Professional Documents
Culture Documents
HYDRO 2019 Curnis-Bronzetti-Sayah Paper
HYDRO 2019 Curnis-Bronzetti-Sayah Paper
Introduction
At the Hydro 2017 Conference in Seville a detailed presentation about the realization of steel penstocks with Hot
Banded Pipe (HBP) technology for high head hydropower plants was exposed. In that paper the benefits of the HBP-
technology were illustrated in comparison with the use of Very High Tensile Strength Steel (VHTSS), providing the
basic knowledge of this particular design method.
The purpose of the present paper is to provide further practical applications examples of HBP-technology for steel
penstocks and steel linings in high head hydropower plants and pumped storage plants, including a comparison with
VHTSS solution. The document illustrates design aspects, analysis of some topics related to erection, construction
schedule, as well as cost-benefits analysis.
The analysis covers the realisation of hydropower plants / pumped storage plants with same configuration, subject to
static head of up to 850 mwc, having steel lined or steel pipes waterway made of different diameters, relevant to
different installed capacities . The realization of the high-pressure portion (HP) it is investigated adopting, for the
steel waterway, different solutions of steel qualities. The same analysis is performed with the HBP solution. The
results are finally compared in terms of erection time duration as well as prefabrication and erection costs.
Fig. 2. Mechanical behaviour resulting from a finite element analysis (FEA) assuming a HBP penstock/steel lining with inner
diameter D=3’600 mm, pipe thickness t=20 mm, number of hoops n= 14 equal-spaced over a pipe length L = 4’000mm
Tab. 1. Some references of projects realized with hot banded pipes still operating nowadays
The previous table shows some references of projects realized with HBP-technology, which are still operating
nowadays. Another reference could be the hydropower plant of Chandoline (Switzerland) which was first put into
service in 1934 and put out of service in 2013 on grounds of energy efficiency and production optimisation. The
plant had a gross head of 1’750 mwc with two HBP-penstocks DN 2100, which were still available for operation.
During their exploitation no problems were reported for HBP-plants up to nowadays and only normal works for
maintenance purpose were performed during their life. References of existing HBP-plants shows that the expected
life duration exceeds 80 years, thus confirming the safety of the adopted HBP-technology.
Fig. 3. Pumped storage plant Edolo (Italy) with two parallel HBP penstocks DN 3700 mm, static head of 1’300 mwc and
1’100 MW installed power
2. Design basics
For the scope of the analysis presented in the present paper, the design of the steel waterway is performed according
to ASCE Manuals and Reports on Engineering Practice No. 79. This code is worldwide recognized and represents a
valid and safe design method to assure a long lifespan to hydropower plants.
Main assumptions made for the calculation in the present paper:
- Stress theory:
The maximum stress theory (Tresca criterion) is adopted.
- Design membrane allowable stress (S):
The design membrane allowable stress (S) is obtained by the minimum value applying different safety factors to
the tensile strength (TS) and to the yield strength (YP) of the material selected for the realization of the
waterway:
S = min (TS/2.4; YP/1.5)
Fig. 4. Example of a 3D-FEA-modelling for an HBP Penstock of an existing Plant in operation, with diameter DN 3600 mm, pipe
shell thickness t = 20 mm and static head of 800 mwc
For information, following table shows a comparison of safety factors with other international codes of
calculation.
Tab. 2. Comparison of safety factors for the design allowable stress for penstocks and steel linings
Tab. 3. Example of allowable stresses (S) according to ASCE Guides No. 79 for different steel qualities
Joint category Joint type Non-destructive testing
100% UT/RT Spot RT
Penstocks – Steel linings
Double-welded butt joints 1.00 0.85
Longitudinal, circumferential and Single welded butt joints with
0.90 0.80
spiral (helical) butt welds backing strips
Single-welded butt joint without
Not allowed Not allowed
backing strips
Bifurcations
Longitudinal and circumferential
butt joints in shell plates. Double-welded butt joints 0.85 0.70
Sickle plate splices butt welds.
Tab. 4. Example of weld joint reduction factors (E) according to ASCE Manuals and Reports No. 79
Tab. 5. Critical path lengths resulting for steel lining and penstock solution
Fig. 7. Steel lining weld seam with backing strip (left: perfect match; right: with possible mismatches)
- The assumed deposit weld rates are result from experiences gained during the realization of many hydropower
projects. Usually, deposit weld rate for penstocks are on average 20% higher than for steel linings.
