Professional Documents
Culture Documents
LBYIE3D - Term Project Northwest Northprint
LBYIE3D - Term Project Northwest Northprint
In partial fulfillment
of the course
in LBYIE3D
Submitted by:
Junsay, Kimberly
and
Rodas, Giannina
Submitted to:
Ms. Jayne Lois San Juan
Seattle 40,727
Chicago 55,608
Dallas 92,680
Denver 23,832
Vancouver 32,581
Calgary 8,145
Duchesne 212,062
Since Northwest Newsprint produces and distributes newsprints to their customers, there
are a variety of costs incurred in the process. The production cost is one of them, as the cost per
unit for this is shown in Table 4. Next, since the company also distributes the newsprints,
transportation costs are also incurred which is displayed in Table 5. Lastly, the revenue for each
tonne of newsprint is dependent on the location of the distribution centers. Those that are located
in the U.S. have higher selling prices compared to those that reside in Canada. They have a $50
difference because the newsprints are sold for $750 per tonne in the U.S. while in the latter
country it is only $700. This is shown in Table 6.
Table 4. Production Cost
Table 6. Revenue
Lastly, the company also planned the desired tonnes of newsprints to be distributed to
each distribution center. Table 7 shows the predetermined values for this case with the total units
per mill are shown.
Table 7. Planned Distribution
Distribution Centers\Production Spruce Mills Naomee Mills Duchesne Total
Plants
II. Objectives
● Maximize profit for each transportation route
● Optimize the production of tonnes of newsprint
● Meet the demands of the distribution centers
Z = Profit
Maximize Z
Figure 2. Decision Variables
The decision variables for the model are depicted in Figure 2 which is denoted by x with
two sets, i and j. Moreover, the mills that produce newsprint were assigned to set i while the
distribution centers were assigned to set j. Variable x was set to be the tonnes of newsprint
produced and delivered from mill i to distribution center j. Lastly, since the objective of the
problem is to maximize cost, it was assigned to the variable Z.
Production Capacity
𝑥1𝑗 ≤ 166, 320 (Spruce Mills)
𝑥2𝑗 ≤ 272, 340 (Naomee Mills)
𝑥3𝑗 ≤ 265, 077 (Duchesne)
Operation Level
𝑥1𝑗 ≥ 133, 056 (Spruce Mills)
𝑥2𝑗 ≥ 217, 340 (Naomee Mills)
𝑥3𝑗 ≥ 212, 062 (Duchesne)
Figure 3. Constraints
Next, the constraints of the model are shown in Figure 3 where the production capacity,
operation level, and initially planned units for each distribution center are formulated. The values
of the constraints of the production capacity are based on Table 1 while the operation level is
based on Table 3. Lastly, the planned units for each distribution center were referenced from
Table 7 which was provided by the company.
Present System
Profit $121,537,867.15
Table 9. Shows the values of the production and profit using the planned distribution.
However, the company would like to see if this can be further improved. And thus, the new
model was set to maximize the profit by optimizing the allocation of x.
Naomee - Duchesne -
Spruce - Chicago . . 55608
Chicago Chicago
Spruce - Dallas 92680 Naomee - Dallas . Duchesne - Dallas .
Naomee -
Spruce - Denver . . Duchesne - Denver 23832
Denver
Naomee - Duchesne -
Spruce - Vancouver . . 32581
Vancouver Vancouver
Naomee -
Spruce - Calgary . 8145 Duchesne - Calgary .
Calgary
This allocation will be able to further increase the profit, generating $ 125,500,604.03 of
profit, $3,962,736.88 more than the previous allocation which is equivalent to 1.6%. Pushing the
Spruce Mill to shoulder more of the demand (7%) will allow the company to profit more
efficiently.
Table 11. Summary of Values After Optimization
A B C D E F G H I
This freight rate discount scheme will yield a profit of $129,896,304.78, or 3.32% more
when compared against the present system. However, the allocation of shipments was not
optimized in the present system. Hence, the Freight Rate Discount Model was compared against
the Optimized system to see how much more the company can profit off, by applying the
discounted rates as they use the same allocation distribution. The Freight Rate Discount scheme
generated 1.72% or $ 4,395,700.75 more profit once applied to the optimized system. Hence, the
company should apply the freight rate discount scheme to maximize profit.
Table 13. Comparison of Freight Rate Discount Profit Against Present and Optimized System
Table 14 shows that reducing a 58,000 tonnes/yr machine in Naomee will shift the
demand to Duchesne as the allocation of Naomee-LA decreased from 111800 to 93468.
Similarly, Duchesne-LA increased from 100041 to 118373.
Table 15. Summary of Changes in 58k Reduction Model Against Present and Optimized System
Table 15 shows that converting a 58,000 tonne/yr machine into groundwood specialties.
Comparing it against the present system, it only yields a 1.58% profit increase, which is less than
the profit increase from the optimized allocation which is at 3.32%, as seen from Table 11.
Again, comparing the 58K Reduction Model against the Optimized System, it can be seen that
the 58K Reduction yields less profit.
LA 234213 173401
Testing the optimized model (after optimization) against the optimistic and pessimistic
demand, the results of the model show that the pessimistic demand yielded an infeasible solution.
The optimistic demand on the other hand was able to yield 6.27% more profit as opposed to the
present system (Table 17). However, this optimistic scenario may not be a good basis as the
demand fluctuates and does not reflect the reality of the expected demand.
V. Conclusion
Table 18. Summary of Results
VI. Appendix
Appendix A. Present System
Appendix B. After Optimization
Appendix C. Freight Rate Discount
Appendix D. 58K Discount
Appendix E. Optimistic
Appendix F. Pessimistic