Professional Documents
Culture Documents
05 Bosena Final
05 Bosena Final
ቁጥር:------------------------------------
ቀን:--------------------------------------
በ05 ቀበሌ ቦሰና ምንጭ መሰኖ ግንባታ ሰራ ለመሰራት ሙሉ ጥናትና ዲዛይን ዶክመንት አዘጋጀተን ከዚህ
ሸኝ ደብዳቤ ጋር 99 ገጽ አባሪ አድርገን የላክን ሲሆን በጠየቅነዉ መሰረት ለግንባታዉ የሚያሰፈልገዉ በጀት
‹‹ከሰላምታ ጋር ››
ግልባጭ፡-
ለደቡብ ወሎ ዞን ግብርና መምሪያ
ደሴ፣
ለኩታበር ወረዳ ምግብ ዋሰትና ቡድን
ኩታበር፣
Engineer Team for his valuable advice, constructive comment for us. Our deepest thanks also go
to our kutaber agriculture office Mr Negatu Yimer dieseling for their valuable advice and
encouragement. And special thanks for all our friends for their idea sharing and help.
II
Summary
This report contains the feasibility study and detailed analysis of engineering population
forecasting, water resource study and detail division box construction, HDPE pipe extension,
installation and cross drainage structures of Bosena spring small scale irrigation project. A
canal length right or left side of the spring 20m, the number of division box is 34, HDPE pipe
extension, installation 1500m and cross drainage pipe extenesion 25m is designed to irrigate
around 20ha of command area. The project costs a total of Birr 950664.60 /nine hundred fifty
thousand six hundred sixty four birr and 60/100 cents including vat for the mobilization,
demobilization, forman, store house renting, canal, division box,HDPE pipe extension,
III
Table of contents
Kutaber woreda agriculture office Jalaya river small scale irrigation project. .................................. I
Acknowledgmet ....................................................................................................................................II
1. Introduction...................................................................................................................................... 1
IV
1.3 Objectives of the project area .................................................................................................... 6
2 Hydrogeology .................................................................................................................................. 10
V
3.2.2 Animal power ....................................................................................................................... 18
3.3.1.1 The effect of climate given by the reference crop evapotranspiration (Eto) ................ 19
VI
5.3 Fire demand (Fwd) ............................................................................................................ ……39
VII
10 Pipe line design ............................................................................................................................. 66
12 Bill off quantity and cost estimation for the project ..................................................................... 79
14 Reference....................................................................................................................................... 86
VIII
List of tables
Table-1 Slope and area distribution………………………………..……………………………………10
Table-3 Slope gradient (Table A) and land use class (Table B) of the catchment………...………14
Table-7 Conveyance field canal and field application efficiencies (Adopted from FAO 1992)…30
Table-13 Bosena spring right side small scale irrigation project surveying data……………...…45
Table-14 Bosena spring left side small scale irrigation project surveying data…………..…....…51
Table-15 B/d ratio side slope, free boards and velocities by discharge rate value (IDD manual)
)………………………….…………………………………………………………………………….…..…54
X
List of figures
Figure -1 Location map of Bosena spring watershed project area…………………………………...3
XI
Salient features
4. Irrigation infrastructure
Command area size (Net):20 ha and Beneficiaries male 69 female 17 total 86 house-holds.
0.022 /s.
5. Project cost
Total cost for the project without Vat 15% = 826664.87 Birr
XII
1 Introduction
1.1 Background
In Kutaber woreda, under the prevalent rain-fed agricultural production system, the progressive
degradation of the natural resource base, especially in highly vulnerable areas of the highlands
coupled with climate variability have aggravated the incidence of poverty and food insecurity.
The major source of growth for kutaber is still conceived to be the agriculture sector. Hence, this
sector has to be insulated from drought shocks through enhanced utilization of the water
Irrigation is the reliable method of increasing agricultural production and productivity and has
greater impacts in solving food security problems in Kutaber. In practicing irrigation activities,
most of the production factors can be controlled and even crop failure which may occur during
rain failure can be supported with irrigation in the course of crop production. Ethiopia has
achievable and conducive irrigation and water resources policy in that development of new and
emerging small and large scale irrigation schemes are increasing from year to year all over the
nation. However the irrigation water management aspect is critically facing a challenge due to
various critical limitations the most important of which can be limited irrigation water access.
In this regard, irrigation investments must be carefully planned since sharing water between its
multiple users‟ calls for integrated forms of design and management. The success of irrigation
1
The prime objective of enhancing the planning and implementation of small-scale irrigation
project lies improving water availability through study, design and implementation of small-
scale irrigation scheme in the country. In this regard, Amhara region bureau of agriculture
development has conducted identification study and assured that beneficiaries require
assistance. Besides, the identification study confirmed that there are adequate spring flows for
Accordingly, as part of the water sector development program, the kutaber woreda agricultural
development office has initiated the study and design of a small scale irrigation scheme on
Bosena Spring at 05 (Mergeja) Kebele and has collaborated with irrigation Engineering team
2
1.2 Description of the project area
Irrigation project is found in Amahara National Regional State, South Wollo Zone, and Kutaber
Woreda. The spring is situated in Mergeja Kebele at the UTM coordinate of 0558059 m east and
1248936 m north. The elevation of the spring at the proposed spring site is around 2859 m.a.s.l.
3
1.2.2 Accessibility of the project area
The distance from kutaber (woreda capital ) to the spring site is about 8 km consists of 6.5 km
from Kutaber (woreda capital ) to the mergeja keble dry weathered road in poor condition and
1.5 km from mergeja Keble to the spring site without access road.
which is classified as dega agro climatic classification. The rainfall pattern of the project area is
two type in which one main rainy season occur during the summer season and the spring time
also start at December. During the summer season, when the rain starts early it begins at May
and ends at mid-September but when the rain starts lately it begins at early June and extends up
to end of September. The major rain is received in the months of July and August. The
distribution is very uneven; sometimes heavy rain was off occurred after it‟s set. The mean
The project area similar to Dessie agro climatic zones, located an Dessie altitude of 2500
m.a.s.l. The mean maximum average annual temperature of the project area is 22.490c and the
mean minimum average annual temperature of 6.490c, in which the highest mean maximum
temperature of 25.420C and a mean minimum temperature of 11.280C were recorded in May and
4
1.2.6 Sunshine of the project area
The project area similar to Dessie agro climatic zones, located an Dessie altitude of 2500
m.a.s.l. The mean average annual sunshine of the project area is 23.880c, in which the highest
mean maximum sunshine of 27.370C and a mean minimum sunshine of 21.320C were recorded in
The project area similar to Dessie agro climatic zones, located an Dessie altitude of 2500
m.a.s.l. The mean maximum average annual relative humidity of the project area is 0.6 in which
the highest mean maximum relative humidity of 0.67 and a mean minimum relative humidity of
The project area similar to Dessie agro climatic zones, located an Dessie altitude of 2500
m.a.s.l. The mean maximum average annual wind speed of the project area is 2.35 in which the
highest mean maximum wind speed of 2.71 and a mean minimum wind speed of 2.30 were
The beneficiaries are male 69 & female 26 total 86 house-holds and the places that irrigate a
There are traditional on the upstream and downstream right/ left side of this spring using
different irrigation practices but as the Hydrogeology study and respondent farmers indicated.
