Professional Documents
Culture Documents
Monthly Dashboard - Exemplar File To Copy From
Monthly Dashboard - Exemplar File To Copy From
Progress Dashboard for 1st January to 6th September 2017 5145599 - 62 - DR – 003
Project Manager Keith Robson Date 6th September 2017 Request for Information (RFI)
Progress Statement Thabat to confirm Typsa Basic Design Deliverable Status and indicate when approval will be provided to allow
forward work planning.
The project has experienced serious delays in period due to extended Basic Design programme and delay of its
approval. It is understood that the project will now recommence at pace due to a change in the project owner from Atkins have collated and submitted RFI’s for all priority structures on 27-08-2017. Atkins await feedback from Thabat
NWC to Miahona. on the RFI items to facilitate progress. Refer to Appendix E.
Receipt of RFI responses is integral to achieving the programmed deliverable dates in accordance with the Priority
Atkins visited the Manfouha site between 22nd and 24th August 2017. During this visit, technical, commercial and Structures Programme. Refer to Appendix C.
programme items where discussed and agreed with Thabat. Follow up emails were issued on 27-08-2017 to
summarize discussions and agreements made. Atkins await confirmation of AMC’s updated Construction Programme.
Thabat Progress Overview – Atkins communicated our current understanding of Typsa design approval and Outstanding CH2M Approvals;
construction programme preferences via email of 27-08-2017, based on email records received from Thabat. Refer to
Appendix A. It is evident that much of the data is out-of-date and Atkins await regular updates of this information. SBR Wall RC – Drawings issued 22/08/2017 - QRF Response issued on 29/08/17
Plate Bearing Test Specification issued 09/08/2017
Atkins Progress Overview – Atkins communicated a summary of the information received from Thabat to date and
Design Status of each structure via email on 27-08-2017. Refer to Appendix B. Atkins will provide monthly updates of CCT General Arrangement Pack issued 01/09/2017
this document within the progress report.
General notes drawings – issued 01/09/2017
Atkins await confirmation of frozen CH2M Approved Typsa’s Basic Design civil guide drawings to allow the design
Confirmation of date of Next Monthly Meeting in Riyadh
team to be fully mobilized for detailed design stage. Please refer to ‘Know Issue and Risks’ section for further details
of current challenges regarding this item.
Known Issus and Risks
Priority Structures Programme – Atkins issued a programme of priority structure deliverables via email on 27-08-
2017. This followed discussions and agreements reached with Thabat at a meeting on-site on 24-08-2017. The Need for new EDMS – One Drive needs to be updated and managed. Information to be placed into separate folders
priority structures include CCT, BTA, DCH, FBL & UVC. Refer to Appendix C. as per RFI request issued 27-08-2017. Thabat to notify Atkins when information is placed on the system via email as per
request sent on 01-09-2017 to Eng. Adam.
Atkins Commercial Items – Atkins submitted a summary of the outstanding commercial items to be addressed by
Thabat via email on 27-08-2017. Please refer to ‘Commercial’ section for more details. Typsa deliverables – Atkins require improved and honest Thabat communication of the status of Typsa’s Basic
Design deliverables and risks for change therein. Drawings stated as frozen have been found to not be fully finalised e.g.
Atkins Deliverables List - Atkins formally issued an updated project deliverables list via email on 27-08-2017. Refer to DCH Mark-ups of Atkins draft drawings received on 24-08-2017 included items not included in the original Typsa
Appendix D. ‘Approved’ Mech drawings. It is also noted that Mechanical QRF’s often include items that are ‘open’ or ‘to be addressed
at detail design’ with no confirmation as to what changes are to be made to the Typsa drawings that Thabat define as
RFI’s – Atkins have collated and submitted RFI’s for all priority structures on 27-08-2017. Atkins await feedback from ‘frozen’.
Thabat on the RFI items to facilitate progress. Refer to Appendix E.
There is a need for improved communication and co-ordination from Thabat technical team. Recent examples have
Atkins have continued to provide support to close the SBR design in period submitting several General Arrangement included:
drawing and RC package updates. CCT – Atkins received 3 different instructions for a wall height from 3 different people.
BTA - Atkins received an instruction from the Thabat team to stop work (Email from Eng. Eslam attached), and
Atkins are progressing with BTA, DCH, CCT and UVC-FBL in accordance with agreed priority structure programme. further email that the design is not frozen (Email Eng Eduardo) yet receive counter instructions to keep going from
Atkins progress update in contained in Appendix C. Eng Abdulmannan. This leads to great confusion.
There is a fundamental need for clarity on lines of communication and who has and does not have authority to instruct
Atkins have continued to provide site construction support in period that has included responding to technical queries
Atkins design within the Thabat team.
and general site related enquiries.
There is a need to close Atkins open commercial issues as a matter of urgency.
Atkins have continued to support AMC with the assessment of SBR backfill material test results in period.
CH2M Review & Approval – Duration of Approval is generally extended and nature of comments display elements of
Atkins have continued to support AMC in concrete mix selection and reinforcement supplier technical reviews in preferential engineering and non-technical reviews that require substantial time and effort to answer. This is a large risk
period. Typsa’s recommendations for concrete coatings has also been reviewed in period. item that has and will continue to delay design progress. QRF replies need to be agreed with CH2M by Thabat prior to
issuing drawings to avoid rework
Atkins have now completed our Basic Design Deliverables. The outstanding Site Layout, road levels, Storm water,
Irrigation and sewage network review comments were submitted in December 2016. For further items please refer to ‘General Items’ within RFI issued 27-08-2017 (Appendix E)
Atkins design is continuing basis of the AMC confirmed project Design Groundwater level of +566.5m. As noted in Design Groundwater levels – Thabat advised that the Design Groundwater level for the project is +566.5m on 5th May
email of 5th May 2016, Thabat assumes design responsibility for this level. 2016. AMC will assume design responsibility for this level. Subsequent change in GWL will attract rework and recovery of
additional expenditure will be sought.
Manfouha Sewage Treatment Plant Fourth Stream
Progress Dashboard for 1st January to 6th September 2017 5145599 - 62 - DR – 003
Contract offer
Commercial
Early Warning – Generator Building – Tender Design allowed for small modification to existing X X
There is a need to close Atkins open commercial issues as a matter of urgency. They cannot be left open while building only – Potential for substantial building extension and/or new building on site now
technical delivery is expected to continue at risk as has occurred historically. Commercial items must be given the priority indicated to be required that exceeds the allowance made within Atkins Contract offer.
they deserve otherwise delivery will be affected.
Early Warning - Fire Fighting Building – Building significantly more complex than allowed for X X
Variation Order 1 to 5 - Atkins and Thabat discussed and agreed a value of SAR 140,000 for VO 1 to 5 at a meeting within Atkins Contract offer (simple slab). Current requirement indicates a 2 compartment above
onsite on 24-08-2017. Atkins subsequently submitted document STP-RP-03-G-G-105 on 01-09-2017 to summarise the ground tank with adjacent mechanical rooms is now required extending to 30m x15m plan area)
agreement reached. Atkins await signed Contract Change Order to release deliverables associated with VO’s.
Lagoon Area Foundations – Atkins Contract offer based on ground bearing or piled foundation X X
Atkins submitted Invoice No. 4 (DRAFT) on 27-08-2017 regarding fees due for completion of milestone CCT General and not the new requirement for specialist column and pad design for each structure including
Arrangement Drawing Pack - SAR 61,600. Atkins await Thabat approval to allow formal invoice submission. In rebar detailing.
accordance with section 6.4 of Atkins-Thabat agreement “The Contractor shall approve or respond to a submitted
application for milestone payment within 7 days of the submission date”. This expired on 04-09-2017.
Haer Channel – Fee proposal assumed pipe connection. Requirement changed to a concrete X X
channel meaning increase design and deliverables including calc report and reinforcing drawings.
NWC Approval – At meeting on 24-08-2017 it was agreed between Atkins and Thabat that approval of deliverables by
CH2M is sufficient to release payments due to Atkins. At present Atkins have SAR 155,000 in payments locked up by
Thabat in relation to this item. These payments are overdue by one year. To resolve the item, it was agreed that: Programme Review
-----Thabat to send a letter to NWC/CH2M to confirm NWC approval will not be required. This was to be completed on 27-
08-2017. Thabat to manage process to bring to a close ASAP. Priority Structures Programme – Atkins issued a programme of priority structure deliverables via email on 27-08-
2017. This followed discussions and agreements reached with Thabat at a meeting on-site on 24-08-2017. The
----- Atkins to be allowed to submit invoice for payments by 15th September 2017. priority structures include CCT, BTA, DCH, FBL & UVC. Refer to Appendix C. Please note that the programme
relies on Thabat inputs such as review and acceptance of draft drawings & RC intent sketches and provision
of RFI responses to achieve target deliverable dates.
Change Control Cost Time
URGENT - There is need for a clear forward programme of work. As Basic Design is not fully approved and many
The following Early warnings reflect historic items on the project and will be submitted formally as Variation Orders over contributing factors are yet to be finalized the programme is difficult to plan as the project is start-stop. This generates
the coming periods: great difficulty in achieving efficiencies and ultimately leads to additional costs.
Early Warning – Process design has produced a more complicated and extended site X X CH2M approvals remains a risk item as the extended review period has been delaying design progress. Reviews are
development than proposed by AMC at tender stage, the basis of Atkins Contract offer e.g. not being completed on a technical basis and drawings/report are being rejected based on reviews by non-technical
addition of coarse screen chamber and building, increase sand & grit chamber size, increased staff for non-technical reasons. This wastes a lot of time and effort and is leading to additional costs.
complexity of distribution chamber, chlorine contact tank doubling in size, requirement for four
unique MCC designs, addition of weighbridge and metering channels, increase in road and Atkins await AMC Construction programme with list of priority structures
drainage infrastructure.
Early Warning – Extension of Ground Investigation Works for enlarged site area to cover an X X Next Month Activities
increased site development area compared to the Tender Design. This included additional
borehole scheduling, laboratory test scheduling, interpretation of results and update to Atkins will continue to progress with BTA, DCH, CCT and UVC-FBL in accordance with agreed Priority Structure
Geotechnical Interpretive Report. Programme. Atkins progress update in contained in Appendix C.
Early Warning – Level of SBR Optioneering undertaken to date including production of ‘Options X X
Report’ was not included in Atkins Contract offer. Appendices
SBR Foundation – Unique design for each tank’s foundations (incl. reinforcement details) not X X
included in Atkins Contract offer. This also includes the substantial time and resource employed to Appendix A – Thabat Progress Overview
justify the design to AMC and CH2M (Geotechnical settlement analysis, reviewing of plate load Appendix B – Atkins Progress Overview
test results etc) Appendix C – Priority Structures Programme and Overview
Appendix D – Atkins Deliverable List
Early Warning – Elongation of programme due to delay in attaining approval of Basic Design. X X Appendix E – RFI Register
Current Thabat programme shows more than 12 months’ delay to Typsa design programme Appendix F – Designers Risk Register
baseline received on 2nd March 2016.ypsa. This delay has led to severe difficulties for Atkins in
project planning and resourcing. The greatly extended programme and “stop-start” nature has
resulted in additional staff costs in developing design options, answering queries, meeting
attendance, prior to receipt of frozen design.
