) is the shape of an electric
of breakdowns, (which was documented and accepted), motor, which , of course, is the shape of a flywheel. The
with a reduction in cost of Failure (COF). Unfortunately, improvement at Fonterra with the MBP program tracks the
many of the maintenance managers did not heed the prediction of Jim Collins’ Good to Great” Flywheel model,
author’s advice, and the result was a lack of clarity (See Figure 7).
regarding the basis of improved performance.
The curve for Site 1, (shown in Figure 7), depicts the
There was , however, a large amount of anecdotal evidence average five year results for CBP scores at the 20
which corroborated the reduced cost of failure at the 17 manufacturing sites. The additional points in the Site 1
remaining sites. For example, the manager at one of the curve, beyond year 5, are predicted by the curve shape of
major sites confirmed that more than $ 1Million p.a. an electric motor which fits the first five points. (See
savings in yield had been achieved as a result of Technical Paper for more discussion)
maintenance initiated RCPE on spray drying nozzle
equipment. Another major site manager agreed that an The average initial score for all Fonterra sites was 21% on
RCPE project had result in a substantial increase in the IDCON, CBP audit. This is based on the fact that all
tonnage and $1 Million increase in site EBITDA. This was sites conducted a self assessment survey in 2003 , the first
also accompanied by a reduction in effluent and year of the project and three sites conducted a CBP audit.
cancellation of a multi-million dollar effluent-handling It was found that the sites that conducted a CBP audit
capital project. Milk tanker diversion costs had been scored exactly half of the score that they had awarded
substantially reduced as a result of plant availability themselves with the self-assessment. The self-assessment
improvements, which provided fuel savings and increased survey was much less rigorous and was self scored by the
transport efficiencies which were acknowledged but not interviewees rather than a trained audit team. The self
quantified by transport management. assessment audit was conducted in Year 2, (2004), and
discontinued in Year 3, when it was replaced at selected
Specific data was collected for the Grade, Yield and sites by the IDCON CBP audit. In 2005, all sites began
production tonnage improvements at the three sites assessment using the IDCON CBP with an “in-house” audit
mentioned and extrapolated for the balance of 17 sites. team trained by IDCON representatives. As noted, this
The data was then assembled for review of trends and was the year that operations management incorporated the
correlation between CBP performance, availability, IDCON CBP score with a 10% increase as a target for their
breakdown work order reduction and financial benefit. personal performance reviews and site performance target.
Julien Maffre, primary author of the accompanying
Technical Paper, created the ROI model which was tested

ROI Engine Model

80
70
IDCON CBP Score

60 Site 1
50 Model
40
30
20
10
0
0 1 2 3 4 5 6 7 8
Year

Figure #7: CBP Audit Score Model Curve = “FLYWHEEL”


The ROI Calculator model utilizes three values for cumulative benefits and costs. These values can be used in
predicting costs and benefits; CBP Score, Plant Availability annual performance plans, and to illustrate potential
and Breakdown Work Order Percentage. A number of improvements for verification and action.
graphs are generated to show cumulative and non-

80.0 100
1
98
70.0
96
60.0 score
% score & breakdowns

breakdowns 94
50.0 Availability

% availability
Now 92
Projected Score
40.0 Projected Time 90

88
30.0
86
20.0
84
10.0
82

0.0 80
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168
months

Figure #8: ROI Engine Model – Key Trends

35
75
6
30

25 65
Total Co sts to come
Total Savings to come
20 Net Benefit
55
Now
$Millions

Pro jected Score


15 Pro jected Time
45
%

Sco re

10
35
5

25
0
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168
-5 MONTHS 15
Figure #9: ROI Engine Model – Cost/Benefit
Non cumulated yearly results

Engineering Operation Staffing


Yield & Grade Loss R&M Expenditure Energy Spend Inventory Value EBITDA Increase Reduction Savings MPP Staffing Reduction
$ Savings Yearly Savings Yearly Savings Yearly Savings Yearly Yearly Yearly Savings Yearly