5
The traditional irrigation practices are under taken by individual farmers that use the spring
flow to the extreme upstream and downstream right/left side of the spring is with hardship. So,
the farmers in the project area are very much interested to upgrading the traditional scheme to
modern scheme.
The project area faces critical the allocation of the available water corresponding to the
potential irrigable land this is mainly due to the variability of rainfall distribution though the
overall rainfall. Accordingly, the rain-fed agriculture needs mean of supplementing during
distribution failures and further full irrigation is required to maximize the use of the potential
land and water resources. Moreover, there is a strong need of the beneficiaries to modernize and
expand the existing efforts of traditional irrigation practices and increase production in the dry
season.
Hence the objective of this project is to contribute a substantial share in the effort to
reduce the risk of production decrease due to rainfall variability and increase the
productivity of the resource in the project specific area. Specifically, the project is
There is a general consensus that irrigation investments will achieve broader food
security and poverty reduction impacts and if efforts are also geared towards up-grading
existing traditional farming practices with support to enhance access to input supply,
6
1.3.2 Specific objectives of the project area
Other benefits that can be expected to appear with the launching of the project are:
Rationale for the intensification and modernization of small-holder agriculture and rural
lifestyles
The engineering study and design enables the realization of the project by the provision of
engineering structures that will allow the appropriate abstraction of the spring water for
delivery in to the identified irrigation fields of the study area. Hence, this engineering design is
The formulation of sound and stable structure, with necessary provisions that allow safe,
Prepare general plans & drawings for all irrigation infrastructure & irrigation system
designs,
7
1.4 Scope of the project area
In General, the scope of this design is mainly limited to the engineering considerations and
hydrological analysis for the safe and reliable function of the project. The focus is on the
planning of the water resource, determination of spring flow and design of the division box,
The irrigation design shall ensure reliability, equity and flexibility of water delivery to
farmers. It will aim at reducing conflicts among water users and will lead to lower operation and
maintenance costs.
Updating the existing irrigation practice, if available and acceptable. and Establish design
criteria for irrigations structures and to be used in the final design stage,
Design proper irrigation system compatible with local conditions and management
capabilities,
Establish flood protection measures for the command area and canal structures and design
Planning and layout of the irrigation system, which include irrigation canals, drainage
channels, inspection roads and alignments, canal spacing, canal length, location of structures,
and water profiles along canal and drains at specified reaches, which is most economical easily
Determination and estimation of water application conveyance and other losses and
Check and test hydraulic and structural designs of main canal considering total demand and
Topographic survey:
Surveying the spring site and the Command area with sufficient radius, using Leveling
Spring flow estimated during the reconnaissance field visit by bucket method.
9
2 Hydrogeology
2.1 Watershed characteristics
2.1.1 Slope of the watershed
The watershed marked topographic variation. All types are present. The dominant class is gently
sloping (3-8%) which covers 30.74% of the total area followed very steep (>50%) which is
2.23%. steep (30-50%) which is 7.46%, Moderately Steep (15-30%) which is 13.43%, sloping (8-
15%) and flat or almost flat (0-3%) accounts 19.91 % and 26.23 % respectively. Below Table
10
Figure-2 Slope map of the watershed
For Bosena watershed bare land covering 2.62% of total area, cultivation land covering 67.82
%, grass land covering 9.18%, plantation land covering 1.78% and shrub & bush land is
18.60%. Five mainly dominate land use of the watershed area is cultivated land.
11
Table-2 land use and area distribution
Sno Land Use Type Area in Ha Percent
For Bosena watershed soil texture is sandy loam and soil type is lithic leptosols.These
hydrological soil groups for Ethiopia is Group A- soil having alow runoff potential due to high
infiltration rates. These soils primarily consists of deep, well drained sands and gravels.
Agro climatic zone classification is based on the crop type, rainfall regime, temperature and
altitude. The annual rainfall of the project area using Dessie meteorological station is around
1350mm.The altitude of specific project area 2859 m.a.s.l. i.e. between 1500-2300 m.a.s.l based
on the above parameters the climatic condition of the watershed is described as wena dega and
2300-3500m.a.s.l dega agro climatic. Therefore, during rainy season, the climate is cold and
during the dry season it is hot. The project area of the watershed is dega.
13
Availability of construction materials etc…
In general, the study of the geomorphology and the geology of the bosena spring site is the most
vital element to identify the type of structure and the extent of the work that has to be
constructed. For this project surface and subsurface investigations have been carried out as
described below. Accordingly, the spring is situated at a geographical location of Bosena (BM-
The slope gradient (Table A) and Land use class (Table B) of the catchment is illustrated in the
following table.
Table-3 slope gradient (Table A) and Land use class (Table B) of the catchment
14
As we can see from the table the dominant land use types of the catchment areas are, cultivated
land, bush and shrub land and grass land. These land use types have high infiltration capacity
and produces low flood concentration. Also the majority of the catchment is mainly from flat to
sloping category with a soil texture of sandy loam. These physiographic characteristics implies,
enriching the ground water potential which is a great advantage for the spring.
During site investigation, natural construction materials required for the construction of the
various proposed engineering structures at the headwork and within the farmland have been
assessed. In addition to identifying the quality, quantity and accessibility conditions of the
construction materials, The materials needed for the construction of the structures of the
proposed hydraulic structures include rock for masonry stones, aggregates (both coarse and
fine), impervious soil for fill and/or lining, backfill soil, and water.
The site that can be used for production of rock for masonry stone and crushed coarse
aggregates and has been assessed during the field work. One possible site has been identified
within downstream side of spring at about 4km – 5km. During site investigation stone required
for masonry and hardcore works were identified on two places within project area, one is in the
downstream left side of spring or in the downstream right side of spring at a distance of 1-1.5km
from Bosena spring location,. The coarse aggregates can produced by grinding and crushing of
the boulder rock in to the appropriate size and shaped that can fit the required mix proportion.