- The number of site joints increases with the length of the high-pressure section. Consequently, to minimize the
site duration, simultaneous weld activities on different joints are necessary. In penstock projects, the possibility to
operate simultaneously on more joints is usually not a problem from the point of view of the planner. It is much
more depending on the anchor blocks configuration and their location. To the contrary, for steel linings great
concerns exist because the operations are performed in tunnels with extremely reduced working space. Therefore,
worldwide safety rules impose a carefully exhaustive safety risk analysis to include the transport of emergency
material and the evacuation of personnel in case of accident. For the scope of the following analysis a maximum
of two joints performed simultaneously are considered.
- The normal site work duration of a shift is height (8) hrs. Since this time includes transfer to and from working
point as well as rest and lunch period, an average net working time spent on production of maximum six (6) hrs is
considered.
4. Penstock analysis
4.1 Site erection critical path analysis
The following tables show an example of typical cycle activities calculated for a DN 3100 mm exposed penstock.
The critical path cycle for the erection of the penstock are analysed for the three different steel qualities solutions.
The duration is presented for two options with two (2) or three (3) joints executed simultaneously.
According to experiences on realized projects, operations on two (2) joints simultaneously is quite a normal solution
and it involves twelve (12) experienced welders per day. In the case of three (3) joints, seldom adopted solution,
eighteen (18) qualified welders per day would be necessary to be involved, quite a large quantity indeed.
In the case of exposed penstocks various crews operating simultaneously does not constitute a hazard in terms of
safety. Of course, planners have to consider the inefficiency of welding teams, being on hold when other activities
are performed on the joints, thus increasing considerably the erection costs.
Tab. 8. Critical path erection duration calculated for an exposed penstock DN 3100 mm for steel type S690
Tab. 9. Critical path erection duration calculated for an exposed penstock DN 3100 mm for steel type S500
Tab. 10. Critical path erection duration calculated for an exposed penstock DN 3100 mm for HBP solution
Tab. 14. Average thicknesses calculated for penstock and steel lining solution
Fig. 8. Dimensionless comparison diagrams for penstock profile for the different investigated solutions
5. Steel lining analysis
The same methodology, as per the penstock profile (presented in chapter 4), is adopted for the steel lining profile.
The following tables show the results of the analysis of a DN 2100 mm steel lining waterway.
Tab. 17. Total estimation costs calculated for a steel lining DN 2100 mm, steel type S500, S690 and HBP solution
Tab. 18. Summary of the results of all the analysis performed for a steel lining profile with steel type S690, S500 and HBP
solution for pipe diameters DN 2100/2600/3100/3600 mm
In order to obtain the minimum site duration, the analysis has been conducted assuming to perform activities in the
tunnel simultaneously on two (2) joints over twenty-four (24) hours per day, organized on three (3) shifts, six (6)
days a week.
The performed analysis indicates that solutions with S500 above DN 2600 mm and solutions with S690 above
DN 3100 mm become unacceptable since extraordinary long duration for the site erection result. The reason for this
is that in some portion of the waterway the weight limit imposed (30 tons) is exceeded due to the DN and the
thickness. Consequently, sections of shorter length, say six (6) meters, have to be considered, thus increasing the
critical erection time.
For similar cases, the project planner could foresee an intermediate access window to split the critical path length in
two sections, in order to reduce the critical path time to an acceptable value.
Fig. 9. Dimensionless comparison diagrams for steel lining profile for the different investigated solutions
The results from the comparison diagrams, over the steel waterway diameter considered, are quite impressive: the
ratio of steel qualities S690 and S500 vs. HBP-solution for the various considered parameters results:
- Pipe shell thickness ratio: ranges from 1.4 to 2.5 for S690 and 2.2 to 3.6 for S500.
- Averaged ratio of single erection cycle duration: about 1.5 for S690 and 2 for S500.
- Averaged ratio of total costs for the realization: about 1.3 for S690 and 1.8 for S500.
- Averaged ratio of total site duration: about 1.6 for S690 and 2.7 for S500, it takes consideration of the
quantity of site joints to be realized.
The capacity of confined cylinders (i.e. penstocks and steel linings) to resist to external pressure has been largely
discussed by engineers in the past. The maximum allowable external pressure (Pall) was originally calculated
dividing the critical external buckling pressure (Pcr) by an appropriate safety factor (typically 1.5) according to
Amstutz (1970) and Jacobsen (1974) formulations. However, these approaches are based on elastic theory and lead
to too conservative results, with the risk to overestimate the weights of the steel waterway.