Early Warning – Review and Reporting on Rising Groundwater levels – not included in Atkins X
Manfouha Sewage Treatment Plant Phase 4
APPENDIX A
THABAT
Received From Eng Eslam 17/08/2017
Construction Need Date
Information ATKINS Received from Eng. Construction Programme
Status with Abdulmannan Received from Eng. Eslam 16/08/2017
Item / Building Mechanical, Electrical and Process Civil, Architectural and Structural Provided by Detail Design
CH2M Email 12/08/2017
TYPSA Completion
PROCESS
Hydraulic flow, Profile & Calculations • ‐ Approved ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐
Design Criteria DC • Approved ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐
PRIMARY TREATMENT AREA
Basic DWGs Approved, DD still Send FM1 and Culvert, Assume steel Basic Design Confirmed to ATKINS ‐ Civil DD
Inlet chamber & Culvert & FM1 ICH • ‐ not issued
No For DD 13/07/2017 Yes
within Haer channel
WIP WIP 80% 20% 15/09/17 22/09/17 01‐Oct‐17 15
to start
Basic DWGs Approved, DD still Need Final DWGs based on equipment DD from Typsa required to commence Civil
Coarse screen building & Container BLD CSB • • not issued
Yes For Info No
assembly DWGs
X X 75% 10% 10‐Aug‐17 4
DD
Basic DWGs Approved, DD still Need Final DWGs based on equipment DD from Typsa required to commence Civil
Inlet pumping station IPS • • not issued
Yes For Info No
assembly DWGs
X X 75% 15% 15‐Aug‐17 5
DD
Basic DWGs Approved, DD still Need Final DWGs based on equipment DD from Typsa required to commence Civil
Fine screen building & FM5 & Container BLD FSB • • not issued
Yes For Info No
assembly DWGs
X X 75% 15% 15‐Aug‐17 6
DD
Basic DWGs Approved, DD still Work in progress – need equipment Basic Design Confirmed to ATKINS ‐ Civil DD
Sand & grease chamber SGR • • not issued
No For DD 31/05/2017 Yes
assembly DWGs
WIP WIP 80% 20% 17/08/17 30/08/17 20‐Aug‐17 7
to start
Basic DWGs Approved, DD still Basic Design Confirmed to ATKINS ‐ Civil DD
Air blowing building (sand & grit) BBA • • not issued
Yes For Info No Waiting Frozen DWGs for the whole block X X 80% 20% 20‐Aug‐17 7
to start
Basic DWGs Approved , The Basic Design Confirmed to ATKINS ‐ Civil DD
Grease concentrator station GCS • • unit became GTP
Yes For DD 31/05/2017 Yes Building is attached to SGR WIP WIP 80% 15% 20‐Aug‐17 7
to start
Basic DWGs Approved, DD still Need confirmation on frozen design,
Odor control (pre‐treatment facilities) OC1 • X not issued
No No
Equipment Details
X X 50% 10% 15‐Jan‐18 22 BD under review
Need confirmation on frozen design,
Substation building mcc1 MCC1 X X Basic DWGs still not approved Yes No
Equipment Details
X X 50% 15% 15‐Nov‐17 20 BD under review
SECONDARY TREATMENT AND SLUDGE AREA
Basic DWGs Approved, DD still Old Str. GA approved – flowmeter details BD Confirmed ‐ Currently excavation
Distribution chamber & FM2 DCH • • not issued
No For DD 17/07/2017 Yes
confirmed
WIP WIP 80% 40% 22/08/17 31/08/17 31‐Aug‐17 10
finished ‐ Civil DD to start
Basic DWGs Approved, DD still Currently
ICEAS SBR tank (Support System) SBR • • not issued
No For DD Closed All DWGs approved • • 100% 100%
Progressing
1 Closed
Basic DWGs Approved, DD still Currently
ICEAS SBR tank (Slab) SBR • • not issued
No For DD 30/05/2017 Closed All DWGs approved • • 100% 100%
Progressing
1 Closed
Basic DWGs Approved, DD still Ready to receive dressing concrete long
Balance tank / intermediate PS & FM3 BTA • X not issued
No For DD 10/07/2017 Yes Site First Priority WIP WIP 80% 40% 16/08/17 25/08/17 25‐Jul‐17 2
time ago, Civil DD to start
For Info + Need confirmation on frozen design,
Sludge tank SLT X X Under Typsa`s Review No
3D
No
Equipment Details
X X 60% 20% 20‐Aug‐17 8 BD under review ‐ approval is imminent
For Info + Need confirmation on frozen design,
Sludge thickener STH X X Under Typsa`s Review No
3D
No
Equipment Details
X X 60% 20% 20‐Aug‐17 8 BD under review ‐ approval is imminent
For Info + Need confirmation on frozen design,
Polymer dosing unit for sludge thickener PD1 X X Under Typsa`s Review No
3D
No
Equipment Details
X X 60% 20% 20‐Aug‐17 8 BD under review ‐ approval is imminent
For Info + Need confirmation on frozen design,
Sludge mixing tank SMT X X Under Typsa`s Review No
3D
No
Equipment Details
X X 60% 20% 20‐Aug‐17 8 BD under review ‐ approval is imminent
For Info + Need confirmation on frozen design,
Supernatant pumping station SPS X X Under Typsa`s Review No
3D
No
Equipment Details
X X 60% 20% 20‐Aug‐17 8 BD under review ‐ approval is imminent
For Info + Need confirmation on frozen design,
Sludge dewatering SLD X X Under Typsa`s Review No
3D
No
Equipment Details
X X 60% 20% 20‐Aug‐17 8 BD under review ‐ approval is imminent
For Info + Need confirmation on frozen design,
Polymer dosing unit for SLD dewatering PD2 X X Under Typsa`s Review No
3D
No
Equipment Details
X X 60% 20% 20‐Aug‐17 8 BD under review ‐ approval is imminent
For Info + Need confirmation on frozen design,
Sludge silos building SLB X X Under Typsa`s Review No
3D
No
Equipment Details
X X 60% 20% 15‐Sep‐17 12 BD under CH2M review
Need confirmation on frozen design,
Substation building mcc2 MCC2 X X Basic DWGs still not approved Yes No
Equipment Details
X X 50% 15% 20‐Aug‐17 8 BD under review ‐ approval is imminent
Basic DWGs Approved, DD still Need confirmation on frozen design,
Odor control (sludge facilities) OC2 • X not issued
No No
Equipment Details
X X 50% 10% 20‐Aug‐17 8 BD under review ‐ approval is imminent
Need confirmation on frozen design,
Substation building mcc3 MCC3 X X Basic DWGs still not approved Yes No
Equipment Details
X X 50% 15% 15‐Sep‐17 12 BD under CH2M review
TERTIARY TREATMENT AREA
Basic DWGs Approved, DD still UVC, UVB, BPS and FBL basic design
Filtration building FBL • X not issued
No For DD 15/08/2017 Yes Disc Filter arrangement Confirmed X X 85% 15% 04/09/17 11/09/17 10‐Sep‐17 11
confirmed
Basic DWGs Approved, DD still UVC, UVB, BPS and FBL basic design
Backwash pumping station BPS • X not issued
No For DD 15/08/2017 Yes Design Confirmed X X 85% 5% 04/09/17 11/09/17 10‐Sep‐17 11
confirmed
Basic DWGs Approved, DD still UVC, UVB, BPS and FBL basic design
UV channel UVC • • not issued
No For DD 18/06/2017 Yes Work in progress, but waiting for FBL WIP WIP 80% 20% 08/09/17 15/09/17 10‐Sep‐17 11
confirmed
Basic DWGs Approved, DD still UVC, UVB, BPS and FBL basic design
UV control building UVB • • not issued
No For DD 18/06/2017 Yes Work in progress, but waiting for FBL WIP WIP 80% 20% 08/09/17 15/09/17 10‐Sep‐17 11
confirmed
Basic DWGs Approved, DD still GA`s Received, RC drawings are much
Chlorine contact tank CCT • • not issued
No For DD 30/05/2017 Yes GA`s Submitted 13‐08‐2017 • WIP 80% 35% Received 18/08/17 05‐Aug‐17 3
needed to prepare RFT
DWGs Approved & Parshall GA`s Received, RC drawings are much
Effluent flow metering chamber FM4 EMC • • flume issue
No For DD Yes Work in progress WIP WIP 80% 35% Received 18/06/17 05‐Aug‐17 3
needed to prepare RFT
Basic DWGs Approved, DD still GA`s Received, RC drawings are much
Service Water Line SWL • ‐ not issued
No For DD 30/05/2017 Yes Work in progress WIP WIP 80% 35% 01/09/17 08/09/17 05‐Aug‐17 3
needed to prepare RFT
Basic DWGs Approved, DD still Need confirmation on frozen design, GRP tank
Chlorine storage building NaOCL & PS CHB • • not issued
Yes No
details
X X 75% 0% 29‐Sep‐17 14 BD under review
Need confirmation on frozen design,
Substation building mcc5 MCC5 X X Basic DWGs still not approved Yes No
Equipment Details
X X 50% 15% 15‐Nov‐17 21 BD under review
Basic DWGs Approved, DD still Basic Design Confirmed to ATKINS ‐ Civil DD
Final distribution chamber FDC • • not issued
No For DD 30/05/2017 Yes Prefer to have confirmation on frozen design X X 80% 10% 01‐Oct‐17 16
to start
OTHER NON‐PROCESS BUILDINGS
Warehouse WHB X • Basic DWGs still not approved No No Need confirmation on frozen design X X 50% 5% 11‐Oct‐17 17 BD under review
CIVIL ELEMENTS
Site Layout
APPENDIX B
SUMMARY OF ATKINS PROGRESS STATUS 27/08/2017
ATKINS
Closed Mech QRF
Item / Building Mech Dwg received Struct Dwg received Arch Dwg received Equipment Loading RFI Queries Deliverables Status Programme
received
Thabat Confirmation Sufficient
Date Date Date Date Date Date Drawing Modelling Draft GA Formal GA Calculation RC Intent Base Slab Wall RC
Name ABB Status Status Status Status Status Status that DD can information Calc Report RC Remarks on Design
Received Received Received Received Received Issued Status Status Drawings Drawings Report Sketches RC Pack Pack
commence to progress?
PROCESS
Hydraulic flow, Profile & Calculations ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐
Piping and Instrumentation DWG P&ID ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐
Design Criteria DC ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐
PRIMARY TREATMENT AREA
Unknown On Hold until
Unknown Yes Await RFI to Await RFI to Await RFI to Await RFI's
Inlet chamber & Culvert & FM1 ICH 13/07/17 ‐ Not received ‐ ‐ ‐ THABAT to ‐ Awaited 22/08/17 Open No design Await further information to start
THABAT to Confirm Eslam ‐ 17/08/17 start start start Inlet channel will be subject to agreement of VO
Confirm completed
Await approved Typsa BD (with correct equipment assembly) and
Awaited Await equipment loading information to allow DD to progress.
Coarse screen building & Container BLD CSB ‐ Draft received ‐ Awaited ‐ Awaited ‐ Awaited ‐ Awaited ‐ drawings to Awaited No On Hold On Hold On Hold On Hold Await BD drawings approval date Thabat to confirm agreement reached in July 2017 regarding separation
18/01/2017 review of primary treatment structures (see RFI). This agreement is to be
incorporated in Typsa BD design
Inlet pumping station IPS ‐ As CSB ‐ As CSB ‐ As CSB ‐ As CSB ‐ As CSB ‐ As CSB As CSB As CSB As CSB As CSB As CSB As CSB As CSB As CSB
Fine screen building & FM5 & Container BLD FSB ‐ As CSB ‐ As CSB ‐ As CSB ‐ As CSB ‐ As CSB ‐ As CSB As CSB As CSB As CSB As CSB As CSB As CSB As CSB As CSB
Unknown Await final Primary Treatment design incl. agreement on interface with
Code B Yes
Sand & grease chamber SGR 31/05/15 ‐ Awaited ‐ Awaited 31/05/17 THABAT to ‐ Awaited 22/08/17 Awaited No On Hold On Hold On Hold On Hold Await further information to start FSB
Requires rework Eslam ‐ 31/05/17
Confirm Await RFI's
Await
Air blowing building (sand & grit) BBA ‐ Awaited ‐ Awaited ‐ Awaited ‐ Awaited ‐ Awaited ‐ drawings to Awaited No On Hold On Hold On Hold On Hold Await BD drawings approval date Part of FSB ‐ Refer to FSB for details
review
Grease concentrator station GCS As SGR As SGR ‐ As SGR ‐ As SGR As SGR As SGR ‐ As SGR As SGR As SGR As SGR As SGR As SGR As SGR As SGR As SGR As SGR As SGR
Await
Odor control (pre‐treatment facilities) OC1 ‐ Awaited ‐ Awaited ‐ Awaited ‐ Awaited ‐ Awaited ‐ drawings to Awaited No On Hold On Hold On Hold On Hold Await BD drawings approval date Await approved Typsa BD and equipment loading to allow DD to progress.
review
Await
Await approved Typsa BD and equipment loading to allow DD to progress.
Substation building mcc1 MCC1 ‐ Awaited ‐ Awaited ‐ Awaited ‐ Awaited ‐ Awaited ‐ drawings to Awaited No On Hold On Hold On Hold On Hold Await BD drawings approval date
Understand Civil Défense comments awaited for BD
review
SECONDARY TREATMENT AND SLUDGE AREA
Unknown Yes Approved Approved On Hold until
Unknown Await RFI's
Distribution chamber & FM2 DCH 17/07/17 ‐ Not received ‐ ‐ 17/07/17 THABAT to ‐ Awaited 22/08/17 Open Eslam ‐ 17/07/2017 Yes 28/11/16 Ongoing 06/12/16 design 22/08/17 04/09/17 08/09/17 12/09/17 28/09/17 28/09/17
THABAT to Confirm VO3 ‐ Subject to receipt of signed Contract change Order
Confirm & 17/08/2017 Ongoing Ongoing completed
Await
Await approved Typsa BD and equipment loading to allow DD to progress.
Air blowing building (ICEAS) & MCC4 BBL ‐ Awaited ‐ Awaited ‐ Awaited ‐ Awaited ‐ Awaited ‐ drawings to Awaited No On Hold On Hold On Hold On Hold Await BD drawings approval date
Provided review of building draft drawings on 08/07/2017
review
Yes
ICEAS SBR tank (Support System) SBR 08/06/17 Code B ‐ Not received ‐ ‐ 08/06/17 Code B ‐ ‐ ‐ ‐ ‐ Approved Complete Approved Approved Complete Complete Complete Complete Complete Complete Early Warning for Foundation Design to be Agreed with Thabat
Eslam ‐ 08/06/2017
Approved
Yes Approved Approved
ICEAS SBR tank (Slab) SBR 08/06/17 Code B ‐ Not received ‐ ‐ 08/06/17 Code B ‐ ‐ ‐ ‐ ‐ 28/11/16 Complete Complete Complete Complete Complete Complete Complete VO4 ‐ Subject to receipt of signed Contract change Order
Eslam ‐ 08/06/2017 06/10/2016 27/06/17
05/07/17
Approved
Yes Approved Await
ICEAS SBR tank (Walls) SBR 08/06/17 Code B ‐ Not received ‐ ‐ 08/06/17 Code B ‐ ‐ ‐ ‐ ‐ 28/11/16 Complete Complete Complete Complete Complete Complete Complete VO1 & 4 ‐ Subject to receipt of signed Contract change Order
Eslam ‐ 08/06/2017 06/10/2017 Approval
05/07/17
Unknown Yes On Hold until
Unknown Await RFI to Await RFI to Await RFI to
Drainage SBR Pump Station DPS 16/07/17 ‐ ‐ ‐ ‐ 16/07/17 THABAT to ‐ Awaited 22/08/17 Open Eslam ‐ 16/07/2017 Yes design Await further information to start Await RFI's
THABAT to Confirm start start start
Confirm & 17/08/2017 completed
More
Yes Approved Approved On Hold until
information VO2 ‐ Subject to receipt of signed Contract change Order
Balance tank / intermediate PS & FM3 BTA 10/07/17 Code B ‐ Not received ‐ ‐ 10/07/17 Code B 10/07/17 22/08/17 Open Eslam ‐ 10/07/2017 Yes 10/11/16 Ongoing 05/11/16 design 24/08/17 13/09/17 18/09/17 22/09/17 17/10/17 24/10/17
required Await RFI's
& 17/08/2017 Ongoing Ongoing completed
(See RFI)
On Hold
Await On Hold
DRAFT Draft drawings received 1st July. Comments sent 8th & 10th July.