Include rock for masonry stones, aggregates (both coarse and fine) and water.
15
2.3.2 Fine Aggregates or Sand
Borrow areas for fine aggregate or natural sand have been assessed starting from the project
stream itself. The sand is one of the main raw materials for construction. This material is used
for mixing of the cement, fine aggregates, coarse aggregates, for the construction of concrete
structure.
The availability of this material at nearby place highly influences on the costs of the project. If
the sand quarry is present at a far distant place the costs of the project increases. The sand
quarry for the Bosena project is identified center of river in Ambassel and delenta woreda .These
rivers are found in the north and south direction of the Delenta town and ambassel keble
respectively.
2.3.3 Water
Water for construction purposes can be found from the project spring itself. The spring is
perennial throughout the year that there is some amount of flow along its course. During this
field time the spring flow was more than 31.78 Litter/second.
16
3 Irrigation Water Requirement
Suitability of soil– the selected crops should give a maximum possible yield with little or
no additional inputs which will increase the soil nutritive value and provide adequate
Method of irrigation
Farmers preference
Taking the above variables into consideration, the following crop types were selected for
farmers ploughed their land every year without any land reclamation measures except on
farmlands around the homestead where they apply compost to improve the fertility and the
animal power for transporting agricultural products to the market and for any other purpose.
The majority of the household of the kebele possess nil or one oxen only, which has great impact
applied for limited crops and improved seed is applied for Teff and potato only. For the rest of
the crops they used local varieties, due to this the yield obtained is very low.
irrigation project. Several methods and procedures are available for this. The Food and
Agriculture Organization (FAO) of the United Nations has also made available several
18
publications so this subject and other issues related with this. The computer program available
in FAO Irrigation and Drainage Paper No .56 “CROPWAT” has been used for the calculation
procedures for calculation of crop water requirements and irrigation requirements are mainly
based on methodologies presented in FAO Irrigation and Drainage Paper No.24 “Crop Water
Requirements” and No. 33 “Yield Response to Water”. The corresponding values of the crop
water requirements of the proposed crop so the project are presented in the Agronomy Study of
Crop water requirement is defined as the depth of water needed to meet the water loss through
conditions including soil water and fertility and achieving full production potential under the
given growing environment (FAO, 1998) The water requirement of crops may be contributed
from different sources such as irrigation requirement, effective rainfall, soil moisture storage
CWR=IR+ER+S+GW
IR = irrigation requirement
ER = effective rainfall
19
3.3.1 Determination of Crop Water Requirement
3.3.1.1 The effect of climate given by the reference crop evapotranspiration (Eto)
Reference crop Evapotranspiration is the rate of evaporation from an extensive surface 8 to
15cm tall, green cover of uniform height, actively growing, completely shading the ground and
not in shortage of water. Estimation of the potential Evapotranspiration for irrigation project
depends on the metrological and climatic data of nearby station, which has nearly the same
latitude and longitude to the command area used. The widely used methods to estimate reference
Thornth-waite method
Hardgrave‟s method
Penman-Monteith method
This method is recommended in the FAO expert consolation held in May 1990 in Rome (FAO-56,
20
Where ETo reference evapotranspiration [mm day-1],
21
June 25.42 9.59 1.14 2.71 0.39 25.05 3.47
There are four main growing stages of crop during its growing period where water requirement
varies
1. Initial stage–germination and early growth whether the soil surface is not or hardly covered
2. Development stage-runs from end of initial stage to attainment of efficient full ground cover.
3. Mid-season stage- runs from attainment of effective full ground cover to time of start of
maturing.
4. Late season stage- runs from end of mid-season stage until full maturing or harvesting.
22
Table-5 Growing stage Kc values of the proposed crops in dry season.
23
Mar 3 Mid 1.05 Mar 1 Mid 1.05 Mar 3 Late 1.02
Apr 1 Mid 1.05 Mar 2 Mid 1.05 Apr 1 Late 0.96
Apr 2 Late 1.04 Mar 3 Late 1.03
Apr 3 Late 0.98 Apr 1 Late 1
May 1 Late 0.91 Apr 2 Late 0.96
Fruit crops
Kc
Month Decade Stage
coeff
Jan 1 Init 0.7
Jan 2 Init 0.7
Jan 3 Init 0.7
Feb 1 Init 0.7
Feb 2 Init 0.7
Feb 3 Init 0.7
Mar 1 Deve 0.69
Mar 2 Deve 0.68
Mar 3 Deve 0.67
Apr 1 Deve 0.65
Apr 2 Deve 0.64
Apr 3 Deve 0.62
May 1 Deve 0.61
May 2 Deve 0.59
May 3 Mid 0.58
Jun 1 Mid 0.57
Jun 2 Mid 0.57
Jun 3 Mid 0.57
Jul 1 Mid 0.57
Jul 2 Mid 0.57
Jul 3 Mid 0.57
Aug 1 Mid 0.57
Aug 2 Mid 0.57
Aug 3 Mid 0.57
Sep 1 Mid 0.57
Sep 2 Mid 0.57
Sep 3 Late 0.6
Oct 1 Late 0.67
24
Oct 2 Late 0.67
Oct 3 Late 0.67
Nov 1 Late 0.67
Nov 2 Late 0.67
Nov 3 Late 0.67
Dec 1 Late 0.67
Dec 2 Late 0.67
Dec 3 Late 0.67
Cropping Coefficient ( )
In the crop coefficient approach the crop evapotranspiration is calculated by multiplying the
Where, ⁄
Most of the effects of the various weather conditions are incorporated into the estimate.
The crop coefficient, is basically the ratio of the crop to the reference , and it
represents an integration of the effects of four primary characteristics that distinguish the crop
Crop height
Canopy resistance
25
Evaporation from soil
It is defined as the part of water requirement of crops that should be fulfilled by irrigation. In
other words, it is the water requirement of crops excluding effective rainfall; carry over soil
IR=CWR-(ER+S+GW)
by crops. All the rainfall that falls is not useful or effective. As the total amount of rainfall varies,
so does the amount of useful or effective rainfall. Some of the seasonal rainfall that falls will be
lost as unnecessary deep percolation; surface runoff and some water may remain in the soil after
Four methods for calculating the effective rainfall from entered monthly total rainfall data.