Year 1 $ 73,123 $ 919,273 $ 303,863 $ 57,455 $ 754,358 $ 23,637 $ 46,485


Year 2 $ 57,792 $ 726,537 $ 240,154 $ 45,409 $ 609,020 $ 63,571 $ 125,023
Year 3 $ 41,493 $ 521,632 $ 172,424 $ 32,602 $ 454,047 $ 93,363 $ 183,613
Year 4 $ 29,214 $ 367,264 $ 121,398 $ 22,954 $ 314,485 $ 114,278 $ 224,747
Year 5 $ 23,021 $ 289,409 $ 95,663 $ 18,088 $ 198,014 $ 129,858 $ 255,387
Year 6 $ 13,205 $ 166,011 $ 54,875 $ 10,376 $ 141,295 $ 141,398 $ 278,083
Year 7 $ - $ - $ - $ - $ - $ 144,090 $ 283,377
Year 8 $ - $ - $ - $ - $ - $ 144,090 $ 283,377

Year 12
Figure #10: ROI Engine Yearly Benefits

The MBP Program at Fonterra documented achievement of implementation was likely to substantially more than the
80% of the 4.4% availability target at the end of the fifth original business case. In 2008 the IDCON CBP audit
year in 2007. This was one year later than the original program was replaced with the Dairy Worker Union
aggressive projection, but a substantial improvement (DWU) -backed Manufacturing Excellence program and
nevertheless. It is important to note that the measurement. The tracking of the MBP initiatives and
implementation of an Automated Plant Availability (APA), improvements was absorbed into the wider-ranging
system in 2005 uncovered additional opportunity by program. Estimates of results for the Fonterra MBP
proving the initial availability gap was greater than 4.7%, program through 2007 are shown in Figure 11.
The total benefit for continuation of the MBP

Fonterra Results
• 4.4% Availability Increase 80%
• $ 11M p.a. deferred cost of capital 80%
• $ 6.4M p.a. reduction in COF 80%
• $ 7.7M p.a. reduction in R&M expenditure 80%
• $ 2.5M p.a. R&M operations cost increase 100%
• $ 8.0M MBP project cost over 4 years
• Business Case IRR of 247% Exceeded!

11

Figure #11: Cumulative Fonterra Results 2002 - 2007


Best Reliability and Maintenance
Practices and Return on Investment
(Implementation)
By,
Christer Idhammar, IDCON Inc.
Rob Probst, Norske Skog
Business and Management /Track 1

1
Presentation Outline
1. Review and confirm the relationship
between ROI and Best Reliability &
Maintenance Practices
2. Return on Investment for Maintenance
Best Practices at Norske Skog Tasman
3. ROI Model development at Fonterra
Dairy Cooperative in conjuction with
IDCON CBP model.

2
Current Best Practices (CBP) Reliability and Maintenance

KEY PROCESS
Leadership Root Cause Planning Preventive Engineering Facilities,
Skills Stores Technical
& Problem & Development Maintenance Management Database Interface with Tools, &
Organization Elimination Scheduling Maintenance Workshops

Work Maintenance Method Selection


SUB Request Cleanliness
PROCESSES Prioritization Lubrication
Backlog Alignment
Planning Balancing
Scheduling Operating Procedures
Execution Filtration
Recording Condition Monitoring
CMMS Tool

Examples of “Lubrication elements”


Examples of “Planning elements”
26. Lubricants are stored properly
32. Standard job plans are used for
ELEMENTS all repetitive and critical jobs
in clean, organized storage
areas.
33. Jobs are always planned before
27. Filtration is used to maintain
they are scheduled
lubricant cleanliness.
34. Operations support the planning
28. Ferro graphic analysis is used to
process identify oil contaminants.
3
Evolution of maintenance
Reliability + 30%
Results
Level 4. Continuous improvement. CBP 75+
CBP Score • Maintenance cost less than 2.5 % of estimated
replacement value.
• Overtime and contractor hours less than 8 %.
75 + • Planned and scheduled work 95%
• 100% of PM executed.
• Root Cause Analysis 30% of available time.
Level 3. Resultsoriented partnership. CBP 50-75.
• Maintenance cost less than 3.0 % of estimated replacement value.
• Overtime and contractor hours less than 10%.
• Planned and scheduled work 85% of total work Reliability + 10%
50 - 75 • 90% of PM executed.
• Root Cause Analysis 20% of available time.