Sludge tank SLT ‐ Awaited ‐ Awaited ‐ Awaited ‐ Awaited ‐ Awaited ‐ drawings to Awaited No DRAFT issued On Hold On Hold Await BD drawings approval date
developed Await approved Typsa BD and equipment loading to allow DD to progress.
review 05/09/2016
05/09/2016
Sludge thickener STH As SLT As SLT ‐ As SLT ‐ As SLT ‐ As SLT ‐ As SLT ‐ As SLT As SLT As SLT As SLT As SLT As SLT As SLT As SLT As SLT
Polymer dosing unit for sludge thickener PD1 As SLT As SLT ‐ As SLT ‐ As SLT ‐ As SLT ‐ As SLT ‐ As SLT As SLT As SLT As SLT As SLT As SLT As SLT As SLT As SLT
Sludge mixing tank SMT As SLT As SLT ‐ As SLT ‐ As SLT ‐ As SLT ‐ As SLT ‐ As SLT As SLT As SLT As SLT As SLT As SLT As SLT As SLT As SLT
Supernatant pumping station SPS As SLT As SLT ‐ As SLT ‐ As SLT ‐ As SLT ‐ As SLT ‐ As SLT As SLT As SLT As SLT As SLT As SLT As SLT As SLT As SLT
Sludge dewatering SLD As SLT As SLT ‐ As SLT ‐ As SLT ‐ As SLT ‐ As SLT ‐ As SLT As SLT As SLT As SLT As SLT As SLT As SLT As SLT As SLT
Polymer dosing unit for SLD dewatering PD2 As SLT As SLT ‐ As SLT ‐ As SLT ‐ As SLT ‐ As SLT ‐ As SLT As SLT As SLT As SLT As SLT As SLT As SLT As SLT As SLT
Sludge silos building SLB As SLT As SLT ‐ As SLT ‐ As SLT ‐ As SLT ‐ As SLT ‐ As SLT As SLT As SLT As SLT As SLT As SLT As SLT As SLT As SLT
Await
Await approved Typsa BD and equipment loading to allow DD to progress.
Substation building MCC 2 MCC2 ‐ Awaited ‐ Awaited ‐ Awaited ‐ Awaited ‐ Awaited ‐ drawings to Awaited No On Hold On Hold On Hold On Hold Await BD drawings approval date
Understand Civil Défense comments awaited for BD
review
Await
Odor control (sludge facilities) OC2 ‐ Awaited ‐ Awaited ‐ Awaited ‐ Awaited ‐ Awaited ‐ Awaited No On Hold On Hold On Hold On Hold Await BD drawings approval date Await approved Typsa BD and equipment loading to allow DD to progress.
drawings to
Await
Await approved Typsa BD and equipment loading to allow DD to progress.
Substation building MCC3 MCC3 ‐ Awaited ‐ Awaited ‐ Awaited ‐ Awaited ‐ Awaited ‐ drawings to Awaited No On Hold On Hold On Hold On Hold Await BD drawings approval date
Understand Civil Défense comments awaited for BD
review
ATKINS
Closed Mech QRF
Item / Building Mech Dwg received Struct Dwg received Arch Dwg received Equipment Loading RFI Queries Deliverables Status Programme
received
Thabat Confirmation Sufficient
Date Date Date Date Date Date Drawing Modelling Draft GA Formal GA Calculation RC Intent Base Slab Wall RC
Name ABB Status Status Status Status Status Status that DD can information Calc Report RC Remarks on Design
Received Received Received Received Received Issued Status Status Drawings Drawings Report Sketches RC Pack Pack
commence to progress?
TERTIARY TREATMENT AREA
Appear to be More
On Hold until
Unknown based on THABAT to information Yes Await RFI's
Filtration building FBL 15/08/17 ‐ Awaited 15/08/17 15/08/17 15/08/17 22/08/17 Open Yes Ongoing Ongoing Ongoing design 04/09/17 14/09/17 21/09/17 22/09/17 11/10/17 19/10/17
THABAT to Confirm superseded Mech Confirm required Eslam ‐ 15/08/2017 Thabat to confirm common raft solution acceptable for FBL‐UVC
completed
drawings (See RFI)
Appear to be
On Hold until
Unknown based on THABAT to Yes
Backwash pumping station BPS 15/08/17 ‐ Awaited 15/08/17 15/08/17 ‐ Awaited 22/08/17 Open No On Hold On Hold On Hold design Await further information to start Await RFI's
THABAT to Confirm superseded Mech Confirm Eslam ‐ 15/08/2017
completed
drawings
More
On Hold until See FBL
information Yes
UV channel UVC 18/06/17 Code B ‐ Awaited ‐ Awaited ‐ Awaited 15/08/17 22/08/17 Open Yes Ongoing Ongoing Ongoing design 04/09/17 14/09/17 21/09/17 22/09/17 11/10/17 19/10/17 Miahona may cancel the structure preferring gas chlorination direct
required Ahmed ‐ 18/06/2017
completed injection
(See RFI)
On Hold until
Yes Current mechanical drawings are of limited use. More detail is required to
UV control building UVB 18/06/17 Code B ‐ Awaited ‐ Awaited ‐ Awaited ‐ Awaited 22/08/17 Open No On Hold On Hold On Hold design Await further information to start
Ahmed ‐ 18/06/2017 progress design (See RFI)
completed
Await RFI's
Code B Await CH2M incl. Updated site layout to confirm co‐ordinates; Approved Site Drainage
Yes Issued Issued Issued Issued
Chlorine contact tank CCT 30/05/17 Require updated ‐ Not provided ‐ Not provided ‐ Not provided ‐ Not provided 22/08/17 Open Yes Complete Approval ‐ 24/08/17 14/09/17 26/09/17 layout to confirm top of wall levels; Approved Typsa BD drawings to
Eslam ‐ 30/05/2017 11/08/17 11/08/17 11/08/17 11/08/17
drawings GA/Calc capture changes since Rev 4 drawing (See RFI)
RC to start on confirmation CH2M satisfied
Effluent flow metering chamber FM4 EMC See CCT See CCT ‐ See CCT ‐ See CCT ‐ As CCT ‐ As CCT As CCT As CCT As CCT Yes As CCT As CCT As CCT As CCT As CCT As CCT
Code B DRAFT
Yes Subject to agreement VO 5
Service Water Line SWL 30/05/17 Require updated ‐ Awaited ‐ Awaited ‐ Awaited ‐ Awaited 22/08/17 Open No Issued On Hold On Hold On Hold Await further information to start
Eslam ‐ 30/05/2017 Require more information (See RFI)
drawings 18/11/16
Awaiting updated BD drawings
Chlorine storage building NaOCL & PS CHB ‐ Awaited ‐ Awaited ‐ Awaited ‐ Awaited ‐ Awaited 25/11/16 Open Awaited No On Hold On Hold On Hold On Hold Await BD drawings approval date Miahona may convert to a Gas Chlorination building ‐ will be subject to
VO if case
Await
Substation building MCC5 MCC5 ‐ Awaited ‐ Awaited ‐ Awaited ‐ Awaited ‐ Awaited ‐ drawings to Awaited No On Hold On Hold On Hold On Hold Await BD drawings approval date Await approved Typsa BD and equipment loading to allow DD to progress.
review
Await
Final distribution chamber FDC ‐ Awaited ‐ Awaited ‐ Awaited ‐ Awaited ‐ Awaited ‐ drawings to Awaited No On Hold On Hold On Hold On Hold Await BD drawings approval date Await approved Typsa BD and equipment loading to allow DD to progress.
review
OTHER NON‐PROCESS BUILDINGS
Await
Warehouse WHB ‐ Awaited ‐ Awaited ‐ Awaited ‐ Awaited ‐ Awaited ‐ drawings to Awaited No On Hold On Hold On Hold On Hold Await BD drawings approval date Await approved Typsa BD and equipment loading to allow DD to progress.
review
Await
Operation building OBL ‐ Awaited ‐ Awaited ‐ Awaited ‐ Awaited ‐ Awaited ‐ drawings to Awaited No On Hold On Hold On Hold On Hold Await BD drawings approval date Await approved Typsa BD and equipment loading to allow DD to progress.
review
Await
Await approved Typsa BD and equipment loading to allow DD to progress.
Firefighting building FFB ‐ Awaited ‐ Awaited ‐ Awaited ‐ Awaited ‐ Awaited ‐ drawings to Awaited No On Hold On Hold On Hold On Hold Await BD drawings approval date
Will be subject to VO
review
Await
Drinking water tank DWT ‐ Awaited ‐ Awaited ‐ Awaited ‐ Awaited ‐ Awaited ‐ drawings to Awaited No On Hold On Hold On Hold On Hold Await BD drawings approval date Await approved Typsa BD and equipment loading to allow DD to progress.
review
Await
Weigh bridge WBF ‐ Awaited ‐ Awaited ‐ Awaited ‐ Awaited ‐ Awaited ‐ drawings to Awaited No On Hold On Hold On Hold On Hold Await BD drawings approval date Await approved Typsa BD and equipment loading to allow DD to progress.
review
Await
Await approved Typsa BD and equipment loading to allow DD to progress.
New Generators Building ‐ ‐ Awaited ‐ Awaited ‐ Awaited ‐ Awaited ‐ Awaited ‐ drawings to Awaited No On Hold On Hold On Hold On Hold Await BD drawings approval date
Will be subject to VO
review
CIVIL ELEMENTS
Await
Essential to allow setting out co‐ordinates of structures to be defined
Site Layout ‐ Awaited ‐ ‐ ‐ ‐ ‐ Awaited ‐ ‐ ‐ drawings to Awaited No On Hold On Hold ‐ ‐ Await BD drawings approval date
Await approved Typsa BD to allow DD to progress.
review
Await
Essential to define finished ground levels on site
Site Access Road and Storm Network ‐ Awaited ‐ ‐ ‐ ‐ ‐ Awaited ‐ ‐ ‐ drawings to Awaited No On Hold On Hold ‐ ‐ Await BD drawings approval date
Await approved Typsa BD to allow DD to progress.
review
Await
Site Pipework Design (including Influent, Effluent, Sludge, Overflow &
‐ Awaited ‐ ‐ ‐ ‐ ‐ Awaited ‐ ‐ ‐ drawings to Awaited No On Hold On Hold ‐ ‐ Await BD drawings approval date Await approved Typsa BD to allow DD to progress.
Sanitary network and Thrust block sizing)
review
Await
Landscape and Site Finishes ‐ Awaited ‐ ‐ ‐ ‐ ‐ Awaited ‐ ‐ ‐ drawings to Awaited No On Hold On Hold ‐ ‐ Await BD drawings approval date Await approved Typsa BD to allow DD to progress.
review
Await
Draw Pit Layout Design ‐ Awaited ‐ ‐ ‐ ‐ ‐ Awaited ‐ ‐ ‐ drawings to Awaited No On Hold On Hold ‐ ‐ Await BD drawings approval date Await approved Typsa BD to allow DD to progress.
review
Manfouha Sewage Treatment Plant Phase 4
APPENDIX C
Manfouha ‐ Atkins Priority Structure Delivery Schedule 29/08/2017
Received QRF Code C ‐ 28‐08‐17
Draft QRF response issued 29‐08‐17 & 30‐08‐17
Thabat confirmation QRF OK received 30‐8‐17
GA's, Gen Notes and QRF issued 31‐08‐17 (based north wall TOW 570.60)
CCT ‐ Formal Issue GA & Calc Report Thu 11/08/2017 11/08/2017 Thabat confirmed north wall TOW 571 (Email 01‐09‐17) (After 3 different instructions)
GA's, Gen Notes and QRF issued 01‐09‐17 (based north wall TOW 571)
Await confirmation drawings submitted to CH2M.
Await CH2M Comments GA re‐submission
CH2M Comments on Calc Report received 05‐09‐2017 and responded to on 06‐09‐2017
Received dwg mark‐ups 24‐08 & comments 28‐08 ‐ New information that is different to
approved Typsa drawing.
DCH ‐ Issue Draft GA Drawing set Tue 22/08/2017 22/08/2017 Base slab outlet increased 800mm ‐ Agreed 29‐08.
Revised set of drawings issued 01.09.2017 ‐ Await agreement of the VO before issue
formally.
Received Feedback 28th & 29th Aug ‐ Thabat wish to use offcuts.
CCT ‐ Issue Reinforcement Intent to Thabat Thu 24/08/2017 24/08/2017 Rebar Sketches re‐sent & Agreed Thabat 30‐08‐17
RC detailing underway.
Thabat feedback of 30‐08‐17 ‐ Limited use. Await:
‐‐ Responses to RFI's
‐‐ Response to Atkins return comments of 31‐08‐17 & 01‐09‐2017 (High level chamber
BTA ‐ Issue Draft Drawing set Thu 24/08/2017 24/08/2017 support and pump risers)
ON HOLD ‐ Email of 31‐08‐3017 ‐ Eng. Eslam.
DESIGN NOT FROZEN ‐ Eduardo 01‐09‐2017
Thabat confirmed 30‐08 that do not want to combine structures (Response to common
slab proposal sent 23‐08‐2017).
UVC‐FBL ‐ Issue Draft GA Drawing set Mon 04/09/2017 01/09/2017
Existing excavation interface ‐ foundation to be confirmed.
DRAFT drawing set issued 01/09/2017 ‐ Await Thabat Comments
Revised set of drawings issued 01.09.2017 DRAFT ‐ Await agreement of the VO before
issue formally.