26
3.3.1.3.1 Fixed percentage effective rainfall
The effective rainfall is taken as a fixed percentage of the monthly rainfall from entire monthly
Where; „a‟ is a fixed percentage to be given by the user to account for losses due to runoff and
deep percolation. An average value of 0.8 was adopted for this project and total rainfall is the
An empirical formula developed by FAO/AGLW based on analysis for different arid and sub-
humid climates. The combined effect of dependable rainfall (80% probability of exceedance) and
estimated losses due to runoff and deep percolation can be estimated from this formula:
This formula is similar to FAO/AGLW formula (see dependable rainfall method above) with
Value for a, b, c, d and Z are correlation coefficients. Adaptation of this empirical relation needs
predetermined values of the coefficients from a long term rain fall of a given area. But,
27
according to the CROPWAT window program, these constants are given as a = 0.5, b = -5,c =
The effective rainfall is calculated according to the formula developed by USDA soil
ER=P*(125-o.2*P)/125------- rainfall<250mm
Dependable
Fixed
Rai Empirical USDA Soil
Month Rain mm percentage
(FAO/AGLW formula Conservation service
80%
Formula)
January 12.20 9.76 11.10 -2.68 11.96
28
December 10.40 8.32 10.20 -3.76 10.23
As can be seen from the Table above the highest effective rainfall was fixed percentage methods
and the lowest was given by Emperical method. In general, as the rain intensity is high, more
will be lost in the form of runoff and less will reach the root zone of the crop and vice versa.
Based on this, Empirical method gives conservative value of effective rainfall. Thus the one
Irrigation efficiency refers to the amount of water removed from the water source that is used by
the crop. This value is determined by irrigation system management, water distribution
characteristics, crop water use rate, weather and soil conditions. The amount of loss depends on
the efficiency of the irrigation system. There are three basic irrigation efficiency concepts.
These are:
29
Table -7 Conveyance, field canal and field application efficiencies (Adapted from:
FAO, 1992)
1 Conveyance efficiency (Ec) Efficiency
1.1 Continuous supply with no substantial change in flow 0.9
Rotation supply in projects of 70-300 ha, with 0.65 – 0.70
1.2
effective water management
2 Field canal efficiency (Ed)
2.1 Blocks larger than 20 ha
Unlined 0.8
lined or piped 0.9
2.2 Blocks up to 20 ha :
Unlined 0.7
lined or piped 0.8
3 Field application efficiency (Ea)
3.1 Surface methods
light soils 0.55
medium soils 0.7
heavy soils 0.6
Graded border 0.6-0.70
Basin and level border 0.60-0.80
Contour ditch 0.50-0.55
3.2 Sprinkler :
hot dry climate 0.6
moderate climate 0.70-0.60
humid and cool 0.8
Source: FAO-SFAR Irrigation Manual 2006
For project efficiency: Based on his project (the conveyance and distribution structures are
30
Conveyance efficiency Ec = 95%;
It is the amount of irrigation water required to meet the evapotranspiration needs of crops as
well as leaching requirement (LR) etc. Thus, NIT=CIR + water lost in deep percolation for the
purposes of leaching.
NIT = IR + LR
The gross irrigation requirement is computed based on the net irrigation requirements and
proposed project and field application efficiency depends on the purpose of the computation. If
the focus of the analysis is to get the gross requirement at project level, then the formula will be:
31
Table -8 Estimation of net and gross irrigation requirement
Estimation of Net and Gross Irrigation Requirement
Crop Type Formula Jan Feb Mar April May Jun Jul Aug Sep Oct Nov Dec
Eto value Eto 3.0 3.4 3.6 3.8 3.8 3.5 3.1 3.3 3.7 3.6 3.3 2.9
Cabbage kc 0.7 0.8 1.0 1.0 1.0
ETc of Cabage
Etc=Kc*Eto 2.1 2.8 3.7 3.9 3.6
(mm/month)
Tomato kc 0.6 1.0 1.2 0.9
ETc of tomato
Etc=Kc*Eto 1.8 3.3 4.2 3.5
(mm/month)
Potato kc 0.5 1.0 1.2 1.1 0.8
ETc of
Etc=Kc*Eto 1.5 3.2 4.2 4.0 3.0
potato(mm/month)
Pepper kc 0.6 0.8 1.0 1.0 0.9
ETc of pepper
Etc=Kc*Eto 1.8 2.7 3.8 3.9 3.4
(mm/month)
Onion kc 0.7 1.0 1.0 1.0
ETc of Onion
Etc=Kc*Eto 2.2 3.3 3.8 3.7
(mm/month)
small vegtable kc 0.7 1.0 1.0 1.0
ETc of small
vegetable Etc=Kc*Eto 2.2 3.3 3.8 3.6
(mm/month)
Fruit crops kc 0.7 0.7 0.7 0.6 0.6 0.6 0.6 0.6 0.6 0.7 0.7 0.7
ETc of fruit
crops Etc=Kc*Eto 2.1 2.4 2.5 2.4 2.2 2.0 1.7 1.9 2.1 2.4 2.2 1.9
(mm/month)
Total Etc 21.3 30.8 36.4 35.4 19.3 6.0 5.4 5.7 6.3 6.6 6.2 5.5
Rainfall mm/month 12.2 15.9 43.8 120.7 80.7 122.9 279.1 326.7 104.8 56.1 24.5 10.4
Peff =
Pmonth
*(125 - 0.2
*Pmonth) /
USDA Soil 125 for
Conservation Pmonth≤250 12.0 15.5 40.7 97.4 70.3 98.7 152.9 157.7 87.2 51.1 23.5 10.2
service mm and
Peff = 125
+ 0.1 *P for
Pmonth
>250mm
Project efficiency
0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5
(Ep)
Discharge q 10*GIR/(30
0.1 0.1 0.0 0.5 0.4 0.7 1.1 1.1 0.6 0.3 0.1 0.0
(l/s/ha) for 24hr *24*3.6)
Discharge
10*GIR/(30
q(l/s/ha) for 18 0.1 0.2 0.0 0.6 0.5 0.9 1.5 1.5 0.8 0.4 0.2 0.0
*18*3.6)
hrs
32
4 Population forecasting
In the designing of rural water supply project, the first thing that should be considered is
knowing the number of existing population and estimating the future population after
some years.
The estimation of the future population of a given area (town) based on the current
New water supply systems are normally made large enough to meet the needs of growing
The design period should neither be too long that the present population of the
community is over-charged nor should it be too short, so that just after a few years it may
The capacity of the reservoir which is going to be constructed in a given place should be
sufficient to carry the quantity of water which will be required to supply the forecasted
The future population of a given area after some years (Design period) can be estimated in
That is,
33
Pn=P+nC
Given that population of a given rural was 80 in 1980, 150 in 1990, 280 in 2000 and 430 in 2000
forecast the population of the rural in 2020, 2030 and 2040.
