Lifting Plan

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 5

Lifting Plan

Date &Time 04-04-2022 Location Substation Boundary wall Wind Speed Permit No:

Crane (s) Detail: (1) Crane 200 ton Reg# 30255, (2) Crane 100 ton Reg# 53304

Crane No 1 Crane No 2
Crawler crane Truck moun ted crane Crawler crane Truck mounted crane
All terrain wheel crane Another crane type All terrain wheel crane Another crane type

Crane 1 – 200 ton (


S. No Description Unit Value
A Main Boom Length Meters 32.1
R1 Radius (R1) Meters 14
R2 Radius (R2) Meters 12
B Counterweight Kg N/A
C Hook Block Weight Kg 950
D Load to be Lifted Kg 15800
E Total Load (Accessories + Hook Kg 17730
Block Weight + Load to be Lifted) –
(980 + 950+15800)
F Load Chart Capacity Kg 25000
% Capacity of Crane 70.9%
(Total Load (E) *100)/Load Chart
Capacity (F)

Description of Work:

Installation boundary wall precast panel

Page 1 of 4
Lifting Plan

Crane 2 – 100 ton


S. No Description Unit Value
A Main Boom Length Mete 30.9
R1 Radius (R1) rs 09
Mete
R2 Radius (R2) rs 09
Mete
B Counterweight rs N/A
Kg
C Hook Block Weight Kg 950
D Load to be Lifted Kg 15800
E Total Load (Accessories + Hook Kg 17730
Block Weight + Load to be Lifted)
(980 + 950+15800)
F Load Chart Capacity Kg 24500
% Capacity of Crane 72%
(Total Load (E) *100)/Load Chart
Capacity (F)

Description of Work:

Installation boundary wall precast panel

Page 1 of 4
Lifting Plan

List of Lifting Gears Required (Following Calculation Note)


Lifting Gears Type Quantity Dimension Capacity (SWL) Weight
Chain sling 2 Adjustable 30.0 T
Snatch block 4 335 mm 22 T
980 KG
Wire rope 4 8 mtr 11.8 ton
Ring Clutch 8 10 ton

Rigging Sketch (Load, Sling, Chains)


(If additional drawings are required. Attached to document & itemize for reference-use graph paper if required)

Attached

Ground Type:
Clay Silt Sand Gravel Loam Others

Page 2 of 4
Lifting Plan

Proximity Hazards
Overhead Obstacles/Power Lines Underground Services Excavations
Yes No Yes No Yes No

Recently Excavated Ground Adjacent Lifting Operations Live Plant


Yes No Yes No Yes No

Site Facilities & Obstructions Roads Others


Yes No Yes No Yes No

Mitigation Measures:

Weather forecast
Wind Speed: km/h or ( miles/h)

Special care must be taken with these conditions

Preventive measures:
Preventive measures will be taken before lifting work starts

Page 3 of 4
Lifting Plan

Communication Means
Hand Signals Radios Both Others

Task Briefing and Attendance Record to be attached


The detail of this plan and applicable job safety have been brought to the attention of the persons listed in attendance sheet, who have
acknowledged that they understand their roles, responsibilities, and procedure of the lifting operation

Approved by: Planned by (Lifting Supervisor):


Name: Position Name: Position

Company: Date/Time: Company: Date/Time:

Signature:
Operator Name: Signature:

Rigger Name: Signature

Banks Man Name: Signature

Page 4 of 4

You might also like