DCH ‐ Formal Issue GA Drawings Mon 04/09/2017
Thabat comments received 06‐09‐2017 . This has delayed finalising drawings ‐ now to
be submitted 07‐09‐2017.
DCH ‐ Issue Calculation Report Fri 08/09/2017 Ongoing
Notes:
Programme logic and delivery dates rely on:
‐‐ Thabat to complete review activates as per programme allowance (refer to programme)
‐‐ Timely completion of CH2M reviews (Thabat to manage)
Manfouha Sewage Treatment Plant Phase 4
APPENDIX D
Atkins Deliverables - Al Manfouha STP4
Documents - Estimate
Drawing Title Date of Issue
STP‐SD‐02‐SBR1‐S‐411 SBR 1 Foundation ‐ Type 1 Pad foundation Reinforcement Details 11/08/2016
STP‐SD‐02‐SBR1‐S‐412 SBR 1 Foundation ‐ Type 2 Pad foundation Reinforcement Details 11/08/2016
STP‐SD‐02‐SBR1‐S‐413 SBR 1 Foundation ‐ Type 4 Pad foundation Reinforcement Details 11/08/2016
STP‐SD‐02‐SBR1‐S‐414 SBR 1 Foundation ‐ Type 3 Pad foundation Reinforcement Details 11/08/2016
STP‐SD‐02‐SBR2‐S‐411 SBR 2 Foundation ‐ Type 1 Pad foundation Reinforcement Details 24/08/2016
STP‐SD‐02‐SBR2‐S‐412 SBR 2 Foundation ‐ Type 2 Pad foundation Reinforcement Details 24/08/2016
STP‐SD‐02‐SBR2‐S‐413 SBR 2 Foundation ‐ Type 4 Pad foundation Reinforcement Details 24/08/2016
STP‐SD‐02‐SBR2‐S‐414 SBR 2 Foundation ‐ Type 3 Pad foundation Reinforcement Details 24/08/2016
STP‐SD‐02‐SBR2‐S‐415 SBR 2 Foundation ‐ Type 5 Pad foundation Reinforcement Details 24/08/2016
STP‐SD‐02‐SBR3‐S‐411 SBR 3 Foundation ‐ Type 1 Pad foundation Reinforcement Details 24/08/2016
STP‐SD‐02‐SBR3‐S‐412 SBR 3 Foundation ‐ Type 2 Pad foundation Reinforcement Details 24/08/2016
STP‐SD‐02‐SBR3‐S‐413 SBR 3 Foundation ‐ Type 3 Pad foundation Reinforcement Details 24/08/2016
STP‐SD‐02‐SBR3‐S‐414 SBR 3 Foundation ‐ Type 4 Pad foundation Reinforcement Details 09/09/2016
STP‐SD‐02‐SBR3‐S‐415 SBR 3 Foundation ‐ Type 5 Pad foundation Reinforcement Details 24/08/2016
22/11/2016
STP‐DD‐02‐SBR‐S‐420 SBR Base Slab Reinforcement SHEET‐1, 4, 12 & 15 Top Mat
01/06/2017
22/11/2016
STP‐DD‐02‐SBR‐S‐421 SBR Base Slab Reinforcement SHEET‐2 & 14 Top Mat
01/06/2017
22/11/2016
STP‐DD‐02‐SBR‐S‐422 SBR Base Slab Reinforcement SHEET‐3,7,9&13 Top Mat
01/06/2017
22/11/2016
STP‐DD‐02‐SBR‐S‐423 SBR Base Slab Reinforcement SHEET‐5&11 Top Mat
01/06/2017
22/11/2016
STP‐DD‐02‐SBR‐S‐424 SBR Base Slab Reinforcement SHEET ‐ 6 & 10 Top Mat
01/06/2017
22/11/2016
STP‐DD‐02‐SBR‐S‐425 SBR Base Slab Reinforcement SHEET‐8 Top Mat
01/06/2017
22/11/2016
STP‐DD‐02‐SBR‐S‐426 SBR Base Slab Reinforcement SHEET‐1, 4, 12 & 15 Bottom Mat
01/06/2017
22/11/2016
STP‐DD‐02‐SBR‐S‐427 SBR Base Slab Reinforcement SHEET‐2 & 14 Bottom Mat
01/06/2017
22/11/2016
STP‐DD‐02‐SBR‐S‐428 SBR Base Slab Reinforcement SHEET‐3,7,9&13 Bottom Mat
01/06/2017
22/11/2016
STP‐DD‐02‐SBR‐S‐429 SBR Base Slab Reinforcement SHEET‐5&11 Bottom Mat
01/06/2017
22/11/2016
STP‐DD‐02‐SBR‐S‐430 SBR Base Slab Reinforcement SHEET ‐ 6 & 10 Bottom Mat
01/06/2017
22/11/2016
STP‐DD‐02‐SBR‐S‐431 SBR Base Slab Reinforcement SHEET‐8 Bottom Mat
01/06/2017
22/11/2016
STP‐DD‐02‐SBR‐S‐446 SBR1 Base Slab Splice Reinforcement Top Mat
01/06/2017
22/11/2016
STP‐DD‐02‐SBR‐S‐447 SBR1 Base Slab Splice Reinforcement Bottom Mat
01/06/2017
17/11/2016
STP‐DD‐02‐SBR‐S‐434 SBR Reinforcement Details Wall reinforcement Sheet 1 of 10
10/08/2017
17/11/2016
STP‐DD‐02‐SBR‐S‐435 SBR Reinforcement Details Wall reinforcement Sheet 2 of 10
10/08/2017
17/11/2016
STP‐DD‐02‐SBR‐S‐436 SBR Reinforcement Details Wall reinforcement Sheet 3 of 10
10/08/2017
17/11/2016
STP‐DD‐02‐SBR‐S‐437 SBR Reinforcement Details Wall reinforcement Sheet 4 of 10
10/08/2017
17/11/2016
STP‐DD‐02‐SBR‐S‐438 SBR Reinforcement Details Wall reinforcement Sheet 5 of 10
10/08/2017
17/11/2016
STP‐DD‐02‐SBR‐S‐439 SBR Reinforcement Details Wall reinforcement Sheet 6 of 10
10/08/2017
17/11/2016
STP‐DD‐02‐SBR‐S‐440 SBR Reinforcement Details Wall reinforcement Sheet 7 of 10
10/08/2017
17/11/2016
STP‐DD‐02‐SBR‐S‐441 SBR Reinforcement Details Wall reinforcement Sheet 8 of 10
10/08/2017
17/11/2016
STP‐DD‐02‐SBR‐S‐442 SBR Reinforcement Details Wall reinforcement Sheet 9 of 10
10/08/2017
17/11/2016
STP‐DD‐02‐SBR‐S‐443 SBR Reinforcement Details Wall reinforcement Sheet 10 of 10
10/08/2017
17/11/2016
STP‐DD‐02‐SBR‐S‐444 SBR Reinforcement Details Central Dividing Chamber Sheet 1 of 2
10/08/2017
17/11/2016
STP‐DD‐02‐SBR‐S‐445 SBR Reinforcement Details Central Dividing Chamber Sheet 2 of 2
10/08/2017
STP‐DD‐SBR‐S‐150‐452 SBR Walkway Support Beams Reinforcement Details 10/08/2017
STP‐DD‐02‐ICH‐S‐400 Inlet Chamber Reinforcement Details 10/08/2017
STP‐DD‐02‐IPS‐S‐400 Inlet Pumping Station Reinforcement Details Sheet 1 of 4 TBC
STP‐DD‐02‐IPS‐S‐401 Inlet Pumping Station Reinforcement Details Sheet 2 of 4 TBC
STP‐DD‐02‐IPS‐S‐402 Inlet Pumping Station Reinforcement Details Sheet 3 of 4 TBC
STP‐DD‐02‐IPS‐S‐403 Inlet Pumping Station Reinforcement Details Sheet 4 of 4 TBC
STP‐DD‐02‐CSB‐S‐400 Coarse Screening Chamber Reinforcement Details Sheet 1 of 6 TBC
STP‐DD‐02‐CSB‐S‐401 Coarse Screening Chamber Reinforcement Details Sheet 2 of 6 TBC
STP‐DD‐02‐CSB‐S‐402 Coarse Screening Chamber Reinforcement Details Sheet 3 of 6 TBC
STP‐DD‐02‐CSB‐S‐403 Coarse Screening Chamber Reinforcement Details Sheet 4 of 6 TBC
STP‐DD‐02‐CSB‐S‐404 Coarse Screening Chamber Reinforcement Details Sheet 5 of 6 TBC
STP‐DD‐02‐CSB‐S‐405 Coarse Screening Chamber Reinforcement Details Sheet 6 of 6 TBC
STP‐DD‐02‐CSB‐S‐406 Coarse Screening Building Reinforcement Details Sheet 1 of 3 TBC
STP‐DD‐02‐CSB‐S‐407 Coarse Screening Building Reinforcement Details Sheet 2 of 3 TBC
STP‐DD‐02‐CSB‐S‐408 Coarse Screening Building Reinforcement Details Sheet 3 of 3 TBC
STP‐DD‐02‐FSB‐S‐400 Fine Screening Building Reinforcement Details Sheet 1 of 10 TBC
STP‐DD‐02‐FSB‐S‐401 Fine Screening Building Reinforcement Details Sheet 2 of 10 TBC
STP‐DD‐02‐FSB‐S‐402 Fine Screening Building Reinforcement Details Sheet 3 of 10 TBC
STP‐DD‐02‐FSB‐S‐403 Fine Screening Building Reinforcement Details Sheet 4 of 10 TBC
STP‐DD‐02‐FSB‐S‐404 Fine Screening Building Reinforcement Details Sheet 5 of 10 TBC
STP‐DD‐02‐FSB‐S‐405 Fine Screening Building Reinforcement Details Sheet 6 of 10 TBC
STP‐DD‐02‐FSB‐S‐406 Fine Screening Building Reinforcement Details Sheet 7 of 10 TBC
STP‐DD‐02‐FSB‐S‐407 Fine Screening Building Reinforcement Details Sheet 8 of 10 TBC
Drawing Title Date of Issue
STP‐DD‐02‐FSB‐S‐408 Fine Screening Building Reinforcement Details Sheet 9 of 10 TBC
STP‐DD‐02‐FSB‐S‐409 Fine Screening Building Reinforcement Details Sheet 10 of 10 TBC
STP‐DD‐02‐SGR‐S‐400 Sand & Grease Chamber Reinforcement Details Sheet 1 of 15 TBC
STP‐DD‐02‐SGR‐S‐401 Sand & Grease Chamber Reinforcement Details Sheet 2 of 15 TBC
STP‐DD‐02‐SGR‐S‐402 Sand & Grease Chamber Reinforcement Details Sheet 3 of 15 TBC
STP‐DD‐02‐SGR‐S‐403 Sand & Grease Chamber Reinforcement Details Sheet 4 of 15 TBC
STP‐DD‐02‐SGR‐S‐404 Sand & Grease Chamber Reinforcement Details Sheet 5 of 15 TBC
STP‐DD‐02‐SGR‐S‐405 Sand & Grease Chamber Reinforcement Details Sheet 6 of 15 TBC
STP‐DD‐02‐SGR‐S‐406 Sand & Grease Chamber Reinforcement Details Sheet 7 of 15 TBC
STP‐DD‐02‐SGR‐S‐407 Sand & Grease Chamber Reinforcement Details Sheet 8 of 15 TBC
STP‐DD‐02‐SGR‐S‐408 Sand & Grease Chamber Reinforcement Details Sheet 9 of 15 TBC
STP‐DD‐02‐SGR‐S‐409 Sand & Grease Chamber Reinforcement Details Sheet 10 of 15 TBC
STP‐DD‐02‐SGR‐S‐410 Sand & Grease Chamber Reinforcement Details Sheet 11 of 15 TBC
STP‐DD‐02‐SGR‐S‐411 Sand & Grease Chamber Reinforcement Details Sheet 12 of 15 TBC
STP‐DD‐02‐SGR‐S‐412 Sand & Grease Chamber Reinforcement Details Sheet 13 of 15 TBC
STP‐DD‐02‐SGR‐S‐413 Sand & Grease Chamber Reinforcement Details Sheet 14 of 15 TBC
STP‐DD‐02‐SGR‐S‐414 Sand & Grease Chamber Reinforcement Details Sheet 15 of 15 TBC
STP‐DD‐02‐IMC‐S‐400 Inflow Metering Flume Reinforcement Details TBC
STP‐DD‐02‐GCS‐S‐400 Grease Concentrator Station Slab Reinforcement Details TBC
STP‐DD‐02‐BTA‐S‐400 Balance Tank / Intermediate Pump Station Reinforcement Details Sheet 1 of 15 17/10/2017
STP‐DD‐02‐BTA‐S‐401 Balance Tank / Intermediate Pump Station Reinforcement Details Sheet 2 of 15 17/10/2017
STP‐DD‐02‐BTA‐S‐402 Balance Tank / Intermediate Pump Station Reinforcement Details Sheet 3 of 15 17/10/2017
STP‐DD‐02‐BTA‐S‐403 Balance Tank / Intermediate Pump Station Reinforcement Details Sheet 4 of 15 17/10/2017
STP‐DD‐02‐BTA‐S‐404 Balance Tank / Intermediate Pump Station Reinforcement Details Sheet 5 of 15 17/10/2017
STP‐DD‐02‐BTA‐S‐405 Balance Tank / Intermediate Pump Station Reinforcement Details Sheet 6 of 15 17/10/2017
STP‐DD‐02‐BTA‐S‐406 Balance Tank / Intermediate Pump Station Reinforcement Details Sheet 7 of 15 17/10/2017
STP‐DD‐02‐BTA‐S‐407 Balance Tank / Intermediate Pump Station Reinforcement Details Sheet 8 of 15 17/10/2017
STP‐DD‐02‐BTA‐S‐408 Balance Tank / Intermediate Pump Station Reinforcement Details Sheet 9 of 15 24/10/2017
STP‐DD‐02‐BTA‐S‐409 Balance Tank / Intermediate Pump Station Reinforcement Details Sheet 10 of 15 24/10/2017
STP‐DD‐02‐BTA‐S‐410 Balance Tank / Intermediate Pump Station Reinforcement Details Sheet 11 of 15 24/10/2017
STP‐DD‐02‐BTA‐S‐411 Balance Tank / Intermediate Pump Station Reinforcement Details Sheet 12 of 15 24/10/2017
STP‐DD‐02‐BTA‐S‐412 Balance Tank / Intermediate Pump Station Reinforcement Details Sheet 13 of 15 24/10/2017
STP‐DD‐02‐BTA‐S‐413 Balance Tank / Intermediate Pump Station Reinforcement Details Sheet 14 of 15 24/10/2017