1980 80
1990 150 70
Total 350
34
That is, Pn=P (1+IG/100)
1970 80
Total 227.74%
Expected population
Pn=P(1+IG/100)
35
4.3 Increasmental increase method
This method is the improvement of the previous two methods. In this method the avg. increases in
the population is determined by arithmetic method and to this is added the avg. of the net
That is, Pn=P+(C+C`)n Where, Pn= Expected population, C=Average of increase, C`=Average
1970 80
1980 150 70
Total 350 80
Expected population
Pn=P+(C+C`)n
36
4.4 General method
Pn=Pp (1+r) n
Pp=Present population
The present population of a given rural town is 430. What will be the number of population of
Solution
Pp = 430 Pn=Pp(1+r)n
r = 3% = 0.03 =430(1+0.03)20
n = 20 years =776.63
The population of the project area using general method 2030 is 777.
37
5 Water demand
Water demand (Awd) is the water required by a community and is a function of different
Which is the quantity of water used for domestic purpose such as drinking, cooking, bathing,
modern towns and 15 Lit/capital/day in rural community. Then the total domestic
Dwd=Pn*Adwd=777*15=11655 l/se/day
Which is the quantity of water used for commercial works such as for banks, shopping's, etc…
modern towns and is neglected in rural community. Then the total Cwd of the community
will be
Cwd=Pn*ACwd
38
5.3 Fire Demand (Fwd)
Which is the quantity of water used for protection of fire and is particularly used in the very
crowded population.
Fwd is a function of population as per the empirical formulas, but very difficult to
2-Fwd=5663(√P)…………(Bustons)
In planning of a water supply project both in rural and urban areas; Pwd is taken to be
10% of Dwd. there is no school, clinics, tea house and public office.
39
In planning of a water supply project both in rural and urban areas, WL is taken to be
Generally:-
Twd=Dwd+Cwd+Fwd+Pwd+WL
Twd=11655+0+0+31680+4335.5=47668.5 Lit/day
NB
Cwd and Fwd can be neglected in the designing of rural water supply.
Maximum daily demand (MDD):- is the maximum daily demand over 24 hrs in a day.
This is taken by multiplying the average daily demand(ADD) 0r (Twd) by a factor of 1.1
to 1.5
40
=Twd +(10% to 15% of Twd)
=47668.5+(0.1*47668.5)=52435.35l/day
Peak hour demand (PHD):- It is greatly influenced by the size of community, mode of
Usually, PHD is obtained by multiplying the average daily demand (ADD) by a factor of
=47668.5+(1*47668.5)
=95337liters
Twd = ADD=Dwd+Pwd+WL
The total spring flow or supply is measured 45763.2 l/day, while as the total water demand is
demand. Therefore to fill this demand and supply gap the we will apply different mechanisms
such as installation of closed pipes to reduce evaporation loss, using gate valves to control
overflow loss, installation of plastic pipe to protect leakage lose, and finally the joints of the pipe
will be installed properly using division box. These measures will able us to get an additional
water of 1905.3l/day. From the total water demand (45763.2l/day), the water needed for
41
The duty at peak month has to be determined from the calculated monthly values in the irrigation
Q= Duty*command Area to be irrigated, Q base flow of the spring is 22 l/se or 0.022 m3/s.
20ha.so the design of the project area is safe spring flow of water.
requirements. The objective of a water delivery and distribution system is to deliver water
adequately, efficiently and reliably to the users there by improving production. In all the cases
the system should deliver the required water that can sustain the field crops within the irrigation
interval (T).
a channel located at the upper reach of the field. Gravity provides the major driving force to
spread water over the irrigated field. Once distributed over the surface of the field and after it
has entered the soil, water is often redistributed by forces other than gravity. For this project the
42
7 Hydraulic Design of the Canal
The alignment should not pass through the valuable lands, religious places, villages, etc.
The alignment should be short as far as possible, but to make it short the alignment
should not be taken through the area where irrigation is not yet all possible.
The alignment should cross the natural stream, drainage, etc. approximately at the right
angles. At the crossing point the width of the drainage should be minimums and the banks
The alignment along the ridge line or water shade line is very good as the water shed
canal can irrigate the area on both the side. Moreover, cross drainage work may be
avoided.
The alignment should be such that the maximum area may be irrigated with minimum
The alignment should not pass through the water logged area because the canal may be
The alignment should not pass through the sandy soil as the percolation in the loss soil
43
soil will be less (Basak, 1999).
Canal is designed in a way which, it‟s longitudinal and cross section is fixed out to suit
requirements; thus various canals dimension like bed width, depth, side slope, longitudinal
slope, etc. are to be fixed in the design of irrigation canal. Irrigation canals are designed to take
Discharge Volume of
5.00
parameter dimension measurement (m3/se) bucket (liter)
44
7.3 Determine canal profile measurement
Table-13 Bosena Spring Right Side Small Scale Irrigation Project Surveying
Data
Station Chainage BS IS FS Rise (+) Fall (-)
BM 1.900
HI RL Remark Chainage RL
0
2859.108 2859.108
2858.798 20 2858.798
2858.796 40 2858.796
2858.485 60 2858.485
47
2858.43 200 2858.43
49
2859.4
2859.2
2859
2858.8
Series1
2858.6
2858.4
2858.2
2858
2857.8
50
Table-14 Bosena Spring left side Small Scale Irrigation Project Surveying
Data
BM 1.900
HI RL Remark Chainage RL
2859.108 0 2859.108
2859.218 25 2859.218
2858.925 50 2858.925
2859.135 75 2859.135
2858.262
2859
2860
2859.5
2859
2858.5
2858
Series1
2857.5
2857
2856.5
2856
2855.5
2855
53
7.4 Determine canal side slopes
Side slopes varies from about 2:1 for main canals down to 1:1 The freeboard varies from about
The duty at peak month has to be determined from the calculated monthly values; the irrigation
hours suggested 24 hrs. then q value or duty is 1.1 l/s/ha and for 20ha Command area the duty is
22 l/s=0.022m3/s. but the spring flow is enough water to the command area.
