PROJECT NAME
SHANTIGRAM TOWNSHIP
00
ENCLOSURES:
1 METHOD STATEMENT
Rev. No: 0
PROJECT NAME
SHANTIGRAM TOWNSHIP
CLIENT
ATRECO
ARCHITECT
SERVICES CONSULTANTS
JHAVERI ASSOCIATES
METHOD STATEMENT
FOR
Rev. No: 0
1 This cover page is a record of all revisions of the document identified above by number and title. All previous
cover pages are hereby superseded and are to be destroyed.
2 The contractor has the full right to modify, amend or change Method Statement and supporting documents as
required or as deemed necessary. All such documents will be submitted to the "Consultant's" for approval.
Rev. No: 0
CONTENTS
01 PURPOSE
02 SCOPE
03 REFERENCES
04 ABBREVIATIONS
05 RESPONSIBILITIES
06 TOOLS / EQUIPMENT
07 MATERIAL
09 INSTALLATION PROCEDURES
10 INSPECTION
Rev. No: 0
Rev. No: 0
1. PURPOSE:
The purpose of generating this Method Statement is to define the procedure step by step to implement the correct
practices for Installation of Electrical Conduits through the guidelines so as to ensure that the job execute complies
with the requirements of Contract specification & serves the intended function to satisfactory level.
2. SCOPE:
This Method Statement refers to various work procedures contained within Contractor's Project Quality Plan for
MEP Works & Contract Specification, which explains and covers the Installation of Electrical Conduits Works.
3. REFERENCES:
3.1 Project Quality Plan for MEP Works (Contractor not yet Submited)
Rev. No: 0
4. ABBREVIATIONS:
5.0 RESPONSIBILITIES:
5.1. Engineer-Incharge :
→ Ensure all required submittals are made and required plant / tools / material and manpower is
available in timely manner.
→ Ensure all execution of works are carried out according to approvals, contract specifications,
approved MEP drawings, Project Quality Plan for MEP works, Method Statements for MEP
works, and safety measures are implemented.
→ Ensure necessary coordination with Client / Consultant Representative and other Agencies work
for timely completion of job.
9 of 17 .
Rev. No: 0
→ Responsible for preparation of quality plan, obtaining necessary approval from the Customer as
applicable and assist PM in effective implementation of approved quality plans and QC
procedures.
→ Responsible for communicating with all site staff about the QA requirements with respect to the
project.Responsible for Receiving and reviewing of all reports related to quality matters.
→ Responsible for organizing and conducting Quality audits with the co-ordination of PI and
planning engineer.
→ To maintain a comprehensive Inspection and Test records as per approved Project Quality plan.
Rev. No: 0
→ Ensure implementation of all safety measures and procedures specific to the nature and type of
execution work being carried out at site.
→ To ensure that all project personnel / site execution team is fully aware of their responsibilities
and have full understanding of the related safety rules, procedures.
→ To advise the involved personnel about the involved risk at work and necessary health,safety
and environment precautions / measures to avoid it.
→ To keep informed the site management and Consultant about the adopted safety measures as site
and ensuring their adequacy.
06 TOOLS / EQUIPMENTS
6.2. Hand Drill machine / Grinding machine 6.15 500V Megger / 1000V Megger
6.3. Groove Cutting Machine 6.16 Crimping Tool with die set
6.9. Cutting set 6.22 Box Spanner / Ring Spanner / DE Spanner Set
Rev. No: 0
09 INSTALLATION PROCEDURES
To carry out installation of Elecrtrical Conduits work , below mentioned procedure shall be followed step by step
in sequential manner.
Rev. No: 0
9.B.1 Ensure that the work area is ready and safe to start
QA/QC
the installation of electrical conduits.
Engineer /
Site Engineer
Engineer-
In charge
Rev. No: 0
9.C The jointing process of PVC conduit will be followed as mentioned below :
9.C.1 Both the joining ends of conduits will be cleaned
from inside as well as from outside by using QA/QC
solvent cleaning fluid and wipe it with clean rag to Engineer /
Site Engineer
make it dry. Engineer-
In charge
QA/QC
9.C.2 A thin layer of solvent cement is applied to the Engineer /
inner surface of the coupler. Site Engineer
Engineer-
In charge
9.C.3 Push fit the conduit ends fully into the coupler by
slight twisting action & remove the spilled or
QA/QC
surplus solvent cement from around the joint.
Engineer /
Make sure the conduit has entered fully into the Site Engineer
Engineer-
box spouts and couplers except expansion
In charge
couplers.
9.C.4 Make sure that the joint is tight enough and entry QA/QC
of water into the conduit through joints is not Engineer /
Site Engineer
possible. Engineer-
In charge
9.C.5 Approved connectors / adopters will be used for QA/QC
connections to back boxes / pull boxes. Engineer /
Site Engineer
Engineer-
In charge
9.C.6 Expansion couplers of approved type shall be QA/QC
provided wherever the conduits pass through the Engineer /
expansion joints of the building. Site Engineer
Engineer-
In charge
Rev.No. Rev. Date. Revision Description Prepared By Reviewed By Approved By
14 of 17 .
Rev. No: 0
Rev. No: 0
Rev. No: 0
01 Installed conduits and outlet boxes are as per approved material submittals.
Location and height of outlet boxes are correct as per approved shop drawing
03
and in proper alignment.
Installed conduits are free of any damages and the routing is coordinated with
04
other services.
05 The required pull boxes are provided as stated in the method statement.
Adequate care is taken to plug the pull boxes / back boxes with thermo Cole
07
material to prevent the ingress of concrete.
Conduit ends or stub-ups are capped or sealed properly to prevent the ingress
08
of dust, moisture or foreign materials.
REMARKS :
Signature
Date