STP‐DD‐02‐BTA‐S‐414 Balance Tank / Intermediate Pump Station Reinforcement Details Sheet 15 of 15 24/10/2017
STP‐DD‐02‐FBL‐S‐400 Filtration Building Reinforcement Details Sheet 1 of 6 11/10/2017
STP‐DD‐02‐FBL‐S‐401 Filtration Building Reinforcement Details Sheet 2 of 6 11/10/2017
STP‐DD‐02‐FBL‐S‐402 Filtration Building Reinforcement Details Sheet 3 of 6 11/10/2017
STP‐DD‐02‐FBL‐S‐403 Filtration Building Reinforcement Details Sheet 4 of 6 19/10/2017
STP‐DD‐02‐FBL‐S‐404 Filtration Building Reinforcement Details Sheet 5 of 6 19/10/2017
STP‐DD‐02‐FBL‐S‐405 Filtration Building Reinforcement Details Sheet 6 of 6 19/10/2017
STP‐DD‐02‐BPS‐S‐400 Backwash Pumping Station Reinforcement Details TBC
STP‐DD‐02‐UVC‐S‐400 UV Channel Reinforcement Details Sheet 1 of 6 11/10/2017
STP‐DD‐02‐UVC‐S‐401 UV Channel Reinforcement Details Sheet 2 of 6 11/10/2017
STP‐DD‐02‐UVC‐S‐402 UV Channel Reinforcement Details Sheet 3 of 6 11/10/2017
STP‐DD‐02‐UVC‐S‐403 UV Channel Reinforcement Details Sheet 4 of 6 19/10/2017
STP‐DD‐02‐UVC‐S‐404 UV Channel Reinforcement Details Sheet 5 of 6 19/10/2017
STP‐DD‐02‐UVC‐S‐405 UV Channel Reinforcement Details Sheet 6 of 6 19/10/2017
STP‐DD‐02‐UVB‐S‐400 UV Building Reinforcement Details Sheet 1 of 3 TBC
STP‐DD‐02‐UVB‐S‐401 UV Building Reinforcement Details Sheet 2 of 3 TBC
STP‐DD‐02‐UVB‐S‐402 UV Building Reinforcement Details Sheet 3 of 3 TBC
STP‐DD‐02‐CCT‐S‐400 Chlorine Contact Tank Reinforcement Details Sheet 1 of 15 14/09/2017
STP‐DD‐02‐CCT‐S‐401 Chlorine Contact Tank Reinforcement Details Sheet 2 of 15 14/09/2017
STP‐DD‐02‐CCT‐S‐402 Chlorine Contact Tank Reinforcement Details Sheet 3 of 15 14/09/2017
STP‐DD‐02‐CCT‐S‐403 Chlorine Contact Tank Reinforcement Details Sheet 4 of 15 14/09/2017
STP‐DD‐02‐CCT‐S‐404 Chlorine Contact Tank Reinforcement Details Sheet 5 of 15 14/09/2017
STP‐DD‐02‐CCT‐S‐405 Chlorine Contact Tank Reinforcement Details Sheet 6 of 15 14/09/2017
STP‐DD‐02‐CCT‐S‐406 Chlorine Contact Tank Reinforcement Details Sheet 7 of 15 14/09/2017
STP‐DD‐02‐CCT‐S‐407 Chlorine Contact Tank Reinforcement Details Sheet 8 of 15 14/09/2017
STP‐DD‐02‐CCT‐S‐408 Chlorine Contact Tank Reinforcement Details Sheet 9 of 15 26/09/2017
STP‐DD‐02‐CCT‐S‐409 Chlorine Contact Tank Reinforcement Details Sheet 10 of 15 26/09/2017
STP‐DD‐02‐CCT‐S‐410 Chlorine Contact Tank Reinforcement Details Sheet 11 of 15 26/09/2017
STP‐DD‐02‐CCT‐S‐411 Chlorine Contact Tank Reinforcement Details Sheet 12 of 15 26/09/2017
STP‐DD‐02‐CCT‐S‐412 Chlorine Contact Tank Reinforcement Details Sheet 13 of 15 26/09/2017
STP‐DD‐02‐CCT‐S‐413 Chlorine Contact Tank Reinforcement Details Sheet 14 of 15 26/09/2017
STP‐DD‐02‐CCT‐S‐414 Chlorine Contact Tank Reinforcement Details Sheet 15 of 15 26/09/2017
STP‐DD‐02‐EMC‐S‐400 Effluent Flow Flume Reinforcement Details 26/09/2017
STP‐DD‐02‐SWL‐S‐400 Service Water Line Reinforcement Details TBC
STP‐DD‐02‐CHB‐S‐400 Chlorine Storage Building Reinforcement Details Sheet 1 of 4 TBC
STP‐DD‐02‐CHB‐S‐401 Chlorine Storage Building Reinforcement Details Sheet 2 of 4 TBC
STP‐DD‐02‐CHB‐S‐402 Chlorine Storage Building Reinforcement Details Sheet 3 of 4 TBC
STP‐DD‐02‐CHB‐S‐403 Chlorine Storage Building Reinforcement Details Sheet 4 of 4 TBC
STP‐DD‐02‐BBL‐S‐400 Air Blowing Building Reinforcement Details Sheet 1 of 4 TBC
STP‐DD‐02‐BBL‐S‐401 Air Blowing Building Reinforcement Details Sheet 2 of 4 TBC
STP‐DD‐02‐BBL‐S‐402 Air Blowing Building Reinforcement Details Sheet 3 of 4 TBC
STP‐DD‐02‐BBL‐S‐403 Air Blowing Building Reinforcement Details Sheet 4 of 4 TBC
STP‐DD‐02‐BBL‐S‐405 Air Blowing Building Foundation ‐ Pad foundation Reinforcement Details Sheet 1 of 4 TBC
STP‐DD‐02‐BBL‐S‐406 Air Blowing Building Foundation ‐ Pad foundation Reinforcement Details Sheet 2 of 4 TBC
STP‐DD‐02‐BBL‐S‐407 Air Blowing Building Foundation ‐ Pad foundation Reinforcement Details Sheet 3 of 4 TBC
STP‐DD‐02‐BBL‐S‐408 Air Blowing Building Foundation ‐ Pad foundation Reinforcement Details Sheet 4 of 4 TBC
STP‐DD‐02‐SLD‐S‐400 Sludge Thickener/Dewatering & Polymer Dosing Building Reinforcement Details Sheet 1 of 15 TBC
STP‐DD‐02‐SLD‐S‐401 Sludge Thickener/Dewatering & Polymer Dosing Building Reinforcement Details Sheet 2 of 15 TBC
STP‐DD‐02‐SLD‐S‐402 Sludge Thickener/Dewatering & Polymer Dosing Building Reinforcement Details Sheet 3 of 15 TBC
STP‐DD‐02‐SLD‐S‐403 Sludge Thickener/Dewatering & Polymer Dosing Building Reinforcement Details Sheet 4 of 15 TBC
STP‐DD‐02‐SLD‐S‐404 Sludge Thickener/Dewatering & Polymer Dosing Building Reinforcement Details Sheet 5 of 15 TBC
STP‐DD‐02‐SLD‐S‐405 Sludge Thickener/Dewatering & Polymer Dosing Building Reinforcement Details Sheet 6 of 15 TBC
STP‐DD‐02‐SLD‐S‐406 Sludge Thickener/Dewatering & Polymer Dosing Building Reinforcement Details Sheet 7 of 15 TBC
STP‐DD‐02‐SLD‐S‐407 Sludge Thickener/Dewatering & Polymer Dosing Building Reinforcement Details Sheet 8 of 15 TBC
STP‐DD‐02‐SLD‐S‐408 Sludge Thickener/Dewatering & Polymer Dosing Building Reinforcement Details Sheet 9 of 15 TBC
STP‐DD‐02‐SLD‐S‐409 Sludge Thickener/Dewatering & Polymer Dosing Building Reinforcement Details Sheet 10 of 15 TBC
STP‐DD‐02‐SLD‐S‐410 Sludge Thickener/Dewatering & Polymer Dosing Building Reinforcement Details Sheet 11 of 15 TBC
STP‐DD‐02‐SLD‐S‐411 Sludge Thickener/Dewatering & Polymer Dosing Building Reinforcement Details Sheet 12 of 15 TBC
STP‐DD‐02‐SLD‐S‐412 Sludge Thickener/Dewatering & Polymer Dosing Building Reinforcement Details Sheet 13 of 15 TBC
Drawing Title Date of Issue
STP‐DD‐02‐SLD‐S‐413 Sludge Thickener/Dewatering & Polymer Dosing Building Reinforcement Details Sheet 14 of 15 TBC
STP‐DD‐02‐SLD‐S‐414 Sludge Thickener/Dewatering & Polymer Dosing Building Reinforcement Details Sheet 15 of 15 TBC
STP‐DD‐02‐SLD‐S‐416 Sludge Thickener/Dewatering & Polymer Dosing Building Foundation ‐ Pad foundation Reinforcement Details Sheet 1 of 4 TBC
STP‐DD‐02‐SLD‐S‐417 Sludge Thickener/Dewatering & Polymer Dosing Building Foundation ‐ Pad foundation Reinforcement Details Sheet 2 of 4 TBC
STP‐DD‐02‐SLD‐S‐418 Sludge Thickener/Dewatering & Polymer Dosing Building Foundation ‐ Pad foundation Reinforcement Details Sheet 3 of 4 TBC
STP‐DD‐02‐SLD‐S‐419 Sludge Thickener/Dewatering & Polymer Dosing Building Foundation ‐ Pad foundation Reinforcement Details Sheet 4 of 4 TBC
STP‐DD‐02‐SLB‐S‐401 Sludge Silos Foundation ‐ Pad foundation Reinforcement Details Sheet 1 of 4 TBC
STP‐DD‐02‐SLB‐S‐402 Sludge Silos Foundation ‐ Pad foundation Reinforcement Details Sheet 2 of 4 TBC
STP‐DD‐02‐SLB‐S‐403 Sludge Silos Foundation ‐ Pad foundation Reinforcement Details Sheet 3 of 4 TBC
STP‐DD‐02‐SLB‐S‐404 Sludge Silos Foundation ‐ Pad foundation Reinforcement Details Sheet 4 of 4 TBC
STP‐DD‐02‐SLT‐S‐400 Sludge Tank incl odour control 2 Reinforcement Details Sheet 1 of 6 TBC
STP‐DD‐02‐SLT‐S‐401 Sludge Tank incl odour control 2 Reinforcement Details Sheet 2 of 6 TBC
STP‐DD‐02‐SLT‐S‐402 Sludge Tank incl odour control 2 Reinforcement Details Sheet 3 of 6 TBC
STP‐DD‐02‐SLT‐S‐403 Sludge Tank incl odour control 2 Reinforcement Details Sheet 4 of 6 TBC
STP‐DD‐02‐SLT‐S‐404 Sludge Tank incl odour control 2 Reinforcement Details Sheet 5 of 6 TBC
STP‐DD‐02‐SLT‐S‐405 Sludge Tank incl odour control 2 Reinforcement Details Sheet 6 of 6 TBC
STP‐DD‐02‐SLT‐S‐407 Sludge Tank incl odour control 2 Foundation ‐ Pad foundation Reinforcement Details Sheet 1 of 4 TBC
STP‐DD‐02‐SLT‐S‐408 Sludge Tank incl odour control 2 Foundation ‐ Pad foundation Reinforcement Details Sheet 2 of 4 TBC
STP‐DD‐02‐SLT‐S‐409 Sludge Tank incl odour control 2 Foundation ‐ Pad foundation Reinforcement Details Sheet 3 of 4 TBC
STP‐DD‐02‐SLT‐S‐410 Sludge Tank incl odour control 2 Foundation ‐ Pad foundation Reinforcement Details Sheet 4 of 4 TBC
STP‐DD‐02‐SMT‐S‐400 Sludge Mixing Tank Reinforcement Details Sheet 1 of 6 TBC
STP‐DD‐02‐SMT‐S‐401 Sludge Mixing Tank Reinforcement Details Sheet 2 of 6 TBC
STP‐DD‐02‐SMT‐S‐402 Sludge Mixing Tank Reinforcement Details Sheet 3 of 6 TBC
STP‐DD‐02‐SMT‐S‐403 Sludge Mixing Tank Reinforcement Details Sheet 4 of 6 TBC
STP‐DD‐02‐SMT‐S‐404 Sludge Mixing Tank Reinforcement Details Sheet 5 of 6 TBC
STP‐DD‐02‐SMT‐S‐405 Sludge Mixing Tank Reinforcement Details Sheet 6 of 6 TBC
STP‐DD‐02‐SMT‐S‐407 Sludge Mixing Tank Foundation ‐ Pad foundation Reinforcement Details Sheet 1 of 4 TBC
STP‐DD‐02‐SMT‐S‐408 Sludge Mixing Tank Foundation ‐ Pad foundation Reinforcement Details Sheet 2 of 4 TBC
STP‐DD‐02‐SMT‐S‐409 Sludge Mixing Tank Foundation ‐ Pad foundation Reinforcement Details Sheet 3 of 4 TBC
STP‐DD‐02‐SMT‐S‐410 Sludge Mixing Tank Foundation ‐ Pad foundation Reinforcement Details Sheet 4 of 4 TBC
STP‐DD‐02‐SPS‐S‐400 Supernatant Pumping Station Reinforcement Details TBC
STP‐DD‐02‐DCH‐S‐400 Distribution Chamber Reinforcement Details Sheet 1 of 4 28/09/2017
STP‐DD‐02‐DCH‐S‐401 Distribution Chamber Reinforcement Details Sheet 2 of 4 28/09/2017
STP‐DD‐02‐DCH‐S‐402 Distribution Chamber Reinforcement Details Sheet 3 of 4 28/09/2017
STP‐DD‐02‐DCH‐S‐403 Distribution Chamber Reinforcement Details Sheet 4 of 4 28/09/2017
STP‐DD‐02‐MCC1‐S‐400 Substation Building 1 Reinforcement Details Sheet 1 of 4 TBC
STP‐DD‐02‐MCC1‐S‐401 Substation Building 1 Reinforcement Details Sheet 2 of 4 TBC
STP‐DD‐02‐MCC1‐S‐402 Substation Building 1 Reinforcement Details Sheet 3 of 4 TBC
STP‐DD‐02‐MCC1‐S‐403 Substation Building 1 Reinforcement Details Sheet 4 of 4 TBC
STP‐DD‐02‐MCC2‐S‐400 Substation Building 2 Reinforcement Details Sheet 1 of 4 TBC
STP‐DD‐02‐MCC2‐S‐401 Substation Building 2 Reinforcement Details Sheet 2 of 4 TBC