Table-15 B/d ratio, side slopes, freeboards and velocities by discharge rate value
(IDD Manual)
Discharge (m3/s) b/d Side slope Freeboard(m) Velocity (m/s)
The bed width should be wide enough to allow easy cleaning and workable for construction. A
bed width of 0.20 to 0.25 m is considered to be the minimum for trapezoidal sections as this still
allows the cleaning of the canal with small tools such as shovel. For small scale irrigation
projects, the recommended minimum top bank width varies from about 1.0 m for main canals
down to 0.3 m for smaller tertiary canals and head ditches. The following is a guide to the
recommended bed width/water depth (b/d) ratios for rectangular masonry canals:
54
Table-16 Canal width to water depth ratio (b/d ratio)
b/d ration
be used as criteria for a design of the canal. A minimum permissible velocity is that which will
not start sedimentation. It is determined by sediment transport capacity of the flow. A maximum
permissible velocity is that which will not cause erosion of the canal. This velocity is very
uncertain and variable and can be estimated only with experience and judgment (Chow, 1983).
and bed slope should be the same as the ground slope as in the case of contour canal because it
55
Small canals, Q < 0.3 m3/s,0.30 to 0.50 % (Abebe, 2011)
the ripple s formed on the bed of the canal. The value of ‟n” depends on the type of the bed
Fb = 0.20 + 0.15Q1/3…...……………………………………………….........…….A
56
7.10 Determine canal dimension
Main Canal (Primary canal) is a canal next to the intake which water enters to for irrigation. In
05 kebele Bosena irrigation project a given main canal is designed lined. The total length of
main canal is 20m; Design of lined canals is usually done based on the permissible velocity
approach. A minimum permissible velocity is that which will not store sedimentation in the canal
and is determined by the sediment transport capacity of the flow. For the design of lined canals
uniform flow equations for open channel flow can be used. This can be Manning‟s formula:
Q A*V
Q A* 1 R 3S
2 1
2
n ………………………………………B
R = hydraulic radius, m
n = Manning‟s coefficient
For a given, Manning‟s coefficient “n” and longitudinal slope “S” of the canal, determine the
hydraulic radius and velocity of flow from above discharge. For 05 kebele Bosena irrigation
Wetted perimeter
P = B+2Y … ……………………………………………….…..............D
R = A/P ……………………………………………………………………E
Flow velocity
V= ………………………….……….………….………F
Therefore, , ,
In ordinary lined canals, the steepest satisfactory side slope from construction point of view is m
= 1.25 or m = 1 (m= cotangent of side slope). For the best hydraulic section the hydraulic
radius is
Discharge (Q)=Area*Velocity
Discharge (Q)=A*
0.022= * ( )*
58
0.022= *55.556* * *0.032
0.0661= * *1.76
0.046= *1.76
=0.046/1.76
d= (0.046/1.76)
b=d=0.25m, take,0.4m.
A=bd=0.4*0.25=0.10m2
Free board
The gap between full supply level and the bank level of the canal is known as free board
Canal size
59
Total depth= water depth + free board = 0.25m+0.25m=0.5m
60
8 Crossing structures
61
9 Division Box
Division structures or boxes regulate the flow from one canal to another or several
others.
They usually consist of a box with vertical walls in which controllable opening are
provided.
Metal or wooden sluice gates or stop logs are usually installed to regulate the division of
flow of all times and to shut off in any branch when desired.
The width of each out-let is generally proportional to the division of water to be made.
Continuous: the flow will be proportionally divided into two or more small canals.
discharge required.
Rotational: in this case the opening should be equipped with gates to close and open
Q=C*L*H3/2
L1 =
= L2 =
= L3 =
62
Figure-8 Division boxes calculation
Sample calculation:
Available data;
Qo=0.022m3/sec
Q=C*L*H3/2
63
H=Depth of flow (m)
Assuming that:
C=1.70
H=0.25m
Then Q=C*L*H3/2
L1 =
= L2 = = L2 = 0.1m
= L3 = = L3 = 0.1m
B = b+2mD
m- Side slope
B = 0.25+2*(1*0.25)
The division box dimension internal length and width is 0.7m and depth is 0.5m.
64
Figure-9 Division boxes and PVC pipe turn out
65
10 Pipe lines design
Gravity main: - It is designed to convey economically the safe yield of the spring to the
D=0.97 *√0.022 =0.181meters=5.66inche we have taken economically 3 inch pipe used and
After obtaining pipe diameter, the velocity (V) of water flowing through the gravity main
should be checked in order to greater than the allowable velocity of 0.6 m/sec. To check
Q=AV,
V=Q/A=0.022/0.026=0.855m/se
hf = (fLv2)/2gd
f=friction factor depends on the relative roughness of the pipe and is:-
66
0.02(1+ (1/35d)) for new pipes
f=0.023
hf = (fLv2)/2gd
hf= (0.023*1000*0.855^2)/2*9.81*0.181=4.73meters.
hf= (0.023*500*0.855^2)/2*9.81*0.181=2.37meters.
Let‟s Consider also minor losses (fittings, bends etc…) as 10% of hf then, total head loss will be
hf + minor loss.
67
Check available head of both side of the spring eye 1.224m is less than the total both side
of head loss 5.20m and 2.60m respectively. Water will reach safely to the command area.