Level 2. Planned and Scheduled, Cost Focus, Internal customer. CBP 25-50
• Maintenance cost less than 3,5% av estimated replacement value.
• Overtime and contractor hours 15% - 20%.
25 - 50 • Planned and scheduled work 70% of total work. Reliability + 5%
• 70% PM executed.
• Root Cause Analysis 3 % of available time.
Level 1. Reactive, Cost Focus, Internal customer. CBP 0-25
• Maintenance cost over 3.5% of estimated replacement value.
• Overtime and contractor hours over 20%.
1 - 25 • Planned and scheduled work 40% of total work
• 30% of PM executed.
• Root Cause Analysis 0% of available time. Effort
4
CBP, Current Best Practices –
Reliability and Maintenance
IDCON’s CBP Methodology is used to:
• Increase Reliability and manufacturing
throughput and to drive down costs.
• Express what practices are
expected to be executed in a
good maintenance organization.
• Educate an organization in
what constitutes best reliability
and maintenance organizations.
5
CBP, Current Best Practices –
Reliability and Maintenance
Facilitate a process that makes
people discover how good their organization is and
how good it can become.
Benchmark maintenance performance.
Develop improvement action plans.
Measure improvements.
Compare performance with other organizations.

6
Results Oriented Reliability and
Maintenance (RORM)
Implementation Model
Continuously
Improving
Results
•Competitiveness, Productivity, OPE, Costs

Action Indicators

Step IV – Root Cause Problem Elimination

-Maintenance Prevention Technical Data – Planning, Scheduling and


Base. Control of Operations and
-Preventive Maintenance Store Room
Step III Maintenance
Management

Step II - Current Best Practices – CBP - Educational Evaluation. Benchmark and


discover and understand how good your organization is compared to how good it
could be. Agree on action plan and commit to results.

Step I - Increase Awareness, Discover improvement potential, Lay down fundamental


Beliefs and principles.
Operations-Maintenance-Engineering
7
VISION
By the end of year 2008 achieve
a CBP score of 75+

Mission
In a partnership with Operations Safely
deliver continuously improved
Equipment Reliability
through the implementation of CBP.

CBP Audit

Action Plan

Implementation KPI
CBP Audit 8
Norske Skog Tasman

• Newsprint mfg 1954


• 300,000 tonnes p.a.
• $1 Billion ERV
• $24 Million R&M
Expense
• 98 Maintenance &
Engineering Staff
• 38% on 1st IDCON
MBP audit in 2007

9
Return on Investment for MBP at Norske Skog
Improved Practices = Reduced Cost of Failure (COF)
Projected breakdown reduction of 66%

$1.25M on the top in 2007

Projection 2012

Labour,
• Equipment Failure
Repair Cost
$ 412K
Labour, Material,
Overheads

Equipment Downtime
(Availability) • Equipment Failure
• Hidden Equipment
Reliability (Stop/Start) Labour,
Labour, Material,
Overheads
Repair Cost

Quality Failure-Related Losses Equipment Downtime


(Availability)
• Hidden Equipment
Reliability (Stop/Start)

Quality Failure-Related Losses


Impact on larger Impact on larger
inventories
inventories Safety
Longer
Customer
Lost Profit
Longer
Lead times

Safety Customer Waste


Increased
Lost Profit Lead times
Cost of
repairs 126

Waste
Increased
Cost of
repairs 126

$ 1.82M

$5.5M on the bottom (COF)


10
“ROI” for MBP at Norske
Skog
MAINTENANCE BEST PRACTICES ROI CALCULATOR
MBP KEY PERFORMANCE INDICATORS

MBP AUDIT SCORE


20 25 30 35 40 45 50 55 60 65 70
75
COMMITMENT INDUSTRY TYPE Pulp & Paper
Excellent Average Poor
Good Low