STP‐DD‐02‐MCC2‐S‐402 Substation Building 2 Reinforcement Details Sheet 3 of 4 TBC
STP‐DD‐02‐MCC2‐S‐403 Substation Building 2 Reinforcement Details Sheet 4 of 4 TBC
STP‐DD‐02‐MCC2‐S‐405 Substation Building 2 Foundation ‐ Pad foundation Reinforcement Details Sheet 1 of 4 TBC
STP‐DD‐02‐MCC2‐S‐406 Substation Building 2 Foundation ‐ Pad foundation Reinforcement Details Sheet 2 of 4 TBC
STP‐DD‐02‐MCC2‐S‐407 Substation Building 2 Foundation ‐ Pad foundation Reinforcement Details Sheet 3 of 4 TBC
STP‐DD‐02‐MCC2‐S‐408 Substation Building 2 Foundation ‐ Pad foundation Reinforcement Details Sheet 4 of 4 TBC
STP‐DD‐02‐MCC3‐S‐400 Substation Building 3 Reinforcement Details Sheet 1 of 4 TBC
STP‐DD‐02‐MCC3‐S‐401 Substation Building 3 Reinforcement Details Sheet 2 of 4 TBC
STP‐DD‐02‐MCC3‐S‐402 Substation Building 3 Reinforcement Details Sheet 3 of 4 TBC
STP‐DD‐02‐MCC3‐S‐403 Substation Building 3 Reinforcement Details Sheet 4 of 4 TBC
STP‐DD‐02‐MCC3‐S‐405 Substation Building 3 Foundation ‐ Pad foundation Reinforcement Details Sheet 1 of 4 TBC
STP‐DD‐02‐MCC3‐S‐406 Substation Building 3 Foundation ‐ Pad foundation Reinforcement Details Sheet 2 of 4 TBC
STP‐DD‐02‐MCC3‐S‐407 Substation Building 3 Foundation ‐ Pad foundation Reinforcement Details Sheet 3 of 4 TBC
STP‐DD‐02‐MCC3‐S‐408 Substation Building 3 Foundation ‐ Pad foundation Reinforcement Details Sheet 4 of 4 TBC
STP‐DD‐02‐MCC5‐S‐400 Substation Building 5 Reinforcement Details Sheet 1 of 4 TBC
STP‐DD‐02‐MCC5‐S‐401 Substation Building 5 Reinforcement Details Sheet 2 of 4 TBC
STP‐DD‐02‐MCC5‐S‐402 Substation Building 5 Reinforcement Details Sheet 3 of 4 TBC
STP‐DD‐02‐MCC5‐S‐403 Substation Building 5 Reinforcement Details Sheet 4 of 4 TBC
STP‐DD‐02‐OC1‐S‐400 Pre‐treatment Odour Control Slab Reinforcement Details TBC
STP‐DD‐02‐WHB‐S‐400 Warehouse Building Reinforcement Details Sheet 1 of 6 TBC
STP‐DD‐02‐WHB‐S‐401 Warehouse Building Reinforcement Details Sheet 2 of 6 TBC
STP‐DD‐02‐WHB‐S‐402 Warehouse Building Reinforcement Details Sheet 3 of 6 TBC
STP‐DD‐02‐WHB‐S‐403 Warehouse Building Reinforcement Details Sheet 4 of 6 TBC
STP‐DD‐02‐WHB‐S‐404 Warehouse Building Reinforcement Details Sheet 5 of 6 TBC
STP‐DD‐02‐WHB‐S‐405 Warehouse Building Reinforcement Details Sheet 6 of 6 TBC
STP‐DD‐02‐OBL‐S‐400 Operations Building Reinforcement Details Sheet 1 of 6 TBC
STP‐DD‐02‐OBL‐S‐401 Operations Building Reinforcement Details Sheet 2 of 6 TBC
STP‐DD‐02‐OBL‐S‐402 Operations Building Reinforcement Details Sheet 3 of 6 TBC
STP‐DD‐02‐OBL‐S‐403 Operations Building Reinforcement Details Sheet 4 of 6 TBC
STP‐DD‐02‐OBL‐S‐404 Operations Building Reinforcement Details Sheet 5 of 6 TBC
STP‐DD‐02‐OBL‐S‐405 Operations Building Reinforcement Details Sheet 6 of 6 TBC
STP‐DD‐02‐OBL‐S‐407 Operations Building Foundation ‐ Pad foundation Reinforcement Details Sheet 1 of 4 TBC
STP‐DD‐02‐OBL‐S‐408 Operations Building Foundation ‐ Pad foundation Reinforcement Details Sheet 2 of 4 TBC
STP‐DD‐02‐OBL‐S‐409 Operations Building Foundation ‐ Pad foundation Reinforcement Details Sheet 3 of 4 TBC
STP‐DD‐02‐OBL‐S‐410 Operations Building Foundation ‐ Pad foundation Reinforcement Details Sheet 4 of 4 TBC
STP‐DD‐02‐FFB‐S‐400 Fire Fighting Building Reinforcement Details Sheet 1 of 4 TBC
STP‐DD‐02‐FFB‐S‐401 Fire Fighting Building Reinforcement Details Sheet 2 of 4 TBC
STP‐DD‐02‐FFB‐S‐402 Fire Fighting Building Reinforcement Details Sheet 3 of 4 TBC
STP‐DD‐02‐FFB‐S‐403 Fire Fighting Building Reinforcement Details Sheet 4 of 4 TBC
STP‐DD‐02‐DWT‐S‐401 Drinking Water Tank Foundation ‐ Pad foundation Reinforcement Details Sheet 1 of 2 TBC
STP‐DD‐02‐DWT‐S‐402 Drinking Water Tank Foundation ‐ Pad foundation Reinforcement Details Sheet 2 of 2 TBC
STP‐DD‐02‐FDC‐S‐400 Final Distribution Chamber Reinforcement Details TBC
STP‐DD‐02‐WBF‐S‐400 Weigh Bridge Substructure Reinforcement Details TBC
STP‐DD‐02‐G‐S‐400 Existing Generator Building (Power House) Modifications Reinforcement Details (if required) TBC
240
Atkins Deliverables - Al Manfouha STP4
Structural Drawings Estimate
APPENDIX E
ATKINS ‐ SUMMARY OF PENDING RFI'S (FOR BD DESIGNS RECEIVED) 06/09/2017
Note: More RFI's will be raised as BD received
GNERAL ITEMS
Atkins ‐ RFI
RFI Title Date RFI Query Thabat Response From Date
Open/closed
Please confirm Contract status – PPP or D&B ‐If PPP what will be effect on project and
Contract Status 27/08/17
approval process and CH2M's role?
Team Structure 27/08/17 Confirm Thabat Team structure – (incl. New PM)
Project Structure 27/08/17 Confirm Project Team structure
Site Progress 27/08/17 Confirm Site Progress
27/08/17
Communication persists as most challenging aspect of project.
Ned for improved I.T. systems to allow regular video/voice conferencing and facilitate
Communication 27/08/17 easy understanding for all.
‐ Improved correspondence on issues/drawing/document submittals and approval status
required
Done, please check below link:
https://muhaidib‐
Please can the SharePoint folder be updated to contain: my.sharepoint.com/personal/30024047_thabat_sa/Documents/Forms/All.asp
‐ A high level folder for each Structures x?FolderCTID=0x012000E9356BCDBC26F148A1A2E6E10BABD1F1&id=%2Fper
‐ Within each folder please provide: sonal%2F30024047_thabat_sa%2FDocuments%2FBIM%2F02‐SHARED%2F03‐
Open
‐‐Sub folders for each design discipline drawings incl. CH2M QRF review comments ATKINS
Can not access
Document Management / SharePoint 27/08/17 ‐‐Sub folder for equipment loading information/data sheets Eslam 30/08/2017
link ‐ Email
‐‐ Upload folder where Atkins can publish new drawings. See Also this link where you can upload your new drawings and share with us
31/08/2017
(Separate Folder):
Thabat should be responsible for management of the information to ensure co‐
ordination and communication is maintained. https://muhaidib‐
my.sharepoint.com/personal/30024047_thabat_sa/Documents/BIM/05‐
INCOMING/03‐ATKINS
Please provide confirmation of the following Typsa drawing deliverables for each
structure on the Manfouha site. With the exception of Mechanical drawings since
December 2016 we have not received an update as to the status of the following
disciplines that we rely upon to fully understand each structure:
‐ Electrical
Typsa Deliverables 27/08/17 ‐ Structural
‐ Architectural
‐ Building services
‐ Structural 3D Model
If Typsa are no longer providing the 3D model then who is developing them (like the one
you added to the folder)?
It has become clear in the last week that design co‐ordination requires some
Design co‐ordination 27/08/17
improvement.
Typsa submission 27/08/17 Mechanical drawings lack sufficient detail to allow detailed design
Equipment Procurement 27/08/17 Confirm status ‐ Are NWC items resolved and it is proceeding?
Equipment submittals are too general and do not provide specific loading/dimensional
Equipment submittals 27/08/17
information required
Confirm strategy for managing CH2M. Quality of Drawing/Document reviews has been of
concern for some time and as a team we can not succumb to preferential engineering.
CH2M Management 27/08/17
Design approvals are long in duration and usually held up by non‐technical and
preferential requests.
Summary of pending basic design items that may effect the detailed design of each
structure.
All Structures 27/08/17 ‐‐ Status of material submittals linked to the buildings (equipment procured and
finalised?)
‐‐ Status of specifications linked to buildings
PROGRAMME & COMMERCIAL
Atkins ‐ RFI
RFI Title Date RFI Query Thabat Response Date
Open/closed
Commercial Items 27/08/17 To be addressed separately
A programme of submitted BD and estimated CH2M approval is required to allow
Basic Design Approval Programme 27/08/17
programme od DD to be developed
Confirmed by Eng. Eslam 16/08/2017
‐ RC and BBS for Chlorine Contact Tank
Atkins ‐ list of priority structures 27/08/17 ‐ Updated GA for Balancing Tank
‐ UVC, UVB, BPS and FBL
‐ Updated GA for Distribution chamber
SITEWIDE DRAWINGS
Atkins ‐ RFI
RFI Title Date RFI Query Thabat Response From Date
Open/closed
Await updated CH2M approved site drainage layout to allow Top of Wall/Threshold
Site Drainage Layout 27/08/17
levels to be confirmed
PRIMARY TREATMENT
Atkins ‐ RFI
RFI Title Date RFI Query Thabat Response From Date
Open/closed
Further to email correspondence of the 3rd, 10th, 19th and 20th July, separation of the
primary treatment structures was discussed in email correspondence between Eng.
Leddy of Atkins and Eng. Eslam of Thabat.
During this discussion results of Robot model of inlet works were shared and agreement
reached on the jointing of the Primary Treatment.
The solution agreed entailed:
Separation Structure 27/08/17
‐‐ CSB/IPS/FSB to be kept as a single structure. Consideration was to be given to stiffening
up the IPS to FSB interface and use of additional foundation/wall arrangement can be
considered at detailed design
‐‐ The SGR was to be moved south and a link culvert structure between FSB and SGR. to
facilitate differential settlement.
Please re‐confirm Thabat' s agreement to this solution
PIPEWORK
Atkins ‐ RFI
RFI Title Date RFI Query Thabat Response From Date
Open/closed
Please confirm acceptance with Atkins 'Thrust Block Design Approach' sent via email on
Thrust Block design concept 27/08/17 12‐12‐2016 From Eng Farrag (Atkins) to Eng. Salah and Eng Eslam (Thabat) as the basis for
completion of the projects pipework design
Please confirm acceptance of Atkins pipework design methodology forwarded by Eng.