68
11 Unit rate analysis for the project
Table-20 Unit rate analysis for the project
05 Kebele Bosena Spring Small Scale Irrigation Project Unit Rate Analysis
Unit Rate Analysis
• Material Cost+ Labor Cost+ Equipment Cost = Direct Costs (DC)
• Profit+ Overhead Costs= Indirect Costs ( IC)= 20% of DC
Unit Rate Analysis
• Labor Cost- skilled and unskilled laborers
• Equipment Cost- 5% labor cost
• Material Cost- cement+ sand+ stone+ gravel+iron bar+timber
formwork+wooden +nail+blackwire etc…
• Indirect Costs- 20 % Dc( profit +overhead costs)
• Add up the above gives the total unit cost
69
2 Unit cost estimate for ordinary soil excavation up to adepth of 1 m depth 113.75
Labor cost (LC)
• Let hourly working rate =0.18M3 per hour
• Daily working time = 8 hour per day
• Daily output w/h is the work norm for soil excavation (m3) 1.44
• Let the Labor payment (Birr/day ) 130.00
• Labor cost (LC) (Birr/m3)=Labor payment/daily out put 90.28
Equipment cost (EC) (Birr/m3) = 5 % of labor cost 4.51
• Direct cost = labor cost + equipment cost 94.79
• Indirect cost (IC)=20 % of direct cost 18.96
• Total unit cost = direct cost + indirect cost 113.75
3 Unit cost estimate for ordinary soil excavation up to adepth of 1-1.5m depth 175.00
Labor cost (LC)
• Let hourly working rate =0.117M3 per hour
• Daily working time = 8 hour per day
• Daily output w/h is the work norm for soil excavation (M3) 0.94
• Let the Labor payment (Birr/day ) 130.00
• Labor cost (LC) (Birr/m3)=Labor payment/daily out put 138.89
Equipment cost (EC) (Birr/m3) = 5 % of labor cost 6.94
• Direct cost = labor cost + equipment cost 145.83
• Indirect cost (IC)=20 % of direct cost 29.17
• Total unit cost = direct cost + indirect cost 175.00
70
Labor cost (LC)
• Let hourly working rate =0.064M3 per hour
• Daily working time = 8 hour per day
• Daily output w/h is the work norm for rock excavation (M3) 0.51
• Let the Labor payment (Birr/day ) 130.00
• Labor cost (LC) (Birr/m3)=Labor payment/daily out put 254.90
Equipment cost (EC) (Birr/m3) = 5 % of labor cost 12.75
• Direct cost = labor cost + equipment cost 267.65
• Indirect cost (IC)=20% of direct cost 53.53
5 Unit cost estimate for Backfill and Compaction in irrigation canal 109.20
Labor cost (LC)
• Let hourly working rate =0.1875M3 per hour
• Daily working time = 8 hour per day
• Daily output w/h is the work norm for backfill & compaction (M3) 1.50
• Let the Labor payment (Birr/day ) 130.00
• Labor cost (LC) (Birr/m3)=Labor payment/daily out put 86.67
Equipment cost (EC) (Birr/m3) = 5 % of labor cost 4.33
• Direct cost = labor cost + equipment cost 91.00
• Indirect cost (IC)=20% of direct cost 18.20
• Total unit cost = direct cost + indirect cost 109.20
71
• Daily output w/h is the work norm for backfill & compaction (M3) 12.00
• Let the Labor payment (Birr/day ) 130.00
• Labor cost (LC) (Birr/m3)=Labor payment/daily out put 10.83
Equipment cost (EC) (Birr/m3) = 5 % of labor cost 0.54
• Direct cost = labor cost + equipment cost 11.38
• Indirect cost (IC)=20% of direct cost 2.28
• Total unit cost = direct cost + indirect cost 13.65
7 Unit Cost estimate for masonry dressed on both sides (1:4) 2891.45
• For 1m3 of masonry work the unit rate analysis:
• Let the mix ratio 1:4 & daily output of 1 mason crew ( m3 ) 1.50
• 1mason Crew composition=1 mason + 4 daily laborers
• payment for the main mason is 270 Birr/day & laborers is 130
birr/each 790.00
• Labor cost (LC) (Birr/m3)=Labor payment/daily out put 526.67
• Equipment cost (EC) (Birr/m3) = 5 % of labor cost 26.33
72
600 Birr/ m3 600.00
Cost of stone 585.00
Water = 0.4 m3 for 1m3 of masonry 0.40
5 Birr/ m3 5.00
Cost of water 2.00
Total material cost birr /1m3of masonry 1856.54
Total direct cost (DC) =Labor cost + Material cost 2409.54
Indirect cost (IC) w/h accounts overhead cost and profits /20 % of direct cost/ 481.91
Total unit cost = direct cost + indirect cost 2891.45
Unit cost estimate for mass concrete up to 10 cm thick mixed by hand C-10
8
(1:3:6) 2802.90
• For 1m3of mass concrete work the unit rate analysis:
• Let the mix ratio 1:3:6 & daily output of 1 mason crew (m3 ) 25.00
• mason Crew composition=1 mason + 6 daily laborers
• payment for the main mason is 270 Birr/day & laborers is 130
birr/each 1310.00
• Labor cost (LC) (Birr/m3)=Labor payment/daily out put 52.40
• Equipment cost (EC) (Birr/m3) = 5 % of labor cost 2.62
• Labor cost + equipment cost 55.02
Material cost ;
73
• Gravel = 6/10*1m3*1.1*1.15 0.76
750 Birr/ m3 750.00
Cost of gravel 569.25
• Water = 0.5 m3 for 1m3 of mass concrete 0.50
5 Birr/ m3 5.00
Cost of water 2.50
Total material cost birr /1m3of mass concrete 2280.73
Total direct cost (DC) =Labor cost + Material cost 2335.75
Indirect cost (IC) w/h accounts overhead cost and profits /20 % of direct cost/ 467.15
Total unit cost = direct cost + indirect cost 2802.90
Unit cost estimate for reinforced concrete footing paid mixed by hand C-15
9
(1:2:4) 9349.68
• For 1m3of Reinforced concrete work the unit rate analysis:
• Let the mix ratio 1:2:4 & daily output of 1 mason crew (m3 ) 2.37
• mason Crew composition=1 mason + 8 daily laborers
• payment for the main mason is 270 Birr/day & laborers is 130
birr/each 1310.00
• Labor cost (LC) (Birr/m3)=Labor payment/daily out put 553.68
• Equipment cost (EC) (Birr/m3) = 5 % of labor cost 27.68
• Labor cost + equipment cost 581.36
Material cost ;
• Cement = 1/7*1m3*1.05 shrinkage * 1.3 wastage *1400 kg /m3 2.73
730 Birr/Quntials 730.00
Cost of cement 1992.90
• Sand = 2/7*1m3*1.3*1.5 0.43
700 Birr/ m3 700.00
74
Cost of Sand 299.00
•Gravel = 4/7*1m3*1.1*1.15 0.72
750 Birr/ m3 750.00
Cost of gravel 542.14
• Iron bar 15cm spacing c/c using 10mm Ø 4.10
cost of iron bar 590.00
total cost of iron bar 2419.00
• Timber formwork (Australia) using length=4m, width=25cm and
t=2.5cm 2.22
cost of Timber formwork 400.00
total cost of Timber formwork 888.00
• Wooden (komi=1 , mager = 3 and carrbat=2 ) 0.89
cost of wooden (150birr ,70 birr and 80 birr) 100.00
total cost of wooden 100.00
• Nails
cost of nails using 6cm,7cm.8cm ………1/2kg. 0.50
1kg cost of nails 120.00
total cost of nails 60.00
• Black wire 0.30
cost of black wire 60.00
total cost of black wire 18.00
• Water = 0.6 m3 for 1m3 of reinforced 0.60
5 Birr/ m3 5.00
Cost of water 3.00
Total material cost birr /1m3of reinforced concrete 7210.04
Total direct cost (DC) =Labor cost + Material cost 7791.40
Indirect cost (IC) w/h accounts overhead cost and profits /20 % of direct cost/ 1558.28
75
Total unit cost = direct cost + indirect cost 9349.68
76
• Labor cost + equipment cost 39.75
Material cost ;
1 m2 of plastering = 0.03 m3 by volume for 3 cm thickness of plastering
• Cement = (1/4*0.03m3*1.3 shrinkage * 1.05wastage *1400 kg /m3
)/100 0.14
730 Birr/Quntials 730.00
Cost of cement 104.63
• Sand = 3/4*0.03m3*1.15*1.3 0.03
700 Birr/ m3 700.00
Cost of Sand 23.55
• Water = 0.5 m3 for 1m3 of masonry 0.50
5 Birr/ m3 5.00
Cost of water 2.50
Total material cost birr /1M2of Plastering 130.67
77
• Labor cost + equipment cost 34.78
Material cost ;
#REF!