Extensive analysis by Karamanos and Vasilikis (2014), published by ASME Transaction, provide a valid instrument
for the evaluation of the critical external buckling pressure, Pcr = Py, which cause the full yield of the section (plastic
hinge formation) at the ultimate collapse state. Pipes have normally initial imperfections, for instance out of
roundness and consequently initial gap with the surrounding hosting cylinder (grouted tunnel), which create the
collapse. The out of roundness plays the most important role in the determination of the critical eternal pressure as its
value drastically reduce Pcr.
In the case of hot banded pipes (HBP), the application of external hoops creates an almost perfect round shaped pipe
without ovality, thus maximizing the critical external buckling pressure (Pcr). By numerical verification (FEA)
correlation and sensitivity analysis, ASME Transaction defines the maximum external pressure: Pmax = alfa*Pcr,
being the correlation factor alfa in function of the imperfections.
Following table shows the results for the application of the investigated cases of the HBP-research to the pipe shell,
assuming a very little imperfection out of roundness.
Tab. 19. Resulting maximum external pressures for buckling instability for HBP-solution calculated with Karamanos and
Vasilikis approach (2014)
Inputs data:
- Installed power: 330 MW
- Static head, Pst: 650 mwc
- Dynamic design head, Pdyn: 860 mwc
- Steel waterway diameter HP portion: 3600 mm
- Steel waterway length: 800 m
- Project-lifespan: 90 years
- Project number of changes of modes, over lifespan at full load: 140’000
- Operational daily modes: N°6 changes, T/P/T, per day
- Design cycles: 3’000’000
Results from Wöhler curves:
The delta allowable stresses for the design fatigue limit of 3’000’000 cycles result from the fatigue Wöhler curves
(time vs. delta fatigue stress):
- Steel lining:
o Circumferential site joint is critical, ref. curve FAT #71, welded one side with backing strip.
→ Delta stress limit equal to about 60 MPa
- Penstock:
o All joints are critical, ref. curve FAT #112, welded both sides.
→ Delta stress limit equal to about 100 MPa
Fig. 10. Wöhler curves for the joint types considered in the different investigated solutions
- The results of investigation on steel lining show that, in the case of HBP-solution, the thickness resulting by the
static design (from FEA calculation) does meet the requirement of the designed fatigue lifetime.
In the case of penstock the fatigue becomes almost unlimited. It means that in this case the fatigue is not an issue
at all.
- The above-mentioned behaviour has also been verified recently by the Materials Innovation Institute (M2i)-Delft
in Netherlands (Pijpers, 2011), in the course of an extended fatigue tests of welded connections made of very
high strength cast and rolled steels. This research has performed laboratory fatigue tests to assess the resistance of
welded joints made of steel qualities S355-S4690 and S690, with different bevel configuration, and someone with
permanent backing strip. The results have shown that steel S355-S460, for the same amplitude of stress fatigue,
cycles were higher and met the expectation.
Tab. 21. Rain-flow analysis and fatigue verification for steel lining and penstock with HBP-solution
Conclusions
- The results obtained by the research confirms that the adoption of HBP-technology is ideal for steel waterway
diameters above DN 2000 mm and static heads above 400 mwc. By the increase of the diameter the benefits of
HBP becomes very important and large savings in site works duration and total costs are determined. HBP
equivalent shell thickness results as much as about the half of the solution with steel S690 and even more for
S500.
- Even though the research has investigated waterways with diameters from DN 2100 mm to DN 3600 mm and
static heads up to 850 mwc, projects realized with HBP-technology cover ranges from DN 1900 mm to DN 4000
mm and static heads up to 1800 mwc.
- For projects where the steel waterway represents the critical path for the realization of hydropower plant,
the HBP solution introduces a further benefit due the shorter site works duration and earlier completion of
the Plant..
- For pumped storage plants (PSP), the daily operational cycle changes of mode of the plant, turbine
/pump/turbine (T/P/T), originates transient pressures in the waterway, which induce fatigue situation in the
welded joints. Therefore, constraints to the mechanical design are originated. Thickness of the waterway is
impacted and increase in the range of 10-18 % may be expected for steel linings, depending on the total
lifespan cycles. Plants are actually designed on the base of 80/90 years of lifespan, consequently 150.000
changes of cycles-modes are an average, creating a significant amount of fluctuation of pressure events,
might then be above 3’000’000.
- HBP solution demonstrates an ideal resistance to fatigue above 3’000’000 cycles and for the case of an
exposed penstock it becomes almost unlimited.
- Regarding the risk-safety analysis it has to be noticed, that dealing with VHTSS- S690 materials, situations
of undetected cold cracks lefts in weldment are very high expected. Steel linings waterways are the riskiest
in the case the site joints are realized with permanent backing strip, which is almost the normal case, as the
inspection of the root zone is very doubtfully due to the presence of the permanent support. In this zone we
really cannot assess the true situation of defects and the type.