ANNUAL R&M SPEND $ 24,000,000 ANNUAL BREAKDOWN W.O.% 6.0

MAINTENANCE PERSONNEL (MPP) 118 ANNUAL EARNINGS / MPP $ 85,000

EQUIPMENT REPLACEMENT VALUR (ERV) $ 1,000,000,000 ENGINEERING STORES VALUE $ 10,000,000

PLANT KEY PERFORMANCE INDICATORS

ANNUAL GRADE LOSS $ 2,000,000 ANNUAL TONNES OF PRODUCT 300000

ANNUAL YIELD LOSS $ 2,000,000 MARGIN PER TONNE $ 200

ANNUAL ENERGY COST $ 34,000,000 ANNUAL EARNING OPERATOR $ 85,000

AVAILABILITY % 94.0 TOTAL OPERATORS 150

11
“ROI” for MBP at Norske
Skog
MAINTENANCE BEST PRACTICES ROI CALCULATOR
COST : BENEFIT OUTPUT PROJECTION

MBP AUDIT TARGET SCORE


20 25 30 35 40 45 50 55 60 65 70
75
CUMULATED YIELD & GRADE SAVINGS $ 200,681 TOTAL MONTHS TO REACH TARGET 48

CUMULATED ENERGY SAVINGS $ 833,933 AVAILABILITY % 97.5

CUMULATED R&M EXP. SAVINGS $ 2,522,890 BREAKDOWNS % 2.0

CUMULATED ENG. INVENTORY SAVINGS $ 157,681 PROGRAM CUMULATED COSTS $ 941,579

CUMULATED EBITDA INCREASE $ 634,320 PROGRAM CUMULATED SAVINGS $ 5,254,698

MPP STAFFING REDUCTION SAVINGS $ 600,073 TOTAL PROGRAM BENEFIT $ 4,313,120

OP. STAFFING REDUCTION SAVINGS $ 305,122 IRR 399% NPV $ 3,881,988

12
ROI Engine Model Development

• Empirical Data from 5 Year MBP project @ Fonterra Dairy Cooperative


• $6B capital / $100M R&M expenditure
• Joint Engineering Union & Management MBP Project
• IDCON-based MBP philosophy
• Annual IDCON audits target 10%+ p.a. MBP score increase
• National MBP Project Team across 20 manufacturing sites
• Project Business Case projection of $22M p.a. bottom line improvement

13
Audit Score Model Curve
ROI Engine Model

80
70
IDCON CBP Score

60 Site 1
50 Model
40
30
20
10
0
0 1 2 3 4 5 6 7 8
Year

14
ROI Engine Model – Key Trends

80.0 100
1
98
70.0
96
60.0 score
% score & breakdowns

breakdowns 94
Availability
50.0

% availability
Now 92
Projected Score
40.0 Projected Time 90

88
30.0
86
20.0
84
10.0
82

0.0 80
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168
months

15
ROI Engine Model – Cost / Benefit
35
75
6
30
Use Benefit
Calcs for annual 65
25 Budgeting
To tal Co sts to co me
To tal Savings to co me
20 Net Benefit
55
No w
$Millions

P ro jected Sco re
15 P ro jected Time
45

%
Sco re

10
35
5

25
0
0 12 24 36 48 60 72 84 96 108 120 132 144 156 168
-5 MONTHS 15

0 – 18 month “lag” for


prgm prep
16
Fonterra Results 2002-2007
• 4.4% Availability Increase 80%
• $ 11M p.a. deferred cost of capital 80%
• $ 6.4M p.a. reduction in COF 80%
• $ 7.7M p.a. reduction in R&M expenditure 80%
• $ 2.5M p.a. R&M operations cost increase 100%
• $ 8.0M MBP project cost over 4 years
• Business Case IRR of 247% Exceeded!

17
Summary
• MBP programs
provide definable ROI
• ROI can be projected
from an empirically
based model
• You can use
projections to build a
business case and
convince your CEO to
commit to your MBP
program
18

You might also like