• Cement = (1/4*0.03m3*1.3 shrinkage * 1.05wastage *1400 kg /m3
)/100 0.14
730 Birr/Quntials 730.00
Cost of cement 104.63
• Sand = 3/4*0.03m3*1.3*1.15 0.03
700 Birr/ m3 700.00
Cost of Sand 23.55
• Water = 0.5 m3 for 1m3 of masonry 0.50
5 Birr/ m3 5.00
Cost of water 2.50
Total material cost birr /1M2of Pointing 130.67
Total direct cost (DC) =Labor cost + Material cost 165.45
Indirect cost (IC) w/h accounts overhead cost and profits /20 % of direct cost/ 33.09
Total unit cost = direct cost + indirect cost 198.55
78
12 Bill of Quantity and Cost Estimation
The quantities of the various items have been worked out as per the final design and final
Bill Off Quantity And Cost Estimation For 05 Kebele Small Scale Irrigation Project
Project-Main canal, Division box, HDPE Pipe installation and cross drainage structure construction
Site- Bosena Spring HDPE pipe installation
Kebele- 05 (Mergeja)
Table-22 Mason and daily labor cost for the project
Item Unit Rate Total Cost
Item of work Unit Quantity
no (Et.Birr) (Et.Birr)
A Main canal construction
1 Earth work
4 Concrete work
79
B HDPE pipe installation
1 Earth work
4 Concrete work
81
Table-23 Transporation and fabric material cost for the project
Unit Rate Total Cost
Item no Item of materials Unit Quantity
(Et.Birr) (Et.Birr)
A Main canal construction
1 Cement Quntials 27.33 730.00 19950.90
Sub total 19950.90
B HDPE pipe installation
1 HDPE pipe Meters 1500.00 260.00 390000
Sub total 390000.00
C Division box construction
1 Cement Quntials 108.49 730.00 79197.7
Sub total 79197.70
D Flume structure construction
1 Cement Quntials 11.06 730.00 8073.80
2 3 inch GI pipe Meters 30.00 533.30 15999.00
3 3/4 inch GI pipe Meters 12.00 220.00 2640.00
4 1 inch HDPE pipe meters 60.00 70.00 4200.00
5 Iron bar 10mm Kg 204.99 85.00 17424.15
6 Timber formwork 30cm thickness Numbers 8.00 400.00 3200.00
7 Black wire Kg 25.00 60.00 1500.00
8 Nails
8.1 6cm Packet 1.00 520.00 520.00
8.2 8cm Packet 1.00 520.00 520.00
8.3 9cm Packet 1.00 520.00 520.00
Sub total 54596.95
Total Sub total 543745.55
Vat 15% 81561.83
Total cost for the project with Vat 15% 625307.38
82
Table-24 Transporation and local material cost for the project
Unit Rate Total Cost
Item on Item of materials Unit Quantity
(Et.Birr) (Et.Birr)
A Main canal construction
1 Sand 6.96 700 4872
2 Aggregate 1.82 750.00 1365
3 Stone 12.60 600.00 7560
Sub total 13797.00
B Division box construction
1 Sand 28.59 700 20013
83
Table-25 Total cost for the project
Unit Rate Total Cost
Item no Item of materials Unit Quantity
(Et.Birr) (Et.Birr)
1 Cement Quntials 146.88 730.00 107222.40
2 HDPE pipe Meter 1500.00 260.00 390000.00
3 3 inch GI pipe Meters 30.00 533.30 15999.00
4 3/4 inch GI pipe Meters 12.00 220.00 2640.00
5 1 inch HDPE pipe meters 60.00 70.00 4200.00
6 Iron bar 10mm Kg 204.99 85.00 17424.15
7 Timber formwork 30cm thickness Numbers 8.00 400.00 3200.00
8 Black wire Kg 25.00 60.00 1500.00
9 Nails
9.1 6cm Packet 1.00 520.00 520.00
9.2 8cm Packet 1.00 520.00 520.00
9.3 9cm Packet 1.00 520.00 520.00
10 Sand 37.50 700.00 26250.00
11 Aggregate 9.80 750.00 7350.00
12 Stone 57.07 600.00 34242.00
Sub total 611587.55
Mason and daily labor cost for the project without vat 215077.32
Total Subtotal without vat 826664.87
Vat 15% 123999.73
Total cost for the project with Vat 15% 950664.60
84
13 Conclusion and recommendation
Bosena spring irrigation project is upgrading traditional irrigation practice. The existing
irrigation practice has more or less two basic problems. The route, along which main
canal is aligned, is made of alluvial deposit as a result there is much water losses.
Solving these problems is very essential for proper utilization of water & soil which in
turn can improve the livelihood of peasants of the project area. That is why Bosena
The designs of each of these structures with their working drawings have been executed.
taking its supply from the Bosena spring irrigation project. The maximum duty of the
For better performance and long service year of the project regular inspection and
Farmers training, how to operate and maintain the project structures as a whole and
The irrigation hours per day and per week should be flexible based on base flow amount
Close supervision of the construction should be made to modify (if needed) each
85
14 Reference
Guideline on small scale irrigation development for woreda and zone IADP experts
design of diversion weir and main canal, By: Endager Getinet, August, 2013 Bahir Dar
design of diversion weir and main canal by: Abdu august -2013 debretabor
Arora K, R. (1996). Irrigation, Water Power and Water Resources Engineering. Napa
Arora, K. (2001). Irrigation Water Power and Water Resources Engineering. Neia Sarak
FAO. (1998). Guide line for computing crop water requirements, irrigation and drainage
Garg, S. (1978). Irrigation and hydraulic structures. New Delhi: Khanna publishers.
S.K, G. (1996). Irrigation Engineering and Hydraulic Structures 6th edition. Delhi:
Khanna Oublishers.
Bahir Dar.
86