Farrag (Atkins) to Eng Haroon and Eng. Al Maghrabi (Thabat) on 07‐12‐2016
Pipe Design Methodology, Bedding,
27/08/17 This included:
Trench and Backfill specifications
‐‐ Flow chart for design development including responsibilities of ACWA, Atkins, Thabat,
Typsa and CH2M
‐‐ Information on pipe trenches, bedding and backfill material
Please provide response to Atkins Civil Pipework RFI submitted on 19‐08‐2016 by Eng.
Civil Pipework RFI 27/08/17
Farrag (Atkins) to Eng. George (Thabat) and re‐copied below for reference:
Please confirm your selected pipework manufacturer and forward supplier submittal
Material 27/08/17
including specifications to enable pipe bedding details to be confirmed
To ensure consistency between valve & fittings, please confirm flanges standard ANSI or
Material 27/08/17
BS?
Please confirm our understanding; Are gravity pipes lowest, then pumping, then air main
Pipework Strategy 27/08/17
highest? Will updated long sections/model be provided to give an indication of level?
Please confirm pipework terminations and ownership of detail and design between
Interface 27/08/17
Typsa/Xylem/Atkins
Please confirm the level of detail to be provided by Typsa to aid civil pipework detailed
Interface 27/08/17
design
Thrust Restraint 27/08/17 Please confirm if restrained joints or thrust blocks can be considered in design
Please confirm how is thrust restraint to be dealt with at pipework interfaces such as
Thrust Restraint 27/08/17
civil/mechanical scope or buried/above ground pipework
Thrust Restraint 27/08/17 Please confirm 0.86 Bar is the maximum working pressure in the system
As previously mentioned by Typsa in RFI response dated 15/3/16, preliminary
Thrust Restraint 27/08/17 calculations and sketches will be provided for thrust blocks. Please confirm when this will
be available
Please confirm if wall couplers or cast‐in puddle flanges are the preferred solution for
Penetration Details 27/08/17 pipe penetrations through walls. Please forward supplier specifications if alternative
details are to be considered
SITE WIDE ARCHITECTURE
Atkins ‐ RFI
RFI Title Date RFI Query Thabat Response From Date
Open/closed
Please re‐confirm the Cooling Requirements & Proposed Architectural Wall Finish for
Building make‐up/insulation and
27/08/17 each building at the Al Manfouha site. Please refer to Atkins email of 5th October 2016
architectural finish requirements
that summarised all buildings and wall finishes/insulation requirements.
Further to discussions in late 2016 please re‐confirm that a double leaf insulated wall
(Confirmed Eng Hani 24/11/2017) can be used in the construction of the buildings at Al
Manfouha.
Wall system 27/08/17
Please note that due to the height of some buildings, intermediate restraint beams will
be required to the wall panels. This system will allow a consistent external façade to be
confirmed.
Please re‐confirm acoustic performance requirements of buildings on site. Typsa to
Acoustic Performance 27/08/17
confirm.
We have completed a re‐assessment of the wall structural requirements and the noted
sizes are a minimum required to ensure an structural competent wall panel system is
achieved.
Drawing of wall system with typical details forwarded to Thabat on 22/11/2016. Please re‐
review and confirm.
Wall components (minimum
27/08/17 Min requirements:
requirements)
Solid concrete blocks (Min. 150mm*)
Insulation boards (50-100mm**)
Hollow concrete blocks (Min 200mm*)
Please re‐confirm the U‐values of wall, floor and roof elements to be used in the design.
Atkins Basis of design stated u = 0.2 for all but discussions in late 2016 indicated Thabat
had agreed with Typsa/CH2M to pursue a target of:
‐‐ Wall ‐ u = 0.5 for walls,
‐‐ Floor ‐ u = 1.825 ('Standard 90.1' values)
‐‐ Roof = 0.273 ('Standard 90.1' values)
In email of 11/10/2016 Atkins had confirmed the 'Transmittance 'u value' of various
Thermal resistance of walls 27/08/17
design standards as noted below. The values stated above are the final agreement
reached.
Please re‐confirm Thabat' s acceptance of Typical Architectural details drawing to be
Building Architectural details 27/08/17 implemented on all buildings on the Manfouha site. This was forwarded by Atkins to
Thabat on 25th August 2016 and agreed with Eng. George.
BUILDING FOUNDATION IN LAGOON AREA
Atkins ‐ RFI
RFI Title RFI Query Thabat Response From Date
Open/closed
Re confirm agreement reached with Eng George via email on 21st August 2016 that all
buildings within the lagoon are to be supported on columns and pad foundations in
Agreed structures foundation accordance with Atkins review forwarded to Thabt on 19/08/2017. This includes MCC2,
27/08/17
solution MCC3, Sludge and Blower. OBL may also be column and pad dependent on the final
design solution from Typsa.
SLUDGE BUILDING
Atkins ‐ RFI
RFI Title Date RFI Query Thabat Response Date
Open/closed
Please confirm that Atkins drawing review comments on the DRAFT Sludge building BD
General 27/08/17 layouts received on the 1st July 2017, forwarded by Eng Leddy will be implemented in the
re‐submission of the Basic Design by Typsa. These included:
‐‐ SPS structure – positioned butting up against external wall – would it be preferred
General 27/08/17
from construction perspective to move further south away from wall?
‐‐ Please confirm how Thabat would intend to construct the SMT overflow channel – is
General 27/08/17
it feasible?
‐‐ The sludge building is positioned within the existing lagoon excavated to rock level.
Atkins had previously reviewed and agreed that the foundation solution with Eng.
George and a column and pad type foundation was indicated as preference. We would
General 27/08/17
note that in the new arrangement where the step in levels between SLT across to MCC2
are more severe that a column and pad type foundation to rock level would seem most
appropriate to safeguard the structure. Please confirm acceptance.
Please confirm the weights and support conditions of all plant and equipment in the
General 27/08/17 building. The 10m spanning floor that has potentially heavy plant loading and monorail
may mean additional beam supports are required. This requires careful consideration.
PD2, STH and MCC2 all have different roof levels, from construction and design
General 27/08/17 perspective it makes sense to have single roof level of +576.28 ‐ Please confirm this
change will be implemented.
From drawings it appears the whole structure is to be constructed in Concrete – Please
General 27/08/17
confirm. Are AMC planning on rendering this finish?
Is MCC2 sizing and details confirmed? Are trenches etc needed as nothing is shown in
General 27/08/17 the drawings. It shares a wall and common foundation solution with the rest of the
structure so needs to be confirmed.
What is the building shown on the south of MCC2 on drawing 212‐100 there are no
General 27/08/17
details.
Can Typsa provide their 3D model of this so we can quickly determine requirements for
General 27/08/17
anti‐flotation. A thick base slab may be required to help resist uplift pressures.
With regard to building foundation we propose mass fill to rock (underneath SLT, Pump
General 27/08/17 room, SMT) – depending on rock level. And Column and pad arrangement to support
Higher level slabs.
FBL
Atkins ‐ RFI
RFI Title Date RFI Query Thabat Response From Date
Open/closed
Confirm STP‐BD‐FBL‐M‐170‐500‐Rev 03 received 15‐08‐2017 is Approved and Frozen and
Confirmation frozen design 27/08/17
to be used as basis for detailed design
Mechanical Drawing QRF 27/08/17 Received 15/08/2017
Typsa Structural/Architectural drawings ‐ current set are superseded as based on an old
Drawings awaited/required 27/08/17
Mechanical layout
27/08/17 Typsa 3D Model
Equipment info required 27/08/17 Penstocks ‐ load, fixing and rebate details
Disc filter
27/08/17 ‐ Unit weight (full) and surface bearing area (can not be found in submission document)
‐ Confirm inlet and out let pipe sizes level
27/08/17 GRP covers ‐ Confirm seating/rebate details
Openings 27/08/17 Confirmation of all structural wall/roof openings/sizes/location
Pipework 27/08/17 Confirmation of all wall penetrating pipework levels and pipe sizes
Electrical Penetrations 27/08/17 Electrical ducts ‐ Confirm location, size and level
RE‐confirm common raft foundation with UVC is accepted as noted in email from Eslam
Structural queries 27/08/17
on 20th June 2017.
BPS
Atkins ‐ RFI
RFI Title Date RFI Query Thabat Response From Date
Open/closed
Confirm STP‐BD‐FBL‐M‐170‐500‐Rev 03 received 15‐08‐2017 is Approved and Frozen and
Confirmation frozen design 27/08/17
to be used as basis for detailed design
Mechanical Drawing QRF 27/08/17 Received 15/08/2017
Typsa Structural/Architectural drawings ‐ current set are superseded as based on an old
Drawings awaited/required 27/08/17
Mechanical layout
27/08/17 Typsa 3D Model
Equipment info required 27/08/17 Pump weight and seating details
27/08/17 Crane details (height of rail, type, fixing details required and maximum design load
27/08/17 Manhole covers ‐ Confirm seating/rebate details
Openings 27/08/17 Confirmation of roof opening sizes and location
Pipework 27/08/17 Confirmation of all wall penetrating pipework levels and pipe sizes
Electrical Penetrations 27/08/17 Electrical ducts ‐ Confirm location, size and level
Benching details 27/08/17 Pump benching details required
Water levels 27/08/17 Maximum water level to be confirmed
Confirm STP‐BD‐UVC‐M‐180‐500‐Rev 02 & STP‐BD‐UVC‐M‐180‐501‐Rev 01 received 15‐
Confirmation frozen design 27/08/17
08‐2017 is Approved and Frozen and to be used as basis for detailed design
UVB
Atkins ‐ RFI
RFI Title Date RFI Query Thabat Response From Date
Open/closed
Confirm STP‐BD‐UVC‐M‐180‐500‐Rev 02 & STP‐BD‐UVC‐M‐180‐501‐Rev 01 received 15‐
Confirmation frozen design 27/08/17
08‐2017 is Approved and Frozen and to be used as basis for detailed design
BTA
Atkins ‐ RFI
RFI Title Date RFI Query Thabat Response From Date
Open/closed
Confirm STP‐BD‐BTA‐M‐160‐500‐Rev 03 received 10‐07‐2017 is Approved and Frozen and
Confirmation frozen design 27/08/17 Approved and frozen as a mechanical and guide drawings Eslam 30/08/2017 Open
to be used as basis for detailed design
Mechanical Drawing QRF 27/08/17 Provide copy of final closed QRF attached with the mail Eslam 30/08/2017 Open
Drawings awaited/required 27/08/17 Typsa Structural Drawings old set only available Eslam 30/08/2017 Open
27/08/17 Typsa 3D Model not available Eslam 30/08/2017 Open
Equipment info required 27/08/17 Pump weight and seating details TBC by Typsa mail ‐ Flygt pump data sheet uploaded to server Eslam 30/08/2017 Open
Please confirm how Thabat wish too construct complex geometry at inlet to pump risers.
Can nibs and chambers be removed and a steel insert used instead to greatly simplify
construction?
DCH
Atkins ‐ RFI
RFI Title Date RFI Query Thabat Response From Date
Open/closed
Confirm STP‐BD‐DCH‐M‐155‐500‐Rev 05 received 17‐07‐2017 is Approved and Frozen
Confirmation frozen design 27/08/17 Confirmed as approved frozen mechanical guide drawings Abdulmannan 06/09/2017 Closed
and to be used as basis for detailed design
Mechanical Drawing QRF 27/08/17 Provide copy of final closed QRF Uploaded on server Abdulmannan 06/09/2017 Closed
Drawings awaited/required 27/08/17 Typsa Structural Drawings old drawings only available Abdulmannan 06/09/2017 Open
27/08/17 Typsa 3D Model not available Abdulmannan 06/09/2017 Open
Equipment 27/08/17 Confirmation flowmeters are accepted by CH2M approved and accepted for the 5 flowmeters Abdulmannan 06/09/2017 Closed
27/08/17 Penstocks ‐ load, fixing and rebate details no rebate required ‐ penstock to be post fixed by bolts Abdulmannan 06/09/2017 Closed
Pipework 27/08/17 Confirmation of all wall penetrating pipework levels and pipe sizes confirmed Abdulmannan 06/09/2017 Closed
Electrical Penetrations 27/08/17 Electrical ducts ‐ Confirm location, size and level to be treated by site Abdulmannan 06/09/2017 Closed
Benching details 27/08/17 Benching details required to pipes As commented Abdulmannan 06/09/2017 Closed
as per agreed before in Rev.0 ‐ please amend drawings No. STP‐DD‐DCH‐S‐155‐
Construction preferences 27/08/17 Please confirm construction preferences for structure ‐ Pour sizes, joint location etc Abdulmannan 06/09/2017 Closed
199‐S‐0
SWL
Atkins ‐ RFI
RFI Title Date RFI Query Thabat Response From Date
Open/closed
Confirm STP‐BD‐UVC‐M‐180‐501‐Rev 01 received 30‐05‐2017 is Approved and Frozen and
Confirmation frozen design 27/08/17
to be used as basis for detailed design
Mechanical Drawing QRF 27/08/17 Provide copy of final closed QRF
Current mechanical drawings are of limited use much more detail is required to progress
Drawings awaited/required 27/08/17 design e.g. Internal dimensions, elevations, door sizes and location, windows, cable
penetrations, structural material (assumed to be concrete) etc.
27/08/17 Typsa Structural Drawings
27/08/17 Typsa Architectural Drawings
27/08/17 Typsa 3D Model
27/08/17 Building Services
Equipment info required 27/08/17 Pump weight and seating details
27/08/17 Manhole covers ‐ Confirm seating/rebate details
27/08/17 Crane details (height of rail, type, fixing details required and maximum design load
Position of stantion's for mono‐rail support – advantageous to locate these off perimeter
27/08/17
wall – will reduce loading on roof (Email Eng Leddy to Eng Salah 18/11/2016).
CCT
Atkins ‐ RFI
RFI Title Date RFI Query Thabat Response From Date
Open/closed
Current design issued based on STP‐BD‐CCT‐M‐200‐500‐Rev 04 received 30‐05‐2017 (and
confirmed as frozen by Thabat). Updated pipe sizes and sump sizes advised 3rd August.