It has to be noticed, that in Japan, the origin Country of use of VHTSS- S800-S690 for steel liners, the use
of permanent backing strip for welded joints is not allowed, because too risky.
To minimize the risks working with VHTSS-S690, exceptional quality control inspection and teams to
follow the full welding operations have to be considered. 100% of the welding works must be followed and
inspected, with consequences of relevant extraordinary costs for the Owner and additional time to be
allocated.
The execution of S690 joints requires highly workmanship to realize all the qualities provisions necessary to
reach and guarantee the sound performances; for pumped storage plants (PSP), quality demand is even
higher for the fatigue situation that largely impacting cost and time of execution.
In some projects, unfortunately, these quality-safe provisions are not in place for reasons of budget leaving
high margin of uncovered risks.
Past experiences of large failures in HEPP/PSP in waterway are very known, we only recall that “recently”
in a large HEPP in Ecuador, more than nine thousand (9.000) cold cracks were found, just at the put in
service of the Plant causing a complete stoppage of a three-billions USD investment on 2500 MW-HEPP,
demonstrating that the Risk it is real.
- HBP, being realized with common carbon steel pipe shell does not presents, as the experience has largely
demonstrated, any problem related to cracks, demonstrating that it is a fully a safe solution.
- Finally, the aim of this paper is that Planner Engineers and Owners reconsider Hot Banded Pipe (HBP)
Technology as a valid alternative for new High Head Hydropower Plants, Pumped Storage Plants or for
rehabilitation works on steel waterways.
References
1. Curnis, C., Bronzetti, D., Calvo S., Realization of steel penstocks with banded pipe technology (BPT) for high head hydro
power plants (HHP) and pumped storage plants (PSP). Hydro 2017 Conference in Sevilla
2. JPA (Japan): Japanese technical standard for gates and penstocks
3. ASCE Manuals and Reports on Engineering Practice No. 79, 2012
4. G. Mattioli: Banded Pipes Technologies, Water Power 1962
5. D. Vasilikis and Spyros A. Karamanos: Mechanics of confined thin-walled cylinders subjected to external pressure, ASME
transaction, 2014
6. R.J.M. Pijpers: Fatigue strength of welded connections made of very high strength cast and rolled steels. 2011
7. Company ATB-RC-SPA (Italy): Documentation on banded pipes penstocks for executed projects in Europe and South
America
The Authors
Clemente Curnis is a Senior Expert Consultant in hydromechanical equipment, penstocks and steel lining for hydropower plants.
He accomplished his Doctorate in Mechanical Engineering with specialisation in Hydropower Plans at the Polytechnic University
of Milan in 1975. Dr. Curnis has collaborated for 25 years with Construction Companies in design, fabrication and erection of
penstocks, gates and guard valves for hydropower plants. His experience has been gained on hydropower projects in more than 20
Countries worldwide and includes, besides conventional hydropower projects (HPP), also 8 Pumped Storage Projects (PSP). Dr.
Curnis has also collaborated over 10 years with major Swiss Engineering Companies in: basic and detailed design, shop and site
supervision and commissioning of Hydro Power Projects. In 2018. Dr. Curnis has been appointed as a Hydro-Mechanical Expert
in the Panel of Experts for Lesotho LHDA Phase II project and for Rufiji 2100 MW. Dr. Curnis collaborates as Expert with the
ICC “International Court of Arbitration”. Curnis has now more than 35 years of experience in hydromechanical equipment,
penstocks and hydropower projects and he is also Expert with ICC- Paris for international Dispute in the field.
Daniele Bronzetti graduated in Civil Engineering from the Swiss Federal Institute of Technology Zurich (ETHZ) in 2012. He has
been working since 2013 at Lombardi Engineering Ltd., Switzerland, in the special studies department. His main activities are
associated with international and national hydropower projects with focus on design of underground structures, hydraulic tunnels,
rock mechanics and civil works.
Sélim Sayah accomplished his Specialized Master Degree at the École Polytechnique Fédérale de Lausanne (EPFL), Switzerland,
and obtained later in 2005 from the same school his Ph.D. in hydraulics at the Laboratory of Hydraulic Constructions. His
activities are associated with international hydropower projects at Lombardi Eng. Ltd. with focus on hydraulic design, Dams,
powerhouses, and underground works. His experiences abroad first as design manager and later as project manager for large
hydro projects allowed him to gain a sound experience in the design, construction and implementation of such projects. Since
2019 he assumes the role of Head of Dam and Hydropower Division at Lombardi Group.