Professional Documents
Culture Documents
03-04-2021 - JOB - 521 - GG - STR - DETRITOR MECHANISM - FINAL-Model
03-04-2021 - JOB - 521 - GG - STR - DETRITOR MECHANISM - FINAL-Model
PROPELLER
E
106.00
B.O.T 105.80
107.00
105.46 ORGANIC RETURN
PE
SL
MECHANISM TANK
C/L OF
O
ORM
SL
PE
107.00 105.05 INLET-100NB
800x700 OPENING 105.05
(BY CONTRACTOR)
ON FLOOR SLAB
C/L OF
PCC FILLING TO BE DONE AFTER CLASSIFIER
PCC FILLING TO BE DONE 100NB DRAIN NOZZLE WITH
SCREW INSTALLATION
AFTER SCREW INSTALLATION
SECTION D-D 100NB DRAIN NOZZLE WITH
BLIND FLANGE(BY CONTRACTOR)
SCOOP
BOX
T.O.T
107.00
BLIND FLANGE (BY CONTRACTOR)
SECTION F-F
BLADE
OVERLOAD
PROTECTION
DETAIL - K
ASSEMBLY
DEFLECTOR PIPE
TIE
107.00 ANGLE
REF, TANK-1 REF, TOT 107.00
DETAIL-M DRIVE
DETAIL-S HEAD (TO SUIT 32NB PIPE SLEEVE
CHAIN WITH STOPPER PLATE)
FEED GUARD DEFLECTOR PIPE TWL
B.O.T
DEFLECTOR SLEEVE (UPPER) 106.70
105.80
MS-FRP
RAKE DEFLECTOR
MACHINE
106.25 ARM
C/L OF
SL
PE ORGANIC RETURN MECHANISM (TO SUIT 60 SQ BOTTOM PLATE
O
LO INLET AND OUTLET INTERCONNECTION WITH 32 NB PIPE SLEEVE)
PE
S
PIPE(BY CONTRACTOR) 106.25
DEFLECTOR PIPE
OUTLET SLEEVE (LOWER)
ISOMETRIC VIEW OF SCREW AND ORM CHAMBER
PE SECTIONAL VIEW OF M-M
SL
S
[TYPICAL REPRESENTATION VIEW SHOWN, ACTUAL VIEW DIFFERS] BOT
T.O.T 105.80
INLET 107.00
BRIDGE(BY CLIENT)
RCC WALKWAY
C/L OF
SCOOP GEARED MOTOR
BOX
106.25
OVERLOAD SECTION X-X
BLADE PROTECTION
ASSEMBLY
60SQ THROUGH C/L OF
ANCHOR POCKETS TANK
FEED TIE 4 NOS
DEFLECTOR ANGLE
TANK-2 DRIVE
HEAD
C/L OF CUT OUT
MACHINE
B.O.T
107.00 105.80
SECTIONAL VIEW OF L-L D/H BASE FRAME FOUNDATION HOLES
SECTION Y-Y
HAND RAIL
RAKE [TYPICAL REPRESENTATION VIEW SHOWN,ACTUAL VIEW DIFFERS] (BY CONTRACTOR)
800x700 OPENING ARM RCC BRIDGE DETAIL - S
(BY CONTRACTOR)
ON FLOOR SLAB
T.O.T 107.00
SL
PE
CLIENT:
O
O
PE
SL T.W.L 106.70
VERTICAL GREATER WARANGAL SMART CITY CORPORATION LIMITED
SHAFT
106.25 PROJECT:
B.O.T 105.80
15 MLD STP AT PRAGATHI NAGAR, GWMC
SCREW DISCHARGE
CONTRACTOR:
50 THK SCREED (TO BE CARRIED OUT
POINT
107.00
AFTER INSTALLATION OF MECHANISM) GAJA ENGINEERING, CHENNAI
SECTION R-R
470 No. REVISIONS DATE BY
RCC CLASSIFIER
450
CHANNEL TITLE
GA DRAWING OF
230
PCC FILLING TO BE
DONE AFTER STATIC LOAD = ~850 KG
DETRITOR MECHANISM
INSTALLATION OF SCREW DYNAMIC LOAD = ~1020 KG
6.0 M SQ x 0.9 M SWD + 0.3 M FB
SECTION E-E C/L OF
MACHINE
NOTE: DRIVE ORDER NO DRAWING NO.
ORGANIC HEAD RCC BRIDGE
RETURN MECHANISM & HAND RAIL
- ALL DIMENSIONS ARE IN MM,LEVELS ARE IN M.(UNLESS OTHERWISE SPECIFIED). (BY CONTRACTOR)
107.00
T.O.T
SP-2076
- SUPPLY SCOPE : COLLECTION MECHANISM WITH DRIVE & OVERLOAD PROTECTION 106.70
C/L OF SCREW
TIE T.W.L
WITH DRIVE ASSEMBLY, FEED DEFLECTOR, WEIR PLATE, & ASSY HARDWARE. 106.25 ROD
- ALL MILD STEEL PARTS SHALL BE SAND BLASTED SA 2.5 WITH 2 COATS OF EPOXY PRIMER,
105.80
1 COAT OF MIO AND 2 COATS OF FINISH EPOXY PAINT WITH TOTAL DFT 150 MICRON. B.O.T
105.46
REF,
- QTY : 2 NOS. PCC FILLING TO BE DETAIL-T
105.05 DONE AFTER SCREW
This document is the property and the work of SHIVPAD ENGINEERS PVT LTD, Must be returned
INSTALLATION
SECTION C-C on demand Any use detrimental to the interest of SHIVPAD ENGINEERS PVT LTD, is prohibited.