Confirmation frozen design 27/08/17
Updated sump location received 7th August 2017. However layout needs to be updated
to capture sumps, relocation SWL and separation of UVC.
SGR
Atkins ‐ RFI
RFI Title Date RFI Query Thabat Response From Date
Open/closed
Provide updated STP‐SGR‐M‐130‐100‐Rev 03, STP‐BD‐SGR‐M‐130‐300‐Rev 03, STP‐BD‐
Frozen Drawings 27/08/17 SGR‐M‐130‐301‐Rev 03 received 31‐05‐2017 which although Coded 'B' contain open
CH2M comments and so revised set of drawings required.
Mechanical Drawing QRF 27/08/17 Provide copy of final closed QRF
Drawings awaited/required 27/08/17 Typsa Structural Drawings
27/08/17 Typsa 3D Model
Equipment info required 27/08/17 Grit & Grease removal bridge ‐ confirm of loading, mounting details
27/08/17 Penstocks ‐ load, fixing and rebate details
27/08/17 GRP covers ‐ Confirm seating/rebate/loading details
27/08/17 Confirmation flowmeters are accepted by CH2M
Openings 27/08/17 Confirmation of all structural wall openings sizes/location
Pipework 27/08/17 Confirmation of all wall penetrating pipework levels and pipe sizes
Electrical Penetrations 27/08/17 Electrical ducts ‐ Confirm location, size and level
Benching details 27/08/17 Channel benching details required
Structural queries 27/08/17 Confirm final cantilever walkway width (QRF comment)
Confirm interface with FSB ‐ a link structure with movement joints at each side is
27/08/17
required
27/08/17 Confirm final top of wall levels on finalisation of site drainage basic design
DPS
Atkins ‐ RFI
RFI Title Date RFI Query Thabat Response From Date
Open/closed
Confirm STP‐BD‐DPS‐M‐232‐500‐Rev 01 received 16‐07‐2017 is Approved and Frozen and
to be used as basis for detailed design. Email from Eslam indicated that QRF comments
Confirmation frozen design 27/08/17
were open including several items that may have affected layout. Confirmation drawing
frozen required
Mechanical Drawing QRF 27/08/17 Provide copy of final closed QRF
Drawings awaited/required 27/08/17 Typsa Structural Drawings
27/08/17 Typsa Architectural Drawings
27/08/17 Typsa 3D Model
Equipment info required 27/08/17 Pump weight (can not find this in brochure)
27/08/17 Manhole covers ‐ Confirm seating/rebate details
27/08/17 Crane details (height of rail, type, fixing details required and maximum design load
27/08/17 Crane details (height of rail, type, fixing details required and maximum design load
27/08/17 Confirmation flowmeters are accepted by CH2M
Pipework 27/08/17 Can the inlet from ICH to CSB be a piped connection?
Electrical Penetrations 27/08/17 Electrical ducts ‐ Confirm location, size and level
Confirmation manhole and penstock opening sizes and location in roof slab required ‐ no
Openings 27/08/17
dimensions on drawing
Thabat Construction methodology required.
‐ It is understood that Thabat wish to retain exiting Haer channel and make modifications
Structural queries 27/08/17 ‐ For sidewall it is noted that Thabat wish to locally cut hole in wall.
‐ Please confirm how Thabat intend to construct shaft on roof of existing Haer and break
out the existing roof.
27/08/17 Please provide as‐built details of Haer channel
Please confirm Thabat stated assumptions in email of 13/07/2017 is to form the basis for
27/08/17
the design:
27/08/17 ‐‐ Haer channel wall thicknesses to be assumed as 350mm
‐‐ Haer wall/roof reinforcement to be assumed as (min Area steel in accordance Eurocode
27/08/17
2)
‐‐ Design TWL in the Haer Channel 564.24m ~ 564.28m, but design should assume flowing
27/08/17
full for conservative
27/08/17 ‐‐ Haer Channel is cast‐in‐situ not pre‐cast building
Water Level 27/08/17 What is the maximum water level within the Haer Channel
Please confirm the outcome of discussions with suppliers regarding waterproofing the
Waterproofing Details 27/08/17 interface between the existing Haer channel and new inlet chamber ‐ Query raised to
Eng. Saad 18/01/2017
CHB
Atkins ‐ RFI
RFI Title Date RFI Query Thabat Response From Date
Open/closed
Architecture & Structural Drawings issued as part of TMT‐046 require update as per
27/08/17
recent mechanical drawing Rev 2. Please advise when this will be available
Please confirm a reinforced concrete bund 1500mm above base slab is required to form
27/08/17
lower part of the masonry building.
Architecture & Structural drawings show a steel truss. AMC preference is for a reinforced
27/08/17 concrete frame. Are removable roof panels required to allow for installation and removal
of the NaOCL tanks? Please provide drawing to indicate opening requirements.
Please confirm if a Vinyl ester floor coating is required as per previous correspondence
27/08/17 02/09/16. Recent correspondence from Daniel Martinez On 23/11/16 indicated no
coatings are required.
27/08/17 Will access be required to roof level externally?
Please confirm if the building has been space proofed to accommodate the steel
27/08/17
walkway. Please advise of walkway fixture details
Is the drainage channel rebated in the base slab to be an open channel for both the main
27/08/17
building and the pump room? What are the dimensions of the channel?
27/08/17 Please confirm drain line outlet size and levels from the Drainage pits
27/08/17 Will a fall be required in base slab to aid in drainage to channel?
27/08/17 Please confirm duct penetrations in/out of the main building and pump room
27/08/17 Please confirm ventilation fan openings and elevations
27/08/17 Please confirm vent pipe size and roof opening requirements
27/08/17 Does the main building and the pump room require insulation wall makeup?
Finished floor level to be confirmed depending on site levels. Please advise when will this
27/08/17
be available
Please confirm chamber size shown to house pipework to the CCT
27/08/17
MCC GENERAL
Atkins ‐ RFI
RFI Title Date RFI Query Thabat Response From Date
Open/closed
Please advise of Thabat preference for MCC building construction.
It seems that Typsa design is requiring substantial and complicated cable trench details
that will lead to an issue in waterproofing, constrictions and potentially require larger
volumes of concrete.
Cable Trench structure 27/08/17
Historically we have simplified this to a ‘cable basement’ with open mesh flooring to the
building.
Can you review the attached and advise? If will have implications for the foundation
proposal.
Can you please provide static and dynamic loading information of current selected
supplier to be considered at this time to assist in the modelling exercise.
E.g.
Equipment Loading 27/08/17 o HVAC equipment on roof
o Transformers
o Control Panels in control room
o Any other plant
BBL
Atkins ‐ RFI
RFI Title Date RFI Query Thabat Response Date
Open/closed
Confirmation frozen design 27/08/17 Please provide frozen BD design drawings for review
Mechanical Drawing QRF 27/08/17 Please provide copy of final closed QRF
Drawings awaited/required 27/08/17 Typsa Mechanical Drawings
27/08/17 Typsa Structural Drawings
27/08/17 Typsa Architectural Drawings
27/08/17 Typsa 3D Model
Can you please provide static and dynamic loading information for all building
equipment:
Blower Building
o Blower & Silencer
Equipment info required 27/08/17
o Oil cooler and exhaust fan on roof
o Control Panels in control room
o Crane capacities and loads
o HVAC equipment on roof
o Any other plant
Pipework 27/08/17 Confirmation of all wall penetrating pipework levels and pipe sizes
Electrical Penetrations 27/08/17 Electrical ducts ‐ Confirm location, size and level
Openings 27/08/17 Confirmation all opening sizes and location in roof slab required
Please confirm column and pad foundation solution to be applied to building as per
Structural queries 27/08/17
instruction from Eng Hani 15th November 2016
Please ensure building is space proofed with sufficient height to accommodate gantry
27/08/17 crane and lifting requirements (incl acoustic housing) within the building. Historically the
building was too low and had to be raised by several metres
OBL
Atkins ‐ RFI
RFI Title Date RFI Query Thabat Response From Date
Open/closed
Confirmation frozen design 27/08/17 Please provide frozen BD design drawings for review
Mechanical Drawing QRF 27/08/17 Please provide copy of final closed QRF
Drawings awaited/required 27/08/17 Typsa Mechanical Drawings
27/08/17 Typsa Structural Drawings
27/08/17 Typsa Architectural Drawings
27/08/17 Typsa 3D Model
SLD
Atkins ‐ RFI
RFI Title Date RFI Query Thabat Response From Date
Open/closed
Confirmation frozen design 27/08/17 Please provide frozen BD design drawings for review
Mechanical Drawing QRF 27/08/17 Please provide copy of final closed QRF
Drawings awaited/required 27/08/17 Typsa Mechanical Drawings
27/08/17 Typsa Structural Drawings
27/08/17 Typsa Architectural Drawings
27/08/17 Typsa 3D Model
Can you please provide static and dynamic loading information for all building equipment
E.G.
1. Sludge Tank & Odour Control Facility
o Scrubber
o Centrifuge Fan
o Carbon Filters
o Crane capacities and loads
2. Sludge Dewatering & thickener
o Sludge Thickeners Drums – information provided previously as per email attached,
Equipment info required 27/08/17
please confirm these values are still valid
o Polymer Dosing units
o Decanter Centrifuge – information provided previously as per email attached, please
confirm these values are still valid
o Sodium Hydroxide Tanks
o Vehicle access on ground floor
3. Sludge Silo Building
o Silos capacity and self‐weight
o Any other equipment
APPENDIX F
PROJECT Doc Ref/Rev: STP-RP-02-G-CSA-102 Rev 0
HEALTH & SAFETY DESIGN RISK REGISTER Issue Date: 01/07/2016
Project: Manfouha Sewage Treatment Plant Fourth Stream Package or Element: Civil, Structural, Architectural & Geotechnical Reviewed By: KR
Project/Design Phase: Detailed Design Prepared by: RF Authorised By: SW
construction, using (as a workplace), Design Significant remaining risks Design doc Cross Reference
operation & maintenance, alteration & Measures Taken by Designer - Hazard Elimination, Risk Risk Suggested work methods/sequences Needed H&S File Detailed ref to Doc or Drg
Activity demolition of a 'structure' Stage Affected Reduction and Control Owner By When Other controls by who Risk Register containing the information
Working in vicinity Can't be eliminated due to hydraulic design dictating the Contractor to erect and set back temporary
of an embankment Risk of personnel injury, plant or debris fall need to construct structures in deep excavations. Detailed safety fencing or edge protection where To be added to appropriate
Construction Y AMC AMC B
edge - Baatha off edge of embankment Site works adjacent to to Baatha Channel to be limited to design required. drawings when developed
Channel outfall pipe only. Associated chamber to be moved inland. Strict vehicular speed limit to be imposed.
5
construction, using (as a workplace), Design Significant remaining risks Design doc Cross Reference
operation & maintenance, alteration & Measures Taken by Designer - Hazard Elimination, Risk Risk Suggested work methods/sequences Needed H&S File Detailed ref to Doc or Drg
Activity demolition of a 'structure' Stage Affected Reduction and Control Owner By When Other controls by who Risk Register containing the information
10
construction, using (as a workplace), Design Significant remaining risks Design doc Cross Reference
operation & maintenance, alteration & Measures Taken by Designer - Hazard Elimination, Risk Risk Suggested work methods/sequences Needed H&S File Detailed ref to Doc or Drg
Activity demolition of a 'structure' Stage Affected Reduction and Control Owner By When Other controls by who Risk Register containing the information
Lead designer to mount equipment at ground level Staff to use appropriate protective equipment
Equipment calibration and maintenance - Fall
wherever possible and applicable. Detailed when work at height cannot be avoided by
Working at height from height during routine instrument Operation & Maintenance N Typsa AMC R -
Ensure that suitable guards and handrails are provided design design. Contractor to adopt permit to
maintenance activities
Ensure maintenance requirements are advised to Client work/enter protocol
25
construction, using (as a workplace), Design Significant remaining risks Design doc Cross Reference
operation & maintenance, alteration & Measures Taken by Designer - Hazard Elimination, Risk Risk Suggested work methods/sequences Needed H&S File Detailed ref to Doc or Drg
Activity demolition of a 'structure' Stage Affected Reduction and Control Owner By When Other controls by who Risk Register containing the information
Confined space, hazard from incorrect Access points for Pipelines and cleaning arrangements to Detailed
Pipeline swabbing Operation & Maintenance N Atkins Contractor to follow defined procedures. AMC F -
opening of valves - Suffocation or Drowning be designed to allow safe maintenance. design
27
Design to minimise requirement for internal maintenance Monitor for any explosive atmosphere.
with man - access. Implement safe working procedures in
To be added to appropriate
Oxygen depletion or poisonous gases inside Use of extended valve spindles to enable operation from a Detailed confined spaces including gas monitoring,
Confined Spaces Operation & Maintenance Y Typsa AMC B drawings when developed e.g.
tanks safe position design rescue arrangements.
sludge tank
Provide adequate openings for ventilation and access Ensure all personnel are inducted and briefed
suitable for rescue of injured personnel. on safe working methods
28
Lead designer to establish safe systems to allow Ensure procedures are detailed in H&S File
Isolation of pipe Detailed
Danger to personnel, danger of flooding Operation & Maintenance N appropriate lengths of pipeline to be isolated for Typsa and O&M Manual, and personnel are trained AMC F -
sections design
maintenance, duplication of supply routes. to implement these.
30
Heavy Construction Personnel Injury, crushing, failure of Design to consider appropriate plant contractor wishes to Detailed Contractor to ensure only approved plant and SBR 1 Foundation Pack
Construction Y Atkins AMC B
Loads structures use in construction design machinery are used SBR 2 Foundation Pack
34